Friday, 24, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Satya Parkash & Bros (P) Ltd vs Government Of Nct Of Delhi & Anr
2019 Latest Caselaw 690 Del

Citation : 2019 Latest Caselaw 690 Del
Judgement Date : 4 February, 2019

Delhi High Court
M/S Satya Parkash & Bros (P) Ltd vs Government Of Nct Of Delhi & Anr on 4 February, 2019
* IN THE HIGH COURT OF DELHI AT NEW DELHI
%                             Date of decision: 4th February, 2019

+       FAO(OS) 27/2019, CM Nos. 5217/2019, 5218/2019 &
        5219/2019

        M/S SATYA PARKASH & BROS (P) LTD        ..... Appellant
                 Through: Mr. Aseem Mehrotra, Adv.

                     versus

        GOVERNMENT OF NCT OF DELHI & ANR
                                                         ..... Respondent
                     Through:       Mr. Sanjay Dewan, Adv.



 CORAM:
 HON'BLE THE CHIEF JUSTICE
 HON'BLE MR. JUSTICE V. KAMESWAR RAO

V. KAMESWAR RAO, J. (ORAL)

CM Nos. 5217/2019 & 5218/2019 (for exemption) Exemption allowed, subject to all just exceptions.

Applications stand disposed of.

CM No. 5219/2019 (for delay) This is an application filed by the appellant seeking condonation

of 30 days delay in filing the present appeal.

For the reasons stated in the application, the delay of 30 days in

filing the present appeal is condoned. Application stands disposed of.

FAO(OS) 27/2019

1. The challenge in this appeal is to the order dated November

14, 2018 passed by the learned Single Judge in O.M.P. 27/2012

filed by the appellant under Section 34 of the Arbitration and

Conciliation Act, 1996 (in short 'Act of 1996').

2. Some of the facts as noted from the appeal are that a

Contract was awarded to the appellant for improvement of "Nelson

Mandela Marg, (Road No.17), New Delhi SH: Development /

Widening of road from 4 lanes to 8 lanes including construction of

drains, footpath and extension of culverts etc. (RD-0 to RD 4040)".

The estimated cost of work was Rs. 10,30,90,036/-. A formal letter

of awarding the contract was issued to the appellant on May 10,

2002. The starting date of the contract was May 17, 2002 and the

date of completion was May 16, 2003.

3. It is a conceded position that the contract was foreclosed on

October 26, 2014; the actual date of completion was taken to be

November 26, 2004. Various disputes arose between the parties.

An Arbitrator was appointed by this Court. The appellant had

raised eight claims which were as under:

 Claim No.1 - Claim towards the final bill

 Claim No.2 - Claim of execution of increased/additional quantity of work

 Claim No.3 - Claim of escalation of Rs.72,58,640/- due to various hindrances resulted for almost delay of 15 months.

 Claim No.4 - Claim due to delay of machinery, deployment including the extra expenses.

 Claim No.5 - Claim due to delay (extra manpower which was deployed)

 Claim No.6 - Prolongation of contract, loss/profit in view thereof.

 Claim No.7 - Pendente lite and future interest.

 Claim No.8 - Litigation cost and expenses."

4. During the pendency of the arbitration proceedings, an

amount of Rs. 17,32,156/- was paid to the appellant. Hence, the

claim insofar as the final bill was concerned, was satisfied. The

learned Arbitrator has awarded 9% interest on the said amount for

the period from June 01, 2007 to March 30, 2011. The challenge

before the learned Single Judge was rejection of claim No.3, which

was a claim for escalation for an amount of Rs.72,58,640/-.

5. The plea taken by Mr. Aseem Mehrotra, learned counsel

appearing for the appellant before the learned Single Judge was that

the hindrance register being an admitted document between the

parties clearly records various hindrances that were caused due to

which delays had taken place in the execution of the contract. The

delay being attributed to the respondents herein, the appellant is

entitled to escalation. The learned Single Judge has in paras 14 to

16 held as under:

"14. As recorded above, it was the common case of the parties that clause 10CC was not applicable. However, the learned Arbitrator, based on the settled position of law as cited by the Contractor holds that since there has been delay which is solely attributable to the Government, the Contractor can still claim escalation. The learned Arbitrator has not committed any error in law. However, learned Arbitrator thereafter records that while the hindrance register records certain hindrances, which were admittedly caused during the execution of the contract, for example on 1st October, 2002, 15th May, 2003, 20th February, 2004 and 14th March, 2003, various electric cables/poles, high tension pillars, huts, acquiring of land from DDA, shifting of pipes and man holes, shifting of DTC bus

stand, removal of trees, shifting of MTNL Boxes and Cables etc. However, evidence on record did not show that the execution of contract was stopped in any manner. It is a factual finding of the learned Arbitrator that hindrances recorded in the hindrance register did not result in stoppage of work. Learned Arbitrator, in fact, relied upon the various letters written by the Government, which show that the Contractor itself had not deployed sufficient labour and machinery on the site. Learned Arbitrator further notes that the Contractor sought repeated extensions for completion of work and at the time when extensions were granted, same were to be granted without claim of any compensation.

