Citation : 2019 Latest Caselaw 1091 Del
Judgement Date : 19 February, 2019
$~24
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P. 760/2012
Date of Decision : 19th February, 2019
CENTRAL WAREHOUSING CORPORATION
..... Petitioner
Through: Mr.K.K. Tyagi & Mr.Iftekhar
Ahmad, Advs.
versus
M/S VARDHAMAN PRECISION PROFILES AND TUBES
PVT LTD ..... Respondent
Through: Mr.Sunil K. Jain, Mr.Punya
Garg & Mr.Abhishek Jain,
Advs.
CORAM:
HON'BLE MR. JUSTICE NAVIN CHAWLA
NAVIN CHAWLA, J. (Oral)
1. This petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the „Act‟) has been filed by the petitioner challenging the Arbitral Award dated 29.07.2009 passed by the Sole Arbitrator adjudicating the disputes that have arisen between the parties in relation to Letter of Intent/Work Order dated 06.08.2004 issued by the petitioner in favour of respondent for the construction work of 8580 sq.mts. covered warehouse (design, supplying and erecting pre-fabricated and pre- engineered warehouse) at 30 Ha. Plot, Sector 10, D'Node, Navi Mumbai.
O.M.P. 760/2012 Page 1
2. The challenge of the petitioner is confined only to the Award under Claim no. 1 and Claim No. 2 awarded in favour of the respondent.
3. Claim No. 1 of the respondent was towards payment of withheld amount towards liquidated damages / penalty amounting to Rs. 23,48,346/-. The learned counsel for the petitioner submits that in terms of Clause 2 read with Clause 25 of the Agreement, decision of the Chief Engineer/Superintendent Engineer/Executive Engineer on the question of delay and consequential compensation in form of liquidated damages is an „excepted matter‟ and cannot be made subject matter of an arbitration proceeding. He has placed reliance on the Judgments of the Supreme Court in Vishwanath Sood v. Union of India and Another, (1989) 1 SCC 657; General Manager, Northern Railway and Another v. Sarvesh Chopra, (2002) 4 SCC 45 and Food Corporation of India v. Surendra, Devendra & Mahendra Transport Co., (2003) 4 SCC 80, as well as of this Court in Union of India v. M/s J.N. Constructions, 107 (2003) DLT 772 (DB), to contend that the Courts have interpreted pari materia clauses in the Agreement to hold that such disputes are not arbitrable, being "excepted matter".
4. On the other hand, the learned counsel for the respondent submits that the dispute was arbitrable inasmuch as the petitioner had not placed on record any notice or decision of the Chief Engineer/Superintendent Engineer/Executive Engineer in accordance with Clause 2 of the Agreement. He submits that even the Arbitrator, in the Impugned Award, has therefore, held that the decision to levy
O.M.P. 760/2012 Page 2 liquidated damages by the petitioner is not an „excepted matter‟ under Clause 25 of the Agreement.
5. I have considered the submissions made by the learned counsel for the parties. Clause 2 and Clause 25 of the Agreement are reproduced hereinbelow:-
"Clause 2- The time allowed for carrying out the work as entered in the tender shall be strictly observed by the contractor and shall be deemed to be the essence of the contract on the part of the contractor and shall be reckoned from the tenth and after the date on which the order to commence the work is issued to the contractor. The work shall throughout the stipulated period of the contract be proceeded with all due diligence and the contractors shall pay as compensation calculated as the Chief Engineer/Supdt. Engineer/Executive Engineer as the case may be (whose decision in writing shall be final) may decide on the amount of tendered value of the work for every complete day/week (applicable) that the work remains uncommence, or unfinished after the proper dates. This will also apply to items or group of item for which a separate period of compensation has been specified.
xxxxxx Clause - 25 - Except where otherwise provided in the contract all questions and disputes relating to the meaning of the specifications, designs, drawings and instructions herein above mentioned and as to the quality of workmanship of materials used on the work or as to any other questions, claims, right matter or thing whatsoever, in any way, arising out of or relating to the contract, designs, drawings, specifications, estimates, instructions orders or these conditions or otherwise concerning the work, or the execution or failure to execute the same whether arising during the progress of the work or after the completion or abandonment thereof shall be referred to the
O.M.P. 760/2012 Page 3 sole arbitrator of the person appointed by the Managing Director, Central Warehouse Corporation................."
6. In Vishwanath Sood (Supra), the Supreme Court was interpreting almost identical Clauses as Clause 2 and 25 of the present Agreement in question. The Supreme held that reading Clause 25 with Clause 2 of the Agreement, it was not open to the Arbitrator to have entered upon reference with regard to the Claim of liquidated damages. I may only quote from the judgment as under:-
"8. We have gone through the judgment of the Division Bench of the High Court and we have also considered the arguments advanced on both sides. With great respect, we find ourselves unable to agree with the interpretation placed by the Division Bench on the terms of the contract. Clause 2 of the contract makes the time specified for the performance of the contract a matter of essence and emphasises the need on the part of the contractor to scrupulously adhere to the time schedule approved by the Engineer-in-charge. With a view to compel the contractor to adhere to this time schedule, this clause provides a kind of penalty in the form of a compensation to the Department for default in adhering to the time schedule. The clause envisages an amount of compensation calculated as a percentage of the estimated cost of the whole work on the basis of the number of days for which the work remains uncommenced or unfinished to the prescribed extent on the relevant dates. We do not agree with the counsel for the respondent that this is in the nature of an automatic levy to be made by the Engineer-in-charge based on the number of days of delay and the estimated amount of work. Firstly, the reference in clause to the requirement that the work shall throughout the stipulated period of the contract be proceeded with due diligence and the reference in the latter part of the clause that the compensation has to be paid "in the event of the
O.M.P. 760/2012 Page 4 contractor failing to comply with" the prescribed time schedule make it clear that the levy of compensation is conditioned on some default or negligence on the part of the contractor. Secondly, while the clause fixes the rate of compensation at one per cent for every day of default it takes care to prescribe the maximum compensation of 10 per cent on this ground and it also provides for a discretion to the Superintending Engineer to reduce the rate of penalty from one per cent. Though the clause does not specifically say so, it is clear that any moderation that may be done by the Superintending Engineer would depend upon the circumstances, the nature and periods of default and the degree of negligence or default that could be attributed to the contractor. This means that the Superintending Engineer, in determining the rate of compensation chargeable, will have to go into all the aspects and determine whether there is any negligence on the part of the contractor or not. Where there has been no negligence on the part of the contractor or where on account of various extraneous circumstances referred to by the Division Bench such as vis major or default on the part of the Government or some other unexpected circumstance which does not justify penalising the contractor, the Superintending Engineer will be entitled and bound to reduce or even waive the compensation. It is true that the clause does not in terms provide for any notice to the contractor by the Superintending Engineer. But it will be appreciated that in practice the amount of compensation will be initially levied by the Engineer-in- charge and the Superintending Engineer comes into the picture only as some sort of revisional or appellate authority to whom the contractor appeals for redress. As we see it, clause 2 contains a complete machinery for determination of the compensation which can be claimed by the Government on the ground of delay on the part of the contractor in completing the contract as per the time schedule agreed to between the parties.
The decision of the Superintending Engineer, it seems to us, is in the nature of a considered decision which he has to arrive at after considering the various mitigating circumstances that may be pleaded by the contractor or his plea that he is not liable to pay compensation at all under this clause. In our opinion the
O.M.P. 760/2012 Page 5 question regarding the amount of compensation leviable under clause 2 has to be decided only by the Superintending Engineer and no one else.
9. The Division Bench has construed the expression in Clause 2 in parenthesis that "the Superintending Engineer's decision shall be final" as referring only to a finality qua the department; in other words, that it only constitutes a declaration that no officer in the department can determine the quantification and that the quantum of compensation levied by the Superintending Engineer shall not be changed without the approval of the Government. After referring to certain judicial decisions regarding the meaning of the word "final" in various statutes, the Division Bench concluded that the finality cannot be construed as excluding the jurisdiction of the arbitrator under Clause 25. We are unable to accept this view. Clause 25 which is the arbitration clause starts with an opening phrase excluding certain matters and disputes from arbitration and these are matters or disputes in respect of which provision has been made elsewhere or otherwise in the contract. These words in our opinion can have reference only to provisions such as the one in parenthesis in clause 2 by which certain types of determinations are left to the administrative authorities concerned. If that be not so, the words "except where otherwise provided in the contract" would become meaningless. We are therefore inclined to hold that the opening part of clause 25 clearly excludes matters like those mentioned in clause 2 in respect of which any dispute is left to be decided by a higher official of the Department. Our conclusion, therefore, is that the question of awarding compensation under clause 2 is outside the purview of the arbitrator and that the compensation, determined under clause 2 either by the Engineer-in-charge or on further reference by the Superintending Engineer will not be capable of being called in question before the arbitrator."
7. In Sarvesh Chopra (Supra), the Supreme Court summed up the law with respect to „excepted matter‟ in the following words:-
O.M.P. 760/2012 Page 6 "17. To sum up, our conclusions are: (i) while deciding a petition under Section 20 of the Arbitration Act, 1940, the court is obliged to examine whether a difference which is sought to be referred to arbitration is one to which the arbitration agreement applies. If is is a matter excepted from the arbitration agreement, the court shall be justified in withholding the reference, (ii) to be an excepted matter it is not necessary that a departmental or an "in-house" remedy for settlement of claim must be provided by the contract. Merely for the absence of provision, for in-house settlement of the claim, the claim does not cease to be an excepted matter, and (iii) an issue as to arbitrability of claim is available for determination at all the three stages- while making reference to arbitration, in the course of arbitral proceedings and while making the award a rule of the court."
8. In Food Corporation of India (Supra), the Supreme Court again, held as under:-
"6. Aggrieved against the order of the High Court the present appeal has been filed. Counsel appearing for the Corporation relying upon the judgment of this Court in Rajasthan State Mines & Minerals Ltd. v. Eastern Engg. Enterprises contended that the arbitrator acted in excess of his jurisdiction in entering upon a dispute and making an award of a claim which was not permitted to be referred to the arbitrator under the contract. According to him, the claim made and given by the arbitrator under Issues 3 and 5 regarding transit loss and demurrage and wharfage charges could not be made as the same had been specifically excluded under clause (XX) read with clause (XII) of the agreement. We find substance in this submission.
Arbitration clause (XX) provided that all disputes and differences arising out of or in any way touching or concerning the agreement whatsoever could be referred to the sole arbitration of a person appointed by the Managing Director except "as to any matter the decision of which is expressly provided for in the contract". Clause (XII) of the agreement provided that the contractor would be liable for all costs,
O.M.P. 760/2012 Page 7 damages, demurrage, wharfage charges and expenses etc. or transit loss suffered by the Corporation and the Senior Regional Manager shall be the sole authority to determine the said failures on the part of the contractors or the loss caused thereby, thus excluding the reference to the arbitrator for the decision of these disputes. This Court in Rajasthan State Mines & Minerals Ltd. case has held: (SCC p. 310, para 44) "44. (f) To find out whether the arbitrator has travelled beyond his jurisdiction, it would be necessary to consider the agreement between the parties containing the arbitration clause. The arbitrator acting beyond his jurisdiction is a different ground from the error apparent on the face of the award.
(g) In order to determine whether the arbitrator has acted in excess of his jurisdiction what has to be seen is whether the claimant could raise a particular claim before the arbitrator. If there is a specific term in the contract or the law which does not permit or give the arbitrator the power to decide the dispute raised by the claimant or there is a specific bar in the contract to the raising of the particular claim then the award passed by the arbitrator in respect thereof would be in excess of jurisdiction."
7. The High Court issued a direction by an order dated 16-6- 1988 referring the disputes for arbitration in terms of clause (XX). The matters which were excluded from the reference to the arbitrator therefore could not be referred to or decided by the arbitrator. Entrance of reference by the arbitrator on disputes which were excluded from reference and the adjudication thereupon would amount to exceeding in the exercise of the jurisdiction as held by this Court in Rajasthan State Mines & Minerals Ltd. case. Since there was a specific bar to the raising of a claim regarding transit, demurrage and wharfage charges, the award made by the arbitrator in respect thereof would be in excess of the jurisdiction."
O.M.P. 760/2012 Page 8
9. This Court also in its Judgment in M/s J.N. Constructions (Supra), held Clauses similar to Clause 2 and 25 herein and constituting an „excepted matter‟ are not referable to arbitration.
10. The Arbitrator has placed reliance on the Judgment of Bharat Sanchar Nigam Limited and Another v. Motorola India Private Limited, (2009) 2 SCC 337 to hold that in spite of Clause 2 and 25 of the Agreement the dispute whether a delay was caused and by whom would be a matter to be determined by the Arbitrator. I am unable to agree with the said finding of the Arbitrator. In the said Judgment, the Clause in question left the decision of quantum of liquidated damages to the Purchaser. The Court held that while the quantum of liquidated damages under Clause 16.2 may be final, the same has to be based on a finding of delay under Clause 15.2 of the Agreement therein, which was not stated to be final and binding. In view of the presence of Clause 15.2 it was held that such dispute would therefore be arbitrable. The Court also distinguished the Judgment of Sarvesh Chopra (Supra) and Vishwanath Sood (Supra) in Bharat Sanchar Nigam Limited and Another (Supra) and held as under:-
"29. The learned Senior Counsel for the appellants relied on the decisions of this Court in Vishwanath Sood v. Union of India and Northern Railway v. Sarvesh Chopra. These cases, we are afraid, will not be of any help to the appellants being distinguishable on facts and having different contractual clauses. We may note that Clause 16.2 cannot be treated as an excepted matter. This is because admittedly, it does not provide for any adjudicatory process for decision on a question, dispute or difference, which is the condition precedent to lead to the
O.M.P. 760/2012 Page 9 stage of quantification of damages nor is it a no-claim or no- liability clause.
30. In Vishwanath Sood case it was held by this Court that a particular claim of the Government was excluded because the Superintendent Engineer acted as the revisional authority to decide disputes between the two parties by an adjudicatory process, there being a complete machinery for settlement of the disputes in the relevant clause and most importantly, the Superintendent Engineer had the discretion on consideration of the facts and circumstances including mitigating facts, held no damages was payable."
31. Again in Sarvesh Chopra this Court had held that the claims covered by the no-claims clause i.e. where the contractor had given up the right to make a claim for breach on the part of the Government was not arbitrable in terms of the arbitration clause contained therein and Clause 63 of the general conditions of the contract which provided for exclusion because no-claim clause was excepted as such claims were simply not entertainable."
11. The above Judgment, therefore, was not applicable to the facts of the present case.
12. A submission has been made by the learned counsel for the respondent that there was no notice issued to the respondent before imposing liquidated damages, neither was the order/decision in terms of Clause 2 of the Agreement placed on record by the petitioner.
13. In my view, this would have no effect inasmuch as it has not been denied that liquidated damages would have been levied pursuant to an order passed by the Chief Engineer/Superintendent Engineer/Executive Engineer under Clause 2 of the Agreement. Further, before the Arbitrator there was no plea raised by the
O.M.P. 760/2012 Page 10 respondent that the petitioner is not entitled to such liquidated damages as no order/decision has been passed/taken by the concerned authority under Clause 2 of the Agreement. This submission of the respondent, therefore has no merit.
14. Claim no. 2 of the respondent was for the refund of the Service Tax paid by it to the Authorities. The respondent claims that the Service Tax had been introduced only by the Finance Act, 2004 with effect from 10.09.2004. In the present case, the Letter of Intent had been issued on 06.08.2004 and therefore, it was a case of subsequent Tax Legislation not contemplated by the parties at the time of the Agreement and was, therefore, reimbursable by the petitioner.
15. The learned counsel for the petitioner submits that the Arbitrator has erred in holding that this was the case of a subsequent Tax Legislation inasmuch as the Service Tax on building activities was already in existence at the time of entering into the Agreement. In fact, the respondent in its letter dated 20.07.2004, while refusing to reduce the price during negotiation, had specifically made reference to the Service Tax stated as under:-
"3. Service tax @10% has been levied on the service provided for building construction. Even we presume the cost of [email protected]%, service tax will be 1%."
16. He submits that, therefore, the Arbitrator has erred in granting above claim in favour of the respondent.
17. I have considered the submission made by the counsel for the petitioner. It may first be noted that before the Arbitrator there was no
O.M.P. 760/2012 Page 11 dispute raised with regard to the Service Tax being imposed only with effect from 10.09.2004, that is after the issuance of Letter of Intent. The only dispute that was raised was with respect to the effect of letter dated 20.07.2004 of the respondent. The Arbitrator had dealt with this contention and held as under:-
"22. I accept the contentions of the claimant. The claimant's letter dated 06.07.2004 (which was after the submission of bids and prior to the imposition of service tax on the job of erection) does not take into consideration of service tax and the same was not taken into account at all as there was no service tax till those dates on the services of „erection‟. Therefore, Respondent-Corporation is liable to reimburse the amount claimed by the claimant with regard to the new statutory levy (tax) brought into effect subsequent to the date of issue tender and issue of Letter of Intent. The relevant date has to be the date of submission of quotation which was 07.04.2004 and there was no service tax on that date in the statute book and the levy of the service tax was brought on 19.09.2004 on the contract work of erection of steel structure. I award Rs. 9,39,339/- in favour of the claimant."
18. Having not raised such objection before the Arbitrator, the petitioner cannot be allowed to assail the Award on this ground.
19. The learned counsel for the petitioner has further placed reliance on Clause 4.20 of the Tender Documents which reads as under:-
"4.20Any other taxes/levies as applicable shall be paid by contractor directly. No claim whatsoever in this regard shall be entertained."
O.M.P. 760/2012 Page 12
20. He submits that in view of the above Clause, all taxes, be it in existence at the time of tender or not, were to be borne by the respondent.
21. I am unable to agree with the said submission of the learned counsel for the petitioner. The taxes being referred to in Clause 4.20 can only be those which are leviable at the time of the tender. A party cannot be held to have taken the burden of taxes which would be levied after the issuance of the tender/Letter of Intent unless such intent is evident from the contractual terms, which I find absent in the present case. Therefore, I find no merit in the objection raised by the counsel for the petitioner as far as Award of claim no. 2 is concerned.
22. In view of the above, the award of claim No. 1 and award of consequential interest thereon in Claim no. 8 is set-aside. The petition is partly allowed. The parties shall bear their own cost.
NAVIN CHAWLA, J
FEBRUARY 19, 2019/rv
O.M.P. 760/2012 Page 13
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!