Citation : 2015 Latest Caselaw 4351 Del
Judgement Date : 28 May, 2015
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Judgment decided on May 28, 2015
+ OMP (I) 267/2015
VIL LIMITED ..... Petitioner
Through: Mr.K.V.Singh, Adv. with
Mr.Nachiketa Goyal,
Mr.Rishabh Arora, Advs.
versus
NATIONAL HIGHWAYS AUTHORITY OF INDIA
..... Respondent
Through: Ms.Ayushi Kiran, Adv. with
Mr.Mukesh Kumar, Adv.
CORAM:
HON'BLE MR. JUSTICE V.KAMESWAR RAO
V.KAMESWAR RAO, J. (Oral)
1. This petition has been filed under Section 9 of the Arbitration and
Conciliation Act, 1996 (Act, in short) inter alia seeking the following
reliefs:
"(i) Restrain the Respondent from recovering or adjusting any or all of the part of the aggregate amounts advanced to the Petitioner as three (3) separate installments, viz. (i) 1st advance installment amounting to Rs. 5.58 crores; (ii) 2 nd advance installment amounting to Rs. 8.37 crores and (iii) 3rd advance installment amounting to Rs. 13.95 crores aggregating approximately Rs. 27.9 crores;
(ii) Restrain the Respondent from taking any other coercive action against the Petitioner, including imposing any penalty or liquidated damages or recovering any other amount(s) whatsoever from the Petitioner for any alleged action or inaction, including slow progress or non-performance on the
part of the Petitioner"
2. It is the case of the petitioner that the respondent invited proposal
by its request for annual pre-qualification dated September 11, 2012 for
short-listing of bidders for two lanning with paved shoulders of
Sitarganj-Bareilly Section of NH-74 from 254.820 KM to 329.280 KM
in the states of Uttarakhand and Uttar Pradesh on Engineering,
Procurement, Construction mode. Thereafter, the respondent invited
bids from the short-listed bidders for undertaking the project. The
respondent accepted the bid of the petitioner for Rs. 279 Crores only. An
EPC Agreement dated October 25, 2013 with a construction period
starting from the appointed date and ending on 730th day was entered
into between the parties.
3. According to Mr.K.V.Singh, the learned counsel for the petitioner,
as per Article 4.1.3 (a) of the agreement, upon the petitioner furnishing
the performance security, the respondent was obliged to provide at least
90% of the total length of the project highway free from any
encroachment and encumbrance to the petitioner within 15 days of the
date of the agreement. According to him, clause 8.2.3 of the agreement,
which is a non-obstante clause, clearly stipulates that under no
circumstance, the cumulative length of the project site which the
respondent could not deliver to the petitioner within 15 days of the date
of the agreement shall exceed 10% of the total length of the project. It is
his submission that in response to the queries of the petitioner in the pre-
bid meeting dated June 20, 2013, the respondent stated that the total
available land with the respondent was 211.72 Hectares i.e. 92.6%. A
performance guarantee for a total sum of Rs.20,92,50,000/- was also
furnished by the petitioner. He states that in terms of clause 19.2.1 of the
agreement, the respondent had made an interest fee advance payment
equal in amount to 10% of the contract price for mobilization expenses
and for acquisition of equipment. The advance payment was made in
three instalments of 2%, 3% and 5% of the contract price respectively
i.e. Rs.5.58 Crores, Rs.8.37 Crores and Rs.13.95 Crores aggregating
approximately Rs.27.9 Crores. He would also state that against the
advance payment made by the respondent in terms of clause 19.2.2, the
petitioner has given an irrevocable and unconditional guarantee from a
Bank for an amount equivalent to 110% of such instalment paid by the
respondent. According to him, the petitioners in all furnished four
irrevocable and unconditional bank guarantees in favour of the
respondent.
4. It is his case that the respondent had not provided 90% of the right
of way to the total project site within 15 days of the submission of the
performance guarantee. He would state, the respondent has only been
able to provide 37% of the total right of way, thus, the respondent has
played egregious fraud upon the petitioner by falsely stating, at the time
of pre-bid queries that the total available land with the respondent was
92.6 % and thereby inducing the petitioner to bid for the project and
enter into an agreement with the respondent. According to him, the
period of 730 days would commence only after 90% of the right to way
was provided to the petitioner. He has drawn my attention to the
definition of "appointed date" to mean that date, which is later of the 15th
day of the date of the agreement, the date of which the contractor has
delivered the performance security in accordance with the provisions of
Article 7 and the date on which the authority has provided the right of
way on no less than 90% of the total length of project highway. He
would rely upon the two judgments in support of his submissions
reported as (1997) 1 SCC 568, U.P. State Sugar Corporation Vs. Sumac
International Ltd. and 177 (2011) Delhi Law Times 248 (DB) Simplex
Infrastructure Ltd. Vs. National Highways Authority of India to
contend that the fraud has been played by the respondent by representing
it in the pre-bid meeting, thereby inducing the petitioner to enter into a
contract and further, to contend that the respondent is required to
maintain the sanctity of the contract and the respondent should maintain
the status quo by not taking an action to the prejudice of the petitioner
till such time the disputes are decided by an appropriate forum.
5. On the other hand, Ms.Ayushi Kiran, learned counsel, who
appears on advance notice on behalf of the respondent, would submit
that there is a concealment of relevant facts by the petitioner which
would disentitle the petitioner to any relief in this petition. According to
her, the respondent has handed over the complete land to the petitioner.
In this regard, she has placed before me a communication dated January
24, 2014 to contend that on as on January 24, 2014, except 1.27 length
Kilo Meter, for the rest of the site, right of way was provided to the
petitioner. She would also state, for the balance stretch of 1.27 Kilo
Meter, the right of way was provided on July 15, 2014 in terms of the
letter of the same date, which also was placed before me. In fact, it is
her submission that the petitioner, vide its own letter dated January 31,
2014 has accepted the appointed date for the above project as January
24, 2014. She would also draw my attention to the provision in the
agreement i.e. clause 19.2.6, which stipulates that advance payment shall
be repaid by the contractor to the authority not later than 365 days from
the respective date of advance payment. Because of failure on the part of
the petitioner to execute the work, so as to recover the amount of
advance payment from the bills, necessity has arisen for invocation of
the bank guarantees furnished by the petitioner against the advance
payment. She would state, out of four bank guarantees, three bank
guarantees have been invoked and honoured by the bank. Insofar as the
fourth bank guarantee for an amount of Rs. 15.345 Crores, that has not
been invoked/encashed till date.
6. Having heard the learned counsel for the parties, suffice to state,
the submissions made by Mr.K.V.Singh, learned counsel for the
petitioner, was on the merit of the dispute between the parties. It may be
necessary to state here, even though, the prayer has been couched in
such a way from where, it appears that the petitioner is seeking only a
restraint order against the respondent from adjusting the money, in
effect, the petitioner is seeking a restraint order against the respondent
from invoking the bank guarantee(s). The position of law insofar as
invocation of bank guarantees are concerned is well settled in terms of
one of the judgments so relied upon by the learned counsel for the
petitioner. In para 12 of U.P.State Sugar Corporation (supra), the
Supreme Court has held that the Courts should be slow in granting
injunction to restrain the realization of a bank guarantee. The Court had
also observed, the two exceptions carved out to include a fraud in
connection with such a bank guarantee would vitiate the very foundation
of such a bank guarantee and cases, where, allowing the encashment of
an unconditional bank guarantee would result in irretrievable harm or
injustice to one of the party concerned. The only plea advanced by the
learned counsel for the petitioner that the respondent has played fraud in
representing that 92.6% of the site was available which induced the
petitioner to enter into an agreement. Suffice to state that such a plea is
not related to fraud having been played by the respondent in connection
with bank guarantee(s) with which we are concerned in this petition. No
submission has been made by the learned counsel for the petitioner
insofar as the other exception carved out by the Supreme Court. Apart
from the judgment in U.P.State Sugar Corporation (supra), there are
other judgments of the Supreme Court wherein the law laid down in
U.P. State Sugar Corporation (supra) has been upheld and ratified. I
note for benefit the judgment in Federal Bank Ltd. Vs. V.M.Jog
Engineering Ltd. and Ors., (2001) 1 SCC 663 wherein, the Supreme
Court observed that the Court ought not to grant injunction, to restrain
invocation of bank guarantees or letters of credit. The Supreme Court
carved out two exceptions to this rule, viz. fraud and irretrievable
damage. It further observed that the contract of bank guarantee or letter
of credit is independent of the main contract between the seller and the
buyer. In case of an irrevocable bank guarantee or letter of credit, the
buyer cannot obtain injunction against the final payment on the ground
that there was a breach of the contract by the seller. The bank is to
honour the demand for encashment if the seller, prima facie, complies
with the terms of the bank guarantee or the letter of credit namely, if the
seller produces the documents enumerated in the bank guarantee or the
letter of credit. If the bank is satisfied on the basis of the documents that
they are in conformity with the list of documents mentioned in the bank
guarantee or the letter of credit and there is no discrepancy, it is bound to
honour the demand of the seller for encashment. It is not permissible for
the bank to refuse the demand on the ground that the buyer is claiming
that there is a breach of contract. The obligation of the bank under the
documents has nothing to do with any dispute as to breach of contract
between the seller and the buyer. The Supreme Court also observed that
in order to obtain injunction against the issuing bank that it is necessary
to prove that the bank had knowledge of fraud. The Supreme Court
relied on the observations of Kerr, J. in R.D. Harbottle (mercantile)
Ltd. Vs. National Westminster Bank Ltd. (1978) QB 146:(1977) 2 All
England Reporter 862 to state that irrevocable Letters of Credit are
"lifeblood of international commerce" and also observed as under:
"Except possibly in clear cases of fraud of which the banks have notice, the Courts will leave the merchants to settle their disputes under the contracts by litigation or arbitration........Otherwise, trust in international commerce could be irreparably damaged."
Denning M,R, .stated In Edward and Owen Engineering Ltd. v. Barclays Sank International Lid. (1978) Q.B. 159 that 'the only exception is where there is a clear fraud of which the bank had notice": Browne, LJ. said in the same case : "but it is certainly not enough to alleged fraud, it must be established" and in such circumstances, I should say, very clearly established", in Bolvinter Oil S.A.v. Chase Manhattan Bank, (1984) 1 All E.R, 351 at P. 352, it was said 'where it is proved that the Bank knows that any demand for payment already made or which may thereafter be made, will clearly be fraudulent. But the evidence must be clear both as to the fact of fraud and as to the bank's knowledge. It would certainly not be sufficient that this rests Upon the uncorroborated statement of the customer,, for irreparable damage can be done to a bank's credit in the relatively brief time "before the injunction is vacated". Thus, not only must 'fraud' be clearly proved but so far as the Bank is concerned, it must prove that it had knowledge of the fraud. In United Trading Corp. S.A. v. Allied Ards Bank, (1985) 2 Lloyds Rep, 554, it was stated that there must be proof of knowledge of fraud on the part of the Bank at any time before payment".
7. Insofar as the other judgment relied upon by the learned counsel
for the petitioner in Simplex Infrastructure Ltd. (supra), is concerned,
the same is not applicable in the facts of this case. In the said case, the
relief sought for by the petitioner was seeking a restrain order from
implementing and/or enforcing or otherwise giving effect to letters and
deducting any amounts from payment due to the petitioner or recovering
any payment in pursuance of letters until eventual resolution of disputes
between the petitioner and the respondent. As stated above, even
though, the petitioner has couched the prayer in such a manner to give an
impression that it is also seeking a similar prayer, but, in effect, the
prayer is to seek a restraint order against the respondent from invoking
the bank guarantee(s), which in view of this Court cannot be granted.
8. I do not see any merit in the petition. The petition is accordingly
dismissed.
(V.KAMESWAR RAO) JUDGE MAY 28, 2015 akb
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!