Saturday, 25, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

National Highways Authority Of ... vs Ncc-Knr
2013 Latest Caselaw 707 Del

Citation : 2013 Latest Caselaw 707 Del
Judgement Date : 13 February, 2013

Delhi High Court
National Highways Authority Of ... vs Ncc-Knr on 13 February, 2013
Author: Indermeet Kaur
*     IN THE HIGH COURT OF DELHI AT NEW DELHI
%                     Date of Judgment:13.02.2013

+   FAO(OS) 302/2012
NATIONAL HIGHWAYS AUTHORITY OF INDIA            .... Appellant
                   Through  Mr. Arun Kumar Varma, Ms.
                            Mansi Wadhera and Mr. Ashish
                            Bansal, Adv.
                   versus
NCC-KNR                                 ..... Respondent
                   Through  Mr. Amit George and Mr.Abin
                            Mathew, Adv.
CORAM:
HON'BLE MR. JUSTICE SANJAY KISHAN KAUL
HON'BLE MS. JUSTICE INDERMEET KAUR

INDERMEET KAUR, J.

1 The National Highways Authority of India (appellant) had

awarded a contract to NCC-KNR (respondent) on 22.03.1999 in terms

of which the work was to commence on 28.04.1999 and the scheduled

date of completion was 27.04.2002. The work could not be completed

within the stipulated period and extension of time was accordingly

granted by a period of five months i.e. up to 26.09.2002.

2 Disputes arose between the parties and the matter was referred to

arbitration. By an Award dated 09.01.2012, the claims of the respondent

were adjudicated and the amounts awarded under various heads.

3 The appellant not satisfied with the Award filed his objections

under Section 34 of the Arbitration and Conciliation Act, 1996

(hereinafter referred to as the 'said Act'). The learned Single Judge

dismissed the objections by the impugned order dated 18.05.2012.

4 Learned counsel for the appellant has today restricted his

submissions under two heads i.e. amounts awarded under claim No. 4

and claim No. 5 as also the amounts awarded under claim No. 1 and

claim No. 2-A. He fairly concedes that the amount awarded under claim

No. 8 which was a refund of royalty on earth deducted from the

respondent's bill stood covered as against the appellant by a judgment of

this Court in FAO (OS) No. 48/2012 titled NHAI Vs. Hindustan

Construction Ltd. decided on 08.11.2002 which in turn referred to a

recent pronouncement in FAO (OS) No.451/2012 titled NHAI Vs.

Oriental Structural Engineers Pvt. Ltd. decided on 18.09.2012. The

aforesaid decisions relied upon NHAI Vs. ITD Cementation India Ltd.

2008 (100) DRJ 431 to hold that the question regarding claim for

additional royalty stood settled in terms of this decision. Learned

counsel for the appellant did not seriously press claim No. 7 which was

a claim on account of bank charges incurred by the claimant due to

undue extension of his bank guarantees.

5 Qua claim No. 4 and claim No. 5, the submission is that there is a

overlap; while under claim No. 4, the amount awarded is additional

overheads incurred for acceleration of work, at the same time, under

claim No. 5, the amount has been awarded on account of idling of the

plant and machinery; submission being that both the aforenoted claims

could not have been awarded simultaneously; the amount awarded under

both the heads would be contrary. Attention has been drawn to the

statement of claim made by the claimant before the Arbitrator.

Submission being that the case of the claimant was that there was an

idling of his machinery for a considerable period before the start of the

work; he was claiming hire charges for equipment and machinery

brought to the site from the date of arrival of the machinery to the start

of the effective working of those machines; this was during the initial

period of contract and as such idling charges during this period could

not be claimed. At best, he could claim idling charges for the extended

period of contract (five months) but this is not what has been set up by

him in his statement of claim and the Arbitral Tribunal has proceeded to

award him both amounts i.e. for acceleration of his work as also for

idling of his plant and machinery which is an infirmity. This finding

having been endorsed by the learned Single Judge is a further illegality.

6 His submission qua claim No. 1 and claim No. 2-A which have

been awarded as extra payments because of variations in the work are

against the express provisions of the contract; Clause 52 of the GCC

(General Conditions of Contract) read along with amendment have been

interpreted incorrectly. There were admittedly two threshold limits; the

respondent had crossed the first threshold limit of 25% but the second

threshold limit of 5% had not been reached by him which fact has been

ignored by the Arbitral Tribunal by wrongly interpreting clause 52.

There was no material to justify claim No. 2-A as well.

7 These submissions have been countered. Submissions being that it

is a reasoned Award and calls for no interference.

8 We shall first deal with the amounts awarded under claim No. 4

and claim No. 5 and to answer this argument, the statement of claim as

set up by the claimant before the Arbitrator is relevant. Under claim No.

4, the claimant has claimed an amount of Rs.12,18,60,452 as additional

overhead expenses incurred by the claimant for acceleration of work.

