Citation : 2017 Latest Caselaw 6735 Del
Judgement Date : 27 November, 2017
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P.(I) 22/2017
O.M.P.(I) 23/2017
Date of decision: 27th November, 2017
REGEN POWERTECH PRIVATE LIMITED ..... Petitioner
Through Mr.Jayant Mehta, Mr.Anshul
Raajan and Mr.S.Aravindan,
Advs.
versus
GREEN INFRA WIND FARM ASSETS LIMITED & ANR.
..... Respondents
Through Mr.Abhinav Vasisht, Sr. Adv.
with Mr.Shankh Sengupta,
Ms.Tine Abraham and
Ms.Prerna Jain, Advs.
CORAM:
HON'BLE MR. JUSTICE NAVIN CHAWLA
NAVIN CHAWLA, J. (Oral)
Cav. 1014/2017 in OMP(I) 22/2017 Cav. 1016/2017 in OMP(I) 23/2017
As respondents appear on receipt of advance notice, Caveats stand discharged.
IA No.13988/2017 (Exemption) in OMP (I) 22/2017 IA No.13989/2017 (Exemption) in OMP (I) 23/2017
Allowed, subject to all just exceptions.
OMP(I) 22/2017 & OMP(I) 23/2017 Page 1 OMP(I) 22/2017 & OMP(I) 23/2017
1. These petitions raise common issues, hence are disposed of together. I may only take the facts of OMP(I) 22/2017.
2. I have heard learned counsel for the petitioner and learned Senior counsel for the respondent No.1.
3. This petition under Section 9 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the 'Act') has been filed by the petitioner inter alia praying for the following reliefs:
"a) Pending disposal and final adjudication of the arbitration proceedings, the Respondent NO.1 be directed to pay back the sum of INR 13,90,50,000 in to the Petitioner's bank that was received by it pursuant to the invocation of the Performance Bank Guarantee BG No. 0993015BG0000178 dated 30 September 2015 and with a further direction to restore the BG No. 0993015BG0000178 dated 30 September 2015 as it stood on 19 November 2017; and
b). Pending disposal and final adjudication of the arbitration proceedings, the Respondent No. 1 be directed that the amount of INR 13,90,50,000, received by the Respondent NO.1 upon encashment of the subject Performance Bank Guarantee BG No. 0993015BG0000178 dated 30 September 2015 be kept in an interest bearing escrow account with lien marked in favour of the petitioner's banker State Bank of India, Industrial Finance Branch, No.2, Harrington Road, KRM Plaza, Ground Floor, Chetpet, Chennai-600 031 and; or
OMP(I) 22/2017 & OMP(I) 23/2017 Page 2
c). Pending disposal and final adjudication of the arbitration proceedings, the respondent No.1 be directed to maintain status quo ante as on 19 November, 2017 with regard to the sum of INR 13,90,50,000/- that was received by it pursuant to the invocation of the Performance Bank Guarantee BG No.0993015BG0000178 dated 30 September, 2015."
4. It is the case of the petitioner that the petitioner had entered into a Wrap Agreement dated 28.03.2012 with the respondents whereunder the petitioner was to supply 30 Nos., ReGen Make, V-82, 1500 KW Wind Energy Converters (WECs), Towers, Transformers and Equipment of Unit Substation at Dalot Site (District Pratapgarh) in Rajasthan (hereinafter referred to as 'Agreement'). It is further submitted that the petitioner has duly commissioned these WECs and for this reliance is placed on the Commissioning Certificates dated 20.09.2012, 27.11.2012 and 27.01.2013. Learned counsel for the petitioner relying upon Clause 3.6 of the Agreement submits that the Bank Guarantees in question were given against the release of balance 10% of the WECs price. These Bank Guarantees were to remain valid for a period of one year from Commercial Operation Date and, therefore, should have remained valid only till 20.09.2013, 27.11.2013 and 27.01.2014 respectively. Learned counsel for the petitioner further relies upon a Certificate dated 03.05.2014 to submit that the parties, in a joint inspection, had also certified regarding the successful completion of the project in terms of Clause 3.6(ii) of the Contract.
5. Learned counsel for the petitioner further draws my attention to the notice dated 18.11.2017 and submits that this is the only Notice of
OMP(I) 22/2017 & OMP(I) 23/2017 Page 3 Default received by the petitioner, however, this notice is not under the Wrap Agreement but under the Operation and Management (O&M) Agreement and Maintenance Agreement both dated 30.05.2012. It is submitted that the respondent could not have invoked the Bank Guarantees relying upon this Notice of Default.
6. I have considered the submissions made by counsel for the petitioner. It is a fact that as on today that Bank Guarantees have been encashed and money thereunder has passed on to the respondents. To grant the relief as claimed in the petitions, the petitioner, in my opinion, would, therefore, have to make out a case which would meet the standards as laid down under Order XXXVIII Rule V of the Code of Civil Procedure, 1908 i.e. it would have to be shown that the respondents, with the intent to obstruct or delay the execution of any decree that may be passed against it, is about to dispose of the whole or any part of its property, or about to remove the whole or any part of its property from the local limits of the jurisdiction of the Court. I find no such case been made out or pleaded by the petitioner in its petition. Learned Senior counsel for the respondent in this regard has drawn my reference to the judgment of this Court in Mala Kumar Engineers Pvt. Ltd. v. B.Seenaiah & Co. (Project) Ltd. 2005 SCC Online Del
38.
7. Learned counsel for the petitioner has placed reliance on judgment of Supreme Court in M/s Gangotri Enterprises Ltd. v. Union of India, AIR 2016 SC 2199, however, I am afraid that the same is not applicable to the present case inasmuch as the case before the Supreme Court was with respect to seeking restrain on the
OMP(I) 22/2017 & OMP(I) 23/2017 Page 4 encashment of Bank Guarantee, however, in the present case, as noted above, the Bank Guarantees have already been invoked and the petitioner is now seeking a direction against the respondent to secure the amount so received. This payer would have to be considered on different parameters as noted by me above.
8. I may only note that the petitioner is yet to invoke the arbitration clause in terms of Article 7 of the Agreement and the question whether the invocation of Bank Guarantees was in accordance with the terms of the Agreement and/or consequences of such invocation has to be determined by the Arbitrator.
9. In view of the above discussion, I find no merit in the present petition. The same is accordingly dismissed.
10. I may, however, hasten to add that my above observations are prima facie in nature and would in no manner bind the Arbitral Tribunal who shall adjudicate the disputes between the parties on its own merits. Either party would be free to raise any further claims, submissions, defence or pray for interim relief from the Arbitral Tribunal, which would be constituted in terms of the Arbitration Agreement.
NAVIN CHAWLA, J
NOVEMBER 27, 2017/vp
OMP(I) 22/2017 & OMP(I) 23/2017 Page 5
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!