15. The Arbitrator relied on letter dated 3rd March, 2006 written by the Contractor, which reads as under:

"In continuation to our letter under reference and as per your verbal instructions we hereby undertake that we have not suffered any financial loss on account of delay in completion. and will not claim anything extra on this."

16. As per this letter, it is clear that the Contractor had agreed to not claim any compensation or financial losses or raise any claims for any extra

amounts in this regard. The Contractor having agreed to not raise any claim, the claims in respect of delays are rightly rejected by the learned Arbitrator. In fact, a perusal of the calculation sheet, in which the Contractor raised the claim for escalation shows, that the same has been raised on the basis of clause 10CC, which is clearly not applicable. The learned Arbitrator based on the three counts i.e. 1) Factual analysis of stoppage of work and deployment of machinery; 2) In view of undertaking dated 3rd March, 2006 and 3) On the basis of non-applicability of section 10CC, rejected the claims in respect of delays, which have been raised by the Contractor."

6. Mr. Aseem Mehrotra has reiterated the submission made by

him before the learned Single Judge, even before us. He has drawn

our attention to page 94 of the record to contend the hindrances that

had taken place in the execution of the contract. It is his submission

that there is enough evidence filed by the appellant to contend that

there was escalation of price. Unfortunately, said aspect has not

been considered / dealt with by the learned Arbitrator in the award.

In other words, it is his case that the appellant was entitled to

escalation. He states that a similar error has been made by the

learned Single Judge while considering objections under Section 34

of the Act of 1996.

7. We are not impressed by the submission made by Mr.

Aseem Mehrotra in view of the reasons given by the learned Single

Judge which we have noted above and also in view of the letter

dated November 16, 2004 written to the appellant by the

respondents approving the extension of time for completion of the

work. The said letter reads as under:

"No. 18/EE/DS&CM/496 Dated: 16/11/04 To, M/s Satya Prakash & Bros. Pvt. Ltd., Govt. Contractors & Engineers, A-1, C.C. Colony, Opp. Rana Pratap Bagh, Delhi - 110007

Sub: Improvement of Nelson Mandela Marg (Road No.1), New Delhi.

(SH: Development / Widening of Road from 4 lanes to 8 lanes including construction of drains / footpath and extension of Culvert etc. (RD 0 to RD 4040) - regarding Provisional Extension of Time.

(Agreement NO. 01 /EE/FD-1/202-03).

Dear Sir, The date of completion of the above mentioned work is 16/5/2003 as stipulated in the agreement dated the 10/5/2002. Provisional Extension of time for completion of the above mentioned work is granted upto 30/11/2004 without prejudice to the right of the Government to recover liquidated damages in accordance with the provision of Clause -2 of the said agreement dated the 10/5/2002.

Provided that notwithstanding the extension thereby granted, time is and shall continue to be the essence of the said agreement.

Yours faithfully For and on behalf of President of India

Sd/-

(B.K. SINHA) Executive Engineer, DS&CM Project, PWD, New Delhi."

8. Suffice it to state that the extension of time was given at the

asking of the appellant, wherein it was clearly stated that the

extension is being granted by the Government without prejudice to

its right to recover liquidated damages in accordance with clause 2

of the agreement. It is not the case of the appellant that it had

objected to the contents of the letter and had also sought escalation.

In fact, Mr. Aseem Mehrotra has conceded that the appellant had

accepted the extension of completion of the work on the terms

stated therein as the appellant was apprehensive that coercive action

shall be taken against it by the respondents.

9. If that be so, the appellant having accepted the terms on

which the extension of completion of work was granted and also the

fact that the appellant himself as noted by the learned Single Judge

has stated that he has not suffered any financial losses on account of

delay in completion of the work, the impugned order needs no

interference, moreso when we are exercising jurisdiction under

Section 37 of the Act of 1996. The appeal is dismissed. No costs.

V. KAMESWAR RAO, J

CHIEF JUSTICE

FEBRUARY 04, 2019/aky

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter