Friday, 24, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Voltas Ltd vs Ncc Ltd & Anr
2014 Latest Caselaw 6624 Del

Citation : 2014 Latest Caselaw 6624 Del
Judgement Date : 10 December, 2014

Delhi High Court
Voltas Ltd vs Ncc Ltd & Anr on 10 December, 2014
Author: Deepa Sharma
      * IN THE HIGH COURT OF DELHI AT NEW DELHI
+                        O.M.P. 1117/2014
%                       Judgment Reserved on: 02.12.2014
                        Judgement pronounced on: 10.12.2014
      VOLTAS LTD                                       ..... Petitioner
                  Through: Mr.P.K.Sharma and Mr.Sanjay
                  Grover, Advocates
                  versus
    NCC LTD & ANR                              ..... Respondents
                  Through: Ms.Priya Kumar, Advocate
CORAM:
HON'BLE MS. JUSTICE DEEPA SHARMA
JUDGMENT

1. The present petition has been filed under Section 9 of the Arbitration

and Conciliation Act, 1996 (hereinafter referred to as "the Act") for the

relief that respondent No.1 be restrained from invoking three bank

guarantees bearing Nos.999513BG0002397, 0999513BG0002398 and

0999513BG0002399 all dated 24.09.2013 of the following nature:-

 S.No.      Date                  Description                 Amount
i)     24.09.2013        Mobilization Bank Guarantee      1,30,56,750.00
ii)    24.09.2013        Performance Bank Guarantee       1,09,50,000.00
iii)   24.09.2013        Retention Bank Guarantee         99,50,000.00
                                             Total Rs.    3,39,56,750.00





2. The admitted facts of the case are that respondent No. 1 was formerly

known as Nagarjuna Construction Company Ltd. and was a part of an un-

incorporated joint-venture (JV), namely M/s CRSSG-NCC(JV). The JV was

awarded the work under a tender floated by National Building Construction

Company Ltd. (NBCC Ltd.) on behalf of Employee State Insurance

Corporation (ESIC) for the construction of ESIC Medical College-cum-

Hospital at Mandi Himachal Pradesh. The Joint Venture ceased to exist and

its rights and liabilities have been taken over by respondent No.1. Work for

supply, erection and commissioning of air-conditioning equipment in the

five buildings of ESIC was awarded to the petitioner for a fixed contract

having value of Rs.2,19,00,000/-. The completion period of the work was 14

months. At that time, the petitioner had furnished three bank guarantees of a

sum of Rs. 4,28,00,000/-. During the course of execution of the work, some

dispute arose between the petitioner and respondent No.1 and respondent

No.1 encashed the bank guarantees of total sum of Rs.4,28,00,000/- on

07.06.2013. The petitioner filed OMP No. 672 of 2013 under Section 9 of

the Act seeking stay of the operation of termination letter dated 01.07.2013

by which the contract was terminated by respondent No.1. The petitioner

also moved a petition under Section 11 of the Act being Arbitration Petition

No. 284/2013, whereby a sole Arbitrator was appointed to resolve that

dispute vide order dated 30.08.2013. Subsequent thereon, the parties

entered into a negotiation. The petitioner sought an adjournment on

11.09.2013 from Arbitrator and subsequently, the petitioner and respondent

No.1 entered into a settlement and pursuant to that settlement, a

Memorandum of Understanding (MoU) dated 18.09.2013 was drawn.

Pursuant to the terms of this MoU, respondent No. 1 refunded the sum of

Rs.4,28,00,000/-, which the respondent was having pursuant to the

encashment of three bank guarantees of the petitioner and in turn the

petitioner furnished fresh bank guarantees for Rs.3,39,56,750/-. Respondent

No.1 also agreed to compensate the petitioner by way of escalation charges

which was quantified at Rs.1,25,00,000/- and agreed to pay in four equal

instalments in the following manner:-

     S. No.           Date                       Amount (Rs.)

     1.            18.12.2013                       31,25,000/-
     2.            18.03.2014                       31,25,000/-
     3.            18.06.2014                       31,25,000/-
     4.            18.09.2014                       31,25,000/-
                                        _______________________
                                          Total Rs. 1,25,00,000/-
                                        _______________________

3. The petitioner resumed the work in view of this MoU. Under the

terms of the MoU, bills for future work were to be paid within 45 days. The

petitioner raised the following bills, details of which are shown as under:-

            RA Bill No.     Bill Date           Due Amount (Rs.)

            11th RA Bill    28.11.2013          3,480,389.00

            12th RA Bill    26.12.2013          5,087,207.00

            13th RA Bill    25.01.2014          2,072,761.00

            14th RA Bill    24.02.2014          854,463.00

            15th RA Bill    25.03.2014          2,781,502.92

            16th RA Bill    14.04.2014          3,110,789.00

            17th RA Bill    28.05.2014          1,041,173.00

            18th RA Bill    26.06.2014          1,249,202.00

                            Total Rs.           1,96,77,486.92



4.    The respondent No.1          against those bills paid a sum of

Rs.1,24,84,211/-. The petitioner has submitted that respondent No. 1 is in

financial difficulties and has been unable to pay its debts and has also not

made the payment of RA bills to the petitioner and in terms of the MoU has

not paid single instalment of escalation amount of Rs. 1.25 crores and is

presently in default to the extent of Rs.1,96,93,275/-. It is submitted that in

its correspondence dated 06.02.2014, 11.02.2014 and 08.03.2014, the

respondent No.1 had admitted his liability. The credit Rating Agency

CRISIL has also downgraded the debt of respondent No.1 to category 'D'

from the earlier category "BB+". It is further contended that respondent

No.1 had in its meeting dated 02.08.2014 had decided to release the balance

payment, including two escalation. It is further submitted that the work of

ESIC Hospital has been stopped because the respondent No.1 has not made

any payment to its contractors and this fact was also reported on 23.08.2014

in the newspaper Amar Ujala. It is further submitted that on account of

inability of respondent No.1 to pay debts, the petitioner has issued a winding

up notice dated 13.09.2014 to respondent No.1 at its registered office at

Hyderabad. The petitioner had received a letter dated 13.09.2014 from

respondent No.1, wherein various false allegations have been made by

respondent No.1 and they had also threatened the petitioner that they were

going to encash the bank guarantees and would get the balance work

executed at petitioner's risk and cost. This letter was received by the

petitioner on 13.09.2014 by e-mail at 3.00 PM. It is submitted that this

threat to encash the bank guarantees amounts to a clear and egregious fraud

by respondent No.1. It is further pleaded that in terms of MoU, it was agreed

between the parties that respondent No. 1 shall pay escalation charges

amounting to Rs. 1.25 crores to petitioner upon the submission of bank

guarantee. Thus, for the release of the escalation charges amounting to Rs.

1.25 crores, the petitioner had submitted bank guarantees to the extent of

Rs.3.39 crores. The respondent is in the breach of MoU has failed to release

the escalation amount and has caused losses to the petitioner who has kept

the bank guarantee alive till date. It is submitted that bank guarantees were

provided as part of consideration for the release of the escalation charges.

Since the respondent No.1 had failed to release the escalation amount, they

are playing fraud upon the petitioner. On these facts, it is prayed that

respondent No.1 be restrained from invoking the bank guarantee.

5. The petition is contested by the respondent. It is pleaded by

respondent No.1 that the petitioner has not pleaded any facts in respect of

fraud. It is submitted that the fraud is required to be pleaded and established,

especially when it is the ground of seeking restraint order for encashing the

bank guarantee. It is submitted that on the other hand, the petitioner has

played a fraud on this Court. It is submitted that contention of the petitioner

that bank guarantees were given for the release of escalation amount and

that the bank guarantee was three times to the escalation amount is contrary

to the fact since the bank guarantees were given for performance, towards

mobilization advance and towards retention money as per agreed terms and

this fact the petitioner has himself stated in his petition as well. It is

submitted that bank guarantee is an independent contract and the Court can

only restrain its encashment either on the ground of egregious fraud or

irretrievable injustice. It is submitted that irretrievable injustice means a

situation where the financial condition of the beneficiary under the bank

guarantee or for any other circumstance, it would be impossible for the

petitioner to recover this amount if it found entitled for that amount at a later

stage. It is submitted that there is nothing on record to show that the

petitioner would not be able to recover the bank guarantee amount from

respondent. It is submitted that this Court has also no jurisdiction to

entertain the dispute between the parties arising out of the contract. It is

submitted that admittedly a work order of Rs. 21,80,00,000/- was awarded to

the petitioner, but the petitioner was only able to complete the work of Rs.

8.84 crores when the contract was terminated by the respondent No.1 and

vide this MoU a total value of the work of Rs.21,90,00,000/- was awarded to

the petitioner to be finished in 14 months, which was extendable to two

more months. It was towards the fulfilment of this contract that the fresh

bank guarantees were furnished. The petitioner had also submitted a

progress schedule dated 17.09.2013 along with the MoU. This schedule had

shown the expected completion date as 20.09.2014 and the petitioner has not

intentionally placed this document on the Court file along with his petition.

It is submitted that it was only on account of the assurance and

representation on the part of the petitioner, that he would be able to

complete the work by 20.09.2014, that the respondent No. 1 had agreed to

enter into an MoU and returned the earlier encashed bank guarantees of Rs.

4,28,00,000/- furnished at the time of earlier work order. As a good gesture,

the respondent No.1 also agreed to pay the escalation price, but it was for

the future work as the petitioner had agreed to finish the work on the same

price on which the contract in the year 2010 was entered into between them.

This escalation was to be paid in four instalments as per schedule keeping in

mind the schedule of the progress submitted by the petitioner. It is submitted

that as per industry practice, there could be no payment, including that of

escalation, if the contractor fails to execute the work as agreed between the

parties or abandons it. The petitioner miserably failed to adhere to the

schedule submitted by him and this fact is clear from the various RA bills

which show that between 28.11.2013 to 26.06.2014, he had completed the

work of Rs.1,96,77,486.92/- while he had to finish within a year a work

worth of Rs.21,90,00,000/-, which itself shows the tardy progress of work

on the part of the petitioner. It is submitted that petitioner had tried to

mislead the Court. It is further submitted that respondent No.1 is a public

company having a turnover of about Rs.6270.83 crores as an individual and

Rs. 7568.69 crores as a group and is engaged in construction businesses of

various types, including housing, hospitals, stadiums, water works, etc. and

also in the process of executing several projects running into hundreds of

crores. Therefore, the petitioner is not entitled for the relief on account of

irretrievable injustice. It is submitted that rating revised by CRISIL is in no

way affect the financial status of respondent No.1 and the respondent No.1

is a solvent company. On these facts, it is submitted that the petition is not

only liable to be dismissed, but the petitioner is also liable to perjury as he

tried to mislead the Court and obtained an order on false facts.

6. Rejoinder has been filed by the petitioner, wherein he has again

attributed the fraud on the part of respondent No.1, on account of

respondent's refusal to pay escalation charges and the balance amount of RA

bills, and argued that it was the consideration for providing the bank

guarantee. It is further submitted that several cheques of respondent No.1

given to the petitioner were dishonoured, on account of respondent No.1

having no sufficient funds. It is further submitted that the petitioner had

made it clear that it was not willing to carry out the work unless it was

provided escalation charges because the respondent No.1 had received an

escalation of approximately 30 crores from ESIC/NBCC. It is further

submitted that after the termination of the work order dated 01.07.2013, the

respondent No.1 made several attempts to get the work completed through

other agencies like Suvidhar Engineers India Pvt. Ltd., but they refused to

take the work knowing that the respondent had defaulted on its obligations

with the petitioner. Thereafter, the respondent again approached the

petitioner for completion of the work and agreed to the petitioner's main

demand, i.e, to provide escalation on the work already carried out by the

petitioner. It was on these grounds that the MoU was executed. It is further

prayed that respondent be restrained from invoking the bank guarantee.

7. The contention of the petitioner on 17.09.2014, before this Court was

that in terms of MoU, the respondent had to pay a sum of Rs.1,96,77,486/-

to petitioner, but instead of paying the said sum, the respondents had

proceeded to invoke the bank guarantee and thereby playing fraud upon the

petitioner. On that day, the counsel for respondent was also present and

while the respondent was given time to file its short-affidavit, an order of

status quo in respect of the bank guarantees was passed. That order is still

operative till date.

8. Parties have also furnished their written synopsis. In the written

synopsis, the submissions made by the petitioner is that the fraud has been

played upon the petitioner since the respondents by making

misrepresentation and fraudulent representation, induced the petitioner to

execute the MoU dated 18.09.2013 and secured three bank guarantees with

the sole purpose to encash the same with the sole objective of financial

enrichment. It is submitted that from the very beginning, the respondent had

no intention of honouring its obligations while the petitioner had fulfilled his

two commitments under the MoU, i.e., providing fresh bank guarantee and

resuming the work. It is submitted that respondent was well aware at the

time of signing the MoU that its financial condition was precarious and they

by inducing the petitioner to enter into an MoU had played fraud upon him.

It is further submitted that the reading of the bank guarantees clearly shows

that the bank guarantees are interlinked with MoU dated 18.09.2013 and

were not executed independently. It is argued that since the fraud has been

played which is egregious in nature, the respondent be restrained from

invoking the bank guarantee. (Reliance is placed on Meghmala and Others

vs. G. Narasimha Reddy and Ors. (2010) 8 SCC 383 and Hindustan

Construction Co.Ltd. vs. State of Bihar and Ors. (1999) 8 SCC 436.

9. On the other hand, it is argued on behalf of the respondent that the

bank guarantees were unconditional and irrevocable. The respondent No.2,

i.e., Bank, as per the terms of the bank guarantee, has undertaken to pay the

amount on demand of the beneficiary, i.e, respondent No.1, without

enquiring into the terms of the agreement or any other circumstance and

notwithstanding any dispute raised by M/s Voltas Limited. The liability of

the bank is absolute and unequivocal under the guarantees. It is further

argued that the law of injunction against the encashment of the bank

guarantee empowers the Court to stay the encashment only on the grounds

when a fraud of egregious nature has been played upon the petitioner or

when the petitioner is going to suffer irretrievable injustice. Reliance is

placed on Consortium of Deepak Cable India Limited vs. Teestavalley

Power Transmission Limited, FAO (OS) 397 and 398/2014.

10. The respondent has also placed reliance in the case of NTPC Limited

vs. Flowmore Private Limited, 1995(4) SCC 515, Hindustan Steel Works

Construction Ltd. Vs. Tarapore & Company, 1996(5) SCC 34, U.P. State

Sugar Corporation vs. Sumac International Ltd. 1997(1) SCC 568,

Mahatma Gandhi Sahakari Sakhar Karkhana Vs. National Heavy

Engineering Coop. Ltd. and Anr. (2007) 6 SCC 470 and Dwarikesh Sugar

Industries Ltd. vs. Prem Heavy Engineering Works Pvt. Ltd. (1997) 6 SCC

450.

11. It is argued that the respondent No.1 is a solvent company having

huge turnover and so the petitioner is not going to suffer any irretrievable

loss. It is further argued that even in the cases of Sick Companies, the

Supreme Court has declined to restrain encashment of the bank guarantee.

(Reliance is placed on U.P. State Sugar Corporation (supra)). It is further

submitted that the petitioner has not been able to show that a fraud has been

played upon him. It is further submitted that whether the escalation price

was payable in relation to the previous work or the work done under MoU is

a matter which qualifies the contractual dispute and does not constitute fraud

which can vitiate the transition of issuance of bank guarantee. Similarly,

whether any amount is payable by the respondent No.1 is again the subject

matter, to be adjudicated upon in the proceedings and is not the scope of

present proceedings. It is submitted that the petition is liable to be dismissed.

12. I have heard the arguments of learned counsel for the parties at length.

I have also gone through the synopsis submitted by the parties and the case

laws supplied by them.

13. The present dispute relates to the encashment of three bank guarantees

of total value of Rs. 3,39,56,750/- which the petitioner had submitted to the

respondent No.1 on execution of MoU dated 17.09.2013 between them. The

respondents' case is that these are unconditional bank guarantees.

14. The petitioner has not pleaded anywhere, either in his petition or in

his rejoinder that these bank guarantees were unconditional bank guarantees.

However, during the course of arguments and also in his written

submissions, it is argued by the petitioner that the bank guarantees were not

unconditional, but were related to the MoU, hence these are conditional

bank guarantees and cannot be encashed unless the terms and conditions of

the MoU are fulfilled. It is argued that one of the terms and conditions of the

MoU was that the respondent No.1 was to clear the RA bills and also make

the payment of the escalation amount, as per the schedule. It is submitted

that part of the money towards RA bills is still due and that no payment has

been made towards escalation charges, therefore, the respondent cannot

encash the bank guarantee. For this purpose, it is essential to understand the

nature of the bank guarantee.

15. The nature and purpose of bank guarantee has been discussed by

Supreme Court in the case of Hindustan Construction vs. State of Bihar

(1999) 8 SCC 436, relied upon by the petitioner. The relevant paragraphs 8

and 9 of the said judgment are reproduced as under:-

"8. Now, a bank guarantee is the common mode of securing payment of money in commercial dealings as the beneficiary, under the Guarantee, is entitled to realise the whole of the amount under that Guarantee in terms thereof irrespective of any pending dispute between the person on whose behalf the Guarantee was given and the beneficiary. In contracts awarded to private individuals by the Government, which involve huge expenditure, as, for example, construction contracts, Bank Guarantees are usually required to be furnished in favour of the Government to secure payments made to the contractor as "advance" from time to time during the course of the contract as also to secure performance of the work entrusted under the contract. Such Guarantees are excusable in terms thereof on the lapse of the contractor either in the performance of the work or in paying back to the "Government Advance", the Guarantee is invoked and the amount is recovered from the Bank. It is for this reason that the Courts are reluctant in granting an injunction against the invocation of Bank Guarantee, except in the case of fraud, which should be an established fraud, or where irretrievable injury was likely to be caused to the Guarantor. This was the principle laid down by this Court in various decisions. In U.P. Cooperative Federation Ltd. v. Singh Consultants & Engineers Pvt. Ltd.: [1988]1SCR1124, the law laid down in Bolivinter Oil SA v. Chase Manhattan Bank [1984] 1 All E.R. 351 was approved and it was held that an unconditional Bank Guarantee could be invoked in terms thereof by the person in whose favour the Bank Guarantee was given and the Courts would not grant any injunction restraining the invocation except in the case of fraud or irretrievable

injury. In Svenska Handelsbanken v. Indian Charge Chrome: AIR1994SC626; Larsen & Toubro Ltd.

v. Maharashtra State Electricity Board: AIR1996SC334; Hindustan Steel Works Construction Ltd. v. G.S. Atwal & Co. (Engineers) (P) Ltd.: AIR1996SC131; National Thermal Power Corporation Ltd. v. Flowmeore (P) Ltd.: AIR1996SC445 ; State of Maharashtra v. National Construction Co.: [1996]1SCR293; Hindustan Steel Works Construction Ltd. v.Tarapore & Co :AIR1996SC2268 as also in U.P. State Sugar Corporation v. Sumac International Ltd.: AIR1997SC1644 , the same principle has been laid down and reiterated.

9. What is important, therefore, is that the Bank Guarantee should be in unequivocal terms, unconditional and recite that the amount would be paid without demur or objection and irrespective of any dispute that might have cropped up or might have been pending between the beneficiary under the Bank Guarantee or the person on whose behalf the Guarantee was furnished. The terms of the Bank Guarantee are, therefore, extremely material. Since the Bank Guarantee represents an independent contract between the Bank and the beneficiary, both the parties would be bound by the terms thereof. The invocation, therefore, will have to be in accordance with the terms of the Bank Guarantee; or else, the invocation itself would be bad."

16. In the light of this settled law, we need to examine the bank guarantee

furnished by the petitioner. The bank guarantee is an independent contract

between the beneficiary and the bank. So, if it is unconditional, then this

contract between the beneficiary and the bank has to be honoured. The

Court cannot restrain the two contracting parties to honour their agreement,

unless except on the two grounds, i.e., an egregious nature of fraud has been

played upon the petitioner, which had issued this bank guarantee, or that he

shall suffer an irretrievable loss. The bank guarantees in dispute had been

issued towards mobilization, advance purpose/execution of the works

awarded. The language used in all the three bank guarantees is the same,

except that one qualifies as bank guarantee towards mobilization and other

towards advance purpose/execution of work. In order to understand the

nature of bank guarantee-one of them is reproduced as under:-

"M/s CRSSG-NCC(JV) 9TH Floor, JMD Regent Square, DLF Qutub Enclave, Phase-II Mehrauli-Gurgaon Road Haryana RE:-Irrevocable and Unconditional Bank Guarantee No.999513BG0002397

At the request of and for the account of M/s. Voltas Limited, A-43, Mohan Coop. Industrial Estate, Mathura Road, New Delhi a company incorporated under the Companies Act, 1956 and having its Registered Office at Voltas House 'A', Baba Saheb Ambedkar Road, Chinchpokli, Mumbai-400033 ("Obligee"), we, State Bank of India, CAG Branch, Ballard Estate, Mumbai-400 001 (Bank) having its Registered Office/Head Office at Nariman Point, Mumbai, a Corporation organized and existing under the laws of India, hereby issue our irrevocable and unconditional Bank Guarantee No. 999513BG0002397

(Guarantee) in favour of CRSSG-NCC (JV), having its Registered Office 9th Floor, JMD Regent Square, DLF Qutub Enclave, Phase-II, Mehrauli-Gurgaon Road, Gurgaon-100022, Haryana, together with its successors and assigns ("Beneficiary"). We understand that M/s Voltas Limited (oblige) was awarded the work of HVAC Works at ESIC Mandi by CRSSG-NCC (JV) (Beneficiary), vide Sub-Contract Agreement No. CRSSG-

NCC(JV)/NBCC/ESIC/WO/008/10-11 dated 12.05.2010. (such Sub-Contract Agreement, as amended and supplemented from time to time, "the sub-Contract Agreement") valued at Rs. 21,90,00,000/- (Rupees Twenty one Crore Ninety Lac only). We further understanding that M/s Voltas Limited (Obligee) is providing the Guarantee seeking release of Mobilization Advance in connection with the Sub- Contract Agreement dated 12.05.2010 ("the Sub- Contract Agreement") entered into between the Beneficiary and the oblige.

We, State Bank of India (Bank) hereby irrevocably and unconditionally undertake on behalf of the Obligee to pay immediately to Beneficiary, on first demand, any sum or sums not exceeding Rs.1,30,56,750/- (Rupees One Crore Thirty Lac Fifty Six Thousand Seven Hundred Fifty only) (The "Stated Amount") if Beneficiary notifies us that the Obligee has failed to perform any of its obligations under "the Sub-Contract Agreement", referred to above.

We, State Bank of India (Bank), agree that we shall have no duty or right to inquire as to the basis upon which Beneficiary has determined to present to us this Guarantee. We shall be entitled to rely and shall rely solely upon this Guarantee and shall be under no duty to, nor shall we under any circumstances whatsoever, inquire into the terms of the Sub-

Contract Agreement or any other circumstances, matters or documents.

We undertake to pay to the said Beneficiary any money so demanded notwithstanding any dispute or disputes raised by the said Obligee in any suit or proceedings pending before any Court or Tribunal relating thereto. Our liability under this Guarantee is absolute and unequivocal.

We, State Bank of India (Bank), hereby waive any right we may have to first require Beneficiary to pursue Beneficiary's legal remedies against the Obligee and waive any presentment, demand, protest or notice of any kind. We hereby agree that the Agreement may be modified, amended and supplemented without our consent in any manner and agree that no such modification, amendment or supplement shall release, affect or impair our liability under this Guarantee.

We, State Bank of India, shall pay any stated amount demanded by the Beneficiary, forthwith on receipt of the Beneficiary's demand.

Partial drawings are permitted, and this Guarantee shall, except to the extent reduced thereby, survive any partial drawings. The Stated Amount shall be reduced by the amount of any partial drawing by invocation under this Bank Guarantee at the request of Beneficiary.

This Guarantee is valid through and including its expiry date of 30.09.2014 (in words Thirtieth day of September Two Thousand Fourteen). Upon request by the Obligee, on or prior to the current Expiraty Date, the Guarantee shall be extended, in which case we will provide Beneficiary with an amendment hereto.

Any notice to Beneficiary in connection with this

Guarantee shall be in writing and shall be delivered by hand with receipt acknowledged, or by Registered mail, postage prepaid, to Beneficiary. Any amendment reducing the amount of this Guarantee or otherwise limiting or impairing Beneficiary's rights hereunder shall not be effective, unless consented to in writing by the Beneficiary.

This Guarantee will not be discharged due to the change in the constitution of the Bank or the Obligee or the Beneficiary.

This Guarantee shall be governed by and construed in accordance with the laws of India.

Notwithstanding anything contained hereinabove:

a) Our liability under the Bank Guarantee shall not exceed Rs. 1,30,56,750/- (Rupees one Crore Thirty Lac Fifty Six Thousand Seven Hundred Fifty only)

b) This Bank Guarantee shall be valid up to 30.09.2014; and

c) We are liable to pay the guaranteed amount or any part thereof under this Bank Guarantee only and only if you serve upon us a written claim or demand on or before 31.12.2014. Unless a claim in writing is presented to us or a suit to enforce any claim under this guarantee is filed with us with in a period of three months after the expiry of the bank guarantee i.e. with in 31.2.2014 all your rights under the said guarantee shall be forfeited and we shall be released and discharged from all liabilities thereunder."

(emphasis supplied)

17. The language and the title of these bank guarantees emphatically

show that it is an unconditional irrevocable bank guarantee and not the

conditional one, as argued by learned counsel for the petitioner. The

contention that this bank guarantee is in relation to MoU does not make the

bank guarantee as conditional one because all the bank guarantees are given

by the contractors, pursuant to the some agreement and thus all the bank

guarantees are pursuant to some agreement. That does not make a bank

guarantee a conditional one, unless it is shown in the bank guarantee that the

banks are to honour the bank guarantee on fulfilment of some condition on

the part of any party. Under this bank guarantee, the bank was under

obligation to encash the bank guarantee in favour of the beneficiary on

demand. Thus, the bank guarantees are unconditional bank guarantees and

the argument of the petitioner to the contrary has no force.

18. The petitioner has relied on the findings in the case of Hindustan

Construction Co.Ltd. (supra). However, the facts in that case are entirely

different. It is apparent from the judgment that after interpreting the bank

guarantees and the terms of the contract, the Court had reached to the

conclusion that the bank guarantees were not unconditional bank guarantees.

In the present case, however, the bank guarantees are unconditional bank

guarantees and not conditional ones. Moreover, the case law discussed by

Supreme Court in Hindustan Construction Co.Ltd. (supra) is squarely

applicable on the facts of this case, as already discussed.

19. This Court in a recent judgment Consortium of Deepak Cable India

Limited (supra), has held as under:-

"145..............Disputes pertaining to the main contract cannot be considered by a court when a claim under a bank guarantee is made and the court would be precluded from embarking on an enquiry pertaining to the prima facie nature of the respective claim of the litigating parties relatable to the main dispute. The dispute between the parties to the underlying contract has to be decided at the civil forum i.e. a civil suit if there exists no arbitration clause in the contract or before the arbitral tribunal if there exists an arbitration clause in the contract. Pendency of arbitration proceedings is no consideration while deciding on the issue of grant of an interim injunction. That certain amounts have been recovered under running bills and have to be adjusted for is of no concern in matters relating to invocation of bank guarantee. That there are serious disputes on questions as to who committed the breach of the contract are no circumstances justifying granting an injunction pertaining to a bank guarantee. Plea of lack of good faith and/or enforcing the guarantee with an oblique purpose or that the bank guarantee is being invoked as a bargaining chip, a deterrent or in an abusive manner are all irrelevant and hence have to be ignored. There are only two well recognized exceptions to the rule against permitting payment under a bank guarantee. The same are:-

A. A fraud of egregious nature;

B. Encashment of the bank guarantee would result in irretrievable harm or injustice of an irreversible kind to one of the parties."

Supreme Court has clearly held that the Court cannot issue an

injunction against the invocation of the bank guarantees, except in case of

fraud or in case of irretrievable injury. The petitioner, therefore, has to

establish before this Court in order to succeed that a fraud has been played

upon him while obtaining the bank guarantee or that he shall suffer an

irretrievable loss.

20. The petitioner has also relied on paras 28, 29 and 33 in the case of

Meghmala and Others (supra), wherein the expression 'fraud' has been

defined and the Courts are advised to take the element of fraud seriously and

the Court has held that any act which is tainted by fraud should not be

condoned and sustained. The Court has also relied while defining the fraud

on the findings in Lazarus Estate Ltd. Vs. Besalay (1956) 1 QB 702: (1956)

2 WLR 502, Andhra Pradesh State Financial Corporation Vs. M/s. GAR

Re-Rolling Mills & Anr. AIR 1994 SC 2151 and State of Maharashtra &

Ors. Vs. Prabhu (1994) 2 SCC 481.

In para 33, the Court has observed as under:-

"Fraud is an intrinsic, collateral act, and fraud of an egregious nature would vitiate the most solemn

proceedings of courts of justice. Fraud is an act of deliberate deception with a design to secure something, which is otherwise not due. The expression "fraud" involves two elements, deceit and injury to the person deceived. It is a cheating intended to get an advantage. (Vide Dr. Vimla Vs. Delhi Administration AIR 1963 SC 1572; Indian Bank Vs. Satyam Fibres (India) Pvt. Ltd. (1996) 5 SCC 550; State of Andhra Pradesh Vs. T. Suryachandra Rao AIR 2005 SC 3110; K.D. Sharma Vs. Steel Authority of India Ltd. & Ors. (2008) 12 SCC 481; and Regional Manager, Central Bank of India Vs. Madhulika Guruprasad Dahir & Ors. (2008) 13 SCC 170)."

So, the question which is required to be determined by this Court is

whether any fraud has been played upon the petitioner for obtaining the

bank guarantees in dispute.

21. Fraud can be ascertained on the basis of facts. The person who comes

before the Court with the allegation that a fraud has been played upon him

has to establish those facts on record, which constitute the fraud. In its

pleading, the petitioner has only pleaded in para 21 that threat to encash the

bank guarantee amounts to a clear egregious fraud by respondent No.1. No

other fact has been pleaded by the petitioner which constitute fraud.

22. In rejoinder also, the petitioner has not pleaded any facts which

constitute fraud, except that the egregious fraud is made out from documents

and pleadings. In written synopsis and during arguments, it has been

submitted that the fraud on the part of respondent No.1 is clear from the fact

that the respondent did not pay the escalation charges under MoU and also

failed to pay the balance amount of RA bills and that the encashment of

bank guarantee was a consideration towards such payment. From the bare

reading of the MoU, it is apparent that payment of escalation charges was

not the condition precedent of submitting the bank guarantee. Encashment of

the bank guarantee was also not made conditional to the clearance of RA

bills. It is thus clear that the submission of bank guarantee was

unconditional. During the course of arguments, however, it is argued by the

learned counsel for the petitioner in a desperate attempt to succeed that the

petitioner was induced into the MoU by misrepresentation and fraudulent

representations by respondent with the sole intention to obtain the three bank

guarantees with sole purpose to encash them in order to save themselves

from financial crisis and to get enriched. These facts they were cheated into

the MoU are not pleaded by the petitioner, rather in the petition, contrary

facts have been pleaded.

23. The relevant Para 9 and 10 of petition are reproduced herein:-

"9. subsequent to the developments, the parties entered into negotiations in

order to settle the differences between them. The petitioner thereupon wrote

to the learned Arbitrator on 11.09.2013 requesting him to defer the matter,

since the parties were negotiating settlement. Thereafter the petitioner and

respondent No.1 executed a Memorandum of Understanding (MoU) dated

18.09.2013, at New Delhi.

10. Petitioner states that in terms of the aforesaid MoU, the respondent No.1

agreed to refund the sum of Rs. 4.28 crores which had been illegally

encashed by the respondent No.1. The petitioner in turn agreed to furnish

fresh guarantees for Rs.3,39,56,750/-. The respondent No.1 also accepted

the claim of the petitioner that the delay in the execution of the project and

the consequential time and cost overruns entitled the petitioner to be

compensated by Escalation. The amount of escalation was quantified at

Rs.1,25,00,000/-"

24. It, therefore, is clear that no contention is there on the part of the

petitioner in his petition that he was induced into the MoU by any

misrepresentation or fraudulent misrepresentation. The pleadings on the

other hand show that the petitioner had voluntarily entered into MoU.

Moreover, the very nature of the MoU (terms and conditions enunciated

therein) clearly shows that two things were done simultaneously. Execution

of three bank guarantees of Rs.1,30,56,750.00, Rs.1,09,50,000.00, and Rs

99,50,000.00 by petitioner and refund of cash of sum of Rs.4.28 crores by

respondent No.1. The record of this fact in the MoU clearly shows that

respondent No.1 bartered a cash amount of Rs.4.28 crores against threes

three bank bank guarantees worth of Rs.3.39 crores executed by petitioner.

The Court is unable to make out as to in what manner the respondent No.1

had got enriched by inducing the petitioner into the present MoU. The

dispute between the parties to the effect whether the escalation charges were

for the work done under this MoU or were for the work already done under

the earlier work order, is not a subject matter of the present petition and the

parties are free to raise this dispute before appropriate forum. The meaning

of the word fraud in Oxford English Dictionary is 'the use of false

representation to gain unjust advantage'. In the present case by entering into

an MoU, the petitioner has failed to show that respondent No.1 had put

himself in a position of undue advantage. As shown earlier, not only they

had paid a cash of Rs.4,28,00,000/- to the petitioner, but also agreed to pay a

sum of Rs.1,25,00,000/- towards escalation charges to the petitioner. The

petitioner, therefore, has failed to satisfy this Court that he has been induced

by respondent No.1 into this MoU and has put him in a position of undue

disadvantage, while putting respondent in a position of undue advantage.

Both parties have voluntarily as part of a settlement entered into MoU and

pursuant to that while the respondent refunded the cash amount of

Rs.4,28,00,000/-, the petitioner executed the present unconditional bank

guarantee. The petitioner, therefore, has failed miserably to show that any

egregious fraud had been played upon him for execution of the present bank

guarantees. There is no dispute to the fact that the respondent is a company

worth of Rs.6270.83 crores as an individual and worth of Rs.7568.69 crores

as a group and is not a sick company, as stated by respondent No.1 on

affidavit.

25. In the case U.P. State Sugar Corporation (supra), the Supreme Court

has clearly held that pendency of reference of the contractor company before

BIFR under Sick Industrial Companies (Special Provisions) Act would not

be sufficient to constitute irretrievable injustice.

26. It, therefore, cannot be said that the petitioner shall suffer an

irretrievable injury if the stay is not granted to it.

27. For the foregoing reasons, I hold that the petitioner is not entitled to

any relief. The stay granted by this Court stand vacated and the petition

stands dismissed.

DEEPA SHARMA (JUDGE) DECEMBER 10, 2014 BG

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter