Citation : 2013 Latest Caselaw 707 Del
Judgement Date : 13 February, 2013
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of Judgment:13.02.2013
+ FAO(OS) 302/2012
NATIONAL HIGHWAYS AUTHORITY OF INDIA .... Appellant
Through Mr. Arun Kumar Varma, Ms.
Mansi Wadhera and Mr. Ashish
Bansal, Adv.
versus
NCC-KNR ..... Respondent
Through Mr. Amit George and Mr.Abin
Mathew, Adv.
CORAM:
HON'BLE MR. JUSTICE SANJAY KISHAN KAUL
HON'BLE MS. JUSTICE INDERMEET KAUR
INDERMEET KAUR, J.
1 The National Highways Authority of India (appellant) had
awarded a contract to NCC-KNR (respondent) on 22.03.1999 in terms
of which the work was to commence on 28.04.1999 and the scheduled
date of completion was 27.04.2002. The work could not be completed
within the stipulated period and extension of time was accordingly
granted by a period of five months i.e. up to 26.09.2002.
2 Disputes arose between the parties and the matter was referred to
arbitration. By an Award dated 09.01.2012, the claims of the respondent
were adjudicated and the amounts awarded under various heads.
3 The appellant not satisfied with the Award filed his objections
under Section 34 of the Arbitration and Conciliation Act, 1996
(hereinafter referred to as the 'said Act'). The learned Single Judge
dismissed the objections by the impugned order dated 18.05.2012.
4 Learned counsel for the appellant has today restricted his
submissions under two heads i.e. amounts awarded under claim No. 4
and claim No. 5 as also the amounts awarded under claim No. 1 and
claim No. 2-A. He fairly concedes that the amount awarded under claim
No. 8 which was a refund of royalty on earth deducted from the
respondent's bill stood covered as against the appellant by a judgment of
this Court in FAO (OS) No. 48/2012 titled NHAI Vs. Hindustan
Construction Ltd. decided on 08.11.2002 which in turn referred to a
recent pronouncement in FAO (OS) No.451/2012 titled NHAI Vs.
Oriental Structural Engineers Pvt. Ltd. decided on 18.09.2012. The
aforesaid decisions relied upon NHAI Vs. ITD Cementation India Ltd.
2008 (100) DRJ 431 to hold that the question regarding claim for
additional royalty stood settled in terms of this decision. Learned
counsel for the appellant did not seriously press claim No. 7 which was
a claim on account of bank charges incurred by the claimant due to
undue extension of his bank guarantees.
5 Qua claim No. 4 and claim No. 5, the submission is that there is a
overlap; while under claim No. 4, the amount awarded is additional
overheads incurred for acceleration of work, at the same time, under
claim No. 5, the amount has been awarded on account of idling of the
plant and machinery; submission being that both the aforenoted claims
could not have been awarded simultaneously; the amount awarded under
both the heads would be contrary. Attention has been drawn to the
statement of claim made by the claimant before the Arbitrator.
Submission being that the case of the claimant was that there was an
idling of his machinery for a considerable period before the start of the
work; he was claiming hire charges for equipment and machinery
brought to the site from the date of arrival of the machinery to the start
of the effective working of those machines; this was during the initial
period of contract and as such idling charges during this period could
not be claimed. At best, he could claim idling charges for the extended
period of contract (five months) but this is not what has been set up by
him in his statement of claim and the Arbitral Tribunal has proceeded to
award him both amounts i.e. for acceleration of his work as also for
idling of his plant and machinery which is an infirmity. This finding
having been endorsed by the learned Single Judge is a further illegality.
6 His submission qua claim No. 1 and claim No. 2-A which have
been awarded as extra payments because of variations in the work are
against the express provisions of the contract; Clause 52 of the GCC
(General Conditions of Contract) read along with amendment have been
interpreted incorrectly. There were admittedly two threshold limits; the
respondent had crossed the first threshold limit of 25% but the second
threshold limit of 5% had not been reached by him which fact has been
ignored by the Arbitral Tribunal by wrongly interpreting clause 52.
There was no material to justify claim No. 2-A as well.
7 These submissions have been countered. Submissions being that it
is a reasoned Award and calls for no interference.
8 We shall first deal with the amounts awarded under claim No. 4
and claim No. 5 and to answer this argument, the statement of claim as
set up by the claimant before the Arbitrator is relevant. Under claim No.
4, the claimant has claimed an amount of Rs.12,18,60,452 as additional
overhead expenses incurred by the claimant for acceleration of work.
Under claim No. 5, the claimant has made a claim of Rs.9,17,88,600/-
for payment due on account of idling of plant and machinery. While
dealing with these claims, the Arbitral Tribunal has arrived at a finding
(not challenged) that the extension of time granted by the appellant of
five months was primarily because of the delay which was attributable
to the appellant. It is in this background that the aforenoted two claims
have to be viewed. The claimant under claim No. 4 has submitted that a
hindrance free site was not handed over in time by the appellant and the
completion of work could finally be achieved by the claimant by
working between 16-20 hours, paying heavy overtime wages and
incentives. Because of this piecemeal handing over of site, payment for
unforeseen costs had to be incurred by the claimant in order to finalize
his work in time. These overheads due to this delay had been
communicated by the respondent to the appellant vide letter dated
16.11.1999. Admittedly the Engineer vide his letter dated 11.12.2004
had recommended a payment of Rs.117.14 lacs to the respondent based
on the contention that the overheads are due in respect of the extended
period only. The claimant was aggrieved by this amount returned by the
Engineer and he had filed his claim before the Arbitral Tribunal. His
submission was that the Engineer had not taken into account the claim
made by the claimant for acceleration of work. Accordingly a sum of
Rs.12,18,16,542/- had been claimed by the claimant under claim No. 4.
Under claim No. 5, the claimant had claimed an amount of
Rs.9,17,88,600/- on account of idling of plant and machinery. His
submission in his claim petition was that he was fully prepared to
execute and finish the whole of the work within the stipulated period of
36 months and the claimant had mobilized and deployed sufficient
resources including machinery and manpower. However, because of
delay caused by the appellant and due to no fault of the claimant, the
machinery which had been deployed by the claimant could not be used
but the same continued to be deployed at the site for the substantial
completion of work. Initially his machinery idled for a considerable
period of time because of these delays and hindrance. The work did not
progress as had been planned; it got prolonged and the same was
completed only in the extended period of time i.e. by September, 2002.
His submission being that had the claimant been allowed to work
without any delay and hindrance, there was no need to keep the
machinery and equipment in this prolonged period. This prolongation
occurred on account of the various delays and hindrances on the part of
the appellant.
9 The Arbitral Tribunal while dealing with claim No. 4 has noted
that the Engineer of the appellant has himself accepted the fact that there
was a five months overstay and the claimant was entitled for a
compensation which had been worked out at Rs.117.14 lacs. The
Arbitral Tribunal had, however, reduced this amount from Rs.117.14 to
Rs.1,04,29,000/-. He had noted that overheads to which the respondent
was entitled was the reduced figure of Rs.104.29 lacs. This sum had
been awarded for the prolongation of the work which was due to the
fault of the appellant and for which the claimant had suffered a loss.
This amount as rightly pointed out by the learned counsel for the
respondent was not for the acceleration of work. Under claim No. 5, the
amount claimed by the claimant was Rs.9,17,88,600/- but the amount
awarded by the Arbitral Tribunal was Rs.1,33,12,303/-. The Arbitral
Tribunal had noted that the claimant could not complete his work as per
the approved programme and he could not mobilize the machines as
planned; part of his equipment was hired and only part was owned by
him. The claimant had in fact made a claim for damages for idling of
machinery for two periods; i.e. during the original contract period which
was between May, 1999 to actual deployment. In the second part, the
claimant had made a claim for idling of machinery from May, 2002 to
September, 2002 i.e. during the extended period of five months. The
Arbitral Tribunal did not award any amount for idling/non-hindrance of
machinery during the original period of contract noting that the claimant
was the best Judge for the deployment of machinery and was solely
responsible for its effective utilization. However, for the extended
period of five months i.e. from May, 2002 to September, 2002 since
there was ample evidence to show that the claimant had to overstay at
the site for doing the balance work, he was entitled to appropriate
compensation.
10 The learned Single Judge while dealing with these claims rightly
thought it fit not to interfere with them. Apart from the fact that there
was evidence to show that during the extended period of five months,
the claimant had to overstay at the site along with machinery, for which
he had to pay hire charges to complete the balance work; the approach
adopted by the Tribunal for calculation of the said amount (detailed as
Annexure 2 with the impugned Award) also did not call for any
interference. The reasoning given by the Arbitral Tribunal was correctly
endorsed by the learned Single Judge. Under claim No. 4, the amount
was not awarded for the acceleration of work; it was additional overhead
expenses borne by the claimant for prolongation of the work. Under
claim No. 5, the amount was awarded as compensation during the
extended period of contract as admittedly the respondent had to overstay
at the site and part of the machinery being on hire and not all of it owned
by the respondent, there was a prolonged deployment of machinery. The
ownership cost method for calculation under this head which was a
detailed calculation (appended as Annexure 3 to the Award) had been
gone into and rightly did not call for any interference by the learned
Single Judge or even by this Court. There was no conflict in the grant of
respective amounts under claim No. 4 and claim No. 5.
11 With regard to claim No. 1, the Arbitral Tribunal had considered
clauses 52.1 & 52.2 of the contract. To better appreciate this
controversy, clauses 52.1 and 52.2 are reproduced hereinbelow:-
"52.1 Valuation of Variations
All variations referred to in Clause 51 and any additions to the Contract Price which are required to be determined in accordance with Clause 52 (for the purpose of this Clause referred to as „varied work‟), shall be valued at the rates and prices set out in the Contract does not contain any rates as prices applicable to the varied work, the rates and prices in the Contract shall be used as the basis for valuation so far as may be reasonable, falling which after due consultation by the Engineer with the Employer and the Contract, suitable rates or prices shall be agreed upon between the Engineer and the Contract. In the event of disagreement, the Engineer shall fix such rates or prices as are, in his opinion appropriate and shall notify the Contractor accordingly, with a copy to the Employer. Until such time as rates or prices are agreed or fixed, the Engineer shall determine provisional rates or prices to enable on account payments to be included in certificates issued in accordance with Clause 60.
52.2 Power of Engineer to Fix Rates
Provided that if the nature or amount of any varied work relative to the nature or amount of the whole of the works or to any part thereof, is such that in the opinion of the Engineer, the rate or price contained in the Contract for any item of the works is, by reason of such varied work, rendered inappropriate or inapplicable then after due consultation by the Engineer with the Employer and the Contractor, a suitable rate or price shall be agreed upon between the Engineer and the Contractor. In the event of disagreement, the Engineer shall fix such other rate or price as is, in his opinion, appropriate and shall notify the Contractor accordingly, with a copy to the Employer. Until such time as rates or prices are agreed or fixed, the Engineer shall determine provisional rates or prices to enable on account payment to be included in certificates issued in accordance with Clause 60.
The following has been added here by way of SCC.
"Provided that no change in the unit rates or prices for any item considered for items included in the Bill of quantities, unless such items individually account for an amount of more than 5 (five) percent of the Contract Price named in the Letter Acceptance, and the actual quantity of work performed under the item exceeds or falls short of the original billed quantity by more than 25 percent."
12 The proviso to clause 52.2 of the contract was added by way of an
amendment. The question which had to be answered by the Arbitral
Tribunal was whether the claimant was entitled to a variation of the rates
and what would be the appropriate method to deal with the fixation of
new rates. The submission of the learned counsel for the appellant that
this proviso under clause 52.2 has been given a go-bye has been
answered by the Arbitral Tribunal. It was noted that this proviso had
been inserted by an amendment and did not find place in the original
GCC of FIDIC. The basic purpose of this proviso was to guard against
difficulties in contract administration arising out of minor variations in
the BOQ item of work. However in the instant case, the situation was
abnormal in as much as increase in the quantity of work was of the order
of 196% and its value (at existing BOQ rates) was 14.82% of the
contract price. The average lead for the varied work would be about
three kilometers. The frequent changes made in the profile by the
appellant had rendered the planned working by the respondent to have
become impossible; he was forced to work in a restricted width of 1-2
meters on both sides. Since the additional work was less than the
eligibility threshold limit of 5%, the enhanced rate was not allowed.
Although there was no alteration in the nature of the work yet the
quantum of variations was material and required a detailed examination;
it was 20% or more of the original contract price. The detailed
calculation was worked out by the Arbitral Tribunal to arrive at the
figure under claim No. 1 and this was after due consideration of clause
52.2 read along with its proviso. The view taken by the Tribunal which
was endorsed by the learned Single Judge being a reasonable view
rightly calls for no interference.
13 Under Claim No.2 the Arbitral Tribunal had noted that there was
no justification for fixation of new rates for the ROB work particularly
since the variation order dated 07.12.2000 regarding construction of the
ROB was issued by the appellant and agreed to; there being no change
of quantities; there was no justification of new rates. However, costs
were quantified taking into account the additional concrete quantities
executed over the BOQ quantities and the percentage increase. The
Arbitral Tribunal arrived at the aforenoted amount by a reasoned
calculation. It was based on an analysis of the figure.
14 Thus although the amounts claimed under the two heads i.e. claim
No. 1 and claim No. 2-A was much higher, yet much lower figures were
awarded which in terms of the tabulated chart on the basis of which the
aforenoted figures were arrived at, call for no interference. We are in
full agreement with the approach of the learned Single Judge.
15 This Court is not an appellate body hearing an appeal against the
fact findings arrived at by the Arbitral Tribunal; the scope of objections
under Section 34 of the said Act is limited; in appeal, the ambit of the
arguments would be confined to what has been answered in the
impugned judgment. It was an expert body of three members of the
Arbitral Tribunal who had dealt with the rival claims of the parties; the
learned Single Judge has also discussed each submission in detail. On
no count, does the impugned order call for any interference.
16 Appeal is without any merit. Dismissed leaving the parties to bear
their own costs.
17 The balance amount lying in the Court is consequently directed to
be released by the Registry to the respondent and the security furnished
by the respondent be discharged.
INDERMEET KAUR, J
SANJAY KISHAN KAUL, J FEBRUARY 13, 2013 A
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!