Friday, 24, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Saisudhir Infrastructures ... vs Union Of India & Ors
2014 Latest Caselaw 6591 Del

Citation : 2014 Latest Caselaw 6591 Del
Judgement Date : 9 December, 2014

Delhi High Court
Saisudhir Infrastructures ... vs Union Of India & Ors on 9 December, 2014
Author: Rajiv Sahai Endlaw
$~24
*    IN THE HIGH COURT OF DELHI AT NEW DELHI

                                   Date of decision: 9th December, 2014
+     LPA 753/2014

      SAISUDHIR INFRASTRUCTURES LIMITED           ..... Appellant
                       Through:    Mr. Arun Kathpalia, Mr. M.
                       Gireesh Kumar and Mr. Vishnu Kumar Jain,
                       Advs.

                                 Versus
    UNION OF INDIA & ORS                         ..... Respondents
                      Through:      Mr. Jaswinder Singh and Ms.
                      Shipra Shukla, Advs.
CORAM:
HON'BLE THE CHIEF JUSTICE
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW

RAJIV SAHAI ENDLAW, J

CM No.19118/2014 (for condonation of 16 days delay in filing the
appeal)

1.    We have heard the counsel for the appellant as well as the counsel for

the respondents No.1 & 2 appearing on advance notice. Need is not felt to

hear the respondent No.3 M/s. Indu Project Limited on the application. For

the reasons stated, the delay in filing the appeal is condoned.

2.    The application is disposed of.


LPA No.753/2014                                                   Page 1 of 7
 LPA 753/2014 & CM No.19115/2014 (for directions)

3.    This intra court appeal impugns the order dated 8 th September, 2014

of the learned Single Judge of this Court of dismissal of W.P.(C)

No.5897/2014 preferred by the appellant, giving liberty to the appellant to

institute appropriate proceedings in accordance with law.

4.    We have heard the counsel for the appellant.

5.    The writ petition from which this appeal arises was filed, pleading:

      (i)   that the respondent No.3 M/s. Indu Project Limited was

            appointed as a contractor, by the respondent No.2 Director

            General of Married Accommodation Projects (MAP), Engineer-

            in-Chief's Branch, Integrated HQ of Ministry of Defence

            (Army), for construction of residential accommodation at a)

            Mamun (Pocket-4), b) Basoli, Mamun (Pockets-1&3), and c) at

            Damtal;

      (ii) that the appellant / writ petitioner is the sub-contractor of the

            respondent No.3 for one portion of the aforesaid works;

      (iii) that disputes arose between the respondent No.1&2 on the one

            hand and the respondent No.3 on the other hand and the


LPA No.753/2014                                                    Page 2 of 7
             respondents No.1&2 cancelled the appointment of the respondent

            No.3 as the contractor for the aforesaid works;

      (iv) that material of the appellant / writ petitioner is lying at the said

            site;

      (v) that the appellant / writ petitioner has learnt that the said material

            is being utilized for completing the works left by the respondent

            No.3;

      (vi) that the appellant / writ petitioner asked the respondents No.1&2

            to return the said material and to stop using the same for the

            purposes of completing the works;

      (vii) however no response was received thereto;

      (viii)that the appellant / writ petitioner filed W.P.(C) No.4083/2014

            seeking a direction to the respondents No.1&2 to return the said

            material;

      (ix) that the said writ petition was however withdrawn on 7 th July,

            2014 with liberty to file a representation and the writ petition was

            disposed of with a direction to the respondent No.2 to dispose of

            the said representation within four weeks of receipt thereof;




LPA No.753/2014                                                      Page 3 of 7
       (x) that the representation so made by the appellant / writ petitioner

            was however rejected by the respondent No.2, on the grounds:

            (a) that the respondent No.3 was barred from subletting any

            portion of the contract without prior approval of the respondent

            No.2 and neither was any such approval sought nor given for

            appointing the appellant / writ petitioner as the sub-contractor;

            (b) that thus no cognizance of the appellant / writ petitioner as

            the sub-contractor can be taken; (c) that as per the terms and

            conditions of the contract, the respondents No.1&2 are at liberty

            to hold and retain in their hands all materials on site and to either

            sell or to use the same; (d) that the respondent No.3 was afforded

            an opportunity to take away the said material against furnishing

            non-revocable bank guarantee but the respondent No.3 did not

            avail of the said opportunity; (e) that as per the terms and

            conditions of the contracts, all materials brought to site, are to

            become the property of the respondents No.1&2 and cannot be

            removed, if not used and / or disposed of, till the completion of

            the work; (f) that the works had not been completed as yet.




LPA No.753/2014                                                       Page 4 of 7
       Aggrieved from the aforesaid, the writ petition from which this appeal

arises, was filed.

6.    The learned Single Judge has dismissed the writ petition observing

that several disputed questions are involved including whether the contract

between the appellant / writ petitioner and the respondent No.3 was

approved by the respondent No.2 and the extent of machinery and material

brought at site by the appellant / writ petitioner and the writ petition was not

the appropriate proceeding where such disputed questions can be considered.

7.    The appellant / writ petitioner, in the appeal, has not controverted that

as per the contract between the respondent No.2 and the respondent No.3,

the respondent No.3 was not entitled to remove the material brought at site.

We have as such enquired from the counsel for the appellant / writ

petitioner, as to how the appellant / writ petitioner, who claims to be a sub-

contractor, can have better rights against the respondents No. 1 and 2

principal than the contractor itself.

8.    The counsel for the appellant / writ petitioner states that since the

respondents No.1&2 do not recognize the appellant / writ petitioner as a sub-

contractor, the respondents No.1&2 are not entitled to enforce the conditions

in the contract with the respondents No.1&2 and since the material belongs

LPA No.753/2014                                                      Page 5 of 7
 to the appellant / writ petitioner, the appellant / writ petitioner is entitled to

remove the same and the respondents No.1&2 are not entitled to retain the

same.

9.      We are unable to agree. The appellant / writ petitioner, who claims to

have entered into a back to back contract with the respondent No.3, was

aware of the terms and conditions of the contract between the respondent

No.2 on the one hand and the respondent No.3 on the other hand and cannot

now be heard to claim contrary thereto. The appellant / writ petitioner, as a

sub-contractor of the respondent No.3, is deemed to have also consented to

the terms and conditions specially those cited by the respondent No.3 in the

order dated 12th August, 2014 rejecting the representation of the appellant /

writ petitioner.

10.     Even otherwise, the matter in issue is a purely contractual one, having

no element of public law and the remedy under Article 226 of the

Constitution of India, according to us is not available. The Supreme Court

in Kerala State Electricity Board Vs. Kurien E. Kalathil (2000) 6 SCC 293

held that interpretation and implementation of a clause in a contract cannot

be the subject matter of a writ petition, being in the realm of private law and

the fact that one of the parties to the agreement is a statutory or a pubic body

LPA No.753/2014                                                        Page 6 of 7
 will not of itself affect the principles to be applied. It was held that every act

of a statutory body need not necessarily involve an exercise of statutory

power. Similarly, in Godavari Sugar Mills Ltd. Vs. State of Maharashtra

(2011) 2 SCC 439 it was held that normally a petition under Article 226 of

the Constitution of India will not be entertained to enforce a civil liability

arising out of a breach of contract and the aggrieved party will have to

agitate the question in a Civil Court. It was further held that only where the

lis has a public law character or involves a question arising out of public law

functions on the part of the State or its authorities, access to justice by way

of a public law remedy will be allowed.

11.   We therefore do not find any merit in the appeal and dismiss the same.

We clarify that none of the observations contained herein will have any

binding effect in the appropriate proceedings taken out by the appellant /

writ petitioner.

      No costs.


                                         RAJIV SAHAI ENDLAW, J.

CHIEF JUSTICE

DECEMBER 09, 2014/bs..

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter