Citation : 2014 Latest Caselaw 7151 Del
Judgement Date : 24 December, 2014
*IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 24th December, 2014.
+ O.M.P. 1641/2014 & I.A. No.26253/2014 (u/O 6 R-17 CPC)
OMAXE INFRASTRUCTURE AND
CONSTRUCTION LTD ..... Petitioner
Through: Mr. Kapil Sibal, Sr. Adv. with Mr.
Sandeep Sharma, Mr. Vikas Sharma,
Mr. Amit Chaudhary & Ms. Risha
Mittal, Advs.
Versus
DIRECTOR CONTRACT (UNION OF INDIA) ..... Respondent
Through: Mr. Jaswinder Singh & Mr. Saqib, Advs.
AND
+ O.M.P. 1642/2014 & I.A. No.26254/2014 (u/O 6 R-17 CPC)
M/S OMAXE INFRASTRUCTURE AND
CONSTRUCTION PVT. LTD. ..... Petitioner
Through: Mr. Kapil Sibal, Sr. Adv. with Mr.
Sandeep Sharma, Mr. Vikas Sharma,
Mr. Amit Chaudhary & Ms. Risha
Mittal, Advs.
Versus
UNION OF INDIA, DIRECTOR GENERAL, MARRIED
ACCOMMODATION PROJECT PHASE-II, ..... Respondent
Through: Mr. Jaswinder Singh & Mr. Saqib,
Advs.
AND
+ O.M.P. 1643/2014 & I.A. No.26255/2014 (u/O 6 R-17 CPC)
M/S OMAXE INFRASTRUCTURE AND
CONSTRUCTION LTD. ..... Petitioner
Through: Mr. Kapil Sibal, Sr. Adv. with Mr.
Sandeep Sharma, Mr. Vikas Sharma,
Mr. Amit Chaudhary & Ms. Risha
Mittal, Advs.
Versus
DIRECTOR GENERAL, MARRIED ACCOMMODATION
PROJECT (PHASE -II) ..... Respondent
Through: Mr. Jaswinder Singh & Mr. Saqib,
Advs.
CORAM:-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Each of these petitions, under Section 9 of the Arbitration and
Conciliation Act, 1996, seeks the interim measure of restraining the sole
respondent in each of the petitions namely Director General, Married
Accommodation Project, E-in-C‟s Branch, Integrated HQ of MoD (Army),
Kashmir House, Rajaji Marg, New Delhi from invoking and encashing the
bank guarantees furnished at the instance of the petitioner in favour of the
respondent.
2. O.M.P. No.1641/2014 is filed with respect to bank guarantee Nos.
172113ILPER0014, 172113ILFIN1619, 172113ILFIN1620,
172113ILFIN1621, 172113ILFIN1622, 172113ILFIN1623,
172113ILFIN1624, 172113ILFIN1625 and 172113ILFIN1626 valid upto
10th February, 2015, 10th March, 2015, 10th March, 2015, 10th March, 2015,
10th March, 2015, 10th March, 2015, 10th March, 2015, 10th March, 2015 and
10th March, 2015 respectively for an amount totaling Rs.9,89,28,900/-
furnished by the United Bank of India (UBI), Nehru Place, New Delhi at the
instance of the petitioner in favour of the respondent.
3. O.M.P. No.1642/2014 is filed with respect to the bank guarantee
Nos.172113ILPER0015, 172113ILFIN1634, 172113ILFIN1635,
172113ILFIN1636 and 172113ILFIN1637 valid upto 10th February, 2015,
10th March, 2015, 10th March, 2015, 10th March, 2015 and 10th March, 2015
respectively for an amount totaling Rs.8,89,63,310/- furnished by the United
Bank of India, Nehru Place, New Delhi at the instance of the petitioner in
favour of the respondent.
4. O.M.P. No.1643/2014 is filed with respect to the bank guarantees
No.172113ILPER0018, 172113ILFIN1629, 172113ILFIN1630,
172113ILFIN1631, 172113ILFIN1632 and 0170813IPG000307 valid upto
10th February, 2015, 10th March, 2015, 10th March, 2015, 10th March, 2015,
10th March, 2015 and 12th May, 2015 respectively for an amount totaling
Rs.14,68,61,000/- furnished by the United Bank of India, Kolkata / Nehru
Place, New Delhi and Allahabad Bank, Kolkata / Okhla Branch, New Delhi
at the instance of the petitioner in favour of the respondent.
5. All the three petitions were listed on urgent mentioning in the post-
lunch session on 19th December, 2014, when the counsels for the respondent
appeared on advance notice. It was however represented by the petitioner on
that date that owing to the urgency of the relief claimed and the paucity of
time, all the requisite papers could not be filed and perused and, while
seeking ad-interim injunction, time therefor was sought. The counsel for the
respondent had however opposed the adjournment and contended that the
petitioner is guilty of concealment of material documents and facts. It was
stated that M/s Reacon Engineers (India) Pvt. Ltd. claimed to have
purchased the petitioner company and had in a letter written to the
respondent admitted the failure of the petitioner to perform its part of the
contractual obligations viz.-a-viz. the respondent, owing to its internal
problems. It was also informed that the respondent had vide letters dated
17th December, 2014, besides invoking the bank guarantees cancelled the
contracts with the petitioner.
6. On enquiry, it was informed on 19th December, 2014 that the
respondent though had invoked the bank guarantees subject matter of all the
three petitions, but the guaranteeing bank(s) had till then not remitted the
monies to the account of the respondent, though the same was stated to be in
process. In the circumstances, while adjourning the matters to 23 rd
December, 2014, it was ordered that if the monies till then had not been
transferred by the bank(s) who had issued the bank guarantees, to the
account of the respondent, the same be not transferred till 23 rd December,
2014.
7. The petitioner has filed I.A. No.26253/2014 in O.M.P. No.1641/2014
for amendment of the petition, to incorporate the plea that M/s Omaxe
Limited has transferred all its shareholding in the petitioner company to M/s.
Reacon Engineers (India) Pvt. Ltd. and now the petitioner is wholly and
fully owned by the said M/s. Reacon Engineers (India) Pvt. Ltd. and that
though originally the bank guarantees were submitted from Delhi but after
the transfer of ownership of the company, the bank guarantees were issued
from the Banks in Kolkata. The petitioner has also filed proposed amended
petition as well as additional documents.
8. The senior counsel for the petitioner and the counsels for the
respondent were heard on 23rd December, 2014 and matter posted for today
for pronouncing orders.
9. I may at the outset state that the senior counsel for the petitioner has
argued all the three petitions as one only and with reference to the
documents filed in O.M.P. No.1641/2014. Axiomatically, the counsels for
the respondent have also argued, as if the arguments made apply to the facts
of each of the three cases.
10. The senior counsel for the petitioner has contended that the bank
guarantees subject matter of these petitions are of three kinds i.e. (I)
performance bank guarantee; (II) bank guarantee in lieu of retention money
against material; and, (III) bank guarantee in lieu of retention money against
work done.
11. Attention has been invited to the performance bank guarantee and the
relevant part whereof is as under:
"Bank Guarantee for Performance Security.
1. In consideration of the President of India (hereinafter called "the Government") having agreed to exempt M/s Omaxe Infrastructure & Construction Limited (Hereinafter called "the said Contractor(s)") from the demand, under the terms and conditions of an Agreement dated 23rd Feb. 2011 "CA No.DG MAP/PHASE II / PKG-24/21 OF 2010-11"construction of Dwelling Units at Deolali (Army) & Nasik (AF) (hereinafter called "the said agreement") of performance security deposit for the due fulfillment by the said Contractor(s) of the term and condition contained in the Said Agreement on production of a Bank Guarantee terms for, Rs.6,79,28,900/- (Rupees Six Crores Seventy Nine Lacs Twenty Eight Thousand and Nine Hundred Only). We United Bank of India, Corporate Finance Branch, 11, Hemanta Basu Sarani, Kolkata-700 001 do hereby undertake to pay to the Government an amount not exceeding Rs.6,79,28,900/- (Rupees Six Crores Seventy Nine Lacs Twenty Eight Thousand Nine Hundred Only) against any loss or damage cause to or suffered or would be caused to or suffered by the government by reason of any breach by the said Contractor(s) of any of the terms or conditions contained in the said Agreement.
2. We United Bank of India, Corporate Finance Branch, 11, Hemanta Basu Sarani, Kolkata-700 001 do hereby undertake to pay the amounts due and payable under this guarantee without any demur, merely on a demand from the Government stating that the amount claimed is due by way of loss or damage caused to or would be caused to or suffered by the Government by reason of any breach by the said Contractor(s) of any of the terms or conditions contained in the said Agreement or by reason of the Contractor's failure to perform the said Agreement. Any such demand made on the Bank shall be conclusive as regards the amount due and payable by the Bank under this guarantee. However, our liability under this guarantee shall be restricted to an amount not exceeding
Rs.6,79,28,900/- (Rupees Six Crores Seventy Nine Lacs Twenty Eight Thousand Nine Hundred Only)."
12. It is contended that the bank guarantee, though unconditional and
though as is now well settled, an independent contract, in Clause (1) supra
has incorporated the "underlying contract between the petitioner and the
respondent" in it.
13. Attention is next invited to the following part of Clause 48 of the
General Conditions of the "underlying contract between the petitioner and
the respondent" and which is as under:
""48. Cancellation of Contract in part or in full for contractor's Default.
If the Contractor:-
(a) Makes default in commencing the Works within a reasonable time from the date of the handing over the site, and continues in that state after a reasonable notice from P.M.; or
(b) In the opinion of the P.M. at any time, whether before or after the date or extended date for completion, makes default in proceeding with the Works, with due diligence and continues in that state after a reasonable notice from P.M.; or
(c) Fails to comply with any of the terms and conditions of the Contract or after reasonable notice in writing with orders properly issued thereunder; or
(d) Fails to complete the Works, Work order and items of Works, with individual dates for completion and clear the Site on or before the date of completion."
14. It was argued that as per the "underlying contract between the
petitioner and the respondent" aforesaid, the respondent could have
terminated the contract only on either of the aforesaid four events happening
/ occurring.
15. Attention was next invited to the letter dated 17th December, 2014 of
the respondent to the guaranteeing bank(s), invoking the bank guarantee and
the relevant part whereof is as under:
"2. And whereas it is expressly provided in the aforesaid Bank Guarantee Bonds that you undertake to pay the amount due and payable under the guarantees without any demur, merely on a demand from the Government stating that the amounts claimed is due by way of loss or damage caused to or suffered or would be caused to or suffered by the Government by reasons of any breach by the contractor of any of the terms and conditions contained in the said Contract Agreement or by the reason of contractor's failure to perform the said agreement.
3. And whereas there has been a breach by the contractor of the terms and conditions of the Agreement and by virtue of such breach there would be loss / damage caused to the Government by reason of such breach by the contractor which in the estimate of the DGMAP, will exceed the value of said Bank Guarantee Bond."
16. Attention was next invited to the letter dated 17th December, 2014 of
the respondent to the petitioner, of termination of the "underlying contract"
and the relevant part whereof is as under:
"2. Inspite of notices issued to you vide referred letters in connection with the work to be executed under the above mentioned contract, you have failed to proceed with the work with due diligence. The work is at standstill at all the site for a considerable period of time. Sufficient opportunities have already been given to your firm to accelerate the progress at site but no response has been received from your side. You have also failed to reply to the final notice issued by me vide letter No.81982/MAP/PH-II/PKG-24/743/E8 dated 20 Nov 2014.
3. Therefore, I, Accepting Officer of the contract on behalf of the Government acting under the power vested in me in terms of condition 48 of the General Conditions on SI page No.126- 127 of contract and without prejudice to any other right or remedy which shall have accrued or shall accrue hereafter to the Government in terms of the above said contract, hereby cancel your contract on account of your default with effect from 18 Dec 2014.
4. Please note that the work as defined in the contract condition 1(c) of the General Conditions of contracts will now be got completed by me through other agency at your risk and cost.
5. You are accordingly requested to report to the Project Manger (Phase-II), Md Accn Project, C/o Station HQ Devlali- 422401 at his office in person or through an accredited representative at 1000 hours on 29 Dec 2014 or on date to be fixed by the Presiding Officer of the BOO to be convened by concerned stn HQ when an inventory of complete / incomplete
items of work and materials, if any, left by you at site will be made and recovered jointly. In the event of your failure to keep the appointment, inventory will nevertheless be prepared notwithstanding your absence and the same shall be fully binding on you and any representation in the matter at later date will not be entertained due to your default."
17. It is argued, i) that the invocation by the respondent of the bank
guarantees is not in terms of the bank guarantees and is not an invocation
entitling the respondent to encash the bank guarantees; and ii) that the
respondent could invoke performance bank guarantee only by specifying as
to in breach of which of the said Clauses (a), (b), (c) and (d) of Clause 48
supra, according to the respondent, the petitioner was and mere parrot like
repetition of the language of the bank guarantee cannot be deemed to be
proper invocation, entitling encashment of the performance bank guarantee.
18. With respect to the other two kinds of bank guarantees, it is contended
that 100% monies were released by the respondent to the petitioner with
respect to the part of the works completed by the petitioner, only after being
satisfied of the successful completion of that part of the work and of the
value of the material brought by the petitioner to the construction site of the
respondent and even though the respondent had made the petitioner furnish
bank guarantees in lieu of retention money but the said part of the work
being complete, and the material brought by the petitioner having been used
/ being still in the custody of respondent, the respondent is not entitled to the
money thereunder.
19. It is also argued that this is a fit case where the encashment of the
bank guarantee should be stayed by an ad-interim order and the respondent
be made to file a reply and the petition be disposed of only thereafter, since
the bank guarantees are alive till March, 2015.
20. Attention is also invited to the communications addressed by the
petitioner to the respondent and listed in the petitions, complaining of the
hindrances being faced by the petitioner in completing the contracted works.
It is stated that the respondent, at the contemporaneous time, maintained a
stoic silence and has now all of sudden terminated the contract and invoked
the bank guarantee. It is also informed that of all the 39 works contracts
issued by the respondent, as many as 29 have been cancelled and bank
guarantees furnished thereunder invoked. It is conveyed that the respondent
is following the practice of repeatedly issuing contracts and terminating the
same and with the result that all its projects are held up.
21. Per contra, Mr. Jaswinder Singh, counsel for the respondent in O.M.P.
Nos.1641/2014 & 1643/2014 has contended that there is no need for filing
any reply to these petitions and the same be heard as the matter is squarely
covered by the judgment dated 21st November, 2013 of the Division Bench
of this Court in FAO(OS) No.529/2013 titled Indu Projects Limited Vs.
Union of India and other connected appeals. He has further contended that
the application aforesaid for amendment has been filed, after the respondent
during the hearing on 19th December, 2014 took the said objection; thus the
petitioner is guilty of suppression of material facts and is not entitled to any
interim relief on this ground alone.
22. He has further contended that the petitioner is not entitled to any
interim relief, having admittedly sublet and assigned the contract. It is
contended that the petitioner was found eligible to be awarded the contracts
for the reason of being part of Omaxe Ltd. and M/s. Reacon Engineers
(India) Pvt. Ltd. and / or the petitioner on its own, was / is otherwise not
even eligible for the subject contracts.
23. It is controverted that the performance bank guarantees have ceased to
be independent from the underlying contract between the petitioner and the
respondent, for the reason of the said contract between the petitioner and the
respondent having been incorporated in the bank guarantees as has been
contended by the senior counsel for the petitioner. It is contended that the
underlying contracts between the parties in pursuance to which the bank
guarantees were furnished, have to be necessarily mentioned / referred to in
the bank guarantee and merely therefrom the same cannot be said to have
got incorporated in the bank guarantee or to have become a part of the bank
guarantee.
24. I may record that the counsel for the respondent wanted to argue that
the invocation and encashment of the bank guarantee can be stayed by the
Courts only on the ground of established fraud and in this regard wanted to
cite Svenska Handelsbanken Vs. Indian Charge Chrome Ltd. (1994) 1
SCC 502, particularly para 60 thereof but the senior counsel for the
petitioner interjected that the petitioner is not seeking any relief on the plea
of fraud (fraud of an egregious nature) and is seeking the stay of invocation /
encashment of bank guarantee only on the ground of invocation of the bank
guarantee being not in terms of the bank guarantee and thus the counsel for
the respondent was not allowed to pursue the said line further.
