Citation : 2012 Latest Caselaw 5685 Del
Judgement Date : 20 September, 2012
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS) No.305/1999
% 20th September, 2012
KAMAL CONSTRUCTION CO. ...... Plaintiff
Through: Mr. Raman Kapur, Sr. Adv.
with Mr. Ankur Gosain, Mr.
R.P.Singh and Mr. Aviral
Tiwari, Advocates.
VERSUS
DELHI DEVELOPMENT AUTHORITY & ANR. .... Defendants
Through: Mr. Bankey Bihari Sharma,
Advocate for DDA.
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
To be referred to the Reporter or not?
VALMIKI J. MEHTA, J (ORAL)
1.
The subject suit has been filed by the plaintiff/contractor
claiming a principal amount of ` 18,77,866 plus interest of `8,22,658/-
totalling to ` 26,90,524/-, under different heads with respect to work done
by it, for the defendant no.1/DDA. The work done by the plaintiff for the
defendant no.1 was construction of 193 SFS House at Gazipur, SH:
Construction of 101 SFS Houses on site No.2 (69 Category II and 32
Category III) including Shops Int. W/S S/I & Internal Development. The
agreement entered into between the parties in this regard is numbered as
14-EE/ED-8/DDA/1993-94.
2. The plaintiff claims that the entire work was completed to
the satisfaction of the defendants on 2.7.1996 as per the completion
certificate recorded by the defendants. Defendant no.2 is the Executive
Engineer of defendant no.1/DDA. The plaintiff has further pleaded in the
plaint that in the present case, the defendant no.1 as per practice was
preparing the running final bills and maintaining all measurement books
and records. The break-up of the principal amount of ` 18,77,866/- is
given in para 16 of the plaint, and the same reads as under:-
a) Towards final bill (details enclosed Rs.9,09,332.00 as Annexure A to the plaint)
b) Towards balance amount payable Rs.3,22,583.00 under clause 10CC of the Agreement (details of calculation under clause 10CC enclosed as Annexure B to plaint)
c) Towards withheld amount from Rs.1,50,951.00 various running bills
d) Towards balance security deposit Rs. 30,000.00
e) Towards watch and ward for the Rs.4,65,000.00 period 1.7.96 to 31.4.99
Total Rs.18,77,866.00
3. The defendant no.1 has contested the claim of the plaintiff.
So far as claim under para 16(a) is concerned, the defendant no.1
contends that the amount claimed under this head towards the balance
payment for the work done is not correct as per the measurements
recorded of the work done, and is a wrongly inflated figure. The claim of
Clause 10 CC under para 16(b) is also denied by stating that whatever
amount was payable for escalation under Clause 10 CC has been paid. So
far as amount of `1,50,951/- in para 16(c) of the plaint is concerned, the
defendant no.1 states that the amount withheld is actually only ` 75,000/-
and which has been withheld because the plaintiff was pointed out the
defects and pending works in the completion certificate issued, but which
defects were not rectified by the plaintiff nor were the pending works
completed. Similar is the defence with respect to the claim of ` 30,000/-
under para 16(d) which pertains to the balance security deposit. So far as
the claim of watch and ward under para 16(e), the defendant no.1 states
that the charges towards watch and ward cannot be paid inasmuch as till
the work is completed by the plaintiff/contractor by remedying the
defects to be rectified and completing the pending works, it is the duty of
the plaintiff to employ the watch and ward.
4. Following issues were framed in this suit on 29.10.2001
which read as under:-
(1) Whether the plaintiff firm is a duly registered partnership
firm?OPP
(2) Whether defendant no.2 is a proper and necessary party and should not be dropped from the array of defendants?OPP
(3) Whether the plaint has been signed and verified by an authorised and competent person? OPP
(4) Whether the plaintiff has not executed its part of contractual obligations as contemplated in the agreement and if not, its effect?OPD
(5) Whether there are any defects and deficiencies in the work done by the plaintiff?OPD
(6) Whether the completion certificate issued by defendant to the plaintiff was provisional completion certification?OPD
(7) Whether the plaintiff is entitled to the amount of final bill as claimed? OPP
(8) Whether the plaintiff is entitled to amount under Clause 10CC as claimed? OPP
(9) Whether the plaintiff is entitled to the withheld amount as claimed?OPP
(10) Whether the plaintiff is entitled to refund of security deposit?
OPP
(11) Whether the plaintiff is entitled to amounts towards watch and ward as claimed?OPP
(12) Whether the plaintiff is entitled to interest, if so, at what rate on which amount and for what period?
(13) Relief."
5. So far as the issue no.1 is concerned, plaintiff has proved the
certificate of the Registrar of Firms as Ex.P-2 in his affidavit by way of
evidence and which shows not only the plaintiff firm being registered, but
also that Sh. Kamal Bassi who has instituted the suit, is a partner in the
plaintiff firm. This issue is therefore decided in favour of the plaintiff
and against the defendant no.1. Issue no.3 is also held in favour of the
plaintiff and against the defendant no.1 as the plaint has been signed by
Sh. Kamal Bassi who is shown to be the partner of the plaintiff firm.
Accordingly, issue nos. 1 and 3 are decided in favour of the plaintiff and
against defendant no.1.
Issue no.2
6. Issue no.2 is not pressed on behalf of the plaintiff as the
defendant no.2 is only an Executive Engineer of the defendant no.1 who
has signed the contract.
Issue nos. 4 to 11.
7. These issues are connected and can be decided together.
These are issues basically with respect to the claim of the plaintiff for the
work done and the defence of the defendant no.1 that no amount is
payable to the plaintiff.
8. I have already reproduced para 16 of the plaint above. This
para 16 of the plaint contains the total amount of claim of the plaintiff of
` 18,77,866.00 under five heads (a) to (e). Let me separately take up
each head of para 16 of the plaint.
(i) The first head is the claim of the plaintiff towards the
balance payment due for the work done. For this purpose, plaintiff has
relied upon the legal notice dated 20.6.1998 (Ex.P-2) sent to the
defendant no.1. This document is also marked as Ex.P-6 in the affidavit
by way of evidence of the plaintiff. This notice gives the total work done
of the value of ` 2,34,29,340.42 and amount already paid being
` 2,25,20,008.41, leaving the balance of ` 9,09,332.01, the figure as
stated in para 16(a). Learned senior counsel for the plaintiff also relies
upon certain portions of the cross-examination of the witness of the
defendant Sh. L.C.Dhingra (DW-1) to argue that the plaintiff has proved
the work done in terms of the legal notice dated 20.6.1998 (Ex.P-2) in
view of such admissions. Learned senior counsel for the plaintiff has
drawn the attention of the Court to the following cross-examination of
Mr. L.C.Dhingra (DW-1) on 14.12.2006 wherein Mr. L.C.Dhingra has
stated as under:-
"I have checked up the entire available records with respect to the present suit made available to me by DDA. From the records, I could not find any amount spent by DDA in carrying out work at the risk and cost of the plaintiff.
Q: Has DDA done any work on the flats constructed by the plaintiff or spent any amount towards the same before the flats were handed over to the allottees?
Ans. I cannot say.
Q. As per record seen by you, made available by DDA, is there any entry with regard to the above or can you produce the records to show that any amount was spent by DDA.
Ans. There is no such entry in the record seen by me.
Q. I put it to you that entire work in completing the flats upto the stage of handing over the flats to the allottees including the finishing work mentioned in the completion certificate was done by plaintiff.
Ans. I cannot say.
Q. As per the records available with you is there any entry for work being done by any one else except the plaintiff.
Ans. There is no such entry."
It is accordingly argued on behalf of the plaintiff that this
Court should hold that there is balance payment due of `9,09,332/-.
(ii) The counsel appearing for defendant no.1 has countered the
submissions on behalf of the plaintiff by referring to the letter dated
16.12.1998, Ex.LCDW1/2, copy of which was endorsed to the plaintiff,
to argue that the plaintiff was duly informed by this letter that the claim
of ` 9,09,332/- is on the basis of presumed quantities of fittings/fixtures
and which is not proportionate to the number of existing flats and that the
plaintiff can depute a person to check the figures/measurements as
recorded in the measurement books. This letter also talks of the fact that
there are various pending works/defects to be rectified and as duly
informed to the plaintiff. Learned counsel for defendant no.1 also argues
that general answers given in the cross-examination of witness will not
help the plaintiff to discharge the affirmative onus of proof that in fact
the balance amount of ` 9,09,332/- is due to the plaintiff.
