Citation : 2019 Latest Caselaw 784 Del
Judgement Date : 7 February, 2019
#14
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CC No.101 /2018 CS(OS)1745/2015
USHAKANT BUILDWELL (P) LIMITED. ..... Plaintiff
Through: None
versus
M/S. CHINAR SHIPPING AND INFRASTRUCTURE (INDIA)
P LTD & ANR. ..... Defendants
Through Mr. Neeraj Jain, Advocate for
D-1/Counter Claimant.
% Date of Decision: 07th February, 2019
CORAM:
HON'BLE MR. JUSTICE MANMOHAN
JUDGMENT
MANMOHAN, J (Oral)
1. Present counter claim has been filed in CS (OS) No.1745/2015, by the defendant no.1 against the plaintiff, for recovery of Rs.1,62,13,857/- .
2. The prayer clause in the counter-claim is reproduced herein below:-
"a. a decree in the sum of Rs. 1,62,13,857/- may kindly be passed in favour of Defendant No. 1 and against the Plaintiff.
b. Interest @ 18% per annum pendentelite and future till the date of payment may be passed in favour of Defendant No. 1 and against the Plaintiff. c. A preliminary decree for accounts be passed in favour of Defendant No. 1 and against the Plaintiff
directing the Plaintiff to render accounts for all fraudulent and illegal lifting of the dredged sand from the site from 10th February, 2014 till 9th October, 2014 and on such accounts being rendered a final decree for recovery of the amount found due may kindly be passed in favour of the Plaintiff and against Defendant No. 1. Defendant No. 1 estimates that a sum of Rs. 50,00,000/- over shall be due and payable by the Plaintiff to Defendant No. 1 on this account d. A decree of permanent injunction may be passed in favour of the Plaintiff and against Defendant No. 1 in the Counter Claimant restraining them their servants and agents anywise from causing any prejudicial action including writing any communication to any person, body incorporate including Delhi Jal Board or creating any impediment in the ingress and egress of the manpower of Defendant No. 1, its agents and servants and from the removal of the dredged sand from the Hanuman Chowk (Wazirabad) and Sonia Vihar.
e. Cost of the Counter claim be awarded
f. Pass such other or further order(s) as may be deemed
fit and proper in facts and circumstances of the present case."
3. On 11th July, 2017, the plaintiff's suit for specific performance, declaration and permanent injunction bearing number CS (OS) No. 1745/2015, was dismissed in default and on account of non-prosecution.
4. On 12th January, 2018, since none appeared for the plaintiff, it was proceeded ex-parte in the counter-claim.
5. At the outset, learned counsel for defendant no.1 / counter- claimant gives up prayers (c) and (d) of the prayer clause of the counter claim. The statement made by learned counsel for defendant no.1 /
counter-claimant is accepted by this Court and defendant no.1 / counter- claimant is held bound by the same.
6. The contentions and submissions advanced by the learned counsel for the defendant no.1 / counter-claimant are as under:-
(i) Vide Contract Agreement dated 15th October 2013, the Delhi Jal Board awarded dredging work in the Yamuna River to the defendant no.1 / counter-claimant at two sites of Hanuman Chowk (Wazirabad) and Sonia Vihar. The defendant no.1 undertook the aforementioned work in a Joint Venture with the technical support of defendant no.2
(ii) The defendant no.1 / counter-claimant and defendant no.2 entered into an Agreement and Supplementary Agreement dated 14th November 2013 and 6th February 2014 respectively, with the plaintiff to lift the dredged sand @Rs. 525 per cubic metre.
(iii) The plaintiff had to deposit the advance amount at the time of lifting the dredged sand. However, the plaintiff was not regular in the depositing the said amount. Since the plaintiff was not performing its part of the Agreements, the defendant no.1 / counter claimant terminated the said Agreements dated 14th November 2013 and 6th February 2014 respectively vide letter dated 11th November 2014.
(iv) The plaintiff filed a suit bearing no. CS(OS) 1745/15 for specific performance, declaration and permanent injunction. The defendant no.1 filed its written statement and counter claim on 20th November, 2015.
(v) The plaintiff overloaded its trucks and dumpers and unauthorisedly and fraudulently removed more dredged sand than agreed in the Agreements dated 14th November 2013 and 6th February 2014. He states that the plaintiff lifted the dredged sand but did not clear the amount due to the defendant no.1/counter claimant.
(vi) The intent of the plaintiff in filing the suit was to stop the work of the defendant no.1/counter claimant and pressurize it to give up its claim on the sand already lifted by the plaintiff.
(vii) On 11th July 2017 the plaintiff's suit was dismissed in default and on account of non-prosecution.
7. The defendant no.1 / counter-claimant has filed its ex parte evidence by way of affidavit of Shri Avnindra Kumar Tripathi (DW1), managing director of the defendant no.1 company.
8. The defendant no.1 witness (DW1) has proved the contract agreement dated 15th October 2013, with the Delhi Jal Board as Exhibit DW1/3. He has proved that the Agreement dated 14 th November 2013 as Exhibit DW1/7 and Supplementary Agreement dated 6 th February 2014 with the plaintiff as Exhibit DW1/8. He has proved that the termination letter dated 11th November 2014 issued by the defendants to plaintiff as Exhibit DW1/4. He has proved the invoices issued by defendant no.1 to the plaintiff as Exhibit DW1/6. He has proved the defendant no. 1's / counter claimant's statement of account as DW1/5.
9. From the un-rebutted evidence on record, it is apparent that the plaintiff did not pay the defendant no.1 / counter claimant for lifting and
removing the dredged sand thereby causing financial loss to defendant no.1 / counter claimant. Accordingly, this Court is of the opinion that the plaintiff failed to perform its obligation under the Agreements dated 14th November 2013 and 6th February 2014.
10. Consequently, the counter claim is decreed in favour of the defendant no.1/counter claimant and against the plaintiff for Rs.1,42,85,337/-along with pendente lite and future interest at 7% per annum. This Court may mention that it is awarding the interest at 7% per annum as that is the normal rate at which the banks are lending monies now-a-days. The defendant no.1/counter claimant is also held entitled to actual costs of litigation. The costs shall amongst others include the lawyer's fees as well as the amount spent on Court-fees. The defendant no.1/counter claimant is given liberty to file on record the exact cost incurred by it in adjudication of the present suit. Registry is directed to prepare a decree sheet accordingly.
MANMOHAN, J FEBRUARY 09, 2019 rn/sp
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!