Friday, 24, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Ajay Kumar vs Northern Railway And Ors
2014 Latest Caselaw 314 Del

Citation : 2014 Latest Caselaw 314 Del
Judgement Date : 17 January, 2014

Delhi High Court
Ajay Kumar vs Northern Railway And Ors on 17 January, 2014
Author: Badar Durrez Ahmed
        THE HIGH COURT OF DELHI AT NEW DELHI
%                                      Judgment delivered on: 17.01.2014

+       W.P.(C) No. 320/2014

AJAY KUMAR                                                 .... Petitioner

                                        versus

NORTHERN RAILWAY AND ORS                                   ..... Respondents


Advocates who appeared in this case:
For the Appellant      : Mr Saurabh Gautam
For the Respondent     : Mr Neeraj Atri and Mr Jairaj Mudgul,
                         for Northern Railways

CORAM:-
HON'BLE MR. JUSTICE BADAR DURREZ AHMED
HON'BLE MR. JUSTICE SIDDHARTH MRIDUL

                                  JUDGMENT

BADAR DURREZ AHMED, J (ORAL)

CM No. 639/2014

The exemption is allowed subject to all just exceptions.

W.P.(C) No. 320/2014 & CM No. 638/2014

1. In this writ petition, the petitioner has inter alia sought the following reliefs:-

"(I) A writ of Certiorari or any other writ, order or direction in the like nature thereby quashing impugned action(s) of the respondents including

all orally communicated order(s) resulting in rejection of lowest bid of petitioner vis-a-vis tender no. 232-Elect/EMU/WC-27/12-13 for the work of: fabrication, supply & fitment (Provision) of stainless steel items in 02 nos. EMU Rakes consisting of 24 coaches;

(II) A writ of mandamus or any other writ, order or direction in the like nature commanding the respondents to hold that the petitioner fulfils the eligibility criteria and to consequently direct the respondent to take necessary steps for awarding the contract to the petitioner.

(III) Grant/pass an ad interim ex-party direction in terms prayer (I) and (II) by refraining respondent no. 3 from allotting the contract of fabrication, supply & fitment (Provisions) of stainless steel items, without taking into consideration the bid of the petitioner vis-a-vis tender no. 232- Elect/EMU/WC-27/12-13 for the work of: Fabrication, supply & fitment (Provision) of Stainless Steel items in 02 nos. EMU Rakes consisting of 24 coaches"

2. By virtue of the Notice Inviting Tender (Case 232-Elect/EMU/WC- 27/12-13), tenders were invited for the fabrication, supply & fitment (Provision) of stainless steel items in 02 EMU Rakes consisting of 24 coaches. The last date of collecting the documents was 24.10.2013. The last date of submission of the bids was 25.10.2013 upto 12.00 hours and the tender opening date was 25.10.2013 itself at 12.15 hours. The approximate value of the work as estimated in the NIT was ` 1,85,41,796/-. It is not in dispute that the petitioner submitted its bid as

per the schedule and the bids were opened on 25.10.2013 at 12.15 hours. The plea taken by the learned counsel for the petitioner is that when the bids were opened the petitioner's bid was the lowest yet the work was not awarded to the petitioner.

3. On the other hand, the learned counsel appearing on behalf of the respondents submitted that the petitioner's bid could not be accepted in view of the fact that the petitioner did not fulfil the eligibility criteria set out in clauses 4.0 and 4.1 read with clause 5.0 of Part II of the tender documents. Clauses 4.0, 4.1 and 5.0 are set out herein below:-

"4.0 Eligibility criteria / Credentials of the Tenderer costing more than ` 50 lakhs 4.1 The firm should have physically completed in last three financial years (i.e. current financial year and three previous financial years) at least one similar single work for a minimum value of 35% of the advertised tender value. The total value of similar nature of work completed during the qualifying period and not the payments received within qualifying period alone, shall be considered.

5.0 Similar nature of work Manufacturer / supplier of Stainless steel panels OR carried out the work of SS fabricated items for EMU / DMU / DMRC / locomotives / wagons & production unit coaches such as RCF/ICF etc."

4. It was pointed out by the learned counsel for the respondent that the certificate submitted by the petitioner indicating the petitioner's purported eligibility did not fulfil the criteria mentioned in the above clauses. Specifically, it was pointed out that the certificate, a copy of which is at page 46 of the paper book related only to provision of stainless steel railing on Foot Over Brides, stainless steel benches on platforms and stainless steel cladding on columns of Main Concourse Hall and Ceremonial Hall at the New Delhi Station. This kind of work, according to the learned counsel for the respondent, did not fall within the eligibility criteria set out in the above mentioned clauses.

5. The learned counsel for the petitioner insisted that the work done for which the certificate at page 46 had been produced was of a similar nature of work as required under the said eligibility conditions. However, when we put it to the learned counsel for the petitioner as to whether he fulfilled the criteria in clause 5.0 referred to above, the learned counsel submitted that he had not produced any certificate indicating that the petitioner was a manufacturer / supplier of stainless steel panels. He insisted that the work done by the petitioner would fall within the latter part of clause 5.0. However, he was unable to show as to whether the petitioner had at all carried out any work of stainless steel fabricated items for EMU/DMU/DMRC/locomotives/wagons. The learned counsel for the petitioner submitted that clause 5.0 ends with the abbreviation "etc" and, therefore, any work of a similar nature could be included and that the works done by the petitioner were of a similar nature. We do not agree with this submission. The expression "etc", at the end of clause 5.0

is to be read as a part of the phrase "& production Unit Coaches such as RCF/ICF etc". The expression "etc" would apply only to production Unit Coaches. It is admitted by the learned counsel for the petitioner that no work with regard to production Unit Coaches has been done by the petitioner. Therefore, this argument which has been advanced by the learned counsel for the petitioner on the interpretation of "etc" cannot be accepted. We also are of the view that clause 5.0 has to be read into clause 4.1 which specifically deals with the expression "similar nature of work". Clause 5.0 prescribes the extent of similar nature of work. Unfortunately for the petitioner, he does not fall within the precincts of the definition of similar nature of work as given in clause 5.0.

6. Consequently, the petition has no merit. The same is dismissed but with no order as to costs.

BADAR DURREZ AHMED, J

SIDDHARTH MRIDUL, J JANUARY 17, 2014 SU

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter