Citation : 2015 Latest Caselaw 7902 Del
Judgement Date : 14 October, 2015
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 14th October, 2015.
+ W.P.(C) No.9448/2015 & CM No.22080/2015 (for stay)
GAIL (INDIA) LTD. ....Petitioner
Through: Mr. Balbir Singh, Sr. Adv. with Mr.
Yoginer Handoo, Adv.
Versus
PETROLEUM & NATURAL GAS REGULATORY BOARD
& ANR ..... Respondents
Through: Mr. Prashant Bezorruah, Adv. for R-1.
CORAM:
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. The petition seeks to restrain the respondent No.1 Petroleum and
Natural Gas Regulatory Board (PNGRB) from encashing the Performance
Bank Guarantee (PBG) No.1501271BGP00289 dated 27th March, 2015
issued by respondent No.2 IDBI Bank Limited (Bank) at the instance of the
petitioner in favour of the respondent No.1 PNGRB.
2. It is the case of the petitioner,
(i) that pursuant to the competitive bids invited by PNGRB, the
petitioner, vide letter dated 25th April, 2012 of PNGRB, was granted
authorization for laying, building, operating or expanding the Natural
Gas Pipeline from Surat (Gujarat) to Paradip (Odisha) spanning 1500
Kms excluding the spur-lines;
(ii) in terms of Regulation 9 of the Petroleum and Natural Gas
Regulatory Board (Authorizing Entities to Lay, Build, Operate or
Expand Natural Gas Pipelines) Regulations, 2008 (PNGRB
Regulations) framed by the PNGRB in exercise of powers under
Section 61 of the Petroleum and Natural Gas Regulatory Board Act,
2006 (PNGRB Act), the grant of the said authorization was subject to
the petitioner achieving a financial closure as per Regulation 10
thereof;
(iii) Regulation 10 of the PNGRB Regulations requires the
authorised entity to achieve financial closure within a period of 120
days from the date of authorization and if internally financing the
project, to within the said 120 days submit "the approval of its Board
of Directors for the detailed feasibility report of the project alongwith
its financial plan";
(iv) the said period of 120 days, for the petitioner was ending on 30th
October, 2012;
(v) the Board of Directors of the petitioner in its 303rd Meeting held
on 26th October, 2012 approved and accorded the laying and operating
of the pipeline aforesaid at an estimated cost of Rs.10281.01 crores
and the petitioner, vide its communication dated 30 th October, 2012 to
PNGRB, informed PNGRB of the same, thus fulfilling the
requirement of Regulation 10 supra;
(vi) however PNGRB vide its communication dated November,
2012, received by petitioner on or about 19th November, 2012,
directed the petitioner to submit a detailed and clear financial closure
report;
(vii) that though the petitioner submitted a detailed and clear
financial closure report on 20th December, 2012 but the PNGRB was
not satisfied therewith and asked the petitioner to make an elaborate
presentation and which was made by the petitioner on 31st January,
2013;
(viii) however PNGRB still, vide communication dated 2nd May,
2013, asked the petitioner to furnish the source of funds in respect of
the financial closure;
(ix) the petitioner informed PNGRB that it does not take particular
project finance but avails Debt of Capex on Company‟s balance sheet
and requested PNGRB to treat the same as a financial closure but the
PNGRB was still not satisfied and asked the petitioner the particulars
of the equity sharing by other companies for the purpose of
completion of financial closure;
(x) the petitioner informed PNGRB that discussions with potential
Joint Venture (JV) partners were in progress and no JV agreement had
been finalised till then;
(xi) the petitioner in the meeting on 10th September, 2013 again
attempted to satisfy PNGRB of having achieved the financial closure
and further informed that the net worth of the petitioner was Rs.24,000
crores and the projected capital expenditure required for the project
aforesaid could be easily financed from its internal generation and
external borrowings and that the petitioner was thus fully capable to
finance the project;
(xii) PNGRB, vide communication dated 8th October, 2013 directed
the petitioner to submit detailed status and execution plan of the
project, without insisting on financial closure and wherefrom the
petitioner gathered that the financial plan of the petitioner had been
accepted by PNGRB;
(xiii) however PNGRB issued show cause notice dated 30th
September, 2013 to the petitioner alleging non-compliance of
Regulation 10(4) and 10(5) of the PNGRB Regulations concerning
financial closure;
(xiv) that again the process of the petitioner satisfying PNGRB of its
financial capability commenced, with the petitioner contending that
the financial closure had already been achieved;
(xv) however PNGRB, vide communication dated 30th September,
2015, has threatened the petitioner with invocation of PBG.
3. The petition came up first, post-lunch on 1st October, 2015 on listing
on urgent mentioning. The matter was posted for hearing on 8 th October,
2015 and the respondent No.2 Bank restrained from remitting the monies
under the PBG to PNGRB. On 8th October, 2015, the senior counsel for the
petitioner was heard at length but whereafter on his plea for grant of one
week‟s time to satisfy PNGRB and the Ministry, the matter was adjourned to
today, continuing the interim order. Today, the senior counsel for the
petitioner has stated that the petitioner has been unable to prevail upon
PNGRB to recall its decision to invoke the PBG. The senior counsel for the
petitioner has been heard further and he has during the hearing, also handed
over the copy of the draft resolution from the minutes of the 346th Meeting of
the Board of Directors of the petitioner held on 13th October, 2015 and which
has been taken on record. The counsel for the respondent No.1 PNGRB
appearing on advance notice has relied on General Electric Technical
Services Company Inc. Vs. Punj Sons (P) Ltd. (1991) 4 SCC 230, Centax
(India) Ltd. Vs. Vinmar Impex Inc. (1986) 4 SCC 136 and Assistant
Collector of Central Excise, Chandan Nagar, West Bengal Vs. Dunlop
India Ltd. (1985) 1 SCC 260 in relation to the encashment of bank guarantee
and interim stay.
4. I have considered the rival contentions.
5. Regulation 10 of the PNGRB Regulations supra is as under:
"10. Capacity booking, natural gas tie-up and financial closure:
(1) The authorised entity shall achieve agreement for transport of natural gas with any entity equal to at least fifty percent of the natural gas pipeline volume bid as specified in clause (d) to sub- regulation (1) of regulation 7 for each of the first five years following the commissioning of the natural gas pipeline.
(2) The agreement specified under sub-regulation (1) shall be entered into a transparent manner and be based on the principle of at an arm's length: Provided that up to ten percent of the throughput in the natural gas pipeline specified under sub- regulation (1) may be booked on firm and mutually agreed terms without insisting on physical delivery
of natural gas.
(3) The entity shall submit copy of the agreement specified under sub-regulation (1) to the Board within a period of ninety days of the date of the issue of the authorization.
(4) The authorized entity shall obtain the financial closure of the project from a bank or financial institution within a period of one hundred and twenty days from the date of the authorization. (5) In case of an internally financed project, the entity shall submit the approval of its Board of Directors' for the detailed feasibility report (hereinafter referred as DFR) of the project alongwith its financial plan within one hundred and twenty days of the authorization:
Provided that the Board may ask the entity to submit any further details or clarifications on the financial closure.
(6) In case the entity fails to meet the requirements at sub-regulation (1) to (5), the authorization of the entity for laying, building, operating or expanding natural gas pipeline shall be cancelled and the performance bond shall be encashed and the Board reserves the right to re-award the authorization in a transparent manner and the entity shall have no right whatsoever against the Board for seeking any compensation or remedy on this account."
6. Clause 7 of Schedule D of the authorization dated 25th April, 2012
aforesaid granted by PNGRB to the petitioner is as under:
"7. The entity shall submit a detailed and clear financial closure report to the Board within a period of one
hundred and eighty days from the date of authorization issued by the Board under regulation 9 of the Petroleum and Natural Gas Regulatory Board (Authorizing Entities to Lay, Build, Operate or Expand Natural Gas Pipelines) Regulations, 2008."
and Clause 17.5 of the terms and conditions of the contract accepting
which bid was made by the petitioner is as under:
"17.5 Financial Closure The entity shall be required to achieve financial closure of the project based on the numbers quoted by them in the financial bid. Failure to achieve financial closure within the stipulated period may result in the termination of the grant of authorization. The entity shall furnish all the documents as required to satisfy PNGRB that the financial closure has been achieved in line with the requirements, which shall include the following:
a) Complete Board agenda items with Annexures detailing total CAPEX, OPEX, year-wise financing plan and detailed feasibility Report (DFR).
b) Copy of all documents submitted to Financial institutions seeking financial assistance.
c) To establish the actual date of achieving financial closure, all documents executed by the company in respect of financial assistance for the project to be provided by the lenders by way of loans, bonds, security arrangements etc."
7. The senior counsel for the petitioner has not even contended that the
PBG furnished was conditional and that the conditions precedent for
invocation thereof have not been satisfied or that the invocation of the PBG
is not in terms thereof. A perusal of the PBG, encashment whereof is sought
to be stayed, shows that the respondent No.2 Bank had agreed to pay a sum
of Rs.20 crores to PNGRB at the request of the PNGRB and had further
agreed that the decision of PNGRB, as to whether the petitioner had failed to
or neglected to perform its duty and obligation under the authorization and /
or whether the service is free from deficiencies and defects and is in
accordance with or not, of the terms and conditions of the authorization and
as to the amount payable to PNGRB to be final and binding on the Bank.
The PBG of which stay of encashment is sought is absolute and
unconditional and with respect to which PBGs the Supreme Court in plethora
of judgments has held that no stay of encashment can be granted. Reference,
besides to the judgments cited by the counsel for PNGRB, may also in this
regard be made to U.P. Co-operative Federation Ltd. Vs. Singh Consultants
& Engineers (P) Limited (1988) 1 SCC 174, Svenska Handelsbanken Vs.
M/s. Indian Charge Chrome (1994) 1 SCC 502, U.P. State Sugar
Corporation Vs. Sumac International Ltd. (1997) 1 SCC 567 and Himadri
Chemicals Industries Ltd. Vs. Coal Tar Refining Company (2007) 8 SCC
110. The settled legal position is that no stay of encashment of bank
guarantee can be granted by the Courts except on finding a fraud of
egregious nature having been practised in obtaining of the bank guarantee so
as to vitiate the underlying transaction. The contract of Bank Guarantee in
Vinetec Electronics Private Limited Vs. HCL Infosystems (2008) 1 SCC
544 has been reiterated to be an independent one between the Bank and the
beneficiary de hors the contract between the beneficiary and the person at
whose instance the Bank has given the guarantee.
8. The senior counsel for the petitioner has neither made out nor argued
that PNGRB, in the matter of obtaining the said PBG from the petitioner, has
played any fraud of egregious nature.
9. The counsel for PNGRB is thus right in his contention that this
petition is liable to be dismissed on this ground alone.
10. However, for the sake of completeness, the arguments of the senior
counsel for the petitioner may also be noticed.
11. The entire case made out is that the stand of PNGRB, of the petitioner
having not satisfied the requirements of the clauses aforesaid of the tender
documents and the authorization and of Regulation 10(4) supra is erroneous.
12. Notice in this regard may first be taken of the letter dated 30 th
September, 2015 of PNGRB which according to the senior counsel for the
petitioner is the letter of invocation of PBG. The stand of PNGRB in the
said letter is, (a) that the Board of Directors of the petitioner in the meeting
held on 26th October, 2012 had accorded approval for the project aforesaid
with an estimated cost of Rs.10281.01 crores including foreign exchange
component of Rs.393.73 crores; (b) that the petitioner, in its letter dated 20th
December, 2012 supra, stated that its Board envisaged that other equity
partners may also be inducted to participate in the project, wherein, the
petitioner would be the lead partner with more than 50% equity, thus
creating uncertainty on mode of financing the project, whether internally by
the petitioner or externally by Bank or Financial Institutions; (c) petitioner
vide subsequent letter dated 21st May, 2013 informed that the petitioner did
not take particular project finance but avails of debt for Capital Expenditure
on Company‟s Balance Sheet but did not present any status update on equity
sharing; (d) that though PNGRB vide its letter dated 11th June, 2013
requested the petitioner to submit details of equity partners and their
contribution / share towards the project but petitioner vide letter dated 15 th
July, 2013 replied that discussions were in progress with different potential
JV partners and no JV agreement had been finalised till then; (e) that though
as per PNGRB Regulations, approval of the Board of Directors would
suffice for an internally financed project but since the petitioner had
informed that its Board of Directors envisaged other equity partners, it could
not be treated as an internally financed project and hence the Board approval
could not be construed as financial closure, in the absence of any details of
other equity partners to be inducted to participate in the project with the
petitioner as the lead partner and there is thus an uncertainty about the equity
sharing pattern of the project; and, (f) that since the petitioner inspite of
ample opportunity had failed to achieve financial closure, the petitioner was
in breach of authorization and accordingly in accordance with Regulations,
25% of the PBG, amounting to Rs.5 crores, was being encashed from the
PBG aforesaid.
13. The senior counsel for the petitioner has drawn attention to the
minutes of the meeting of the Board of Directors of the petitioner held on
26th October, 2012 which is as under:
"Item No.14 Sub: Laying of Surat-Paradip Pipeline (SPPL) authorised to GAIL by PNGRB through bidding route The Board discussed the agenda in detail. It was informed that HOA/MoU for transportation of natural gas for at least 50% of volume as per PNGRB regulations is in progress. It was also informed that a number of initiatives are taken for
sourcing long term gas for the project. Some of the oil PSUs have expressed interest to take equity and participate in the project. In the event of formation of JV, GAIL as lead partner will need to have more than 50% equity stake in the JV and if GAIL's share of equity exceeds Rs.1000 crores, necessary Government approval would be sought. It was decided by the Board that financial commitment for the project should synchronize with tie-up of gas source and signing of requisite HOA/MoU with consumers.
The Board after detailed discussions approved the agenda and passed the following resolutions:
"RESOLVED THAT approval of the Board be and is hereby accorded for laying and operating cross-country pipeline from Surat (Gujarat) to Paradip (Orissa) (SPPL) with an estimated cost of Rs.10,281.01 crores (including IDC & escalation) with estimated foreign exchange component of Rs.393.73 crores."
to contend that same satisfies the requirement of Regulation 10(4) &
(5). Attention was next invited to the resolution passed by its Board by
circulation on 15th June, 2015 and which is as under:
"RESOLVED THAT, the financing of Surat Paradip Pipeline Project as approved by Board in its 303rd Meeting shall be done on the basis of internal generations and borrowings based on the strength of GAIL's Balance Sheet subject to following:
(i) Extension of authorization by PNGRB for further 36 months linked to development of dharma RLNG terminal as gas source.
(ii) Approval of PNGRB for creation of lien or charge or hypothecation on the assets of the natural gas pipeline to secure finances."
14. Two questions arise for consideration. One, whether there can be
judicial review under Article 226 of the Constitution of India of the
conclusion of the PNGRB of the petitioner having not achieved the financial
closure and / or having not satisfied the conditions of Regulation 10 supra
and if the answer to the same is in the affirmative, two, whether the
conclusion of PNGRB in this respect can be said to be so arbitrary and
illogical as to be struck down in writ jurisdiction and axiomatically the
encashment of the PBG be stayed.
15. The Bank, in the Bank Guarantee, of invocation whereof stay is
sought, has absolutely, irrevocably and unconditionally undertaken to
PNGRB that the decision of the PNGRB as to whether the petitioner has
failed to or neglected to perform or discharge its duties and obligations under
the authorization and as to the amount payable by the bank to the PNGRB
under the guarantee shall be final and binding on the bank. Supreme Court
in National Highway Authority of India Vs. Ganga Enterprises (2003) 7
SCC 410, also concerned with the relief of refund of the bid security
forfeited by NHAI held that it is settled law that disputes relating to contracts
cannot be agitated under Article 226 of the Constitution of India; the dispute
regarding forfeiture of bid security is regarding the term of offer and thus
contractual in respect of which a writ Court is not the proper forum; invoking
Bank Guarantee and / or enforcing the bid security is not in exercise of any
statutory right; forfeiture of earnest / security in no way affects any statutory
rights; such earnest / security is given and taken to ensure that a contract is
performed; the law regarding enforcement of an on demand Bank Guarantee
is very clear; if the enforcement is in terms of the guarantee then Courts must
not interfere with the enforcement of Bank Guarantee; the Court can
interfere if the invocation is against terms of the guarantee or if there is any
fraud; if the guarantee is rightly invoked, there is no question of directing
refund. Accordingly, the writ petition was dismissed. Supreme Court in
Jagdish Mandal Vs. State of Orissa (2007) 14 SCC 517 held that judicial
review of administrative action is intended to prevent arbitrariness,
irrationality, unreasonableness, bias and mala fides but cautioned that a
Court, before interfering in a tender or contractual matter in exercise of
power of judicial review, should pose to itself the questions whether the
process adopted or decision made by the authority is mala fide or intended to
favour someone or whether the process adopted or decision made is so
arbitrary and irrational that the Court can say that the decision is such that no
reasonable authority acting reasonably and in accordance with relevant law
could have reached and whether public interest is affected. It was further
held that if the answers to the said questions are in the negative then there
should be no interference under Article 226. This view has been reiterated in
Michigan Rubber (India) Ltd. Vs. State of Karnataka (2012) 8 SCC 216
and in Maa Binda Express Carrier Vs. North-East Frontier Railway (2014)
3 SCC 760. Applying the said test to the present controversy, no case for
exercise of power of judicial review of the decision of PNGRB to invoke the
Bank Guarantee for Rs.20 crores in the sum of Rs.5 crores only is made out.
It cannot be lost sight of that instead of 120 days from the grant of
authorization on 25th April, 2012, more than 4 years have since lapsed.
16. Though the expression „financial closure‟ is not defined in the
PNGRB Act or PNGRB Regulations supra copy of which was handed over
during the course of hearing by senior counsel for petitioner but is
commercially understood as the process of completing all project related
financial transactions, finalising and closing the project financial accounts,
so that it is definitely known that the project will not be held up for the
reason of financial constraints.
17. The senior counsel for the petitioner stated that Regulation 10(4) supra
applies, in case of the project finance being obtained from a Bank or a
Financial Institution and is not applicable in the present case, since the
petitioner intends to internally finance the project aforesaid.
18. The only question for consideration thus is whether the petitioner, by
submitting the documents aforesaid, has satisfied the conditions of
Regulation 10(5) supra.
19. The contention of the senior counsel for the petitioner is that once the
Board of Directors of the petitioner has decided to undertake the said project,
the same is sufficient.
20. However that is not the requirement of Regulation 10(5). What
Regulation 10(5) requires is the approval of the Board of Directors of the
detailed feasibility report of the project along with its financial plan. The
same is understood by me, as an approval by the Board of Directors of the
allocation of the project, cost from its internal funds. The senior counsel for
the petitioner inspite of repeated asking could not show that the Board of
Directors has at any time agreed so. Even in the meeting held on 13th
October, 2015, during the hearing of this petition, all that the Board of the
petitioner has agreed is as under:
"Item No.346.15 Sub: Financial Closure of Surat - Paradip Pipeline (SPPL) Project
"RESOLVED THAT the financing of Surat Paradip Pipeline Project as approved by Board in its 303 rd meeting of Board shall be done based on the strength of GAIL's Balance Sheet"."
21. In my opinion, the conclusion reached by the PNGRB, of Regulation
10(5) having not been satisfied, cannot be said to be wholly illogical or
which no reasonable person could have reached. It cannot be lost sight of
that the petitioner, in the communication dated 17th September, 2013 stated
that "it is to assure the Hon‟ble Board that GAIL has already done the
financial closure of SPPL and is capable to finance the said project internally
and with external borrowings". No details of external borrowings have been
given. Before that, in the communication dated 20th December, 2012
enclosing the minutes of the meeting of the Board of Directors held on 26 th
October, 2012, it was stated that "GAIL‟s Board has also envisaged that
other equity partners may also be inducted to participate in the project,
wherein, GAIL would be the lead partner with more than 50% equity".
Thereafter, in the resolution passed by the Board of Directors of the
petitioner by circulation on 15th June, 2015, it was again stated that the
financing of the said project "shall be done on the basis of internal
generations and borrowings based on the strength of GAIL Balance
Sheet....". It is thus not clear as yet, whether the petitioner intends to involve
other partners in the project and whether it intends to borrow externally, to
meet the project cost and if so, from what source. Merely because the
petitioner may have reserves of Rs.24,000 crores, as is repeated / asserted
during the hearing, would not be sufficient for the purposes of Regulation
10(5) supra, without the Board of Directors of the petitioner being ready to
earmark the said reserves to meet the project cost. Similarly, the argument
of the senior counsel for the petitioner that the time for completion of the
project being of three years, the same can be meted out from the annual
earnings of the petitioner, is also of no avail, without the petitioner satisfying
the PNGRB of the certainty of such finance and of the same being not
already allocated for some other project.
22. Thus, neither a case for grant of an injunction restraining encashment
of PBG is made out nor otherwise any merit is found in the claim of the
petitioner.
23. The petition is accordingly dismissed.
24. It is however clarified that none of the observations herein, which are
made only for the purposes of examining, whether a case for restraining
encashment of PBG is made out, would have any sway on the claim, if any
of the petitioner in arbitration or suit, against the respondents for wrongful
encashment of the PBG.
No costs.
RAJIV SAHAI ENDLAW, J.
OCTOBER 14, 2015 bs..
(corrected & released on 18th November, 2015)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!