(iii) In my opinion, the plaintiff, if it wanted to prove that the
total value of work done by it was ` 2,34,29,340.42, and as so stated in
the legal notice dated 20.6.1998 (Ex.P-2), then nothing was easier for the
plaintiff than to prove the same and which would have been done by
summoning the measurement books with respect to the work done, and
which admittedly were with the defendant no.1. The plaintiff however,
failed to summon these measurement books or file any other proof with
respect to the total value of the work done of `2,34,29,340.42, except the
sending of the legal notice dated 20.6.1998 (Ex.P-2) with which the
plaintiff is said to have attached the final bill. In my opinion, a final bill
can contain any figure(s) or any item(s), however, containing of
figures/items in a notice cannot mean that such work was in fact carried
out by the contractor at site. The only way to prove the work done is
through the recording of measurements in the measurement books and
the plaintiff has failed to rely on/prove these measurement books. Of
course, the plaintiff could also have led other evidence in case there was
a dispute as to recoding of measurements in the measurement books that
in fact the amount/quantity/type of the work done is as stated by the
plaintiff, however, no other evidence has been led on behalf of the
plaintiff except a self serving statement. A self serving statement with
respect to the huge monetary claims cannot be accepted by Courts as
discharge of onus of proof once the same is contested and disputed on
behalf of the defendant. I may state that the defendant no.1 in fact, has in
its letter Ex.LCDW1/2 dated 16.12.1998 stated to the appropriate
authority as also to the plaintiff to whom this letter was marked, that if
there is any dispute with respect to the measurements as recorded in the
measurement book, the same can be jointly reviewed on the plaintiff
deputing his person for the purpose. I however find nothing on record
that pursuant to this letter dated 16.12.1998 the plaintiff ever asked for
review of the measurements contained in the measurement books. This
could be including for the reason that the plaintiff may have thought that
measurement books may not support the case of the plaintiff with respect
to the total value of the work done and the measurements alleged by him,
and therefore, the plaintiff seems not to have summoned this
measurement book which admittedly is lying with the defendant no.1.
Accordingly, I hold that the plaintiff has failed to discharge of onus of
proof to claim that the total value of the work done, under the subject
contract was that ` 2,34,29,340.42 of which payment of ` 2,25,20.008.41
was made and thus there was balance amount due of ` 9,09,332/- to it.
This part of the claim is therefore not substantiated by the plaintiff and
hence rejected.
9. The next item of claim is claim of balance towards
escalation under Clause 10CC of ` 3,22,583/-. Learned senior counsel
for the plaintiff states that this claim is actually and only a percentage
calculation over the balance amount of ` 9,09,332.00. Once I have held
that the plaintiff has failed to prove his entitlement to ` 9,09,332/-, and
since this claim of Clause 10CC is only consequential to the claim of `
9.09,332.00 as per the plaintiff, I therefore, hold that this claim of
`3,22,583/- also does not stand proved inasmuch as the claim of `
9,09,332/- has been rejected. On this aspect I must note once again, the
specific stand of the defendant no.1 in LCDW1/2 dated 16.12.1998
wherein the defendant no.1 has taken the categorical stand that all
existing valid claims under Clause 10CC for escalation have already been
paid. The defendant no.1 has also further taken up a fair stand that if
there would be any other amount payable under Clause 10CC after
completion of the balance work and rectification work, the same can be
paid to the plaintiff/contractor, and the correct position will emerge only
after finalization of the bill, but as already stated above, that the plaintiff
in spite of receipt of the letter dated 16.12.1998 has not shown anything
on record that it ever had asked for review of the measurements in the
measurement books.
10(i). The third claim is the claim towards the amounts withheld
under various running bills of ` 1,50,951/-. In this regard, the defendant
has admitted an amount only of ` 75,000/- as per the written statement.
To substantiate its contention the plaintiff has drawn the attention of this
Court to the following portion of the cross examination of the DW-1 Sh.
L.C.Dhingra reading as under:-
"Q. I put it to you that DDA withheld Rs.20,000/-
from 4th R.A. Bill vide voucher No.50 of May 1994, Rs.20,000/- from 6th. R.A.Bill, Rs. 15000 from 10th R.A.Bill vide voucher No.51 of 10th May 1995, Rs.20,000 from 12th R.A.Bill vide voucher No. 79 of 25.11.1995 and Rs.75,951 vide voucher No.16 dated 7.11.1996 in all total amount withheld coming to Rs.1,50,951/-, which amount has still not been released by DDA to the plaintiff.
Ans. Amount can be released after checking the record if the plaintiff reports the office and accepts the measurement and the final bill."
(ii) In response, counsel for defendant no.1 has drawn the
attention of this Court to the following admission made in the cross-
examination of PW-1 Sh. Kamal Bassi.
" I do not remember as to how many running bills. I have given to the department. However, I can point out
the same only after I see the records maintained by me. I have not brought the said record today. I do not remember when the last running bill was submitted and paid."
(iii) In my opinion, not too much will turn on the fact whether
the withholding of the amount by the defendant is only of ` 75,000/- or `
1,50,951/- as per the plaintiff inasmuch as, the amount which has been
retained by the defendant no.1 is with respect to deficiencies/defects and
pending work and plaintiff has failed to prove that it has rectified the
defects or done the balance works. In the completion certificate
Ex.LCDW1/1/Ex.P-4, the defendant no.1 has specifically noted that the
plaintiff was to rectify the following defects/deficiency and do the stated
pending works.
:::::::::::
"This is however subjected to measurements being recorded and quality being checked by the competent authority and also rectification of defects already pointed out to the Contractor from time to time of which are given below.
1. Rectification of plaster and grit wash where ever required.
2. Final grinding of mosaic surface2/c flooring.
3. Fixing of panes glass and window and skirting etc fittings 2/c replacement of broken glass panes etc.
4. Fixing of bran and CP bran and other sanitary fittings 2/c bib cock, pillar taps, water tower rails, shower ball cock and looking mirror.
5. Replacement and damages of aluminium fittings. Such as tower bolts, pull bolts etc and replacement of wraped, damages defective door shutters with fittings etc.
6. Attending to seepage/leakage and testing of line if any & disinfecting of water line and making connection with 150 mm. Dia CI L.A pipe
7. Replacement/welding of grills glazed windows and frames etc. wherever left out and damages.
8. Replacement of broken damages pipe and fittings C.I.& SCI pipe)
9. Final coat/more coat of paints on steel/wood work and G.I , SCI and AC pipes and final coat of white wash, sheeem etc. on walls.
10.Easing of doors and windows shutters etc.
11.Cleaning of doors and windows of glass panes done wherever.
12.Defects if observed during maintenance in road, parking, cic paths, s.w.Drain, Sewerage and water supply line etc.
13.Providing of necessary fittings in PVC tanks.
14.Replacement of broken water meter boxes wherever required.
15.Fixing of C.I.Covers for house manholes and gully traps to be provided.
16.Replacement of broken kota stone and glazed tiles grinding and polishing with proper finishing of joints and nose wherever required.
17.Leakage through joints of SCI stacts.
18.At places cover on sluice value, fire hydrants chamb ers are damages if any this may be got repaired or replaced.
19.Sluice value and fire hydrants being rusted may be painted with anti-corrosive paint.
20.Seepage to WC and bath rooms, wherever noticed to be attended.
21.Replacement/rectification of damages and defective wire making of kitchen, door shulders and kitchen windows wherever noticed.
22.Grit wash and plaint plaster junction to be repaired wherever noticed defective.
23.Cleaning of spouts and proper fixing to be done wherever required.
24.Providing and fixing of rawl plugs in doors frame and steel windows sections wherever required.
25.Rectification of defects as pointed.
Out in defect register from time to time.
26.Premixing is to be done in parking area.
27.Internal s.w.drain is to be connected with existing peripheral s.w. drain for proper draining out water. Besides these various defects pointed out by chief Engineer (East Zone), Chief Engineer (Quality Control , Superintending Engineer,Circle-8, C.T.E and this office may also be attended and rectified and necessary repair/recoveries may be initiated where defects can not be rectified if otherwise structurally safe.
These defects be rectified by the Contractor or by the department at his risk and cost, action will be taken in term & conditions of the contract."
11(i) During the course of arguments I put a query to the learned
senior counsel for the plaintiff as to how the aforesaid long list of
defects/deficiencies and pending works were done by the plaintiff, and to
which, the response on behalf of the plaintiff is that since in the cross-
examination of the witness of the defendant no.1, it is admitted that the
defendant no.1 has not spent any amount towards any work till these flats
were handed over to the allottees therefore it should be held that the
pending works have been done.
(ii) I cannot agree. Once in a completion certificate
(Ex.LCDW1/1) a huge list of defects/deficiencies and pending works
have been pointed out, surely, if the plaintiff would have carried out such
works, he would not have left it to the oral good faith and would have
surely prepared some documentary evidence to ensure record of the fact
that the deficiencies/defects have been removed and the pending works
have been done. However it admitted that on the record of this Court,
nothing has been filed after drawing up of the completion certificate
Ex.LCDW1/1 that there exists documentary evidence showing removal
by the plaintiff of all the defects/deficiency or doing of the pending
works.
(iii) Learned senior counsel for the plaintiff has argued that the
contractor always does such work because it is under pressure of the
DDA and therefore, it should be held that the deficiencies were removed
and pending works done. I cannot agree to this argument because if I
agree to this argument it would mean that merely on self serving
statement a huge list of pending works will be deemed to be done and
defects removed/deficiencies rectified, and therefore, I cannot accede to
the argument. In civil law, onus of proof has to be reasonably
discharged. As already stated above, a mere oral statement made in a
deposition, once it is disputed cannot amount to discharge of onus of
proof.
(iv) I therefore, hold that the plaintiff is not entitled to the claim
of ` 1,50,951/- under para 16(c) of the plaint inasmuch as, the withheld
amount cannot be paid till the plaintiff has completed the balance works
and removed the defects/deficiencies.
12. The next head of claim as per para 16(d) is the claim
towards security deposit of ` 30,000/-. The findings and conclusions
given with respect to para 16(c) of the plaint, and given in paras 10 and
11 above, will also apply with respect to this claim, and which is
accordingly rejected.
13(i) This leaves me with the final claim towards watch and ward
for the period 1.7.1996 to 31.4.1999 of ` 4,65,000/- i.e around two years
and 10 months. Learned senior counsel for the plaintiff has invited the
attention of this Court to two documents to show that in fact the
defendant no.1 itself admits that watch and ward was kept by the
plaintiff, and therefore, the claim of watch and ward has to be allowed in
terms of the general circular of the defendant no.1 dated 12.5.1997
Ex.DW1/P2 which provides that contractor should be paid a sum of
`6,600/- towards payment of two chowkidars.
(ii) The two documents relied upon by the plaintiff of the
defendant no.1 are first the letter dated 11.5.1999,Ex.P-3(exhibited as P-
14 in the affidavit by way of evidence of the plaintiff) and second the
letter dated 15.4.1998, Ex.P-5. Portion of the first document i.e letter
dated 11.5.1999 relied upon by the plaintiff reads as under:-
"xxxx xxxx xxxx xxxx It would be pertinent to mention here that this office shall not be responsible for any theft, loss/damages occurred at site as watch and ward is being done by your goodself. If watch and ward is terminated, same shall be at your risk
and const and this office shall not be responsible for any damage/theft/loss."
So far as the letter dated 15.4.1998 is concerned, the
following portion is relied upon:-
"You are therefore requested to depute adequate numbers of security guards/Chowkidars for the effective watch and ward of these houses round the clock. Please note it is obligatory on your part to provide/handover these flats with complete fittings and fixtures to the department until all the flats are physically handed over to the allottees."
(iii) In my opinion, before the plaintiff succeeds in relying upon
the circular for claiming a sum of ` 6,600/- per month as watch and ward
charges, two things are necessary. Firstly, it must be shown that in fact
there was some watch and ward i.e there was employment of some
chowkidars/guards. No doubt, the circular of the defendant no.1 will
help to show that what should be the quantification of the watch and
ward charges per month, but the pre-condition for application of the
circular would be existence of chowkidars/guards. Admittedly, on the
record of this Court there is absolutely nothing to show that there was in
fact employed by the plaintiff chowkidars/guards for the relevant period.
The portions of the letters dated 11.5.1999 and 15.4.1998 of the
defendant no.1 to the plaintiff only ask the plaintiff to keep the watch and
ward, but the same do not prove that in fact, watch and ward was kept by
the plaintiff pursuant to those letters.
(iv) The second aspect is that the entitlement of the plaintiff to
the claim of watch and ward charges would be if the work was
completely done and thereafter though the defendant no.1 was liable to
take possession, the defendant no.1 did not take possession. If, however,
the work is not complete, i.e defects/deficiencies are not removed and
pending works are not done, and the list of which is found in
Ex.LCDW1/1 (and which is reproduced above), the plaintiff cannot say
that it is entitled to claim of watch and ward charges till the work is done
and completed. The plaintiff has to remain in possession of the site, and
has to complete the works, and thus for the period for which works under
the contract had to be done, the watch and wards charges cannot be
claimed unless the plaintiff had set up a specific case that possession was
handed over to the defendant No.1 in spite of the fact that works were
pending, and which is not so.
14(i) Learned senior counsel for the plaintiff relied upon two
judgments of two learned single judges of this Court in the cases of
K.R.Builders Pvt. Ltd. Vs. Delhi Development Authority & Anr.
144(2007) DLT 741 and A.S.Sachdeva and sons (P) Ltd. Vs. D.D.A. and
Anr. 164(2009) DLT 162 in support of the claim of watch and ward
charges.
(ii) With respect to the judgment in the case of K.R.Builders
Pvt. Ltd., learned senior counsel for the plaintiff has relied upon paras
105 to 109. In my opinion, the judgment in the case of K.R.Builders Pvt.
Ltd. as cited on behalf of the plaintiff cannot apply inasmuch as, paras
referred to on behalf of the plaintiff show that all the defects were
removed by the contractor, and it is for the period thereafter, that watch
and ward charges were claimed. Para 108 shows the conclusion arrived at
in the said judgment which says that the testimony in that case showed
that the defects were removed during the maintenance periods and watch
and ward charges were for the period thereafter. In my opinion, therefore,
the judgment in the case K.R.Builders Pvt. Ltd. (supra) does not support
the plaintiff.
(iii) So far as the judgment in the case of A.S.Sachdeva and sons
(P) Ltd.(supra), reliance is placed upon by the plaintiff on paras 21, 30
and 31 of the said judgment. Once again, in my opinion, this judgment
does not apply to the facts of the present case because in the cited case,
the letter extending time for completion was issued after the completion
certificate was prepared and the DDA was not able to establish that the
plaintiff did not carry out the defects as pointed out in the completion
certificate. Also para 30 of the said judgment shows finding in the said
case that evidence of the plaintiff showed that it did employ watch and
ward and which is not the position in the present case. It is in those
different facts that the Court in the cited case granted claim of watch and
ward charges. The facts of this case as stated above are different because
the plaintiff has failed to prove that any watch and ward was appointed,
or that the defects were removed. This judgment also therefore does not
help the plaintiff.
15. In view of the above, issue nos. 4 to 11 are decided in favour
of the defendant no.1 and against the plaintiff. Plaintiff is held disentitled
to the claims as stated in para 16 of the plaint. Suit is accordingly
dismissed for the claims in para 16 of the plaint.
Issue no.12
16. This issue is the claim of interest. Since the main claims
have been dismissed there does not arise any issue of grant of interest.
This issue is therefore decided against the plaintiff.
Relief:-
17. In view of the above discussion, suit of the plaintiff is
therefore dismissed, leaving the parties to bear their own costs. Decree
sheet be prepared.
VALMIKI J. MEHTA, J SEPTEMBER 20, 2012 ib
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!