Citation : 2017 Latest Caselaw 2278 Del
Judgement Date : 8 May, 2017
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Reserved on: 01.05.2017.
Pronounced on: 08.05.2017
+ RFA (OS)(COMM) 6/2016 & C.M. APPL.41061-62/2016 &
352/2017
GAIL (INDIA) LIMITED ..... Appellant
Through : Sh. Sanjay Jain, ASG with Sh. N.L.
Ganapathi, Sh. Mitash Charan, Sh. Vignrai
Passayat, Ms. Natasha Thakur and Ms. Adrija
Thakur, Advocates.
versus
PUNJ LLOYD LIMITED ..... Respondent
Through : Sh. J.P. Sengh, Sr. Advocate with Sh.
Manish Jha, Sh. Akhil Bhardwaj and Ms. Manisha Mehta, Advocates.
CORAM:
HON'BLE MR. JUSTICE S. RAVINDRA BHAT HON'BLE MR. JUSTICE YOGESH KHANNA
MR. JUSTICE S. RAVINDRA BHAT
%
1. The present appeal questions the judgment and order of a learned single judge, which decreed in part a civil suit filed by the respondent (Punj Lloyd). The said plaintiff, Punj Lloyd has also preferred cross objections, which were heard finally, with the consent of counsel for parties. The said cross objections shall be treated as admitted; the Registry shall accordingly register it and appropriately number it. The record of the suit and the
proceedings before the learned single judge were called for and were part of the appeal file at the time of hearing, of this appeal.
2. Punj Lloyd sued to recover `29,15,07,084.80/- from the appellant (hereafter "GAIL") The suit amount was deducted towards interim liquidated damages in terms of Clause 57.2 of the Special Conditions of Contract (SCC) to which the present disputants were parties. Punj Lloyd complained that GAIL had withheld amounts on account of the liquidated damages deducted for interim stages delays in the completion of works, in exercise of GAIL's rights under Clause 57.2 of the SCC from Punj Lloyd's bills.
3. GAIL was to lay down gas pipelines for transportation of re-gasified natural gas originating from Petronet LNG Terminal at Dahej in Gujarat and terminating at Vijaipur in Madhya Pradesh. This and other associated facilities was called the DAHEJ-VIJAIPUR Pipeline Project (DVPL Project). It consisted of four parts (called "spreads"). The invitation for bids described the spreads as follows:-
SPREAD DETAILS TOTAL LENGTH (IN KMS) I. Dahej to Sherpura 169.9 II. Sherpura to Jhabua 100.8 III. Jhabua to Jagoti 152.3 IV. Jagoti to Vijaipur 193.3
4. Punj Lloyd submitted its bid for spreads I, II and III from DAHEJ to Jagoti for a pipeline length of 423 kms consisting of spreads I, II and III. It also bid for overall commissioning of the four spreads for the Project. It was awarded the laying of pipeline work for the Spreads I, II and III. Spread IV
was awarded to another bidder M/s RNGS. Punj Lloyd was also awarded the commissioning contract for the entire DVPL Project- for all four spreads. GAIL's Fax of Intent (FOI) intimating the grant of contract for laying of the pipelines for three spreads and for the commissioning of the entire pipelines of all four spreads was dated 05.05.2003 (Ex.PW2/2). The detailed Letter of Acceptance was issued on 14.05.2003 (Ex.PW2/3). The Contract Agreement was executed on 31.05.2003 (Ex.PW2/4).
5. The contractual time schedule for spreads I, II and III for laying pipeline, the completion schedule/period prescribed was as follows:-
SPREAD DETAILS COMPLETION PERIOD
I. Dahej to Vemar 7 Months up to pre-commissioning
II. Vemar to Sherpura 7½ Months up to pre-commissioning
III. Sherpura to Jhabua 7½ Months up to pre-commissioning
III. Jhabua to Jagoti 7½ Months up to pre-commissioning
The period of commencement of seven months/seven and a half months was
from 5.5.2003.
6. With respect to commissioning of the DVPL Project, the completion period (Clause 45.1 of the General Conditions of Contract (GCC)) prescribed for Dahej to Vemar was 3 weeks for overall commissioning; Vemar to Sherpura was 6 weeks for overall commissioning, as was in the case of Sherpura to Jhabua and Jhabua to Jagoti. As compared to the scheduled date for pre-commissioning being 19.12.2003 (seven or seven and a half months from 5.5.2003) and the scheduled date for commissioning of the entire DVPL Project as 30.1.2004, the actual
completion date for spreads I, II and III to the pre-commissioning stage was 22.2.2004 and the actual date of completion of commissioning of all the spreads was 10.4.2004. It is, therefore, seen that with respect to the pre- commissioning date there is a delay from 19.12.2003 to 22.2.2004 i.e delay of approximately 65 days. So far as the date of final commissioning of the complete DVPL Project is concerned, the actual date of completion was 10.4.2004 instead of 30.1.2004 i.e a delay of 71 days approximately.
7. GAIL deducted liquidated damages on account of the failure of the plaintiff to complete the works at intermediate dates fixed for the spreads I, II and III of the pipelines laying project. The defendant has not deducted any damages on account of delay caused beyond the final date for commissioning of the work inasmuch as, and as given in detail below, the defendant has given extension to the plaintiff for completion of the project upto 10.4.2004 while simultaneously levying interim liquidated damages as per Clause 57.2 of the SCC for failure of the plaintiff to meet interim deadlines/dates.
8. Punj Lloyd sued GAIL for the amounts deducted, apart from other claims. GAIL, in its written statement, inter alia, argued that:
"16. Para 16 of the Plaint is not only incorrect and frivolous, but the same is also an attempt on part of the Plaintiff to mislead this Hon'ble Court on fact. As a matter of fact, as per the records of contract performance maintained at site, there was a big Punch List towards pending works on part of the Plaintiff as on 05.02.2004 and the Plaintiff was attending Electrical/instrumentation/civil works at almost all SV stations during February/March, 2004. River protection works were pending at almost all crossing locations. Also pipe-line swabbing work (an activity required before Mechanical completion) was not done by the Plaintiff as per the specified
Item in the contract, and therefore, the contention of the Plaintiff is not correct that the Plaintiff's scope of work upto pre-commissioning stage was completed on 05.02.2004. In fact in the present para, the Plaintiff has stated only about the delay in achieving the final completion of the contract by the Plaintiff, while suppressing the fact that the Defendant had levied only Interim Liquidated Damages to the extent of 5.425% of the value of the contract in terms of Clause 57.2, and that there was no Liquidated Damages levied on the overall performance of the contract by the Plaintiff. As a matter of fact, the contract between the parties duly provided for Interim Liquidated Damages applicable against delays by the Contractor in achieving the agreed stipulated targets, "in addition to" the Liquidated Damages applicable against any delay in performance of the overall contract. In any event, the contract was being performed under the direct supervision of the Engineer-in- charge, whose decision on the said issue was agreed by the parties to be final and binding against them. It is submitted at the cost of repetition that the Plaintiff has not challenged the decision of the Engineer-in-charge at all and the same is binding against the parties."
9. Six issues were framed in this suit on 15.12.2008; the material issues, for the present purposes were No. 3 and No. 5:-
"3. Whether the levy of the liquidated damages by the defendant was not in accordance with the agreement between the parties and the law and whether the plaintiff is entitled to recover the suit amount or any other amount from the defendant? OPP
5. Whether the defendant could deduct intermediate liquidated damages? OPP"
10. To decide these issues, the conditions of the contract, particularly Clauses 26.1, 27, 57.1 and 57.2 were taken into account. These are as follows:
"26.1 CONDITIONS FOR FORCE MAJEURES In the event of either party being rendered unable by Force Majeures to perform any obligations required to be performed by them under the CONTRACT the relative obligation of the party affected by such Force Majeure shall upon notification to the other party be suspended for the period during which Force Majeure event lasts. The cost and loss sustained by the either party shall be borne by respective parties.
The term "Force Majeure‟ as employed herein shall mean acts of God, earthquake, war (declared or undeclared), revolts, riots, fires, floods, rebellions, explosions, hurricane, sabotage civil commotions and acts and regulations of respective Government of the two parties, namely the OWNER and the CONTRACTOR.
Upon the occurrence of such cause (s) and upon its termination, the party alleging that it has been rendered unable as aforesaid thereby, shall notify the other party in writing immediately but not later than 72 (Seventy-two) hours of the alleged beginning and ending thereof, giving full particulars and satisfactory evidence in support of its claim.
xxxx xxxxx
xxxxx
27.0 COMPENSATION FOR DELAY (LIQUIDATED
DAMAGES): 27.1 Time is essence of the CONTRACT. In case the CONTRACT fails to complete the WORK within the stipulated period then, unless such failure is due to Force Majeure as defined in Clause 26 here above or due to OWNER's defaults, the CONTRACTOR shall pay to the OWNER, by way of compensation for delay and not as penalty, a sum @ 1/2% (Half Percent) of the VALUE OF CONTRACT for delay per week on pro-rata for part thereof subject to a maximum of 10% (Ten percent) of the VALUE OF CONTRACT.
The parties agree that this is a genuine pre-estimate of the loss/damage which will be suffered on account of delay/breach on the part of the CONTRACTOR and the said amount will be payable on demand without there being any proof of the actual loss or damages caused by such delay/breach. The decision of the ENGINEER-IN-CHARGE in regard to applicability of Compensation for Delay shall be final and binding on the CONTRACTOR.
27.2 All sums payable by way of compensation under any of the conditions shall be considered as reasonable compensation without reference to the actual loss or damages which shall have been sustained.
xxxxxxxxxxxxxx
57.0 WORK IN MONSOON AND DEWATERING:
57.1 The execution of the WORKS may entail working in the monsoon also. The CONTRACTOR must maintain a minimum labour force as may be required for the job and plan and execute the construction and erection according to the prescribed schedule. No extra rate will be considered for such work in monsoon.
57.2 During monsoon and other period, it shall be the responsibility of the CONTRACTOR to keep the construction work site free from water at his own cost."
The relevant stipulations in the Special Conditions of Contract (SCC) and are as under:-
"57.0 COMPENSATION FOR DELAY/LIQUIDATED
DAMAGES
57.1 Clause No:27.0 of GCC, pertaining to Compensation For Delay (Liquidated Damages) stands modified to the following extent: 57.1.1 "Price Reduction/Liquidated Damages @ 2% of the total contract/order value per week or part thereof shall be
levied for delay in delivery/completion of work subject to a maximum of 20% of total contract/order value."
11. These conditions in the SCC underwent a change and the applicable clauses of Clause 57, additionally thereafter having Clauses 57.1.2, 57.2, 57.2.1, 57.2.2 and 57.3, read as under:
"57.2 Intermediate Compensation for Delay/Liquidated Damages 57.2.1 Pipeline Laying Schedule as per Appendix-XV to SCC shall be considered as contractual schedule for the purpose of determining intermediate compensation for delay, to be paid by Contractor to Owner, which shall be calculated on the following basis:
1. No compensation for delay shall be payable in case the cumulative progress at the end of month in lowering of pipeline is less upto 5% of corresponding cumulative length as per the above mentioned schedule.
2. For every 1% additional slippage beyond 5% as mentioned above in monthly cumulative scheduled progress, compensation for delay shall be levied @0.5% of contract value subject to maximum of cumulative 10% of contract value. With this provision, the compensation for delay shall get re-adjusted with recovery/improvement in progress by the Contractor in subsequent months, within the contractual completion period. For cumulative slippage resulting to compensation for delay exceeding 10% of contract value, other relevant provisions of contract document shall be applicable.
57.2.2 Intermediate compensation for Delay/Liquidated Damages stated in sub- clause 57.2.1 above shall be in addition to compensation for Delay/Liquidated Damages stated in sub- clause 57.1.1 of SCC.
57.3 The total liability of the contractor to Owner under sub- clause 57.1.1 of SCC on Compensation for Delay/Liquidated Damages and sub-clause 57.2 of SCC on Intermediate
Compensation for Delay/Liquidated Damages shall not exceed 20% (Twenty Percent) of contract value. The compensation on account of any liability (ies) other than above shall be as per provisions of bidding document."
15. For completion of narration it is noted that Engineers India Limited was a consultant of the defendant for the project and the Engineer-in-Charge of the project as per the definitional Clause 1.3 of the GCC was the person who was authorized by the defendant and the defendant authorized the concerned person of Engineers India Limited as the Engineer-in-Charge of the DVPL Project."
12. It was held by the learned single judge that:
"Admittedly, there were delays on the part of the plaintiff to complete the project, and as already stated above. Delays exist because the scheduled date for pre-commissioning was 19.12.2003 whereas the actual date for pre-commissioning for spreads I, II and III (falling to the share of the plaintiff) was 22.2.2004 and whereas the scheduled date for completion or commissioning of the entire DVPL Project was 30.1.2004, and the actual date of commissioning was 10.4.2004. Whereas the case of the plaintiff is that it was entitled to and was granted extension of time by the defendant for completion of the project, the case of the defendant is that though plaintiff was granted extension upto 10.4.2004; on which date the project was actually commissioned; however, the defendant is entitled to interim liquidated damages in terms of Clause 57.2 of the SCC on account of the plaintiff failing to meet intermediate deadlines/timelines. I have already reproduced above para 16 of the written statement, and I will refer to the admitted documents between the parties hereinafter, but one thing is an undisputed fact between the parties that the liquidated damages which have been levied upon the plaintiff by the defendant are not the liquidated damages as per Clause 57.1.1 of the SCC of delay beyond the final date of the complete project, but the liquidated damages are interim liquidated damages imposed in terms of Clause 57.2 with its various sub-clauses of the SCC as reproduced above. In sum and substance, the contract provided
for liquidated damages upto a maximum of 10% as interim liquidated damages and further liquidated damages not exceeding 10% on account of the liquidated damages beyond the contract completion final date as per Clause 57.1.1 of the SCC. Clause 57.2.2 of the SCC clarifies that interim compensation and the interim liquidated damages accordingly payable in terms of Clause 57.2.1 would be in addition to the liquidated damages payable as per Clause 57.1.1 of the SCC. Effectively, therefore a total of 10% interim liquidated damages and 10% of overall liquidated damages with respect to the last date fixed for commissioning of the DVPL Project was fixed as per the aforesaid terms of the contract, totaling to the total liquidated damages of 20%. We are in the present case only concerned with the issue as to whether the defendant was entitled to levy the interim liquidated damages of 5.425% of the value of the contract in terms of Clause 57.2 of the SCC."
13. After so holding, the learned single judge discussed the law applicable to damages, under Sections 73 and 74 of the Contract Act and held that only in the event of actual loss can damages be recovered, relying on Fateh Chand v Balkishan Dass AIR 1963 SC 1405. The difference between the grant of damages under Section 73 and 74 of the Indian Contract Act, besides Section 73 dealing with unliquidated damages and Section 74 dealing with the liquidated damages, is that Section 74 provides the upper limit of damages which can be granted subject to the condition that the liquidated damages specified are not in the nature of penalty. Punj Lloyd argued that neither were there breaches of contract by it inasmuch as time had been extended for overall completion of the contract, nor was monetary loss caused to the GAIL inasmuch as once there was extension of time, for overall completion of the project, no monetary loss for the interim delays could have been caused to the defendant.
14. It was held that:
"though there are breaches with respect to delays caused qua interim completion periods of the three spreads of the project granted to the plaintiff upto the stage of pre-commissioning inasmuch as the contractual date for pre-commissioning was 19.12.2003 with actual date of pre-commissioning being 22.2.2004, actually there are no legal breaches and no losses have been caused for the delays in completion of interim stages of the project to the defendant and the defendant has extended the period of final completion of the project till 10.4.2004, and admittedly by which date the entire spreads I, II and III were constructed by the plaintiff and the entire project from spreads I to IV were commissioned by the plaintiff for the defendant. These aspects of existence of breaches of delays at interim stages of completion of the spreads I to III upto the stage of pre-commissioning and whether any loss would have been caused to the defendant merely on account of such preliminary delays/breaches by failing to meet the interim completion dates, and grant of extension of time by the defendant to the plaintiff for completion of the final stage of the work by commissioning all the spreads I to IV, are subject matter of the following correspondences entered into between the Engineer- in-Charge of the project with the defendant; the defendant with the Engineer-in-Charge and the Engineer-in- Charge with the plaintiff:-
(i) Letter dated 21.4.2004 by the Engineer-in-Charge of the project to the defendant, Ex.PW2/6.
(ii) Letter dated 26/27.5.2004 of Engineer-in-Charge to the plaintiff, Ex.PW2/8.
(iii) Letter dated 3.7.2004 by the Engineer-in-Charge to the plaintiff, Ex.PW2/7.
(iv) Letter dated 5.7.2004 by the defendant to the Engineer-in- Charge, Ex.PW2/10.
(v) Letter dated 6.7.2004 by the Engineer-in-Charge to the plaintiff, Ex.PW2/11.
(vi) Letter dated 16.8.2004 by Engineer-in-Charge to the plaintiff, Ex.PW2/9.
(vii) Letter dated 1.8.2005 by the defendant to the plaintiff, Ex.PW2/14."
15. The learned single judge then analyzed the letter dated 21.4.2004 (Ex.PW2/6) of the Engineers India Ltd. The said letter inter alia, said that:
"5.0 EXTENSION OF TIME SCHEDULE The work of pipeline laying and commissioning was awarded to PLL under single contract. Though there are separate completion periods for laying of pipeline for spread I, II, III and for overall commissioning of pipeline system, the date of commissioning entire pipeline work, being last activity is considered as contractual date for completion of total work. Accordingly, extension of time schedule has been worked out w.r.t. last activity i.e commissioning of Pipeline System. Although pre- commissioning of Spreads in PLL scope (Spread I, II &III) was delayed by 65 days but it has not delayed the commissioning of pipeline system. From para 4.2, following has been observed:
i) PLL has started Gas-in-activity on 29th February'04 immediately after gas for commissioning was made available. The commissioning of pipeline system and Performance Test Runs were completed on 10th April '04.
ii) The last section taken up for commissioning was Spread IVA. The commissioning for this section was taken up on completion of pre-commissioning activities by other contractor.
Therefore, completion of Pipeline System was governed by availability of gas from owner and readiness of spread IVA by other contractor. In view of above, we are of the opinion that the time schedule for completion of entire work shall be
extended to the actual date of completion of commissioning i.e upto 10th April' 04.
6.0 COMPENSATION FOR DELAY/LIQUIDATED DAMAGE
6.1 INTERMEDIATE COMPENSATION FOR DELAY/LIQUIDATED DAMAGE As on 15th Dec.' 03, the extended date worked out for completion of lowering of pipeline (as indicated under para 4.1.3 above), total 358.412 KM of lowering was completed in 425.905 KM length of pipeline. Accordingly, the progress of lowering of pipeline works out to be 84.15% as against scheduled requirement of 100%, which amounts to delay in lowering of pipeline by 15.85%.
In line with para 2.2.2 above, the liquidated damage shall be leviable on slippage above 5% i.e on 10.85% (15.85-5.00). Liquidated damage for this slippage works out to be 5.425% of contract value @ ½% of contract value for delay of 1% in lowering (with a ceiling of 10% of contract value).
6.2 FOR DELAY IN COMPLETION OF ENTIRE WORK As seen under para 4.2.2. above, there is no delay in completion of commissioning activity by PLL. Therefore, no liquidated damage is leviable on this account.
xxxxxxxxxxxxxx
7.0 CONCLUSION & RECOMMENDATION
In view of what has been analyzed under para 6.0 above, EIL recommends the following:
7.1 Extension of time period to PLL for completion of pipeline lowering upto 15th Dec.'03 and entire work upto 10th April' 04 (till commissioning of entire systems) without compensation for extended stay or any other claim, may be granted.
7.2 No liquidated damage on account of delay in completion of commissioning is recommended.
7.3 Liquidated damage on PLL on account of intermediate delay equivalent to 5.425% of contract value is applicable.
xxxxxxxxxxxxxxxx Keeping in view the best effort made by contractor for timely completion in line with project/commissioning requirement of pipeline for his own as well as other's (RNGS) scope of work in spite of various difficulties encountered during execution. And also considering our above recommendation for extension of contract for entire work completion upto 15.04.04 without levying compensation for delay/LD, GAIL may consider to condone the intermediate compensation for delay/liquidated damages as stated in para 7.3 above. While on the subject, it may be appreciated that the purpose of intermediate LD is basically to pressurize the contractor for achieving intermediate milestones which in turn ensures the final completion of job in time.
GAIL may further examine the recommendation and take final decision on the issue at the earliest, considering the above and the fact that "Gas-in" as well as commissioning of entire pipe line was not delayed.
Thanking you and assuring you of our best services at all times, Very truly yours, Sd/-
16. GAIL's letter dated 5.7.2004 (Ex.PW2/10) to Engineers India Ltd observed as follows:
"GAIL management has accepted your recommendations towards extension of contractual completion time period upto 10.04.2004 with an imposition of compensation for delay up to 5.425% of the executed contract value. Accordingly, the same may be communicated to M/s PLL."
17. The letter, dated 6.7.2004 (Ex.PW2/11) was relied on. Another letter dated 16.8.2004 (Ex.PW2/9) was noticed and quoted by the learned single judge. It stated that:
"Sub: Final Time Extension-Pipe laying & Association facilities-Sp-I, II & III. Ref: LOA No.GAIL/NOIDA/C&P/4844/02-134-006/C-369 dated 14.05.03. Dear Sir, This has reference to your letter No.PLL/PROJ/PIIN01/116/099 dated 09.06.2004, PLL/PROJ/PIIN01/116/098 dated 09.06.2004 and PLL/DVPL/PIIN01/101/535 dated 14.07.04 regarding final time extension for aforementioned contract. The following had been considered in recommending final extension of time for above referred contract in line with contract provisions.
1. The contract of Spread-I, II & III upto "GAS-IN" has been considered as one contract in line with ITB clause 34.3. The overall completion upto 10th April 2004 has been granted with intermediate compensation for delay/Liquidated Damages limited to 5.425% of contract value.
2. The delay due to rain has been considered as per contract provisions. The delay of Seventeen days has been considered for Dahej to Vemar Section. In spread II and III, the delay of one and two days respectively has been considered. All the above delays have been concurrent.
3. The delay of two days has been considered for stoppage of work in ROU in Dahej to Vemar Section.
4. The delay of fifteen days has been considered due to delay in forest clearance in Spread II.
5. Accordingly, the contractual completion time for lowering has been extended upto 15th Dec‟03 in line with SCC Clause 4.5 and GCC Clause 45.1. The lowering completed on 15th Dec‟03 was 358.412 KM against total 425.905 KM. The intermediate Compensation for Delay/LD against lowering works out to be 5.425% of contract value as per contractual provisions i.e. SCC Clause 57.2.
6. No price Reduction/Liquidated Damages against SCC Clause 57.1.1. have been levied for delay in overall completion of works.
7. The total liability under sub clause 57.1.1 of SCC on Compensation for Delay/Liquidated Damages and sub clause 57.2 of SCC on intermediate Compensation for Delay/Liquidated Damages has been restricted to 5.425% of contract value as per the provisions of the contract. Thanking you, Very truly yours, Sd/-
18. According to the learned single judge, a cumulative reading of the said portions of the letters Ex.PW2/6, PW2/10, PW2/11 and PW2/9 showed two aspects: one, that no liquidated damages were imposed with respect to overall completion of the project/works and two liquidated damages were only imposed in terms of Clause 57.2 of the SCC towards intermediate compensation for delay, and being restricted to 5.425% of the contract value. He then rendered his findings as follows:
"22. The facts of the present case are very peculiar with respect to the issue as to whether or not legally, the liquidated damages being the interim liquidated damages for interim delays, ought or ought not to be imposed i.e whether such damages are legally allowable or not legally allowable as per Section 74 of the Indian Contract Act. In order to answer this issue, it is required to be noted that failure to meet intermediate compliance schedules of spreads I to IV with their scheduled dates of completion would not have caused monetary losses to the defendant as actual transportation of gas through the pipelines laid was not envisaged on completion of interim stages of spreads I to III. What is being stated by this Court is that it is not as if there was a commencement point at the beginning of spread I with a point of delivery at the end of spread I or spread II or spread III, i.e commencement of delivery of gas to a customer by commencement of
transportation at spread I with ending at end point of spread I or spread II or delivery point commencing for that matter at the beginning of spread II to end at spread II with the end point of spread II or spread III etc etc. Meaning thereby, there was no transportation of gas to be done at any midpoint between spreads I to IV and the supply of gas by the defendant to its customers was only to be at the end point of spread IV. Therefore unless the entire pipeline was laid down for the four spreads and commissioning of the same was also done, there was no question of gas being supplied by the defendant to its customer viz Petronet LNG and which was only at the end point of spread IV. In these peculiar facts, even if therefore there existed interim delays of completion of stages of spreads I to IV, once the defendant gives extension of time for completion of the project till the project was actually commissioned on 10.4.2004, intermediate dates of completion and breaches would not result in any loss of profits or any other monetary loss to the defendant on account of the facts that on account of these delays there was no failure of the transportation of the gas by the defendant to any of its customers including Petronet LNG i.e no loss of profits to the defendant. In my opinion, therefore, in the peculiar facts of this case, defendant was not entitled to fix and demand liquidated damages for interim delays from the plaintiff as interim delays have not caused any monetary loss to the defendant once the project completion date upto commissioning was extended upto 10.4.2004 by the defendant as evident from Ex.PW2/10, Ex.PW2/11, and Ex.PW2/9 dated 5.7.2004, 6.7.2004 and 16.8.2004 respectively as reproduced above. It is not the case of the defendant that liquidated damages have been levied for delay in final completion of works inasmuch as the final date of completion stands extended to 10.4.2004, and the case of the defendant is only of interim compensation for delays in not meeting interim timelines. This stand of the defendant becomes abundantly clear from paras 6 and 7 of Ex.PW2/9 dated 16.8.2004 of the Engineer-in-Charge to the plaintiff and para 16 of the written statement of the defendant. Thus two aspects emerge of firstly of the damage amount claimed by the defendant from the plaintiff being
5.425% of the contract and secondly that this is the figure of interim liquidated damages in terms of the written statement and the documents Ex.PW2/6, Ex.PW2/10, Ex.PW2/11 and Ex.PW2/9. Therefore, the only claim of the defendant is towards interim liquidated damages but interim breaches of contract in the facts of the case have not caused any monetary loss to the defendant and therefore for the defendant to claim interim liquidated damages from the plaintiff.
23. In view of the above, issue nos.3 to 5 are decided in favour of the plaintiff and against the defendant and it is held that since no monetary loss was caused to the defendant by any delay caused by the plaintiff for failure to meet interim timelines for the interim stages of performance during the spreads I to III of the contract, hence, plaintiff is not liable to pay any liquidated damages to the defendant under Clause 57.2 of the SCC. For the sake of completion of discussion, I would like to note that there is no evidence led on behalf of the defendant with respect to any monetary loss suffered for any failure to comply with the interim timeline by the plaintiff, and which in my opinion, in any case, would not have been possible in the facts of the present case as stated above because the issue of transportation of gas was only after civil works of laying of the pipelines from commencement of spread I to spread IV was completed and also the commissioning took place of the entire DVPL Project by the transportation of gas in the pipeline from the commencement of spread I to the end of spread IV.
Relief
24. In view of the above, the suit of the plaintiff is decreed against the defendant for an amount of Rs.17,79,76,710/- plus Indian equivalent of US$ 7,79,536 as on the date of the filing of the suit i.e Rs.3,17,62,194.32/-. I may note that in view of the judgment of the Supreme Court in the case of Forasol Vs. Oil and Natural Gas Commission, AIR 1984 SC 241, plaintiff has exercised the option of conversion of US dollar into Indian rupees as on the date of the filing of the suit. On the date of the
filing of the suit the conversion rate of dollar into Indian rupees was Rs.40.7450/- for every US dollar. The suit is therefore decreed for a total amount of Rs.20,97,38,904.32/-. Plaintiff is also entitled to interest pendente lite and future till payment @ 6% per annum simple in view of Section 34 CPC. In the peculiar facts of this case, however, parties are left to bear their own costs. Decree sheet be prepared."
Arguments in appeal:
19. Sh. Sanjay Jain, learned Additional Solicitor General appearing for GAIL argued that the impugned judgment is unsustainable for the reason that the rule of damages enunciated in ONGC v. Saw Pipes 2003 (5) SCC 705, was overlooked. The Supreme Court had clearly stated that where the agreement unambiguously recorded/stipulated liquidated damages in the case of breach of contract, unless it is found that the estimate of damages or compensation was unreasonable or was not genuine or was by way of penalty, the party committing breach had to pay that amount and the party complaining of the breach was not under an obligation to prove actual loss. It was argued that the learned Single Judge failed to appreciate that the extension time of the entire contract, particularly the commissioning contract was conditioned upon payment of interim liquidated damages at 5.425% of the contract value in terms of the provisions, i.e. Clause 57.2. Furthermore, importantly, the EIL's letter dated 06.07.2004 and the letter dated 16.08.2004 (by GAIL) also pointed to a qualified extension with the imposition of levy of intermediate liquidated damages. Significantly, the levy of such intermediate liquidated damages was never disputed at the time it was granted in August, 2004.
20. GAIL urges that the impugned judgment is in error of law in holding that, "no loss had occurred due to intermediate delays when though the parties had expressly and unambiguously agreed that the intermediate delay in lowering of pipelines would result in losses and that 1/2% of the contract value per week or part thereof (subject to a maximum of 10%) was a genuine pre-estimate of such losses and that the said stipulation was not a penalty. The said finding of the learned Single Judge is contrary to the intention of the parties and amounts to rewriting the terms of the contract which is impermissible in law."
21. It is argued that the learned Single Judge erred in presupposing the loss caused by delayed transportation of gas to customers (given by the loss for GAIL as a result of delay of work by Punj Lloyd). It is next urged that the interpretation of the expression "in addition to" in clause 57.2 clarified that such intermediate liquidated damages was unconnected with the independent liquidated damages stipulated in clause 57.1.1. As a corollary, losses due to delay in intermediate milestones were in addition to and independent of the losses that the parties contemplated would arise in the completion of the entire contract.
22. Learned ASG referred to the impugned judgment and submitted that the evidence led in the form of letters written by EIL and GAIL with respect to unsatisfactory progress of the work at site, was not even adverted to or considered by the learned Single Judge. Learned counsel relied upon a letter dated 16.09.2003 (Ex. DW-1/4) which had rejected overlooking of delays in mobilization of equipment; letter of 18.09.2003 (Ex. PW-1/5) with respect to inadequate mobilization of equipment, shifting of equipment to other
stretches that affected work progress and the letter of EIL dated 25.09.2003 (Ex. D-1/6) which conveyed the satisfaction with the progress of work. Likewise, reliance was also placed upon the letters [Ex. PW-1/9, 1/10, 1/11 and 1/16]. The last, i.e. PW-1/16 was emphasized to highlight that Punj Lloyd had failed to appreciate farmers' grievances at the work site which in turn harmed the GAIL resulting in several disputes. The other letters with respect to indifferent progress in various areas such as defective planning, consistently falling behind the agreed schedules etc. were relied upon.
23. Learned counsel relied upon Maula Bux v.UOI 1969 (2) SCC 554, to highlight that it is not in every case of breach of contract that the person aggrieved is expected to prove actual loss or damages before the Court and the Court is within powers to award reasonable compensation even if no actual damages is proved to be suffered. It is highlighted that in Maula Bux (supra) the Court held that in case of breach of some contracts, it may be impossible for the court to assess compensation arising from the breach while in other cases, compensation can be calculated in accordance with established rules. Where the Court is unable to assess the compensation, the sum named by the parties, if it be recorded as a genuine pre-estimate may be taken into consideration as a measure of reasonable compensation. But not if the sum named is in the nature of a penalty. Learned counsel also relied upon H.M. Kamaluddin Ansari and Co. v. Union of India 1983(4) SCC 417, to say that in a contract such as the present, it was open to GAIL to appropriate any sum payable to contractors. Learned ASG also relied upon the ruling in Construction and Design Services v. Delhi Development Authority 2015 (14) SCC 263). The Court observed as follows:
"14. There is no dispute that the appellant failed to execute the work of construction of sewerage pumping station within the stipulated or extended time. The said pumping station certainly was of public utility to maintain and preserve clean environment, absence of which could result in environmental degradation by stagnation of water in low lying areas. Delay also resulted in loss of interest on blocked capital as rightly observed in para 7 of the impugned judgment of the High Court. In these circumstances, loss could be assumed, even without proof and burden was on the appellant who committed breach to show that no loss was caused by delay or that the amount stipulated as damages for breach of contract was in the nature of penalty. Even if technically the time was not of essence, it could not be presumed that delay was of no consequence. Thus, even if there is no specific evidence of loss suffered by the respondent-plaintiff, the observations in the order of the Division Bench that the project being a public utility project, the delay itself can be taken to have resulted in loss in the form of environmental degradation and loss of interest on the capital are not without any basis."
24. Sh. J.P. Sengh, learned senior counsel appearing for Punj Lloyd relied upon Ex. PW-2/6, i.e. the letter of the EIL, making its recommendations to GAIL. He emphasized that Punj Lloyd, despite severe monsoon, continued to work to the utmost extent possible and that its overall conduct was such that even though levy of intermediate delay/liquidated damages had been indicated in para 6, EIL went on to say that:
"7.0 CONCLUSION & RECOMMENDATION
In view of what has been analyzed under para 6.0 above, EIL recommends the following:
7.1 Extension of time period to PLL for completion of pipeline lowering upto 15th Dec. 03 and entire work upto 10th April 04 (till commissioning of entire systems) without compensation for extended stay or any other claim, may be granted.
7.2 No liquidated damage on account of delay in completion of commissioning is recommended.
7.3 Liquidated damage on PLL on account of intermediate delay equivalent to 5.425% of contract value is applicable.
It has also been noticed that during severe and extended monsoon, the contractor proactively continued the work to the extent possible, even at high cost, without resorting for stoppage which would have entitled them for time extension. Also, the contractor took the risk of executing the work in forest areas, even without formal clearance of statutory authorities by close interaction with local authorities/GAIL in the overall interest of the project.
It will not be out of place to mention here that the contractor extended all possible help to GAIL/EIL in completing the offloaded work of other contractor, M/s. RNGS who failed miserably. This in turn resulted in timely completion/commissioning of DVPL pipeline and commitments made by GAIL to M/s. Petronet LNG could be honoured.
Keeping in view the best effort made by contractor for timely completion in line with project/commissioning requirements of pipeline for his own as well as other's (RNGS) scope of work in spite of various difficulties encountered during execution. And also considering our above recommendation for extension of contract for entire work completion upto 15.04.04 without levying compensation for delay/LD, GAIL may consider to condone the intermediate compensation for delay/liquidated damages as stated in para 7.3 above.
While on the subject, it may be appreciated that the purpose of intermediate LD is basically to pressurize the contractor for achieving intermediate milestones which in turn ensures the final completion of job in time."
25. Learned counsel contrasted the language of clause 27.1 of the General Conditions of Contract which specifically talked about time being of essence of the contract and also stipulated compensation "not as a penalty a
sum @ ½ % (half percent) of the value of contract for delay per week on pro-rata for part thereof subject to a maximum of 10% (ten percent) of the value of the contract. The parties agree that this is a genuine pre-estimate of the loss/damage which will be suffered on account of delay/breach on the part of the contractor and the said amount will be payable on demand without there being any proof of the loss of such loss or damages caused by such delay/breach." It was submitted that the original clause 57.2, especially the payment of intermediate compensation for delay/liquidated damages did not exist and parties introduced it after the agreement. This provision did not, significantly, mention that the damages or compensation for delay was a genuine pre-estimate of the loss. The contrast in the language, according to the learned counsel, was significant in that it did not relieve GAIL of the onus of establishing and proving actual loss. It was, therefore, submitted that the rule that not in all cases is an aggrieved party obliged to prove loss, and that there can be some cases where it can be relieved of such burden, is inapplicable to the facts of the present case.
26. Learned senior counsel argued that in the present case, the findings of the learned Single Judge as to the actual conduct of the contract show that in fact there was no delay in the performance of the commissioning contract and as a consequence there was no loss to GAIL. In the circumstances, the case law relied upon by it, i.e. Maula Bux (supra) were inapt. Learned counsel relied upon the judgment reported as Kailash Nath Associates v. DDA (2015) 4 SCC 136, to say that only reasonable compensation in respect of the incurred or suffered losses/damages can be accepted by the aggrieved party. In these circumstances, the letter of EIL recommending extensions on the one hand and at the same time saying that
the conduct of Punj Lloyd was such that intermediate delayed compensation should not be levied, was a powerful factor that weighed against the award of damages or entitled GAIL to take such amounts on the automatic assumption of loss. GAIL, as a matter of fact, did not lead any evidence or prove loss and could not, therefore, claim any amount in that regard. Cross objection
27. Learned senior counsel argued that the plaintiff/Punj Lloyd's cross-objection in this appeal highlights that the suit filed was for recovery of US$ 779536.21 and the amount sought for in final relief was in Indian Rupees solely for the purpose of calculating court fees. It was urged that the learned Single Judge while decreeing the suit should have applied the exchange rate for payment of US$ and not the rates prevailing at the time of the suit. It was also argued importantly, that the learned single judge accepted the plaintiff's contentions but did not grant any pre-suit interest which has been specifically sought @ 12%. In this regard, it was submitted that the suit had claimed `29,15,07,084.80 together with interest @ 18% per annum from 04.07.2004, i.e. from the date of cause of action when the amounts were deducted on the assumption of liability. In the absence of any reasons, learned Single Judge could not have refused the grant of any interest for the pre-suit period. That the decree granted pendente lite and future interest only highlighted the learned Single Judge's awareness that withholding of sums due could result in severe economic consequences. The omission to adduce any reasons for refusing to grant interest on a substantial amount for three years, i.e. the pre-suit period was, therefore, a clear error of law. Learned counsel highlighted that having regard to the totality of circumstances, the rate claimed, i.e. 18% was justified and legal.
Analysis and Conclusions
28. Kailash Nath Associates (supra) is an authority of recent vintage on the question of the power of the principal to invoke the performance guarantee condition, notwithstanding its inability to recover liquidated damages specified in a contract. The Supreme Court had considered the law in Fateh Chand's case (supra) and several other decisions, and held as follows:
"The law laid down by a Bench of 5 Judges in Fateh Chand's case is that all stipulations naming amounts to be paid in case of breach would be covered by Section 74. This is because Section 74 cuts across the rules of the English Common Law by enacting a uniform principle that would apply to all amounts to be paid in case of breach, whether they are in the nature of penalty or otherwise.
43. On a conspectus of the above authorities, the law on compensation for breach of contract under Section 74 can be stated to be as follows:
1. Where a sum is named in a contract as a liquidated amount payable by way of damages, the party complaining of a breach can receive as reasonable compensation such liquidated amount only if it is a genuine pre-estimate of damages fixed by both parties and found to be such by the Court. In other cases, where a sum is named in a contract as a liquidated amount payable by way of damages, only reasonable compensation can be awarded not exceeding the amount so stated. Similarly, in cases where the amount fixed is in the nature of penalty, only reasonable compensation can be awarded not exceeding the penalty so stated. In both cases, the liquidated amount or penalty is the upper limit beyond which the Court cannot grant reasonable compensation.
2. Reasonable compensation will be fixed on well known principles that are applicable to the law of contract, which are to be found inter alia in Section 73 of the Contract Act.
3. Since Section 74 awards reasonable compensation for damage or loss caused by a breach of contract, damage or loss caused is sine qua non for the applicability of the Section.
4. The Section applies whether a person is a plaintiff or a defendant in a suit.
5. The sum spoken of may already be paid or be payable in future.
6. The expression "whether or not actual damage or loss is proved to have been caused thereby" means that where it is possible to prove actual damage or loss, such proof is not dispensed with. It is only in cases where damage or loss is difficult or impossible to prove that the liquidated amount named in the contract, if a genuine pre-estimate of damage or loss, can be awarded.
7. Section 74 will apply to cases of forfeiture of earnest money under a contract. Where, however, forfeiture takes place under the terms and conditions of a public auction before agreement is reached, Section 74 would have no application."
29. In ONGC (supra), after noticing Maula Bax (supra) the Supreme Court held that in certain eventualities parties may contemplate payment of damages or compensation to cater to specific situations because the quantification of such damages by evidence is impossible or impracticable.
The Court observed as follows:
"Under Section 73, when a contract has been broken, the party who suffers by such breach is entitled to receive compensation for any loss caused to him which the parties knew when they made the contract to be likely to result from the breach of it. This section is to be read with Section 74, which deals with penalty stipulated in the contract, inter alia (relevant for the present case) provides that when a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, the party complaining of breach is entitled, whether or not actual loss is proved to have been caused, thereby to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named. Section 74 emphasizes that in case of breach of contract, the party complaining of the breach is entitled to receive reasonable compensation whether or not actual loss is proved to have been caused by such breach. Therefore, the emphasis is on reasonable compensation. If the compensation named in the contract is by way of penalty, consideration would be different and the party is only entitled to reasonable compensation for the loss suffered. But if the compensation named in the contract for such breach is genuine pre-estimate of loss which the parties knew when they made the contract to be likely to result from the breach of it, there is no question of proving such loss or such party is not required to lead evidence to prove actual loss suffered by him.
67........In our view, in such a contract, it would be difficult to prove exact loss or damage which the parties suffer because of the breach thereof. In such a situation, if the parties have pre- estimated such loss after clear understanding, it would be totally unjustified to arrive at the conclusion that the party who has committed breach of the contract is not liable to pay compensation. It would be against the specific provisions of Section 73 and 74 of the Indian Contract Act. There was nothing on record that compensation contemplated by the parties was in any way unreasonable. It has been specifically
mentioned that it was an agreed genuine pre- estimate of damages duly agreed by the parties. It was also mentioned that the liquidated damages are not by way of penalty. It was also provided in the contract that such damages are to be recovered by the purchaser from the bills for payment of the cost of material submitted by the contractor. No evidence is led by the claimant to establish that the stipulated condition was by way of penalty or the compensation contemplated was, in any way, unreasonable. There was no reason for the Tribunal not to rely upon the clear and unambiguous terms of agreement stipulating pre-estimate damages because of delay in supply of goods. Further, while extending the time for delivery of the goods, the respondent was informed that it would be required to pay stipulated damages."
30. Again, in Bharat Sanchar Nigam Ltd v Reliance Communication Ltd 2011 (1) SCC 394, it was observed by the court, that:
"17. According to Chitty on Contracts "whether a provision is to be treated as a penalty is a matter of construction to be resolved by asking whether at the time the contract was entered into the predominant contractual function of the provision was to deter a party from breaking the contract or to compensate the innocent party for breach. The question to be always asked is whether the alleged penalty clause can pass muster as a genuine pre-estimate of loss". (See para 26-126 of Chitty on Contracts, 30th edition) The fact that damage is difficult to assess with precision strengthens the presumption that a sum agreed between the parties represents a genuine attempt to estimate it and to overcome the difficulties of proof at the trial. According to the Law of Contract by G.H. Treitel (10th edition), a clause is penal if it provides for "a payment stipulated as in terrorem of the offending party to force him to perform the contract. If, on the other hand, the clause is an attempt to estimate in advance the loss which will result from the breach, it is a liquidated damages clause. The question whether a clause is penal or pre-estimate of damages
depends on its construction and on the surrounding circumstances at the time of entering into the contract". Lastly, the fact that a sum of money is payable on breach of contract is described by the contract as "penalty" or "liquidated damages" is relevant but not decisive as to categorization."
31. GAIL'S argument is that the parties' agreement that intermediate delay compensation, at the agreed rate was a genuine pre-estimate of liquidated damages that Punj Lloyd agreed to pay to it, if there were indeed delays. Punj Lloyd does not dispute that the clause was agreed to voluntarily; it however premises its resistance to the appeal, on the argument that sans proof of actual loss suffered, the amount could not be recovered from it, and further that the overall commissioning was not delayed.
32. The commissioning of the three spreads was over a period of 7 to 7½ months each. The performance of these contracts, treated as one whole meant that Punj Lloyd had to ensure that equipment was in place, the requisite material and men were on site and all necessary work (welding, joining etc) was done according to a pre-arranged schedule. Now, there is no dispute that there were intermediate delays - to the extent of about 65 days. If one sees from the perspective of the contractor (Punj Lloyd) that this did not impact the final commissioning schedule, undoubtedly the imposition of the liquidated damages clause would seem unjustified. However, two aspects are to be kept in mind here: first, that when bidding was done, there was every likelihood of different contractors being declared successful in respect of different spreads, which would have meant that as far as they were concerned this condition was essential to ensure compliance with timelines. That one party (Punj Lloyd) secured three spreads was providential, perhaps
a coincidence. Secondly, the objective of this condition was to ensure that timelines were adhered to. For instance, if one spread were completed in time and the other not completed in time, there could potentially be an adverse impact on the commissioning/overall pipeline laying schedule. Furthermore, at the time when the delays occurred, the final picture was unknown. The nuanced nature of the condition, introduced as an amendment meant that the parties were alive to these details and voluntarily agreed that such compensation was recoverable. The court finds insubstantial the argument of Punj Lloyd that omission to the reference to the liquidated damages from the later condition, agreed to by the parties, meant that necessarily GAIL had to prove actual damage, to recover the amounts agreed. It is well settled that the nature of a condition does not depend on its nomenclature, but on its effect having regard to the overall circumstances of the case.
33. Punj Lloyd's position that certain events (excessive rainfall, delayed forest clearance and hold up on account of villagers' ire) being the reason for delays, in the opinion of the court, are not sufficient to absolve its liability. When it accepted the contract, it was aware of the possibility of rainfall in the areas where it had to operate; this included inclement conditions such as excessive rainfall, etc. Its inability to provide and plan in certain matters (welding, etc) despite these conditions, actually indicates its failure. It is not unknown for such activities to be performed in extreme weather conditions. The challenge is to perform the job in the agreed time, ensuring that all resources are deployed. Likewise, this court was not shown anything to suggest that forest clearance or permissions were outside Punj Lloyd's
domain. They certainly were not force majeure situations. Therefore it could not have legitimately sought shelter because of those facts, to claim immunity from payment of compensation.
34. These considerations apart, there is sufficient correspondence after the letter dated 21 July 2003 (i.e. Ex. DW-1/4, DW-1/5 and DW-1/6, DW-1/9, DW-1/11 and DW-1/16 clearly shows that even after August, 2003, EIL, the consultant, repeatedly wrote to Punj Lloyd about slippages in work and delay in completion within the scheduled time agreed in the spreads for which contracts were awarded. These, in the opinion of the court, emphasize that the consultant and GAIL were concerned about the timely performance of the contract, evident from close monitoring of the progress of work at site. Besides, Punj Lloyd does not appear to have in any meaningful manner, registered its protest contemporaneously with respect to the decision communicated that liquidated damages would be levied for the intermediate period delays.
35. This court is of the opinion that considering all these materials on record, the stipulation in clause 57.2.1and the amounts deducted were by way of liquidated damages and a genuine pre-estimate of the loss calculated in monetary terms. They were not merely precautionary conditions not meant to be enforced, but conditions that could be insisted upon, as is evident from clause 57.2.2, which clarifies that"compensation for Delay/Liquidated Damages stated in sub- clause 57.2.1 above shall be in addition to compensation for Delay/Liquidated Damages stated in sub-clause 57.1.1 of SCC." Furthermore, the overall cap on damages at 20% (Clause 57.3) includes intermediate liquidated damages contemplated under clause 57.1.1.
These intermediate delay liquidated damages were of the kind contemplated in Maula Bux (supra) and Bharat Sanchar Nigam (supra), which the parties agreed, would be payable by one of them (Punj Lloyd) without proof of actual loss.
36. For the above reasons, this court is of the opinion that the appeal should succeed. The impugned judgment and decree is set aside; consequently Punj Lloyd's suit is dismissed. The appeal is accordingly allowed. Punj Lloyd's cross objections to the appeal too, for the above reasons, have to fail. The appeal is allowed and cross-objections are dismissed.
S. RAVINDRA BHAT (JUDGE)
YOGESH KHANNA (JUDGE) MAY 8, 2017
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!