Under claim No. 5, the claimant has made a claim of Rs.9,17,88,600/-

for payment due on account of idling of plant and machinery. While

dealing with these claims, the Arbitral Tribunal has arrived at a finding

(not challenged) that the extension of time granted by the appellant of

five months was primarily because of the delay which was attributable

to the appellant. It is in this background that the aforenoted two claims

have to be viewed. The claimant under claim No. 4 has submitted that a

hindrance free site was not handed over in time by the appellant and the

completion of work could finally be achieved by the claimant by

working between 16-20 hours, paying heavy overtime wages and

incentives. Because of this piecemeal handing over of site, payment for

unforeseen costs had to be incurred by the claimant in order to finalize

his work in time. These overheads due to this delay had been

communicated by the respondent to the appellant vide letter dated

16.11.1999. Admittedly the Engineer vide his letter dated 11.12.2004

had recommended a payment of Rs.117.14 lacs to the respondent based

on the contention that the overheads are due in respect of the extended

period only. The claimant was aggrieved by this amount returned by the

Engineer and he had filed his claim before the Arbitral Tribunal. His

submission was that the Engineer had not taken into account the claim

made by the claimant for acceleration of work. Accordingly a sum of

Rs.12,18,16,542/- had been claimed by the claimant under claim No. 4.

Under claim No. 5, the claimant had claimed an amount of

Rs.9,17,88,600/- on account of idling of plant and machinery. His

submission in his claim petition was that he was fully prepared to

execute and finish the whole of the work within the stipulated period of

36 months and the claimant had mobilized and deployed sufficient

resources including machinery and manpower. However, because of

delay caused by the appellant and due to no fault of the claimant, the

machinery which had been deployed by the claimant could not be used

but the same continued to be deployed at the site for the substantial

completion of work. Initially his machinery idled for a considerable

period of time because of these delays and hindrance. The work did not

progress as had been planned; it got prolonged and the same was

completed only in the extended period of time i.e. by September, 2002.

His submission being that had the claimant been allowed to work

without any delay and hindrance, there was no need to keep the

machinery and equipment in this prolonged period. This prolongation

occurred on account of the various delays and hindrances on the part of

the appellant.

9 The Arbitral Tribunal while dealing with claim No. 4 has noted

that the Engineer of the appellant has himself accepted the fact that there

was a five months overstay and the claimant was entitled for a

compensation which had been worked out at Rs.117.14 lacs. The

Arbitral Tribunal had, however, reduced this amount from Rs.117.14 to

Rs.1,04,29,000/-. He had noted that overheads to which the respondent

was entitled was the reduced figure of Rs.104.29 lacs. This sum had

been awarded for the prolongation of the work which was due to the

fault of the appellant and for which the claimant had suffered a loss.

This amount as rightly pointed out by the learned counsel for the

respondent was not for the acceleration of work. Under claim No. 5, the

amount claimed by the claimant was Rs.9,17,88,600/- but the amount

awarded by the Arbitral Tribunal was Rs.1,33,12,303/-. The Arbitral

Tribunal had noted that the claimant could not complete his work as per

the approved programme and he could not mobilize the machines as

planned; part of his equipment was hired and only part was owned by

him. The claimant had in fact made a claim for damages for idling of

machinery for two periods; i.e. during the original contract period which

was between May, 1999 to actual deployment. In the second part, the

claimant had made a claim for idling of machinery from May, 2002 to

September, 2002 i.e. during the extended period of five months. The

Arbitral Tribunal did not award any amount for idling/non-hindrance of

machinery during the original period of contract noting that the claimant

was the best Judge for the deployment of machinery and was solely

responsible for its effective utilization. However, for the extended

period of five months i.e. from May, 2002 to September, 2002 since

there was ample evidence to show that the claimant had to overstay at

the site for doing the balance work, he was entitled to appropriate

compensation.

10 The learned Single Judge while dealing with these claims rightly

thought it fit not to interfere with them. Apart from the fact that there

was evidence to show that during the extended period of five months,

the claimant had to overstay at the site along with machinery, for which

he had to pay hire charges to complete the balance work; the approach

adopted by the Tribunal for calculation of the said amount (detailed as

Annexure 2 with the impugned Award) also did not call for any

interference. The reasoning given by the Arbitral Tribunal was correctly

endorsed by the learned Single Judge. Under claim No. 4, the amount

was not awarded for the acceleration of work; it was additional overhead

expenses borne by the claimant for prolongation of the work. Under

claim No. 5, the amount was awarded as compensation during the

extended period of contract as admittedly the respondent had to overstay

at the site and part of the machinery being on hire and not all of it owned

by the respondent, there was a prolonged deployment of machinery. The

ownership cost method for calculation under this head which was a

detailed calculation (appended as Annexure 3 to the Award) had been

gone into and rightly did not call for any interference by the learned

Single Judge or even by this Court. There was no conflict in the grant of

respective amounts under claim No. 4 and claim No. 5.

11 With regard to claim No. 1, the Arbitral Tribunal had considered

clauses 52.1 & 52.2 of the contract. To better appreciate this

controversy, clauses 52.1 and 52.2 are reproduced hereinbelow:-

"52.1 Valuation of Variations

All variations referred to in Clause 51 and any additions to the Contract Price which are required to be determined in accordance with Clause 52 (for the purpose of this Clause referred to as „varied work‟), shall be valued at the rates and prices set out in the Contract does not contain any rates as prices applicable to the varied work, the rates and prices in the Contract shall be used as the basis for valuation so far as may be reasonable, falling which after due consultation by the Engineer with the Employer and the Contract, suitable rates or prices shall be agreed upon between the Engineer and the Contract. In the event of disagreement, the Engineer shall fix such rates or prices as are, in his opinion appropriate and shall notify the Contractor accordingly, with a copy to the Employer. Until such time as rates or prices are agreed or fixed, the Engineer shall determine provisional rates or prices to enable on account payments to be included in certificates issued in accordance with Clause 60.

52.2 Power of Engineer to Fix Rates

Provided that if the nature or amount of any varied work relative to the nature or amount of the whole of the works or to any part thereof, is such that in the opinion of the Engineer, the rate or price contained in the Contract for any item of the works is, by reason of such varied work, rendered inappropriate or inapplicable then after due consultation by the Engineer with the Employer and the Contractor, a suitable rate or price shall be agreed upon between the Engineer and the Contractor. In the event of disagreement, the Engineer shall fix such other rate or price as is, in his opinion, appropriate and shall notify the Contractor accordingly, with a copy to the Employer. Until such time as rates or prices are agreed or fixed, the Engineer shall determine provisional rates or prices to enable on account payment to be included in certificates issued in accordance with Clause 60.

The following has been added here by way of SCC.

"Provided that no change in the unit rates or prices for any item considered for items included in the Bill of quantities, unless such items individually account for an amount of more than 5 (five) percent of the Contract Price named in the Letter Acceptance, and the actual quantity of work performed under the item exceeds or falls short of the original billed quantity by more than 25 percent."

12 The proviso to clause 52.2 of the contract was added by way of an

amendment. The question which had to be answered by the Arbitral

Tribunal was whether the claimant was entitled to a variation of the rates

and what would be the appropriate method to deal with the fixation of

new rates. The submission of the learned counsel for the appellant that

this proviso under clause 52.2 has been given a go-bye has been

answered by the Arbitral Tribunal. It was noted that this proviso had

been inserted by an amendment and did not find place in the original

GCC of FIDIC. The basic purpose of this proviso was to guard against

difficulties in contract administration arising out of minor variations in

the BOQ item of work. However in the instant case, the situation was

abnormal in as much as increase in the quantity of work was of the order

of 196% and its value (at existing BOQ rates) was 14.82% of the

contract price. The average lead for the varied work would be about

three kilometers. The frequent changes made in the profile by the

appellant had rendered the planned working by the respondent to have

become impossible; he was forced to work in a restricted width of 1-2

meters on both sides. Since the additional work was less than the

eligibility threshold limit of 5%, the enhanced rate was not allowed.

Although there was no alteration in the nature of the work yet the

quantum of variations was material and required a detailed examination;

it was 20% or more of the original contract price. The detailed

calculation was worked out by the Arbitral Tribunal to arrive at the

figure under claim No. 1 and this was after due consideration of clause

52.2 read along with its proviso. The view taken by the Tribunal which

was endorsed by the learned Single Judge being a reasonable view

rightly calls for no interference.

13 Under Claim No.2 the Arbitral Tribunal had noted that there was

no justification for fixation of new rates for the ROB work particularly

since the variation order dated 07.12.2000 regarding construction of the

ROB was issued by the appellant and agreed to; there being no change

of quantities; there was no justification of new rates. However, costs

were quantified taking into account the additional concrete quantities

executed over the BOQ quantities and the percentage increase. The

Arbitral Tribunal arrived at the aforenoted amount by a reasoned

calculation. It was based on an analysis of the figure.

14 Thus although the amounts claimed under the two heads i.e. claim

No. 1 and claim No. 2-A was much higher, yet much lower figures were

awarded which in terms of the tabulated chart on the basis of which the

aforenoted figures were arrived at, call for no interference. We are in

full agreement with the approach of the learned Single Judge.

15 This Court is not an appellate body hearing an appeal against the

fact findings arrived at by the Arbitral Tribunal; the scope of objections

under Section 34 of the said Act is limited; in appeal, the ambit of the

arguments would be confined to what has been answered in the

impugned judgment. It was an expert body of three members of the

Arbitral Tribunal who had dealt with the rival claims of the parties; the

learned Single Judge has also discussed each submission in detail. On

no count, does the impugned order call for any interference.

16 Appeal is without any merit. Dismissed leaving the parties to bear

their own costs.

17 The balance amount lying in the Court is consequently directed to

be released by the Registry to the respondent and the security furnished

by the respondent be discharged.

INDERMEET KAUR, J

SANJAY KISHAN KAUL, J FEBRUARY 13, 2013 A

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter