Saturday, 25, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Edcil (India) Ltd vs Visesh Infotecnics Ltd
2014 Latest Caselaw 5213 Del

Citation : 2014 Latest Caselaw 5213 Del
Judgement Date : 16 October, 2014

Delhi High Court
Edcil (India) Ltd vs Visesh Infotecnics Ltd on 16 October, 2014
$~11

*      IN THE HIGH COURT OF DELHI AT NEW DELHI
+      RFA 484/2012
                                               Decided on 16th October, 2014

       EDCIL (INDIA) LTD                                   ..... Appellant

                          Through      : Mr. K.C. Dubey, Adv.

                          versus

       VISESH INFOTECNICS LTD                              ..... Respondent

                          Through      : Mr. Tarun Kr. Bedi, Adv.

CORAM:
HON'BLE MR. JUSTICE A.K. PATHAK

A.K.PATHAK, J.(ORAL)

1.     Appellant - defendant no. 2 was acting as Consultant for defendant

no. 3 - National Institute of Foundry & Forge Technology (NIFFT), Hatia,

District Ranchi, Jharkhand.        Government of India through Secretary,

Ministry of Communication and Information Technology was impleaded as

defendant no. 1. However, defendant nos. 1 and 3 have not been impleaded

in the appeal as respondents on the pretext that neither any decree has been

passed against them nor any relief has been pressed in this appeal qua them.


2.     Briefly stated facts are that defendant no. 3 requested the appellant to

supply and install desktop computers at the institute of defendant no. 3 at
RFA 484/2012                                                   Page 1 of 6
 Hatia, District Ranchi in the State of Jharkhand. In turn, appellant awarded

contract to respondent for supply and installation of desktop computers

along with accessories at the defendant no.3 institute vide purchase order

dated 28th August, 2006. As per the purchase order, respondent was to

supply HP DX 7200 desktop computers.            As the said model was not

available in the market at the time of delivery, therefore, specifications were

changed with the consent of appellant and it was agreed that respondent will

supply more advanced model, that is, HP-DC-7600. Respondent completed

the supply and installation of computers by 5 th January, 2007 to the

satisfaction of defendant no.3.


3.    As per the purchase order, full supply and installation was to be

completed by November, 2006. There was delay of about two months in

completion of contract. Appellant made payments from time to time but

withheld `4,85,598/- on the ground that penalty @ 2% of the delivery price

for each week, subject to maximum deduction of 8% was to be leviable on

the respondent in terms of Clause 10 of purchase order, on account of

delayed supply and installation of computers. Respondent was aggrieved on

account of withholding of the amount of `4,85,598/- by the appellant,

therefore, approached the trial court by filing the suit for recovery of

RFA 484/2012                                                   Page 2 of 6
 `4,85,598/- together with interest @ 18% per annum. It was alleged that

appellant could not have withheld `4,85,598/- towards penalty. Supply and

installation of the computers at the premises of defendant no. 3 was done to

the satisfaction of defendants. Specification was changed with the consent

of defendant no.2 on account of non-availability of the ordered model.

Thus, appellant had no right to withhold the payment of respondent to the

extent of `4,85,598/-.


4.    Case, as set up by the appellant before the trial court, was that

`4,82,205/- was withheld on account of liquidated damages. Appellant was

well within its rights to withhold the said payment, in terms of purchase

order, which envisaged that liquidated damages equivalent to 2% of the

delivered price for the delay in delivering the goods for each week was

payable by the respondent, subject to maximum deduction of 8%.

Appellant alleged that respondent had failed to adhere to the time scheduled

for delivery of installation, thus, appellant had rightly withheld the payment.

It was not disputed that purchase order was issued by the appellant. It was

also not disputed that respondent had completed the supply and installation

of the computers to the satisfaction of defendant no. 3 and the appellant by

5th January, 2007.

RFA 484/2012                                                   Page 3 of 6
 5.    On scrutiny of the evidence adduced by the parties, trial court has

held that facts were not in dispute to the extent that purchase order was

issued for the supply of desktop computers. It was also not in dispute that

supply and installation of computers at the premises of defendant no. 3 was

successfully completed by 5th January, 2007. It was also not disputed that

there was delay in completion of supply and installation of computers.

Installation was to be completed by November, 2006 but was completed on

5th January, 2007. However, trial court has concluded that the amount was

withheld by way of penalty and not on account of pre-estimated liquidated

damages. There was nothing on record to suggest that loss of about 4 lacs

was suffered by the appellant. The penalty was in the nature of in terrorem,

thus, the provision of Section 74 of the Indian Contract Act, 1872, was

attracted and in absence of any evidence on record to indicate actual loss

suffered by the appellant with regard to the delayed supply and installation,

appellant was only entitled to reasonable damages and not to an amount of

`4,82,205/-. Trial court has held that the damages to the extent of `50,000/-

towards penalty would be sufficient.



RFA 484/2012                                                  Page 4 of 6
 6.    I have heard learned counsel for the parties and perused trial court

record. From the facts narrated above, it is clear that `4,82,205/- was

withheld by way of penalty and not on account of pre-estimated assessed

damages. It is also borne out from the records that HP-DX-7200 model

which was agreed to be supplied, was discontinued.             Accordingly, a

proposal was given by the respondent for supplying another model, that is,

HP DC 7600 and some time took place in this process. Ex. PW1/D1 is the

document in respect of permission sought by the respondent for supply of

computers of different model on account of discontinuance of earlier model,

which was agreed to be supplied. It is also borne out from the records that

supply was completed on 5th January, 2007, at the premises of defendant no.

3 that too to the satisfaction of defendant no.3. It is also not in dispute that

appellant has received the entire payment from the defendant no. 3, thus,

question of any loss does not arise. No penalty was imposed by defendant

no. 3 on the appellant in respect of delayed installation, for the reasons

beyond the control of respondent. In view of this, it is clear that `4,82,205/-

was withheld under the garb of Clause 10 by way of penalty and not on

account of pre-estimated liquidated damages. Accordingly, trial court has




RFA 484/2012                                                    Page 5 of 6
 not committed any error by holding that appellant was only entitled to

reasonable damages and not the amount calculated as per Clause 10.


7.    Trial court has awarded damages to the tune of `50,000/- and has

directed appellant to pay balance withheld amount.         I do not find any

illegality in the view taken by the trial court.


8.    Appeal is dismissed. Amount lying deposited in this Court together

with interest accrued thereon, if any, be released to respondent.




                                                           A.K. PATHAK, J.

OCTOBER 16, 2014 rb

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter