Citation : 2017 Latest Caselaw 1378 Del
Judgement Date : 15 March, 2017
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Reserved on: January 19, 2017
Date of decision: March 15, 2017
+ CS (OS) 352/2015
V3S INFRATECH LTD. ..... Plaintiff
Through: Mr Sunil Gupta, Senior Advocate with
Mr. Praveen Kumar Singh, Mr. Utkarsh Singh,
Md. Ziauddin Ahmad, Advocates.
versus
NBCC & ORS. ..... Defendants
Through: Mr. Sanjeev Mahajan, Advocate for D-1.
Ms. Archana Gaur, Advocate for Defendant Nos. 2
and 4.
CORAM: JUSTICE S. MURALIDHAR
JUDGMENT
% 15.03.2017
IA No. 2786/2015 (under Order XXXIX Rules 1 and 2 CPC) IA No. 7330/2015 (Objections filed by the Defendants to the report of the LC) IA No. 16470/2015 (under Order XII Rule VI CPC by Plaintiff seeking decree against admission) IA No. 24532/2015 (under Section 51 for refraining Defendant No. 1 from encashing the Bank Guarantee)
Background facts
1. The background to these four applications is that the Plaintiff, V3S Infratech Ltd., which is engaged in the business of civil construction, was
awarded a contract for the work of "Construction of 200 Bedded Referral Hospital & other facilities for Central Para Military Forces (CPMF) at Greater Noida" for which a contract was executed between the Plaintiff and NBCC Ltd. („NBCC‟) (Defendant No. 1) on behalf of the Indo-Tibetan Border Police („ITBP‟) (Defendant No. 2) on 23rd June, 2011.
2. The estimated price of the work was Rs. 96,00,04,000. This was worked out on the basis of the rates quoted by the Plaintiff on the Bill of Quantities („BOQ‟) of the tendered documents. Pursuant to the contract, the Plaintiff submitted a Security Deposit-cum-Performance Bank Guarantee in the sum of Rs.4,80,00,200 (being 5% of the estimated cost) by way of a Performance Bank Guarantee („PBG‟) dated 5th July, 2011 issued by the Punjab National Bank („PNB‟) (Defendant No. 3). It may be mentioned herein that the said PBG has been extended from time to time.
3. The date of commencement of the work was agreed to be the 10th day of issue of the Letter of Intent („LOI‟) (dated 16th June, 2011) and the works as detailed in the tender were to be executed and completed within 24 months from the date of commencement. The stipulated date of completion thus worked out as 25th June, 2013.
4. The case of the Plaintiff is that it mobilised the site within the described time and the requisite tool, plant and machinery, labour and staff were deployed at the site promptly for the timely completion of the works. It is further stated that on the basis of the Tentative Macro Construction Schedule submitted to NBCC on 14th May, 2011, the Plaintiff on 25th June, 2011 submitted the Final Good for Construction („GFC‟) Drawing Release
Schedule for the works.
5. According to the Plaintiff, NBCC "miserably failed to adhere to the timeline" for the release of the GFC drawings. It is submitted that the schedule of work submitted by the Plaintiff was dependent on timely release of the drawings. According to the Plaintiff, the drawings which were requested on 8th July, 2011 were received by the Plaintiff only on 25 th August, 2011. Likewise, the GFC drawings for the Foundation Level Column details were received after a delay of 135 days. The Basement Slab Beam Reinforcement details were received after a delay of 95 days, ramp details were received on 7th November, 2011 after a delay of 95 days.
6. By letters dated 14th December, 2011 and 20th December 2011, the Plaintiff reminded NBCC that the authorised layout plans such as light and power circuit layout plan, T.V., telephone and computer conduit layout plan, fire alarm layout plan etc. along with certain other working drawings and details were yet to be received. Further, there were discrepancies in the working drawings received by the Plaintiff. In some of them, certain sections, reference numbers etc. were missing and this caused further delay in the execution of the works. The Plaintiff‟s case is that the delay was solely attributable to NBCC.
7. By further letters dated 23rd April 2012, 7th September, 2012 and 21st September 2012, the Plaintiff reminded NBCC that the aforementioned details pertaining to column schedule of all floors, internal painting, ceiling plans of all floors, terrace layout for slope, terrace waterproofing, terrace garden and sections, mumty slab, SS and MS railing details, sanitary and
plumbing details, Machine Room's structural and architectural Drawings, toilet layout plans etc. were pending with NBCC.
8. It is stated that meetings were held between the Plaintiff NBCC and ITBP on several dates. On 14th January, 2012, it was pointed out by ITBP that the progress of work till then was not satisfactory. At a further meeting held on 19th January, 2012, the position was the same. It was further noticed that various enabling features were not provided at the site. By 23rd January 2012 against a target of Rs.8.93 crores, the Plaintiff had achieved only work of a value of Rs. 3.60 crores. At the meeting held on 1st June, 2012, NBCC asked the Plaintiff to complete the work by June 2013.
9. On 19th June, 2012, it was again pointed out by NBCC that the progress of work was slow. This was reiterated on 26th June, 2012. Against the target of Rs. 227 lakhs for the said month, work of a value of only Rs. 54 lakhs was completed. At the meeting on 11th July, 2012, ITBP expressed its displeasure that between April and June 2012 only a turnover of Rs. 265 lakhs was achieved against a target of Rs. 504 lakhs.
10. At the meeting held on 10th December, 2012, the Plaintiff agreed that the minimum turnover for December 2012 would be Rs. 2.5 crores and for the succeeding month it would be Rs. 5 crores. The overall work was agreed to be completed by 31st July, 2013. It is further agreed that if the Plaintiff failed to achieve the above targets, ITBP could take action as per the contract. At the meeting held on 7th November, 2013, ITBP expressed its displeasure at the poor turnover. While the claimant requested for extension of time („EOT‟) up to June 2014, ITBP asked the Plaintiff to finish the work by
March 2014. At the meetings held on 27th November, 2013, 3rd May, 2014, 14th May, 2014 and 14th June, 2014, it was noticed that the progress of work was still slow.
11. On 22nd August, 2014, a show cause notice („SCN‟) was issued to the Plaintiff asking it to explain why action to terminate the contract should not be taken under Clause 72 of the Contract.
12. Meanwhile, the work came to a standstill. The Plaintiff filed CS (OS) No. 3201 of 2014 in this Court in which an application for interim injunction was also filed. The prayers in that suit were to restrain ITBP from encashing the PBG dated 5th July, 2011 and to restrain NBCC from dealing with the construction work or terminating the contract. An order was passed in the said suit on 17th October, 2014 initially recording the suggestion made by the Court to the parties to explore the possibility of a settlement. However, the Court was, later during the same date, informed by learned counsel appearing for NBCC that there was no possibility of a settlement. NBCC was Defendant No. 3 in the said suit. The Court directed deletion of PNB from the array of parties. It gave time to Union of India represented by Ministry of Home affairs and ITBP (Defendant No. 2) to file their respective replies/written submissions and directed listing of the matter on 10 th November, 2014. However, since by that date, the PBG stood encashed and no interim order in that regard was passed.
Settlement of 13 December, 2014
13. On 13th December 2014, a settlement was entered into between the Plaintiff and NBCC. It recorded the fact that the Plaintiff was willing to
complete the project by 15th February, 2015 and that NBCC was agreeable to the said offer. The terms of the settlement were reduced to writing as under:
"Now this deed witness:
1. The Contractor agrees and undertakes to execute the entire scope of work on the same rates and terms as contained in the original agreement dated 23.06.2011.
2. The contractor agrees to complete the construction of various buildings at the project by 15.02.2015 as per the following milestone target agreed hereinbelow:-
(a) Pour No.1 31.01.2015
(b) Pour No.2 l0.02.2015
(c) Pour No.3 31.01.2015
(d) Pour No.4 15.02.2015
(e) Pour No.5 15.02.2015
(f) Pour No.6 15.02.2015
(g) Pour No.7 20.01.2015
(h) Pour No.8 25.01.2015
(i) Pour No.9 31.12.2014
NBCC accept the same subject to the provisions of the contract. The payments for the works executed shall be released as per terms and condition mentioned in the contract.
3. The contractor agrees that it will submit new performance Bank Guarantee(s) for the equal amount of PBG which was enchased by NBCC on 17.10.2014 and on submission of the same NBCC shall remit the amount to the contractor within 7 days subject to verification to the submitted BG from the concerned bank. The said bank guarantee shall be unconditional and as per the contract agreement. On breach, of the present Settlement Agreement or as per provisions of the contract, NBCC shall be entitled to invoke and encash the said bank guarantee.
4. The contractor agrees that they shall not raise any dispute/claim towards interest against NBCC in respect of the encashment of BG(s).
5. That the present settlement shall not be construed in any manner as waiver of any rights and obligation under the contract dated 23.06.2011 executed between NBCC and Contractor and both parties shall remain bound by the terms and conditions of the contract. The contractor shall execute and complete the works as per terms of the contract.
6. It is further agreed by both the parties that this Settlement Agreement will be jointly submitted before the Hon'ble High Court of Delhi on the next date of hearing on 19.12.2014 in view of the settlement the Contractor shall unconditionally withdraw the suit.
In Witness Whereof, the parties through their duly authorized representatives have executed these presents (executed whereof has been approved by the competent Authorities of both the parties) on the day first above mentioned at New Delhi."
14. It must be noted here that on 29th December, 2014, in terms of the Settlement Agreement, the entire PBG amount that was encashed was refunded by NBCC to the Plaintiff.
15. At the hearing of CS (OS) No. 3201/2014 on 19th December 2014, the Court was informed of the aforesaid Settlement Agreement. The Plaintiff accordingly sought permission to withdraw the suit. The Court directed that "the suit is dismissed as withdrawn, as settled". The Plaintiff on 29th December, 2014 submitted a new PBG dated 26 th December, 2014 which was valid till 14th February, 2016.
16. On 15th January, 2015, the Plaintiff wrote to NBCC stating that after the Settlement Agreement, it had accelerated the execution of the work and spent at least Rs. 1.5 crores for the work done thereafter. It is stated that non-release of payment had hampered the progress of the work. The Plaintiff drew the attention of NBCC to Clause 2 of the Settlement Agreement against which "payments for the works executed shall be released as per terms and condition mentioned in the contract." It requested for release of payment under 36th & 37th RA Bill.
Interim orders in the present suit
17. When no further payment was made by NBCC, the Plaintiff filed the present suit in which, as already noticed, NBCC is arrayed as Defendant No. 1, ITBP as Defendant No. 2, PNB as Defendant No. 3 and the Union of India through the MHA as Defendant No. 4. The prayers in the suit are for:
(i) directions to NBCC to pay to the Plaintiff a sum of Rs. 9,32,81,011/- along with interest @ 24% per annum;
(ii) restraining NBCC from dealing with the construction of the works and encashing:
(a) PBG for the sum of Rs. 4,80,00,200 valid till 14th February, 2016;
(b) Rendition Money Bank Guarantee („RMBG‟) dated 30th March, 2013 for Rs. 1,07,00,000;
(c) Bank Guarantee („BG‟) for a sum of Rs.1.29 crores dated 23rd July, 2012; and
(d) BG dated 16th January, 2014 for a sum of Rs. 1 crore; and
(iii) restraining NBCC from dispossessing the Plaintiff from the site of the said works.
18. IA No. 2786/2015 was filed under Order XXXIX Rule 1 and 2 CPC seeking interim reliefs. When the matter came up for hearing on 10th February 2015 inter alia the following order was passed:
"5. The plaintiff has instituted the accompanying suit against the defendant No. l/NBCC Ltd., defendants No.2 & 4/ITBP and the defendant No.3/PNB praying inter alia for passing a decree for a sum of Rs. 9,32,81,011/- against the defendant No. l along with interest towards the payment for works executed by it in respect of a project for construction of a 200 Bedded Referral Hospital meant for the Central Paramilitary Forces of the defendant No.2/ITBP at Greater Noida. Apart from the above relief, the plaintiff has prayed for permanent injunction to restrain the defendant No. l from invoking the bank guarantees offered by it for undertaking the construction work.
6. Pursuant to the order dated 9.2.2015, the defendant No. l is represented through counsel and he confirms that he has received a complete set of the paper book.
7. In the course of making submissions, counsels for the parties draw the attention of the Court to the order dated 19.12.2014 passed in CS(OS)No.3201/2014 an earlier suit instituted by the plaintiff against the defendants in respect of the same project, which was dismissed as withdrawn in terms of a Settlement Agreement dated 13.12.2014 executed by the plaintiff and the defendant No. l/NBCC.(Annexure P-25 at pages 406-410).
8. On enquiring from the counsels for the parties as to why has the settlement arrived at only a month ago, broken down so soon. Mr. Chandhiok, learned Senior Advocate appearing for the plaintiff submits that the defendant No.l/NBCC has illegally
withheld the rightful dues of the plaintiff under the garb of liquidated damages for the works already executed, as per the conditions recorded in the settlement.
9. Counsel for the defendant No. l/NBCC disputes the aforesaid submission and states that the payments were to be released to the plaintiff only in terms of the contract and the plaintiff has clearly defaulted in executing the contract. He explains that while the plaintiff had agreed that it would complete the project by 15.2.2015, as recorded in para 2 of the Settlement Agreement dated 13.12.2014, even the first milestone target that was required to be achieved by 31.12.2014 for Pour No.9, has not been achieved so far.
10. Mr. Chandhiok, learned Senior Advocate for the plaintiff disputes the submission made by counsel for the defendant No.l/NBCC and states that despite the settlement arrived at between the parties, the defendant No.l/NBCC has failed to release any amount and even the payment in respect of the certified bills, i.e. RA 36 & 37 have not been paid by the defendant No. 1. He further submits that out of the list of milestone targets recorded in para 2 of the Settlement Agreement/contract, the plaintiff has completed the work to the tune of Rs.1.50 crores, but the milestone targets could not be achieved due to the hindrances created by the defendant No.l and on account of non-release of the outstanding amounts to the plaintiff.
11. To resolve the controversy to some extent, counsels for the parties have been asked if they are agreeable to the appointment of an independent engineer to visit the site along with their respective representatives for carrying out the measurement of the works completed by the plaintiff after 31.8.2014, the date of RA 37.
12. Both the parties are agreeable to the said suggestion.
13. Accordingly, Mr. H. S. Dogra, Retd. D.G., CPWD (Mobile
No. 9818695335) is appointed as a Local Commissioner to visit the site on 18.2.2015 so as to carry out the measurement of the works undertaken by the plaintiff w.e.f. 1.9.2014 till date, along with the assistance of a person, whom he may deem fit to engage. The representatives of the plaintiff and the defendant No. l/NBCC shall remain present at the site on the aforesaid date at 10.00 AM along with the relevant documents and site plans to assist the Local Commissioner, who shall submit a report in respect of the works completed by the plaintiff w.e.f. 1.9.2014, till date.
14. The fees of the Local Commissioner is tentatively fixed as Rs. 1.00 lac, to be borne equally by both the parties, apart from the out of pocket expenses.
15. Counsel for the defendant No.l/NBCC states that contrary to the impression sought to be given by the plaintiff that his clients have sought to encash the bank guarantees offered by the plaintiff, they have not taken any such coercive measures till date and nor shall they do so till the next date of hearing.
16. Having regard to the importance of the project that is being executed to cater to the requirements of the Paramilitary Forces, it has been enquired from the learned Senior Advocate appearing for the plaintiff if the work at the site has been stopped, as has been claimed by the other side. He assures the Court that the work has not been stopped and the plaintiff shall continue executing the contract with despatch.
17. While binding the plaintiff and the defendant No.l to the aforesaid submissions, list on 18 March, 2015 in the category of 'directions', to await the Local Commissioner's report."
19. According to the Plaintiff, in the meanwhile, it submitted the 38th RA Bill dated 31st January, 2015 of Rs.1,52,76,913. The 39th RA Bill dated 20th February, 2015 in the sum of Rs. 28,24,521 was also submitted.
20. The Local Commissioner („LC‟), Mr. H.S. Dogra, Retired Director General, CPWD visited the site, carried out the measurements, etc. and filed his report in the Court on 16th March, 2015. On 18th March, 2015 when the matter came up before the Court, time was granted to the parties to get a copy of the LC‟s report and make submissions, in particular, in regard to his observations in Annexure-VII to the Report.
21. At this stage, the Plaintiff filed IA No. 5872/2015 under Order VI Rule 17 CPC to amend the plaint. Later on, another IA No.11185/2015 was filed by the Plaintiff against under Order VI Rule 17 seeking further amendment to the plaint. A third application being IA No. 12389/2015 was filed seeking amendment. When this application came up for hearing on 7 th July 2015, the Plaintiff withdrew the earlier IAs filed in this regard under Order VI Rule 17 CPC.
22. Subsequently, the Plaintiff filed IA No. 14549/2015 under Order 39 Rule 1 and 2 CPC followed by an IA No. 15392/2015 under Order 39 Rule 1 & 2 CPC, which came up for hearing on 31st July, 2015.
Termination of contract by NBCC
23. In the meanwhile, on 16th April, 2015, NBCC wrote to the Plaintiff stating that „liquidated damages‟ („LD‟) amounting to Rs. 9.60 crores were recoverable and that Rs. 5.78 crores had already been recovered from the works. By reply dated 22nd April, 2015, the Plaintiff protested and pointed out that NBCC had itself not agreed with ITBP on the question of deduction of LD from the RA Bills.
24. On 28th April, 2015, a SCN was issued by NBCC proposing to terminate the contract. On 7th May, 2015, the Plaintiff replied to the SCN.
25. On 8th May, 2015, a letter was written by the Chief General Manager („CGM‟) of NBCC to the Plaintiff exercising powers under Clause 72.2 of the General Conditions of Contract („GCC‟) and terminating the contract with immediate effect. The security deposit recoverable under the contract was forfeited. It was stated that the unused material of construction, etc. would be at the absolute discretion of NBCC and that the entire balance work would be completed by NBCC at the risk and cost of the Plaintiff. The excess expenditure would be recovered from the money due to the Plaintiff. The Plaintiff was further put to notice that the work executed till then would be measured on 13th May, 2015 at 10:00 hours. The Plaintiff was asked to depute an authorized representative to record joint measurement in the absence of which NBCC would undertake a unilateral measurement.
26. On 3rd June, 2015, NBCC issued a 'Notice Inviting Tender' ('NIT‟) for the balance work. On 20th July, 2015 it issued a Letter of Award („LOA‟) for the balance work to a new contractor.
Further applications by the Plaintiff
27. The Plaintiff filed IA Nos.14549/2015 and 15392/2015 for staying the award of the balance work. On 31st July, 2015 when the matter came up for hearing, the Court directed completion of pleadings on the said application. The Court noted the submissions on behalf of NBCC that the entire outstanding amount till RA bill 37 had been paid to the Plaintiff, except statutory deductions and LD. However, learned counsel for the Plaintiff
stated that no such amount had been received by the Plaintiff and the LD were also in dispute. The Court in the said order noted that the contract between the parties had already been terminated on 8 th May, 2015. It was submitted by learned counsel appearing for NBCC that the balance work had already been awarded to the third party who had already started the work.
28. IA No. 16470/2015 was filed by the Plaintiff under Order XII Rule 6 CPC in which the main contention was that NBCC had admitted that the entire amount due to the Plaintiff had been adjusted by it against LD. It was pointed out that RA Bill No. 36 dated 3rd July, 2014 for Rs. 4,18,72,794/- and RA Bill No. 37 dated 14th September, 2014 amounting to Rs. 1,27,70,318/- had already been duly certified by NBCC for payment. It was contended that EOT was also granted for justifiable reasons by NBCC. It was contended that the levy of LD by NBCC was "arbitrary, unfair, illegal and contrary to the provisions of the Contract/GCC" and further that the delay in completion of the project was attributable solely to NBCC and ITBP. Even the withholding of the amount of Rs.1,35,82,173/- against the LD up to 35th RA Bill was termed by the Plaintiff to be illegal and arbitrary. Consequently, in view of that admissions purportedly made by NBCC, the Plaintiff claimed that a decree should be pronounced for a sum of Rs.6,82, 25,285/- (i.e., Rs. 5,46,43,112/- due and payable to the Plaintiff against RA Bill No. 36 and 37 + Rs. 1,34,82,173/- being LD adjusted up to 35th RA Bill) with interest @ 24% per annum.
29. By its order dated 28th September, 2015, this Court allowed IA No. 12389/2015 under Order VI Rule 17 CPC. The Court was of the view that
the said amendments did not change the nature of the suit. The Court permitted the Defendants to raise all its objections in the written statement to the amended plaint.
30. On 9th March, 2016, the Court disposed of as infructuous IA Nos. 11761/2015, 14549/2015 and 15392/2015 which had sought stay of the operation of the SCN dated 28th April, 2015 and termination letter dated 8th May, 2015; stay of the award of balance work to new contractor and stay of the letter of award dated 20th July, 2015 to a new contractor. It was made clear that "whatever rights have accrued to the parties on account of the aforesaid actions taken by the defendants are preserved".
31. As regards IA Nos. 2786/2015 and 24532/2015, the Court observed that "these applications, therefore, concern only with the aspect of whether or not the Plaintiff is entitled to an interim injunction during the pendency of the suit and encashment of the performance bank guarantee." The Court further directed that IA No. 7330/2015 (objections to the report of the Local Commissioner filed by the defendant) and IA No. 16470/2015 (by the Plaintiff under Order XII Rule 6 CPC) would also be taken up for consideration on the next date.
Submissions on behalf of the Plaintiff
32. Mr Sunil Gupta, learned Senior Counsel appearing for the Plaintiff, made the following submissions:
(i) It was only the Engineer-in-charge („EIC‟) of NBCC who was designated as such under Clause 72.4.1 (a) who was competent to decide the question of
grant of EOT, levy of LD or termination of the contract. ITBP itself had no jurisdiction to decide any such question. In terms of Clause 72.4.2 (viii), it was the absolute discretion of the EIC of NBCC and not of any official of ITBP to decide whether the costs for the delay are beyond the control of the Plaintiff.
(ii) Under Clause 72.4.3, the EIC was to give a fair and reasonable EOT to the contractor under Clause 72.2 (ii) in order to be satisfied that the contractor was unable to complete the work The EIC had to be satisfied that the contractor has without reasonable cause failed to proceed with the work with due diligence.
(iii) On at least 3 occasions, EIC and NBCC found that the grant of EOT was justified. Although the letters dated 17th September, 2013, 4th December, 2013 and 16th April, 2014 termed the EOT as „provisional‟ that terminology was not to be found in the contract. Therefore, the EOT should be held to have been granted voluntarily under Clauses 72.4.2 and 72.4.3 and treated as complete and final.
(iv) There was no occasion for NBCC to submit its decision regarding grant of EOT for approval to ITBP by its letter dated 4 th December, 2013. Still the technical expert of the Chief Engineer (DIG), ITBP found NBCC‟s recommendations for EOT to be justified to the extent of 253 days. Mr. Gupta referred to the decision dated 16th January 2014 of ITBP as being within the purview of paras 9.1 and 19.6 of the Memorandum of Understanding („MOU‟) between ITBP and NBCC. However, the decision of the Chief Engineer (DIG), ITBP was arbitrarily overruled by the IFA of
ITBP vide letter dated 11th July, 2014.
(v) In the minutes of meeting („MOM‟) dated 21st March, 2014 and the letters dated 5th August, 2014, 10th September, 2014 etc., NBCC rightly and legitimately protested about the long delays by ITBP in its approvals in the matters of IT Networking, CCTV etc. because of which the false ceiling work of the entire building was held up for more than one to one-and-a -half years. NBCC also protested against the long delays by ITBP in its approvals and levying compensation (LD) even though, even according to NBCC, the hindrances were beyond its control mainly due to delay in payment of running bills beyond 30 days as per the MOU. However, on each occasion, the IFA and other officials of ITBP prevailed over NBCC.
(vi) Ultimately, NBCC had to give in to the pressure of ITBP regardless of the contractual and legal rights of the Plaintiff to EOT. Even when it was found to be „fair and reasonable‟ under para 72.4.3, NBCC lacked the courage to face ITBP and object to the illegal acts of withholding payments, imposition of LD etc. Accordingly, NBCC, as a cascading effect of ITBP‟s behaviour, sought to minimize its own loss by maltreating the Plaintiff by invocation of its BG, issuance of SCN, termination of the contract etc.
(vii) The Plaintiff earned its legal and contractual right to EOT for a fair and reasonable period of 300 days without deduction of any compensation or LD as per the decision of EIC and NBCC under Para 72.4.3 of the Contract. NBCC was, therefore, guilty of abdication of its legal and contractual duties and subordination of its discretion and decision-making power under the Contract to the extra-legal dictates of ITBP. The Plaintiff
had reason to believe that NBCC had been making an excuse and deducting LD from and withholding payment of the RA bills arbitrary without any formal order of ITBP. Consequently, the acts of NBCC and ITBP were arbitrary and untenable. Reliance is placed on the decision of Kailash Nath Associates v. DDA (2015) 4 SCC 136.
(viii) The actions of NBCC were also violative of the orders passed by this Court. The recommendations of the LC in Annexure-VII were constructive. The matter could not be taken up in the Court for various reasons. Mere absence of an interim order did not mean that NBCC had been permitted, in the meanwhile, to take action like issuance of SCN, terminating the contract, etc.
(ix) As regards IA No. 16470/2015 under Order XII Rule 6 CPC, it was pointed out that NBCC had itself granted EOT and in turn sought the same from NBCC without compensation/LD. In fact, NBCC had itself protested to ITBP as regards the imposition of LD.
(x) The payment of Rs. 6,82,25,285/- was wrongfully and illegally withheld by NBCC from the Plaintiff. The decisions in Raveesh Chand Jain v. Raj Rani Jain (2015) 8 SCC 428 and Uttam Singh Duggal & Co. Ltd. v. Union of India & Ors. (2000) 7 SCC 120 were relied upon. As regard the plea for stay of encashment of the BG, the decisions in Hindustan Construction Co. Ltd. v. State of Bihar (1999) 8 SCC 436; Gangotri Enterprises Limited v. Union of India & Ors. 2016 11 SCC 720 and the decisions of this Court in P.D. Alkarma Pvt. Ltd. v. Canara Bank 1998 (45) DRJ 423; Hindustan Construction Co. Ltd. v. Satluj Jal Vidyut Nigam Ltd. AIR 2006 Del 169
and State Trading Corporation of India Ltd. v. State Bank of India & Ors. (2013) SCC Online Del 935 were relied upon.
Submissions on behalf of NBCC
33. Mr Sanjeev Mahajan, learned counsel appearing for NBCC referred to Clause 72 of the Contract which provides for compensation for delay in execution of the work. He referred to SCN dated 7th August, 2012 which pointed out that instead of 85% of construction having to be completed by them, only 49% was completed. Under the revised plan, the Plaintiff was to complete construction by 15th December, 2012.
34. Mr. Mahajan also referred to the SCN dated 16th November, 2012 which showed that only Rs. 32 crores worth of work had been done till then. That SCN was dropped after the Plaintiff gave an assurance vide letter dated 6 th December, 2012 that it would complete Rs. 5 crores‟ value of work per month. The third SCN was issued on 17th May, 2013 wherein it was pointed out that only 51% of the work was completed.
35. Mr Mahajan pointed out that even after the settlement dated 13 th December, 2014, which extended the period of completion of work up to 15th February, 2015, the right to impose LD remained. However, again the Plaintiff was unable to complete it by 15th February, 2015.
36. As regards the report of the LC submitted on 16 th March, 2015, Mr. Mahajan referred to the interpolation which had been made in the chart annexed as Annexure V, which itself demonstrated the huge difference between what was claimed by the Plaintiff and that claimed by NBCC. He
also referred to the interpolations made in the LC‟s report in various columns on pages 9, 11 and 14. For instance, at internal page 14, the rate was altered from 90% to 95% by hand. Likewise, the value of the work done was altered by hand. Annexure-IV concerned the material at the site and significantly, this was not signed by NBCC. He submitted that this was also outside the scope of the mandate of the LC. He pointed out that the LC‟s report was not supplemented by photographs or documents. He submitted that whole of Annexure-VII i.e., additional information for the Court was entirely outside the mandate of the LC.
37. Mr. Mahajan pointed out that there was no admission as regards the MOM dated 21st March, 2014 and the meeting held between NBCC and ITBP. The contract between the NHAI and ITBP was separate and the Plaintiff could not take advantage of any of the clauses therein to avoid liability arising out of the escalation for NBCC.
38. As regards the encashment of the PBG, Mr. Mahajan pointed out that there can be only two exceptions to the rule that a Court will not interfere with the encashment of the BG: one was egregious fraud and the other irretrievable injustice. He placed reliance on the decisions in Dwarikesh Sugar Industries Ltd v. Prem Heavy Engineering Work (P) Ltd. & Anr. (1997) 6 SCC 450 and BSES Ltd. (Now Reliance Energy Ltd.) v. Fenner India Ltd. & Anr. (2006) 2 SCC 728. He submitted that no case was made out for passing of a decree on admissions under Order XII Rule 6 CPC.
Law in relation to stay of encashment of BGs
39. At the outset, the Court would like to consider whether any case was
made out by the Plaintiff for stay of encashment of the BGs in question. The law in this regard is well settled. In State Trading Corpn. of India Ltd. v. Jainsons Clothing Corpn.(1994) 6 SCC 597, although fraud was pleaded by the Plaintiff, the Court held that it was at best a case of cancellation of the contract by the appellant-principal supplier. The Court then proceeded to explain the law in relation to the scope of judicial review in the matter of encashment of BG as under:
"8. The grant of injunction is a discretionary power in equity jurisdiction. The contract of guarantee is a trilateral contract which the bank has undertaken to unconditionally and unequivocally abide by the terms of the contract. It is an act of trust with full faith to facilitate free flow of trade and commerce in internal or international trade or business. It creates an irrevocable obligation to perform the contract in terms thereof. On the occurrence of the events mentioned therein the bank guarantee becomes enforceable. The subsequent disputes in the performance of the contract does not give rise to a cause nor is the court justified on that basis, to issue an injunction from enforcing the contract, i.e., bank guarantee. The parties are not left with no remedy. In the event of the dispute in the main contract ends in the party's favour, he/it is entitled to damages or other consequential reliefs.
9. It is settled law that the court before issuing the injunction under Order 39 Rules 1 and 2, CPC should prima facie be satisfied that there is triable issue strong prima facie case of fraud or irretrievable injury and balance of convenience is in favour of issuing injunction to prevent irremediable injury. The court should normally insist upon enforcement of the bank guarantee and the court should not interfere with the enforcement of the contract of guarantee unless there is a specific plea of fraud or special equities in favour of the plaintiff. He must necessarily plead and produce all the necessary evidence in proof of the fraud in execution-of the contract of the guarantee, but not the contract either of the
original contract or any of the subsequent events that may happen as a ground for fraud."
40. The above decision was followed by the much cited case of U.P. State Sugar Corporation v. Sumac International Limited (1997) 1 SCC 568 where the Court again explained the law as under:
"12. The law relating to invocation of such bank guarantees is by now well settled. When in the course of commercial dealings an unconditional bank guarantee is given or accepted, the beneficiary is entitled to realize such a bank guarantee in terms thereof irrespective of any pending disputes. The bank giving such a guarantee is bound to honour it as per its terms irrespective of any dispute raised by its customer. The very purpose of giving such a bank guarantee would otherwise be defeated. The courts should, therefore, be slow in granting an injunction to restrain the realization of such a bank guarantee. The courts have carved out only two exceptions. A fraud in connection with such a bank guarantee would vitiate the very foundation of such a bank guarantee. Hence if there is such a fraud of which the beneficiary seeks to take advantage, he can be restrained from doing so. The second exception relates to cases where allowing the encashment of an unconditional bank guarantee would result in irretrievable harm or injustice to one of the parties concerned. Since in most cases payment of money under such a bank guarantee would adversely affect the bank and its customer at whose instance the guarantee is given, the harm or injustice contemplated under this head must be of such an exceptional and irretrievable nature as would override the terms of the guarantee and the adverse effect of such an injunction on commercial dealings in the country. The two grounds are not necessarily connected, though both may co- exist in some cases."
41. The Court explained that there must be a clear case of fraud in the underlying transaction of which bank has notice. The fraud must be of an
egregious nature such as to vitiate the entire underlying transaction. As regards irretrievable injustice, reference was made to the decision in Itek Corporation v. First National Bank of Boston 566 Fed Supp. 1210, where it was held that to avail of this exception, certain 'exceptional circumstances' which make it impossible for the guarantor to reimburse himself if he ultimately succeeds will have to be decisively established.
42. In Dwarikesh Sugar Industries Ltd. v. Prem Heavy Engineering Works (P) Ltd. & Anr. (supra), the Supreme Court observed that, "in the absence of established fraud and not a mere allegation of fraud and that also having been made only in the injunction application, the court could not, in the present case, have granted an injunction relating to the encashment of the bank guarantees".
43.1 In BSES Limited v. Fenner India Limited & Anr. (supra) the two exceptions were again explained as under:
"There are, however, two exceptions to this rule. The first is when there is a clear fraud of which the bank has notice and a fraud of the beneficiary from which it seeks to benefit. The fraud must be of an egregious nature as to vitiate the entire underlying transaction. The second exception to the general rule of non-intervention is when there are "special equities" in favour of injunction, such as when "irretrievable injury" or "irretrievable injustice" would occur if such an injunction were not granted. The general rule and its exceptions has been reiterated in so many judgments of this Court, that in U.P. State Sugar Corporation v. Sumac International Ltd., (hereinafter "U.P. State Sugar Corporation") this Court, correctly declared that the law was "settled" .
43.2 In BSES Limited v. Fenner India Limited & Anr. (supra), an argument
was made that the invocation of BG for oblique purposes was not permissible and that, "the unconscionable calling of a bank guarantee was an exception independent of fraud". This was, however, rejected by the Supreme Court and it was observed as under:
"We are afraid that in the face of the law succinctly laid down in U.P. Cooperative Federation (supra) and reiterated in numerous judgments of this Court referred to earlier, we are unable to accept the wide proposition of law laid down in the foreign judgments cited by Mr. Sorabjee. Whatever may be the law, as to the encashment of bank guarantees in other jurisdictions, when the law in India is clear, settled and without any deviation whatsoever, there is no occasion to rely upon foreign case law."
43.3 In BSES Limited v. Fenner India Limited & Anr. (supra), the Court further explained that it was beneficiary in whose favour the BG is issued which is the best judge to decide as to when and for what the BG should be encashed. It was held as under:
"Further, it is no function of the Second Respondent-Bank, nor of this Court, to enquire as to whether due performance had actually happened when, under the terms of the guarantee, the Second Respondent-Bank was obliged to make payment when the guarantee was called in, irrespective of any contractual dispute between the Appellant and the First Respondent. Indeed, in similar circumstances, this Court in General Electric Technical Services Company Inc. v. Punj Sons (P) Ltd., held:
"The Bank must honour the bank guarantee free from interference by the courts. Otherwise, trust in commerce internal and international would be irreparably damaged. It is only in exceptional cases that is to say in case of fraud or in case of irretrievable injustice, the court should interfere. The nature of the fraud that the courts talk about is fraud of an "egregious nature as to
vitiate the entire underlying transaction". It is fraud of the beneficiary, not the fraud of somebody else."
44. In Himadri Chemicals Industries Limited v. Coal Tar Refining Company (2007) 8 SCC 110, the legal position was reiterated as under:
"14...(i) While dealing with an application for injunction in the course of commercial dealings, and when an unconditional Bank Guarantee or Letter of Credit is given or accepted, the Beneficiary is entitled to realize such a Bank Guarantee or a Letter of Credit in terms thereof irrespective of any pending disputes relating to the terms of the contract.
(ii) The Bank giving such guarantee is bound to honour it as per its terms irrespective of any dispute raised by its customer.
(iii) The Courts should be slow in granting an order of injunction to restrain the realization of a Bank Guarantee or a Letter of Credit.
(iv) Since a Bank Guarantee or a Letter of Credit is an independent and a separate contract and is absolute in nature, the existence of any dispute between the parties to the contract is not a ground for issuing an order of injunction to restrain enforcement of Bank Guarantees or Letters of Credit.
(v) Fraud of an egregious nature which would vitiate the very foundation of such a Bank Guarantee or Letter of Credit and the beneficiary seeks to take advantage of the situation.
(vi) Allowing encashment of an unconditional Bank Guarantee or a Letter of Credit would result in irretrievable harm or injustice to one of the parties concerned."
45. This Court in Consortium of Deepak Cable India Limited v.
Teestavalley Power Transmission Limited 2014 215 DLT 246 (DB)
succinctly summarised the law thus:
"145. ... That certain amounts have been recovered under running bills and have to be adjusted for is of no concern in matters relating to invocation of bank guarantee. That there are serious disputes on questions as to who committed the breach of the contract are no circumstances justifying granting an injunction pertaining to a bank guarantee. Plea of lack of good faith and/or enforcing the guarantee with an oblique purpose or that the bank guarantee is being invoked as a bargaining chip, a deterrent or in an abusive manner are all irrelevant and hence have to be ignored. There are only two well recognized exceptions to the rule against permitting payment under a bank guarantee. The same are:
A. A fraud of egregious nature;
B. Encashment of the bank guarantee would result in irretrievable harm or injustice of an irreversible kind to one of the parties.
146. The irretrievable harm or injustice of an irreversible kind must relate to a situation akin to the one found in Itek Corporation's case (supra) or of the kind or in Elian's case (supra).
147. There is no separate third exception of a special equity justifying grant of an injunction to restrain the beneficiary from receiving under an unconditional bank guarantee and if there exists any third exception of a special equity the same has to be of a kind akin to irretrievable injustice or putting a party in an irretrievable situation."
No case made out for stay of encashment of BGs
46. In the above background, the Court proceeds to consider whether there exists any prima facie case in favour of Plaintiff for grant of stay of encashment of the BG in question.
47. The submission that it is only the EIC, NBCC who is authorized to take a decision regarding grant of EOT and not ITBP pertains to the legality of the invocation of the BG. This is a disputed question which cannot possibly be examined at this stage. Even the plea that NBCC induced the Plaintiff into withdrawing the earlier suit CS (OS) No. 3201/2014 in order to deprive the Plaintiff of the over-due payments is a disputed question. This is not the kind of 'egregious fraud' spoken of in the decisions of the Supreme Court discussed hereinbefore.
48. As regards the plea of irretrievable injustice, the factors pointed out by Mr. Gupta are not uncontroverted and would essentially be matters for evidence. Under Clause 72.4, time was to be the essence of the contract. Where the contractor commits default in the execution of the work, NBCC is at liberty to forfeit the earnest money absolutely. Further, under clause 72.4.1, the compensation for the delay as per clause 72.1 shall be leviable at intermediate stages also, in case the required progress is not achieved to meet the time deadlines for completion. Compensation for the delay shall not exceed 10% of the tendered value of work. The grant of EOT is governed by Clause 72.4.3. The clause does say that non-application by the contractor for EOT shall not be a bar for the EIC to grant a fair and reasonable extension. The question whether the action of NBCC in recovering LD was justified is a disputed question which cannot be examined by this Court at the present stage. The materials on record do not enable the Court to even come to a prima facie conclusion in that regard.
49. The Court is unable to agree with the submissions of Mr. Gupta that the
provisional EOT granted by NBCC should be taken to be final EOT. That, again, is a matter of interpretation and no final view can be expressed by the Court at this stage. What should be the inference drawn from the MOM dated 21st March, 2014 between NBCC and ITBP and the letters dated 5 th August, 2014 and 10th September, 2014 is, again, is a matter in dispute. As pointed out by Mr. Mahajan, NBCC itself has made a counter-claim of Rs.13,30,24,908/- It is the case of NBCC that even by the first deadline of 31st December, 2014, the requisite target was not achieved. As to who was responsible for the delay is again a disputed matter and it is not possible, on the basis of what is available on record, to even come to a prima facie conclusion in favour of the Plaintiff at this stage.
50. Mr. Gupta's submission that the progress of work was hampered o account of NBCC anticipating approval of work of the IT network and CCTV work by ITBP has been contested by Mr. Mahajan by pointing out that the IT network and CCTV were not even part of the scope of the Plaintiff‟s work.
51. The above factors, in the view of the Court, do not even pima facie show that irretrievable injustice would be caused to the Plaintiff in the event of encashment of the BGs in question.
52. Turning to the decisions cited by Mr. Gupta, in Hindustan Construction Company Limited v. State of Bihar (supra), the Court there interfered with the enforcement of the BG only because of the particular wording of the BGs involved which required certain conditions to be fulfilled. In Gangotri Enterprises Limited v. Union of India & Ors. (supra), the facts were held to
be more or less similar to the facts in Union of India v. Raman Iron Foundry (1974) 2 SCC 231. Certain circumstances were noticed in para 42 of the said decision which justified the grant of injunction in the facts and circumstances of that case. None of the said factors exist in the instant case. The decision in P. D. Alkarma Pvt. Ltd. v. Canara Bank (supra) turned on its facts and is distinguishable.
LC's Report
53. Mr. Gupta relied upon the report of the LC and, in particular, on Annexure - VII thereto. NBCC has filed objections to the LC‟s report.
54. A perusal of the report of the LC shows, as noted earlier, that the LC had gone beyond the scope of reference by the Court. It must be recalled at this stage that all that the LC was required to do in terms of the order dated 18 th May, 2015 was "to carry out measurement and whatever undertaken by the Plaintiff with effect from 1st September, 2014 till date, along with assistance of person, whom he may deem fit to engage".
55. Nonetheless, the Court has proceeded to consider the entire Annexure- VII which is in the form of suggestions. The Court is of the view that the LC has indeed exceeded his mandate in giving those suggestions which are at best his opinion which cannot obviously be binding on the parties, much less the Court. In the considered view of the Court, the entire Annexure-VII titled "additional information for the Court" should be ignored as it was not called for by the Court.
56. As far as Annexure-IV is concerned, there is no explanation as to why
the LC failed to obtain signatures of the AR of NBCC on that sheet which is titled as „stock balance‟. It is in fact on the letterhead of the Plaintiff. Since the attendance sheets show that the representative of NBCC was present, the absence of the signature of the AR of NBCC thereon leads to the inevitable result of Annexure-IV also having to be kept out of reckoning while considering the issue of how much work was done by the Plaintiff up to 1 st September, 2014.
57. The criticism of NBCC as regards interpolation on the report of the LC also appears to be justified. There are interpolations on important parts of the Annexures. The dispute was essentially with regard to the extent of the work which was to be done between 1st September, 2014 and the date of the termination of the contract i.e., 18th February, 2015. It is pointed out how the GFRC Jali which was claimed by the Plaintiff to be 205 sq. meters, was on measurement found to be 74.63 sq. meters. The LC in his report has indicated the same to be of 100 sq. meters without giving any reasons. Likewise, the measurement of the quantity of granite appears to be increased by the LC from 305.4 sq. meters from 2015.17 sq. meters without indicating the basis. In fact, the Plaintiff claimed the quantity to be 305.04 sq. m.
58. Likewise, in respect of structural glazing, the Plaintiff claimed the quantity as 207.62 and NBCC found it as 107.62 sq. meters. This, again, has been arbitrarily raised to 207.62 sq. meters. Even as regards the rates, there are problems. For work done prior to 1st September, 2014 in respect of HBAC, 95% the full rate has been released by the LC contrary to the CPWD specifications. In respect of 750 KVA DG, the LC released 90% rates
whereas NBCC had released 85% rates as per CPWD guidelines.
59. Photographs have been enclosed by NBCC with its objections to show that the DG sets were simply placed on the foundation and not installed. The photographs at Annexure-V show that even the UPS on the site was not installed.
60. The Court, therefore, upholds the objections of NBCC to the report of the LC.
No decree on admissions
61. The Court now proposes to deal with the prayer of the Plaintiff for a decree on admissions. In its decision in Himani Alloys Limited v Tata Steel Limited (2011) 15 SCC 273, the Supreme Court has explained that in order to succeed in such an application, the Plaintiff has to show that the admission is unambiguous and categorical. It should be a conscious and deliberate act of the party making it, showing an intention to be bound by it. As far as the Court is concerned, Order XII Rule 6 being an enabling provision, it is neither mandatory nor peremptory but discretionary. The Court, on examination of the facts and circumstances, has to exercise its judicial discretion keeping in mind that a judgment on admission is a judgment without trial which permanently denies any remedy to the Defendant by way of an appeal on merits. Therefore, unless the admission is clear, unambiguous and unconditional, the discretion of the Court should not be exercised to deny the valuable right of a Defendant to contest the claim. In short, the discretion should be used only when there is a clear „admission‟ which can be acted upon.
62. To the same effect is the decision of this Court in Vijay Gupta & Ors. v. Ashok Kumar Gupta 2007 VII AD (Delhi) 266. Turning to the decision relied upon by Mr Gupta in Raveesh Chand Jain vs Raj Rani Jain (supra), on facts, it was found that the requirement of Order XII Rule 6 CPC was indeed not satisfied.
63. Turning to the facts on hand, the recovery of LD from the RA bills of the Plaintiff cannot be construed to be a categorical and unequivocal admission by NBCC that the said amount was due to the Plaintiff. If that were so, it would not explain the considerable amount claimed by NBCC against the Plaintiff as counter-claim. In the considered view of the Court, none of the conditions for applicability of Order XII Rule 6 stand satisfied in the present case.
64. The Court, accordingly, dismisses IA Nos. 16740/2015, under Order XII Rule 6 CPC.
65. IA No. 2786/2015 is also dismissed. It will be open to NBCC to proceed to invoke and encash the BGs in question. A specific direction is issued to the Plaintiff not to frustrate the invocation and encashment of such BGs by failing to extend them as required by the orders of this Court from time to time.
66. IA No. 7330/2015 i.e., the objections filed by NBCC to the report of the LC, is allowed.
67. IA No. 24532/2015 filed by NBCC for permitting it to encash the BGs is
also allowed.
68. It is clarified that the observations on merits by the Court in this order will not influence the independent decision thereon to be arrived at finally in the suit.
IA No. 2787/2015 (Seeking leave to dispense with the compliance of Section 80(1) of CPC)
69. In view of the order passed above, this application does not survive and is disposed of as such.
CS (OS) 352/2015
70. List before the Roster Bench for further steps on 10th April, 2017.
S. MURALIDHAR, J MARCH 15, 2017 dn/rd
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!