Citation : 2014 Latest Caselaw 5524 Del
Judgement Date : 7 November, 2014
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 7th November, 2014.
+ LPA No.665/2014 & CM No.16288/2014 (for stay)
GURU PREMSUKH MEMORIAL COLLEGE
OF ENGINEERING & ANR. ..... Appellants
Through: Mr. Jatan Singh, Mr. Soayib Qureshi
& Mr. Mudit Gupta, Advs.
Versus
ALL INDIA COUNCIL FOR TECHNICAL
EDUCATION & ORS. ..... Respondents
Through: Mr. Amitesh Kumar & Ms. Mamta
Tiwari, Advs. for R-1.
Mr. Mukul Talwar with Mr.
Sradhananda Mohapatra & Mr. Vipin
Singh, Advs. for GGSIPU.
Ms. Bandana Shukla for Ms. Ruchi
Sindhwani, Adv. for R-3.
CORAM:
HON'BLE THE CHIEF JUSTICE
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
RAJIV SAHAI ENDLAW, J.
1. This intra court appeal impugns the judgment dated 15 th September,
2014 of the learned Single Judge of dismissal of W.P.(C) No.4007/2014
preferred by the appellants.
2. This appeal came up before this Court first on 29th September, 2014,
when the counsels for the respondents having appeared on advance notice,
we, with consent, heard the appeal finally and reserved judgment.
3. The writ petition from which this appeal arises was filed impugning
the order dated 24th June, 2014 of the respondent No.1 All India Council for
Technical Education (AICTE) placing the appellant No.1 Guru Premsukh
Memorial College of Engineering, established by the appellant No.2
Bhagwan Mahavir Education Society (Registered), under "withdrawal of
approval status" for the academic year 2014-2015 and seeking a direction to
the respondent No.1 AICTE to grant approval to the appellants for extension
of affiliation for the academic year 2014-2015 for engineering courses,
pleading:
(i) that the appellant No.1 College was granted affiliation by the
respondent No.2 Guru Gobind Singh Indraprastha University
(GGSIPU) from academic session 2000-2001 and had been
functioning since then i.e. for the past 13 years;
(ii) that the appellant No.1 College from its inception has been
functioning from a temporary site and though had taken all reasonable
steps to shift to a permanent location but for the reasons not
attributable to the appellants, has not been able to do so;
(iii) that in the National Capital Territory (NCT) of Delhi,
institutional land was under the control of Delhi Development
Authority (DDA) and to establish an institution, land was required to
be procured from the DDA;
(iv) that the appellants on 13th March, 2000 applied to the DDA for
five acres of land for construction of a college building as per the
respondent No.1 AICTE‟s norms;
(v) that the application aforesaid of the appellants was sponsored /
recommended by the Govt. of NCT of Delhi (GNCTD) (respondent
No.3);
(vi) that in the meeting of Institutional Allotment Committee of the
DDA held on 13th February, 2003, allotment of three acres of land in
PSP Area No.2 in between Sectors 21 & 23, Rohini, Delhi to the
appellants was approved;
(vii) that however due to change of Union Government, all
allotments made during the period of previous government came to be
scrutinized and a committee was constituted for the said purpose;
(viii) that on the basis of the report of the said committee, the
allotment approved in favour of the appellants was cancelled;
(ix) that due to the aforesaid cancellation, the respondent No.1
AICTE started threatening the appellants with the withdrawal of
affiliation;
(x) that the appellants filed W.P.(C) No.2459/2005 seeking a
direction to the DDA to give effect to the recommendation dated 13th
February, 2003, of allotment of land aforesaid to the appellants and
also seeking a direction to the respondent No.1 AICTE to not withhold
the approval to the appellants for running the Engineering Degree
College for the academic session 2005-2006; vide interim order dated
5th February, 2005 in the said writ petition, DDA was restrained from
disposing of the plot earlier allotted to the appellants and it was also
observed that the respondent No.1 AICTE could not unreasonably
withhold the approval on appellants‟ application for Engineering
Courses for the academic year 2005-2006, only on the ground that the
appellants did not possess the permanent site;
(xi) that due to the pendency of the aforesaid writ petition, the
appellants were not able to procure the permanent site and were on the
contrary threatened by the respondent No.1 AICTE before the start of
each academic session with cancellation of approval, compelling the
appellants to approach the Court for grant of approval before the start
of every academic year and the interim order dated 5 th February, 2005
was continued for the academic years 2006-2007, 2007-2008, 2009-
2010 and 2010-2011;
(xii) that W.P.(C) No.2459/2005 was vide order dated 25th March,
2011 disposed of owing to the respondent No.1 AICTE vide its order
dated 18th February, 2011 having extended the approval in favour of
the appellants for academic years 2011-2012 as well as 2012-2013; it
may be mentioned that the respondent No.3 GNCTD also issued
Policy Circular dated 6th May, 2011 to the effect that the institutions
being run on rented premises be allowed to run for two academic years
i.e. 2011-2012 and 2012-2013;
(xiii) that the appellants acquired 16.7 acres of land at Moorthal,
Sonepat, Haryana and constructed the required building and
infrastructure thereon and applied to the respondent No.2 University
for grant of affiliation at the said address; however the respondent
No.2 University did not agree, taking a stand that its affiliation could
not extend beyond the borders of NCT of Delhi;
(xiv) that the appellants filed W.P.(C) No.1566/2012 challenging the
said decision of the respondent No.2 but which could not succeed;
(xv) that the appellants thus, in or about the year 2014 disposed of
the Moorthal campus;
(xvi) that the appellants are still in search of suitable land for the
purpose of running the appellant No.1 College;
(xvii) that the respondent No.1 AICTE in the year 2012, without any
basis, on its website showed the status of the appellant No.1 College
as "CBI"; the appellants immediately protested but without avail;
(xviii) that the respondent No.1 AICTE issued a show cause notice
dated 14th June, 2013 to the appellants and to which a reply dated 27 th
June, 2013 was given; the respondent No.1 AICTE vide letter dated
11th July, 2013 called the appellants for a hearing;
(xix) that the respondent No.1 AICTE thereafter vide letter dated 16th
/ 22nd July, 2013 informed the appellants of its decision to conduct
inspection by Expert Visiting Committee (EVC) to ascertain the
infrastructural requirement as per norms;
(xx) that the respondent No.1 AICTE thereafter served the appellants
with another notice dated 24th September, 2013, asking the appellants
to show cause as to why they should not be proceeded against for
failure to disclose factual information and / or for having suppressed /
misrepresented information and be held to be in violation of terms and
conditions contained in the letter of approval;
(xxi) that a reply dated 4th October, 2013 was given to the aforesaid
show cause notice and a hearing was held on 21st October, 2013;
(xxii) that the respondent No.1 AICTE vide letter dated 30th October,
2013 informed the appellants of its decision to place the appellant
No.1 College under "No Extension of Approval 2013-2014" Status,
even though the respondent No.1 AICTE had vide its earlier letter
dated 13th April, 2013 extended the approval for affiliation for the
academic year 2013-2014;
(xxiii) that no further action was taken by the respondent No.1 AICTE
and the students already admitted by the appellants for the academic
year 2013-2014 continued with the course;
(xxiv) that the appellants on 15th May, 2014 applied for approval for
the academic year 2014-2015 and were intimated of the inspection
proposed of their premises on 23rd May, 2014;
(xxv) that on 23rd May, 2014, the appellant No.1 College was closed
due to vacation;
(xxvi) that the respondent No.1 AICTE vide letter dated 2nd June,
2014 called the appellants for hearing before the Standing Appellate /
Complaint Committee on 5th June, 2014; and,
(xxviii) that the appellants attended the hearing of 5th June, 2014 but
the same was held with a pre-determined mind and the reply tendered
by the appellants was also not taken / considered and without any
hearing, the impugned order dated 24th June, 2014 (supra) was passed.
4. The petition was entertained and a counter affidavit filed by the
respondent No.1 AICTE and whereafter the appellants as well as respondent
no.2 University filed an additional affidavit. The learned Single Judge, vide
the impugned judgment dated 15th September, 2014, dismissed the writ
petition, finding / observing / holding:
(a) that W.P.(C) No.2459/2005 (supra) filed by the appellants had
been dismissed vide a detailed judgment dated 25 th March, 2011;
however extension of approval for two academic years i.e. 2011-2012
and 2012-2013 was granted to the appellants;
(b) that in the meanwhile, on 29th January, 2010, Central Bureau of
Investigation (CBI) vide its letter informed the Chief Vigilance
Officer, AICTE that from 1999, the appellants had been continuing to
operate from temporary accommodation despite significant shortage of
area and marginal shortage in built-up area and paucity of students
cadre ratio, computer, internet etc.; that in pursuance thereto, the
respondent No.1 AICTE issued the show cause notice dated 14 th June,
2014 to the appellants and to which the reply dated 27th June, 2014
(supra) had been given by the appellants and after hearing the
representatives of the appellants, the Standing Complaint Committee
of the respondent No.1 AICTE had furnished its report dated 12 th July,
2013 recommending that the appellants be directed to shift to a
permanent campus and an EVC be sent to ascertain the infrastructural
requirement;
(c) that after the report dated 29th July, 2013 of the EVC, the show
cause notice dated 24th September, 2013 (supra) had been issued to the
appellants and to which reply dated 4th October, 2013 had been given;
a detailed hearing was given to the appellants before the order dated
30th October, 2013 (supra);
(d) that the said order dated 30th October, 2013 of the respondent
No.1 AICTE was not challenged by the appellants and had attained
finality;
(e) that inspite of the aforesaid, the appellants filed application for
extension of approval for the academic year 2014-2015;
(f) that the said application of the appellants was accordingly
considered as per the procedure prescribed for the "restoration against
punitive action";
(g) that the EVC by its inspection on 23rd May, 2014 also had
reported, (I) that the building from which the appellant No.1 College
was functioning, appeared to have been constructed for a hotel;
therefore the room sizes are not as per norms; (II) that the
infrastructure and neatness needs to be improved; (III) that the faculty-
cadre ratio is to be maintained and more Doctorates in Domain areas
are required; and, (IV) that the college to be shifted to own building;
(h) that in accordance with the aforesaid report another show cause
notice dated 2nd June, 2014 (supra) was issued and to which reply was
given and hearing held on 5th June, 2014 as per record of which the
appellants did not produce any explanation for the deficiencies and
accordingly the impugned order dated 24th June, 2014 (supra) was
passed;
(i) that this Court in exercise of the power of judicial review was
not to examine the correctness of the decision dated 24th June, 2014
but only the decision making process;
(j) that the argument of the appellants that the decision dated 24 th
June, 2014 had been taken without affording any hearing to the
appellants is contrary to facts; the said decision was taken after
following a very elaborate procedure;
(k) that the Standing Appellate / Complaint Committee of the
respondent no.1 AICTE which had given hearing to the appellants
comprises a retired High Court Judge, a Principal and a Professor and
does not include any serving officer or employee of AICTE; no
allegation of bias or malice has been levelled against any member of
the Standing Appellate / Complaint Committee; consequently the
contention of the appellants that their reply or documents were not
taken on record could not be accepted;
(l) the contention of the appellants that they were unaware of the
CBI report prior to the issuance of the decision dated 24th June, 2014
was also incorrect; the said CBI report was extensively referred to in
Show Cause Notices dated 14th June, 2013, 24th September, 2013 and
in AICTE's order dated 30th October, 2013.
(m) in any case, CBI's report dated 29th January, 2010 was only a
starting point of inquiry and the decision dated 24th June, 2014 was
based on deficiencies pointed out by the AICTE's EVC‟s report dated
23rd May, 2014;
(n) that the principles of natural justice have been complied before
taking the decision dated 24th June, 2014;
(o) the contention of the appellants that the report of the EVC dated
23rd May, 2014 points out only minor deficiencies, also cannot be
accepted in as much as EVC had reported deficiencies like shortfall in
building area and qualified faculty as well as cadre ratio, boys‟
common room, girls‟ common room, cafeteria, classrooms, tutorial
rooms, computer centre, libraries, seminar halls etc. The said
deficiencies are major in nature.
(p) reliance by the appellants on respondent no.2 University‟s
Inspection Report dated 16th June, 2014 was misplaced as the
respondent no.1 AICTE had taken the decision dated 24th June, 2014
in accordance with the procedure prescribed in its regulations and
which procedure did not provide for inspection by the affiliating
University;
(q) the respondent no.2 University also in its affidavit had admitted
that its inspection was purely an annual exercise to evaluate academic
standards and teaching methods and not for evaluating the
infrastructure and other physical parameters; thus the respondent no.2
University's inspection report cannot be taken into account;
(r) the contention of the appellants, of Amity School of
Engineering and Technology also inspite of similar deficiencies
having been granted approval was also of no avail as Amity College
was granted permission on self assessment basis while the appellants‟
application for approval was rejected after EVC inspected the
appellants‟ premises in accordance with procedure prescribed under
Clause 11 of Chapter IV of AICTE Approval Process Handbook; there
could also be no negative equality; and,
(s) that the appellants‟ institute thus suffers from deficiencies
which had not been cured.
5. We have perused the records and considered the rival contentions.
Besides the reasoning given by the learned Single Judge, what immediately
struck us about the matter was that the appellant no.1 College since the year
2000 and till the year 2013-14 has been functioning from a premises from
which it was temporarily allowed to commence functioning in the year 2000
on the condition that it will make arrangements for a permanent location as
per the prescribed norms within two years therefrom.
6. Though the said time of two years expired in the year 2002 but it
appears that the appellants, on the basis of their plea that the allotment of
land for permanent site applied for to the DDA was under process, were
allowed till the year 2005 to so function from the said temporary site.
However the respondent no.1 AICTE in the year 2005 refused to allow the
appellants any further from functioning from the temporary site and
withdrew the approval and which led to W.P.(C) No.2459/2005. The
appellants thereafter continued to function from the said temporary site
under the interim orders aforesaid in W.P.(C) No.2459/2005. The said writ
petition also however stands dismissed on 25th March, 2011 and which order
has attained finality. Though the interim orders in the writ petition came to
an end on dismissal of the writ petition but the appellants continued to
function till the end of the Academic Year 2013-14 owing to the policy
decision taken by the respondent no.3 GNCTD to allow such institutions to
function from temporary site till 31st December, 2014. The appellants now,
by filing this appeal, want this Court to perpetuate the functioning of the
appellant no.1 College from the premises from which the appellant no.1
College was allowed to function temporarily and which premises does not
fulfil the norms prescribed and from which the appellants, under the interim
orders of the Court in W.P.(C) No.2459/2005, continued to function till the
end of the Academic Year 2013-14.
7. The appellants thereby want to make the accommodation, which was
„temporary‟, „permanent‟. We thus straightaway enquired from the counsel
for the appellants as to how the same can be permitted.
8. The counsel for the appellants first took a strange argument that the
appellants having been so allowed to function for the last 13 years, should be
continued to be allowed to function. The said argument has to be recorded,
only to be rejected. The appellants forget that the respondent no.1 AICTE
had pulled the strings on the appellants as far back as in the year 2005. The
continued functioning of the appellants thereafter was under the interim
order in W.P.(C) No.2459/2005 and which stands dismissed and the order of
dismissal whereof the appellants have not even placed before the Court.
9. We have further enquired from the counsel for the appellants whether
these proceedings do not amount to re-litigation. Though the appellants have
not placed copy of W.P.(C) No.2459/2005 also before us but from the
narrative it can safely be assumed that the claim of the appellants in the said
earlier writ petition which stands dismissed was the same as in this
proceeding. Once the order of dismissal in the earlier proceeding has attained
finality, the appellants cannot be permitted to re-agitate the same issues
contending that the approval sought is for a subsequent academic year. The
decision in a proceeding for a previous academic year for the reason of the
appellants being not entitled to continue functioning from a site /
accommodation from which they were temporarily so allowed would be
binding for the subsequent academic years also till the appellants shift to a
proper premises. We may further notice that though at the time of filing of
W.P.(C) No.2459/2005, the cancellation by the DDA of allotment of land
earlier approved in favour of the appellants was also in issue and perhaps for
which reason interim orders were granted in favour of the appellants, the said
issue has also been now finally decided against the appellants. Today, there
is no possibility of the appellants being allotted any land by the DDA. The
DDA in or about the year 2004 changed its policy qua institutional land and
the same is now disposed of only by auction. It is not the case of the
appellants that they have participated in any auction or taken any steps for
acquiring land for shifting to a permanent site as they were required to even
as a condition of grant of the initial approval.
10. When the matter is seen in this light, all arguments raised by the
appellants, of non-compliance of the principles of natural justice, bias, wrong
procedure having been followed by the respondent no.1 AICTE in reaching
the decision dated 24th June, 2014, pale into insignificance. The hard reality
is that the appellant no.1 for the last 13 academic years has been functioning
from a premises not fit for functioning of such an institution and obviously to
the detriment of the students who owing to an extreme paucity of educational
institutions are compelled to take admission therein. However the norms
prescribed qua the accommodation, infrastructure etc., required to be
satisfied to be entitled to approval for running such an institution, and to
which there is no challenge and which the appellants admittedly do not
satisfy are not to be reduced to an empty formality. The Supreme Court in
State of Maharashtra v. Vikas Sahebrao Roundale (1992) 4 SCC 435
noticed the mushroom growth of ill-equipped and under staffed educational
institutions, at times in complicity with the statutory authorities who fail to
effectively enforce the provisions of the statutes, all as a result of least
capital outlay by the government for education. The Supreme Court recently
in Shri Morvi Sarvajanik Kelavni Mandal Sanchalit MSKM B.Ed. College
v. National Council for Teacher Education (2012) 2 SCC 16 also held that
inadequacy of space and staff is something which disqualifies any institution
from seeking recognition. The Supreme Court further expressed surprise as
to how the institution could have reported compliance with the requirements
of the Regulations and complete removal of the deficiencies when the
institution had neither the land standing in its name nor the building
constructed in which it could conduct the courses and that the said fact was
sufficient to justify withdrawal of recognition.
11. In any case the appellants having obtained initial approval in the year
2000 on the promise and condition to, within two years therefrom, shift to its
permanent site, cannot now be heard to contend that the said temporary site
fulfils the requirements. These proceedings, after the dismissal of earlier
proceeding being W.P.(C) No.2459/2005 and after the decision dated 30th
October, 2013 of the respondent no.1 AICTE of refusal of approval for the
year 2013-14 (but inspite of which the appellants were allowed to complete
the academic session which had by then begun) having remained
unchallenged, are clearly an abuse of process of the Court.
12. We accordingly in accordance with the above and which is in addition
to the reasons given by the learned Single Judge, dismiss this appeal with
costs of Rs.20,000/- payable by the appellants to the respondent no.1 AICTE.
RAJIV SAHAI ENDLAW, J.
CHIEF JUSTICE
NOVEMBER 7, 2014 bs/pp
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!