Tuesday, 28, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

North Municipal Corporation Of ... vs Shri Umesh Kumar Gupta & Anr
2014 Latest Caselaw 5929 Del

Citation : 2014 Latest Caselaw 5929 Del
Judgement Date : 18 November, 2014

Delhi High Court
North Municipal Corporation Of ... vs Shri Umesh Kumar Gupta & Anr on 18 November, 2014
$~2
*     IN THE HIGH COURT OF DELHI AT NEW DELHI
+     FAO 473/2013
                          Decided on 18th November, 2014

      NORTH MUNICIPAL CORPORATION OF DELHI &
      ANR                               ..... Appellants
                   Through: Mr. Sunil K Goel, Adv.

                          versus

      SHRI UMESH KUMAR GUPTA & ANR                  ..... Respondents

                          Through:     Mr. Ranjeet Kumar, Adv.

CORAM:
HON'BLE MR. JUSTICE A.K. PATHAK

A.K.PATHAK, J.(ORAL)


1.    Respondent was enrolled as a contractor with the appellant.

Appellant awarded work of improvement of Hall, Duty Room adjoining

Labour Room in GLM Hospital in City Zone to the respondent. Work was

completed by the respondent in time, inasmuch as, same was inspected by

the Engineer-in-Chief who recorded the same in measurement book no.

1018, after taking measurement.      After completing the work respondent

raised the final bill. Appellant did not pass the bill despite requests of the

respondent for preparing and passing the final bill. Instead, appellant started

disputing the factum of work done by the respondent. In these

FAO 473/2013                                                        Page 1 of 5
 circumstances, respondent invoked Arbitration Clause No. 25 of the General

Terms and Conditions of Agreement and issued notice dated 17th April,

2008. Appellant sent a reply and requested the respondent to submit details

of the work carried out including names of Junior Engineers and Assistant

Engineers under whose supervision he had executed the work.             Entire

information was submitted by the respondent to appellant vide letter dated

2nd May, 2008.      Despite this bill was not prepared and passed by the

appellant.

2.    Ultimately, respondent approached this Court for appointment of an

Arbitrator wherein Arbitrator was appointed, vide order dated 15th May,

2009, passed in Arbitration Application No. 237/2008 titled Shri Umesh

Kumar Gupta vs. Municipal Corporation of Delhi & Anr. Pursuant to the

order passed by this Court, Arbitrator entered upon the reference and

afforded opportunity to the parties file their respective pleadings,

documents, inasmuch as, to lead oral evidence.

3.    Following issues were framed by the Arbitrator :-

      i)       Whether the claims filed by the Claimant are not
               arbitrable as the Claimant has not raised the claims
               before the SE concerned/CE concerned in view of Clause
               25 of the General Terms & Conditions?




FAO 473/2013                                                     Page 2 of 5
       ii)      Whether the Claims no.2,3 and 4 of the Claim Petition
               are also not arbitrable being beyond the General Terms &
               Conditions of the Agreement and as such are out of the
               ambit of Section 28(3) of the Arbitration & Conciliation
               Act, 1996?

      iii)     Whether the claims of the Claimant are barred by
               limitation?

      iv)      Whether the Claimant is entitled to the claims as made
               out by him in the Claim Petition?

4.    On the basis of evidence adduced by the parties, Arbitrator held that

claim no.1 did not survive as the principal amount was paid during the

pendency of arbitration proceedings. As regards claim no. 2 about earnest

money, it was ordered to be refunded. Claim no. 3 regarding damages was

declined. Claim no. 5 was in respect of interest on the delayed payment and

withheld earnest money @ 18 % per annum from the date of completion of

work/notice till the date of payment. This claim has been allowed and

appellant has been directed to pay interest @ 9 % per annum on `1,31,460/-

with effect from 1st September, 2006, that is, 3 months after submission of

the bill till the date of payment, that is, 31st March, 2011. Interest on the

earnest money has also been allowed. Claim no. 4 was with regard to the

cost of proceedings which has been partially allowed.




FAO 473/2013                                                       Page 3 of 5
 5.    Aggrieved by the Award appellant preferred a petition under Section

34 of the Arbitration & Conciliation Act, 1996 (for short, hereinafter

referred to as the 'Act') which has been dismissed by the trial court by the

order impugned in this appeal. Trial court has held that full opportunity was

given to appellant to contest the case by the Arbitrator, inasmuch as, Award

was well reasoned Award. All the objections of appellant had been taken

due care of. It has been further held that court could not have sifted and

weighed the evidence on record so as to substitute its findings as against the

findings returned by the Arbitrator, as if hearing the appeal. Trial court

concluded that none of the grounds, as envisaged under Section 34 of the

Act, could be made out.

6.    I have heard learned counsel for the parties and perused the Award as

well as impugned order and do not find any illegality or perversity therein.

Learned counsel for the appellant submitted that awarded amounts have

already been paid and appellant is challenging the Award only with regard

to award of interest. It is contended that respondent had failed to pursue the

matter, thus, appellant cannot be blamed for the delayed payment.

Respondent did not follow up the matter with the officials of respondent and

was himself guilty of contributory negligence. I do not find any force in this



FAO 473/2013                                                       Page 4 of 5
 contention. First of all, no such ground was taken before the Arbitrator,

therefore, appellant cannot rake up this issue at this stage. Findings of

Arbitrator on merits cannot be sifted and weighed by scrutinizing the

evidence adduced before the Arbitrator at threadbare as if this Court is

hearing an appeal against the award. The grounds of challenge as envisaged

under Section 34 of the Act have to be disclosed before an award can be

interfered with. Award can also be interfered with if it is shown to be

absurd that it shocks the conscience of the court. Arbitrator has given

reasons for awarding interest. Admittedly, there was a long delay in

processing the bill by the appellant for which no justification could be

offered before the Arbitrator. Respondent had submitted the bill, therefore,

it was obligatory on the part of the appellant to process the bill on the basis

of records available with it. It was also obligatory on the part of appellant to

clear the bill within a period of three months as envisaged in Clause 9 of the

General Terms and Conditions of the Agreement. Arbitrator has taken note

of all these facts and has awarded the interest.

7.    In view of above discussions, appeal is dismissed. Dasti.



                                                     A.K. PATHAK, J.

NOVEMBER 18, 2014/ga

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter