Citation : 2017 Latest Caselaw 978 Del
Judgement Date : 20 February, 2017
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment Reserved on: 03.01.2017
Judgment delivered on: 20.02.2017
+ FAO(OS) 382/2016
M/S GEO MILLER & CO PVT LTD ..... Appellant
versus
BIHAR URBAN INFRASTRUCTURE DEVELOPMENT
CORPORATION PVT LTD & ANR ..... Respondents
Advocates who appeared in this case:
For the Appellant : Mr S.D. Singh with Mr Rahul Kr. Singh & Mr
Jitender Singh.
For the Respondents : Mr Shivam Singh with Mr Vikram Singh
Chauhan.
CORAM:-
HON'BLE MR JUSTICE BADAR DURREZ AHMED
HON'BLE MR JUSTICE ASHUTOSH KUMAR
JUDGMENT
ASHUTOSH KUMAR, J
CM 47779/2016 (Exemption) Allowed, subject to all just exceptions.
FAO(OS) 382/2016
1. This appeal is directed against the order dated 06.12.2016 passed
by a learned single Judge of this Court in the appellant‟s petition under
Section 9 of the Arbitration and Conciliation Act, 1996 being OMP (I)
No. 290/2015 whereby it was held by the learned single Judge that such
petition was not maintainable by the appellant in its individual capacity.
2. The appellant had sought setting aside of orders dated 26.10.2013
and 27.05.2015 debarring the appellant from participating in future
tenders by the respondent no.1 and blacklisting the appellant for a period
of 5 years respectively.
3. The respondent no.1 had invited bids for a project for design,
construction, installation, commissioning, management, operation and
maintenance of Intake, RWPH, 220 MLD water treatment plant and water
distribution network in Patna.
4. The appellant (Geo Miller) and another company, Gammon India,
intending to bid jointly, formed a consortium by way of a „Joint Bidding
Agreement‟ dated 12.01.2012. Under this agreement the parties intended
to constitute a proposed SPV i.e. Patna Water Supply Distribution
Networks Pvt. Ltd. for the purpose of conducting the works under the
agreement. The lead member of the consortium was Gammon India
having an equity participation of 74% and Geo Miller held 26% equity.
5. The bid of the consortium/JV was accepted vide Letter of
Acceptance dated 27.02.2014 at a bid price of Rs. 5,48,83,14,670/-. A
tripartite agreement (TPA) was entered between the JV/consortium,
Respondent no.1 (BUIDCO) and Patna Nagar Nigam in terms of which
bank guarantees were furnished by the appellant and Gammon India up to
the value of 10% of the contract value.
6. A supplementary agreement (SA) was also entered into between
aforesaid three parties, containing the dispute resolution clause, the
arbitration clause and a clause regarding applicability of law and
jurisdiction. In terms of Clause 20.4 of the agreement, it was agreed that
arbitration would be held in accordance with the rules of arbitration of the
International Centre for Alternative Dispute Resolution, New Delhi. The
venue of arbitration was to be Patna. Clause 24.1 provided for "governing
law and jurisdiction." viz. that the Courts at Delhi would have jurisdiction
over matters arising out of or relating to the contract.
7. Because of the disputes between the respondents and the
JV/consortium as also because of delay in execution of contract, the
respondents, by order dated 26.10.2013 debarred the appellant and
Gammon India from participating in future tenders to be floated by
BUIDCO. On 27.05.2015, the appellant as well as Gammon India were
blacklisted for 5 years.
8. The learned single Judge, by noticing the Clause 20.4 of the
agreement dealing with arbitration, held that arbitration clause could be
invoked only in case of dispute between the parties. The "party", the
learned single Judge further observed, was defined under section 2(1)(h)
of the Arbitration and Conciliation Act, 1996 which means party to an
arbitration agreement. Since the "party" to the arbitration agreement in
the present case was the consortium and not Geo Miller in its individual
capacity, it was held that such invocation of the arbitration clause by only
the appellant was not maintainable.
9. For the sake of completeness, Clause 20.4 of the agreement is
being reproduced below:
"20.4 Arbitration
1. Any Dispute which is not resolved amicably by conciliation of the Expert Committee, as provided in Clause 20.3 shall be finally decided by reference to arbitration by a Board of Arbitrators appointed in accordance with the Rules of Arbitration of the International Centre for Alternative Dispute Resolution. New Delhi (the "Rules") or such other rules as may be mutually agreed by the Parties. And shall be subject to the provisions of the arbitration Act. The venue of such arbitration shall be Patna Bihar (India) and the language of arbitration proceedings shall be English.
2. There shall be a board of three arbitration of whom each Party shall select one and the third arbitrator shall be appointed by the two arbitrators so selected and in the
even of disagreement between the two arbitrators, the appointment shall be made inaccordance with the Rules.
3. The arbitrators shall make a reasoned award (the "Award").Any Award made in any arbitration held pursuant to this Article 20.4 shall be final and binding on the Parties as from the date it is made and the Contractor and the Employer, agree and undertake to carry out such Award without delay.
4. The Contractor and the Employer agree that an Award may be enforced against the Contractor and/or the Employer as the case may and their respective assets wherever situated.
5. This Contract and the rights and obligations of the Parties shall remain in full force and effect pending the Award in any arbitration proceedings hereunder."
10. The agreement dated 12.01.2012 between the members of the
consortium clearly indicates that Gammon India shall be the lead member
of the consortium and shall be authorised to receive instructions and incur
liabilities for the project. The lead member i.e. Gammon India, according
to the agreement, had equity participation and total shareholding of 74%
whereas the appellant being the other consortium member had a
shareholding of 26%. Only the consortium, according to the agreement,
could invoke the arbitration agreement.
11. The contention of the appellant that the agreement had been signed
not only by the lead member but also by the appellant who could invoke
the arbitration clause in its own capacity was rightly rejected by the
learned single Judge as the wordings of the agreement unambiguously
indicate that the consortium would be represented through the lead
member of the consortium.
12. Mr S. D. Singh, the learned counsel for the appellant submitted that
the appellant could not have been blacklisted for the non-performance of
the contractual obligations of the JV/Consortium unless the same was
determined by a competent court and that holding of the appellant as not
a "party" to the agreement in terms of section 2(1)(h) of the Arbitration
Act was unnecessary and unreasonable. In fact, it was argued that the
blacklisting of the appellant individually for alleged non-performance of
the consortium could not be justified and therefore, by a reverse logic, the
appellant ought not to have been precluded from invoking the arbitration
clause individually. It was further contended that the blacklisting of the
appellant under Rule 8 of Bihar Contractors Registration Rules was
illegal as the appellant was not registered under the said rules, which in
fact is a precondition for attracting the provision of the rules. The
blacklisting and debarring, it was asserted, was an individual and separate
action on the appellant and the appellant being a member of the
consortium could invoke the arbitration clause individually and was not
dependant on the action of the consortium.
13. We are afraid we cannot accept the submission of the appellant as
the intention reflected in the agreement clearly belies the contention of
the appellant that the arbitration clause could be invoked by any member
of the consortium/JV independently or individually. The learned single
Judge was absolutely justified in holding that the remedy of the appellant
does not lie under the Tripartite Agreement between the respondent,
consortium and Patna Nagar Nigam.
14. In Automation Technologies (I) Pvt. Ltd. v. Unitech Ltd.:, 2009
(1) RAJ 444 (Del), the court had permitted the invocation of the
arbitration clause in the Memorandum of Understanding at the instance of
one of the members of the agreement because of the special wordings of
the arbitration clause which permitted invocation in case of any dispute or
difference arising out of or in connection with the agreement or with the
interpretation thereof. In the arbitration clause of that agreement, it was
not covenanted that only a party to the agreement could invoke the
arbitration clause. A broad meaning was, in that context given to the word
"party" as defined under section 2(1)(h) of the Arbitration and
Conciliation Act, 1996.
15. In the present case, the arbitration clause (Clause 20.4), clearly
refers to a dispute between the "parties". It was the consortium which
was one of the 'parties' and not the appellant.
16. Thus we do not find any reason to differ with the view taken by the
learned single Judge.
17. The appeal is dismissed but without any order as to costs.
CM 47778/2016
1. In view of the appeal having been dismissed, the application has
become infructuous.
2. The application is disposed of accordingly.
ASHUTOSH KUMAR, J
BADAR DURREZ AHMED, J FEBRUARY 20, 2017/ab
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!