25. The counsel for the respondent argued that the language of the bank
guarantees subject matter of Indu Projects Limited supra was identical to the
bank guarantees subject matter of these petitions and the same was
interpreted by the Division Bench to be an "unconditional bank guarantee"
and it was held that the invocation thereof, claiming that there had been a
breach by the contractor of the terms and conditions of the agreement and by
virtue of such breach there would be loss / damage caused to the
Government which in the estimate of HQ DG MAP would exceed the value
of the bank guarantee, was proper invocation in terms of the bank guarantee
and it was not at all necessary to quantify the amount of loss and damage.
26. Mr. Saqib, Counsel for the respondent in O.M.P. No.1642/2014
invited attention to Clause 13A of the General Conditions of the contract to
show that time was of the essence of the contract. He has further invited
attention to Clause 19.4 of the contract under the caption "performance
security" to show that the performance bank guarantee is in lieu of the said
performance security in terms of the contract. Attention was next invited to
Clause 48 supra to contend that upon cancellation of the contract on any of
the grounds a,b,c,d supra, the respondent is entitled to complete the work by
any means at the contractor‟s risk and cost. With respect to the retention
money bank guarantees, attention was invited to Clause 54 of the contract to
contend that though in terms thereof the petitioner as contractor was entitled
to 95% only of the value of the work executed on the site and the balance
5% was to be retained by the respondent and payable only on satisfactory
completion of entire contractual work. It is argued that the petitioner
obtained 100% of the value of the work and gave a bank guarantee for the
balance 5% and since the petitioner has not completed the works, it has not
become entitled to the balance 5% and the respondent is entitled to invoke
the bank guarantee in lieu thereof.
27. Attention was invited to paras 4 & 6 of OMP No.1642/2014 to
contend that the petitioner has erroneously pleaded that the bank guarantee
in lieu of retention money against material is for 70% of the value of the
material (the senior counsel for the petitioner at this stage admitted that it is
a typographical error as the bank guarantee is for 30% only). It is also
argued that the petitioner in para 6 of the OMP has portrayed as if the
respondent had unilaterally changed the terms of the contract, when the
same was consensual and under signatures of both parties (the senior counsel
for the petitioner again interjected that he has not even argued on the said
aspect).
28. Attention is also invited to Clause 2 of the Special Conditions of the
Contract providing for the contractor to, by visiting the site, satisfy himself
and it is contended that the pleas raised by the petitioner, of admitted delay,
being attributable to the respondent owing to the site being unavailable, is
contrary to the contract. However the senior counsel for the petitioner again
interjected to contend that the respondent in reply is referring to pleas, facts
and documents which have not even been urged on behalf of the petitioner.
29. The counsel for the respondent in OMP No.1642/2014 further referred
to the terms aforesaid of the performance guarantee to contend that the
purpose thereof was to secure the respondent against the likely loss assessed
by the respondent. It is contended that as many as five extensions of 750
days were given to the petitioner but the progress in the contract subject
matter of OMP No.1642/2014 was only 27%.
30. The counsel for the respondent in OMP Nos.1641/2014 and
1643/2014 stated that the date of completion of the work subject matter of
OMP No.1643/2014 was 24th October, 2012; was extended till 28th March,
2014, but the progress was only of 37.43%.
31. However before such particulars with respect to OMP No.1641/2014
could be given, the senior counsel for the petitioner again contended that the
arguments of fact cannot be urged by the respondent without filing a reply.
He further contended in rejoinder that the judgment of the Division Bench in
Indu Projects Ltd. is only on the aspect of whether the loss suffered / likely
to be suffered was required to be quantified while invoking the bank
guarantee. He reiterated that it was essential for the respondent to invoke the
bank guarantee by specifying as to in breach of which clause of the contract
the petitioner was and without the respondent so specifying, there is no
proper of invocation of the bank guarantee and hence the encashment thereof
ought to be stayed during the pendency of arbitration of disputes between
the parties.
32. I have considered the rival contentions.
33. As would be obvious from the aforesaid, the petitioner in its
arguments has not even drawn attention to the bank guarantees in lieu of
retention money and to be fair to the senior counsel for the petitioner, rightly
so. The said bank guarantees are unequivocal and unconditional and the
guaranteeing bank thereunder has agreed to pay to the respondent the
amount thereof to the respondent "against any loss or damage caused to or
suffered or would be caused to or suffered" by the respondent "by reason of
any breach" by the petitioner "of any of the terms and conditions contained
in the agreement" of the petitioner with the respondent and "without any
demur, merely on a demand" from the respondent "stating that the amount
claimed is due by way of loss or damage caused to or suffered or would be
caused to or suffered" by the respondent "by reason of any breach" by the
petitioner "of any of the terms or conditions contained in the said agreement
or by reason of" the petitioner‟s "failure to perform the said agreement". The
guaranteeing bank further agreed that "any such demand made on the bank
shall be conclusive as regards the amount due and payable by and the
liability of the bank" under the guarantee and the bank would pay the
amount demanded "notwithstanding any dispute or disputes raised" by the
petitioner "on any ground whatsoever and notwithstanding any proceeding
pending in any Court or Tribunal relating to the said agreement" between the
petitioner and the respondent or the subject bank guarantee and "the liability
of the bank under this guarantee being absolute and unconditional".
34. The argument of the senior counsel for the petitioner, that the
respondent is not entitled to invoke the bank guarantees in lieu of retention
money, is without regard to the petitioner in the contract having agreed to
retention by the respondent of a percentage of the payment due, towards
completed parts of the work or for the material brought to the construction
site by the petitioner and the reason therefor. If merely for the reason of
having brought the material to the construction site and / or for having
completed a part of the work, the petitioner was to be entitled to the entire
payment therefor, the occasion for furnishing the bank guarantees in lieu of
retention money would not have arisen. At least at this interim stage, no
interim measure contrary to the contract between the parties can be ordered.
The same would amount to, at the interim stage only, ordering the
respondent to pay to the petitioner the monies which the respondent, as per
the contract, is entitled to retain and which the petitioner can only recover
from the respondent only upon being ultimately found entitled thereto. It
cannot be forgotten that the said bank guarantees are „in lieu of‟ the monies
which the respondent was not immediately liable to pay to the petitioner and
which were released to the petitioner „in lieu of‟ the petitioner furnishing
bank guarantee. I therefore find that the petitioner has not even made out
any case for restraining encashment of the bank guarantees in lieu of
retention money.
35. As far as the case made out by the petitioner for injuncting
encashment of performance bank guarantees is concerned, the short point for
adjudication is whether the invocation thereof is not in terms of bank
guarantee, i.e. not as required to invoke the bank guarantee.
36. I tend to agree with the counsel for the respondent that mere mention
of / reference to the underlying contract in the bank guarantee does not
amount to incorporation thereof in the bank guarantee and that mention /
reference thereof in the bank guarantee is essential to show the consideration
for which the bank guarantee has been furnished.
37. The performance bank guarantee was issued to secure the respondent
against any loss or damage caused to or suffered or would be caused to or
suffered by the respondent by reason of any breach by the petitioner of any
of the terms or conditions of the contract entered into between them.
Without mentioning the said contract, the bank guarantee could not also
have conveyed as to for securing losses or damages against what, it was
being furnished.
38. Moreover, a bank guarantee being but a contract, has to be interpreted
like a contract i.e. no single part or clause of the contract can be picked and
read/interpreted in isolation and the contract between the parties and their
intention, is to be gauged from a complete reading thereof. If it were to be
held, that before the bank guarantee could be encashed the respondent was
required to satisfy the bank that the petitioner had breached the contract and
that it had indeed suffered loss or damage or was likely to suffer loss or
damage therefrom, then, the clauses of the said bank guarantee whereunder
the bank had agreed to pay the amount thereunder, without any demur,
merely on demand from the respondent stating that the amount claimed was
due by way of loss or damage caused or would be caused to or suffered by
the respondent by reason of any breach by the petitioner of any of the terms
and conditions contained in the agreement or by reason of the petitioner‟s
failure to perform the said agreement and of such demand made by the
respondent on the bank being conclusive as regards the amount due and
payable by the petitioner under the guarantee, would become otiose/
meaningless.
39. No merit is also found in the contention of the senior counsel for the
petitioner, of the respondent, for invoking the bank guarantees being
required to specify the breach on the part of the petitioner. Clause (2) of the
performance bank guarantee, as set out hereinabove, uses the expression "by
reason of any breach" and which is indicative of the respondent, while
invoking the bank guarantee, being not required to specify the breach and
the only requirement being for the respondent to state that the petitioner was
in breach of the terms and conditions of the agreement or had failed to
perform the agreement. Rather, it is felt that if such detailed reasons were to
be required to be stated, the same would make the matter contentious,
negating the very purpose of obtaining an unconditional unequivocal bank
guarantee.
40. Having gone through the judgment of the Division Bench of the Court
in Indu Projects Limited supra, I find that not only is the language of the
bank guarantee subject matter thereof identical to the language of the
performance bank guarantee with which these petitions are concerned but
the letter of invocation of the bank guarantees in that case also did not
specify the breach or the clause of the agreement of which the contractor
therein was claimed to be in breach. Though undoubtedly the contention of
the counsel for the contractor in that case before the Division Bench was that
the losses or damages suffered or likely to be suffered were required to be
quantified in the letter of invocation of bank guarantee and which was
negated by the Division Bench but what the Division Bench has held is that
a categorical assertion on the part of the respondent that there had been a
breach by the contractor of the terms and conditions of the agreement and
that by virtue of such breach, there would be loss / damage which in the
estimate of the respondent would exceed the value of the bank guarantee,
was a proper and sufficient invocation of the bank guarantee. The Division
Bench also held that since the bank had agreed that the demand made shall
be conclusive as regard the amount payable thereunder, the bank had agreed
to pay without demur.
41. Thus, though undoubtedly, the invocation of bank guarantee being not
in terms thereof, is a ground for injuncting the invocation/encashment of
bank guarantees, but in the facts of the present case I do not find the same to
have been made out. The invocation by the respondent of the bank
guarantees subject matter of these petitions is found to be in terms of the
bank guarantees. If the intention of and the agreement of the parties was that
the respondent, to be entitled to invoke the bank guarantees, must specify the
breach on the part of the petitioner of the agreement and/or the clause of the
agreement which the petitioner had breached, nothing prevented the parties
to specify so. It is not so specified, not in the bank guarantees and even if the
agreement/contract between the parties could be seen, not even therein. The
petitioner cannot be allowed to now, when the respondent has already
invoked the bank guarantee, contend so and have the invocation by the
respondent of the bank guarantees defeated, by springing a surprise of such a
plea on the respondent. The same would amount to giving unfair advantage
to the petitioner, to the prejudice of the respondent. The respondent could
not be expected to conduct itself in a manner not required by the written
contract. It cannot also be lost sight of that these are commercial contracts
prepared by experts deft in drafting thereof, and the parties cannot as an
afterthought be permitted to ascribe or impute a meaning thereto not borne
out from the language thereof and which could have been, by use of
different language which the parties chose not to use.
42. No other argument has been urged on behalf of the petitioner.
43. I therefore do not find the petitioner to have made out any case for
grant of interim measure of injuncting the encashment of the bank
guarantees.
44. I clarify that though no formal order of allowing the application for
amendment has been made but the counsels have argued on the basis of the
amended petition in O.M.P. No.1641/2014 and I have also in view thereof
not taken notice of the plea of the respondent of the petitioner being guilty of
concealment as contended on 19th December, 2014 and as contended
yesterday i.e. 23rd December, 2014 and decided the entitlement of the
petitioner to the interim measure de hors the same.
45. I further clarify that though no reply is filed but no need is felt to keep
these petitions pending, considering the nature of the interim measure
sought.
46. The petitions are accordingly dismissed with costs of Rs.15,000/- in
each of the petitions payable by the petitioner to the respondent within four
weeks of today.
RAJIV SAHAI ENDLAW, J.
DECEMBER 24, 2014 „bs‟
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!