$~36
*       IN THE HIGH COURT OF DELHI AT NEW DELHI
%                                      Judgment delivered on: 13.02.2017

+       W.P.(C) 4752/2015 & CM 8599/2015
VED WATI & ORS                                               .... Petitioners
                                       versus
GOVERNMENT OF NCT OF DELHI & ORS                             ..... Respondents

Advocates who appeared in this case:

For the Petitioners        : Mr Sanjay Parikh with Mr Aagney Sail, Ms N.S.
                             Thomas
For the Respondent LAC    : Mr Yeeshu Jain with Ms Jyoti Tyagi
For the Respondent DSIIDC : Ms Renuka Arora

CORAM:-
HON'BLE MR JUSTICE BADAR DURREZ AHMED
HON'BLE MR JUSTICE ASHUTOSH KUMAR

                                  JUDGMENT

BADAR DURREZ AHMED, J (ORAL)

1. The petitioners seek the benefit of Section 24(2) of the Right to

Fair Compensation and Transparency in Land Acquisition, Rehabilitation

and Resettlement Act, 2013 (hereinafter referred to as 'the 2013 Act')

which came into effect on 01.01.2014. A declaration is sought to the

effect that the acquisition proceeding initiated under the Land Acquisition

Act, 1894 (hereinafter referred to as 'the 1894 Act') in respect of which

Award No.6/2008-09 dated 20.06.2008 was made, inter alia, in respect of

the petitioner's land comprised in Khasra Nos. 13//7 (4-16), 15 (3-15) and

14//10 min (2-06) measuring 10 bighas 17 biswas in all in village

Kanjhawala, Delhi, shall be deemed to have lapsed.

2. Though the respondents claimed that possession of the said land

was taken on 11.07.2008, the petitioners dispute this and maintain that

physical possession has not been taken. However, insofar as the issue of

compensation is concerned, it is an admitted position that it has not been

paid.

3. Without going into the controversy of physical possession, this

much is clear that the Award was made more than five years prior to the

commencement of the 2013 Act and the compensation has also not been

paid. The necessary ingredients for the application of Section 24(2) of

the 2013 Act as interpreted by the Supreme Court and this Court in the

following cases stand satisfied:-

(1) Pune Municipal Corporation and Anr v. Harakchand Misirimal Solanki and Ors: (2014) 3 SCC 183;

(2) Union of India and Ors v. Shiv Raj and Ors: (2014) 6 SCC 564;

(3) Sree Balaji Nagar Residential Association v. State of Tamil Nadu and Ors: Civil Appeal No. 8700/2013 decided on 10.09.2014;

(4) Surender Singh v. Union of India & Others: WP(C) 2294/2014 decided on 12.09.2014 by this Court; and

(5) Girish Chhabra v. Lt. Governor of Delhi and Ors:

WP(C) 2759/2014 decided on 12.09.2014 by this Court.

4. As a result, the petitioners are entitled to a declaration that the said

acquisition proceedings initiated under the 1894 Act in respect of the

subject land are deemed to have lapsed. It is so declared.

5. The writ petition is allowed to the aforesaid extent. There shall be

no order as to costs.


                                          BADAR DURREZ AHMED, J


FEBRUARY 13, 2017                                ASHUTOSH KUMAR, J
kb





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter