Citation : 2014 Latest Caselaw 5914 Del
Judgement Date : 18 November, 2014
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P. 745/2014
% Judgement pronounced on: 18.11.2014
M/S OPAQUE INFRASTRUCTURE PVT LTD ..... Petitioner
Through: Mr Harish Malhotra, Senior Advocate
with Mr R.K. Modi, Advocate
versus
M/S MILLENNIUM REALTECH PVT LTD ..... Respondent
Through: Mr B.R. Sharma and Mr Satpal Singh,
Advs.
CORAM:
HON'BLE MS. JUSTICE DEEPA SHARMA
JUDGMENT (ORAL)
1. The present petition has been filed under Section 9 of the Arbitration
and Conciliation Act, 1996 (hereinafter referred to as "the Act") by the
petitioner, who was the builder under a Collaboration Agreement dated
07.11.2011 between him and the respondent. The respondent was the owner
of plot of land admeasuring 1148 square yards in Khasra No. 260, situated in
the revenue estate of village Bahapur, Tehsil Kalkaji, New Delhi. Under this
Collaboration Agreement, a vertical building was to be raised comprising of
Wing-1 (South West Side) and Wing-2 (North East Side). Under the
agreement, it was the obligation of the owner, i.e., the respondent to seek
requisite permissions, sanctions and approvals for development on the said
plot at his costs and expenses after getting the building plan sanctioned from
the concerned authorities. The sanctioned plan was to be obtained within 60
days of the date of execution of this collaboration agreement. As per the
terms, the petitioner had paid a sum of Rs. 50 lakhs to the respondent on
execution of this Collaboration Agreement. As per clause 5(c) of the said
Collaboration Agreement, the petitioner was required to pay a sum of Rs. 1
core 50 lakhs to the owner, i.e., the respondent on his getting the
approval/sanction plan of the building approved from the concerned
department within 60 days of the signing of this Collaboration Agreement. It
is the admitted fact that uptil now, the respondent has not obtained any
sanctioned plan of the building from the concerned department. After
waiting for about two years, the petitioner wrote a letter dated 07.03.2013
asking the petitioner to act as per the terms of the agreement. The
respondent, however, instead of acting as per the terms of the agreement,
i.e., obtaining the sanctioned plan, offered to refund the security amount of
Rs. 50 lakh to the petitioner and sent the said amount by way of a cheque
along with his letter dated 22.03.2014. Vide this letter, the respondent also
terminated the Collaboration Agreement as null and void. The ground taken
by the respondent in this letter was that the petitioner was not financially
sound and had not developed any property and that he had not submitted the
requisite documents showing his capability to raise such a construction. The
said letter was duly replied by the petitioner vide letter dated 02.07.2014,
whereby he refused to accept the refund of the security amount and took the
plea that there was no such term or the condition in the agreement that the
petitioner was required to submit its financial credentials to the respondent
and also invoked the arbitration clause. Thereafter, the petitioner had moved
this Court under Section 9 of the Act with the prayer that so long their
dispute is resolved by the Arbitrator, the situs of the dispute, i.e., the
property should be protected and the respondent be restrained from selling,
transferring, or parting with the possession of the disputed property.
2. This Court vide order dated 15.07.2014 by way of ad interim
injunction, restrained the respondent from creating any third party interest in
the disputed property.
3. The respondent filed an application under Order 39 Rule 4 of CPC
praying for the vacation of the stay. It has also been requested by the
respondent that the said application be considered as their reply to the
petition of the petitioner under Section 9 of the Act. In their application, the
respondent has submitted that since the petitioners are not financially sound
and also have no experience to develop the building, they are not capable of
raising the construction on the said property and, therefore, the respondent
does not want that the property be developed by them. It is also submitted
that the respondent is ready to return the security amount of Rs. 50 lakh to
the petitioner.
4. During the course of arguments on the previous date before this
Court, the respondent offered to deposit the security amount of Rs. 50 lakh
with the Registrar General of this Court and accordingly, the respondent was
allowed to do so and pursuant to that, the respondent had deposited a sum of
Rs. 50 lakh as a security with the Registrar General of this Court. The
money has been kept in FDR.
5. Arguments have been heard.
6. There is no doubt that there exists a dispute between the parties
relating to the Collaboration Agreement entered into by the parties
voluntarily. There is no dispute to the fact that the Collaboration Agreement
was not conditional to the petitioner disclosing his financial status or his
experiences. It is also not in dispute that under the agreement, it was for the
respondent to obtain the sanctioned plan and all the other requisite
permissions from the concerned departments, before the obligation of the
petitioner to make the payment of Rs 1 crore 50 lakh would have arisen.
There is also no dispute to the fact that the respondent has no where
contended that he took any steps pursuant to the terms and conditions of the
Collaboration Agreement, to get the plan sanctioned. The only plea taken is
that the petitioner is not capable to fulfil the conditions of the Collaboration
Agreement. All these facts clearly show that prima facie it is the respondent
who has failed to comply with the terms and conditions of the Collaboration
Agreement and that there exists an arbitrable dispute between the parties. It
is also clear that despite the petitioner invoking the arbitration clause vide
his letter dated 02.07.2014, asking the respondent to nominate the three
Arbitrators, the respondent has not moved any further in this direction.
7. In view of this, I am satisfied that the property, which is the situs of
the dispute between the parties, needs to be protected.
8. At this stage, the learned counsel for the respondent has argued that
there is no need to pass a separate order and the property is protected under
Section 52 of Transfer of Property Act. However, Section 52 of Transfer of
Property Act deals with entirely different situation. Section 9 of the
Arbitration and Conciliation Act, despite the existence of Section 52 of the
Transfer of Property Act, confers right and jurisdiction upon the Court to
pass appropriate order in order to protect the subject matter of arbitration.
9. In view of this, the petitioner has a prima facie case in his favour and
he would suffer an irreparable loss and injury. It is apparent that if the stay
is not granted and the respondents are permitted to create third party interest
pending arbitral proceedings, it may create multiplicity of litigations. The
balance of convenience thus also lies in favour of the petitioner. I hereby
confirm my order dated 15.07.2014 and restrain the respondent, its agents
and employees from, in any manner, dealing, selling, transferring or parting
with possession of the plot of land admeasuring 1148 square yards in Khasra
No. 260, situated in the revenue estate of village Bahapur, Tehsil Kalkaji,
New Delhi.
10. The order shall remain effective till the termination of the arbitration
proceedings or till the same is modified by the Arbitrator.
11. At this stage, learned counsel for the respondent makes a request that
in view of this order, he may be permitted to withdraw the amount of Rs.50
lakhs which he had deposited with the Registrar General of this Court. He is
permitted to do so. The amount of Rs. 50 lakh be returned to the respondent.
12. The petition stands disposed of.
DEEPA SHARMA (JUDGE) NOVEMBER 18, 2014 BG
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!