Citation : 2012 Latest Caselaw 5575 Del
Judgement Date : 17 September, 2012
*IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 17th September, 2012
+ LPA No. 887/2011 & CM No.2270/2012 (for modification of order
dated 15th December, 2011).
CHIEF COMMERCIAL MANAGER & ORS ..... Appellants
Through: Mr. Joydeep Mazumdar with
Ms.Sainina Shek & MNr. Rohit Putta,
Advs.
versus
JUGNU JAYANT ..... Respondent
Through: Mr. Ashish Mohan, Adv.
CORAM :-
HON'BLE THE ACTING CHIEF JUSTICE
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
RAJIV SAHAI ENDLAW, J.
1. This intra court appeal impugns the order dated 15 th July, 2011 of
the learned Single Judge allowing WP(C) No. 4779/2011 preferred by the
respondent, by directing the appellant Railways to extend the lease of the
respondent for a period of two years from the date of expiry of the original
lease, in terms of Clause (E) of the Comprehensive Parcel Leasing Policy
and Clause 18 of the Contract of RSLR in Train No.2394 Ex NDLS to
PNBE. Notice of the appeal was issued, though no stay of operation of the
order of the learned Single Judge granted. This appeal was on 15 th
December, 2011 admitted for hearing. The counsels have been heard.
2. Pursuant to invitation of tenders for parcel space in the aforesaid
train, the respondent herein submitted his bid and was allotted the contract
of leasing of 4 tonnes RSLR space in the said train and a formal contract
dated 22nd July, 2008 was signed between the appellant Railways and the
respondent. As per the terms of the said contract, the lease was for a
period of three years w.e.f. 21st June, 2008 till 20th June, 2011. Clause 18
of the contract was as under:
"Extension of lease contract:
Extension of lease is permissible only in case of long term lease of 3 years wherein the same can be extended only once, by 2 more years at a lease rate of 25% more than the lumpsum leased freight rate subject to satisfactory performance by the leaseholder, without any penalty for overloading or violation of any provision of the contract."
3. The respondent vide his letter dated 10th February, 2011 sought
extension of the lease for a period of two years in terms of the aforesaid
Clause and offered to pay 25% more freight during the extended period of
two years. The appellant Railways however vide letter dated 15 th June,
2011 rejected the request of the respondent for extension. No reasons
whatsoever were given for rejection.
4. Aggrieved therefrom the respondent filed the writ petition from
which this appeal arises. It appears that the writ petition was allowed
without calling for any counter affidavit of the appellant, finding the
subject matter to be covered by the earlier judgment in Kishan Freight
Forwarders Vs. Union of India 181 (2011) DLT 547 and in other
connected batch of writ petitions, holding :
i. the writ remedy to be available notwithstanding the arbitration clause in the agreement;
ii. the Comprehensive Parcel Leasing Policy of the appellant Railways to be applicable to Parcel Vans as well as SLRs and the distinction sought to be drawn by the Railways to
justify adopting a different policy in respect of SLRs being inconsistent with the said policy ;
iii. that the policy applied throughout India and no exception is made to any particular zone;
iv. the said policy was issued in exercise of powers conferred on the Railway Board by Section 71 of the Railways Act, 1989 r/w Section 2(a) of the Railway Board Act, 1905 and notification of the Government of India, Ministry of Railways dated 23rd January, 1995 and all of which lend a statutory character to the policy which was binding on the railways;
v. that the Railways could not therefore adopt a different policy for leasing of spaces in SLRs and Parcel Vans and such a decision would on the face of it be arbitrary;
vi. that the Northern Zone could not choose to adopt a different policy for leases concerning parcel spaces on trains emanating from that Zone;
vii. that a standard form lease contract was drawn up and sent to every Zone;
viii. that the contracts subject matter of those petitions were also in the same standard form and uniformly contained an
extension Clause which granted a two-year extension with a 25% increase in the lease rate;
ix. that the rights and obligations of the parties flowed from the contracts and could not be arbitrarily repudiated by the Northern Railway without any change in policy of the Railway Board;
x. that even though the Railways had in the year 2010 brought out a new policy but had decided that the contracts signed under the 2006 policy, as the subject contract in those petitions as well as this LPA are, are to be governed by the policy in force at the time of execution thereof;
xi. that the Railways in the matter of contracts was required to satisfy the test of non-arbitrariness under Article 14 of the Constitution of India;
xii. the explanation of the Northern Railways of wanting to maximize revenues by departing from the policy overlooked the binding nature of the policy;
xiii. the Railways was indulging in a `pick and chose‟ policy while granting extension to some contractors, refusing it to others and granting extension to yet others on different conditions.
5. The respondent, in the writ petition itself admitted that penalty had
been imposed upon it once on account of overloading of parcels. The
appellant on the basis thereof contended that the case was not covered by
the judgment aforesaid, as the performance of the respondent was not
satisfactory. Per contra, the contention of the counsel for the respondent
was that the rejection letter dated 15th June, 2011 was not based on any
such violation by the respondent. The learned Single Judge held that the
administrative authorities are expected to give clear reasons for rejection
and the appellant Railways in the rejection letter dated 15 th June, 2011
having not given any such reasons could not before the Court justify the
rejection of the request for extension of contract, thereon. It was further
observed that in another case before the learned Single Judge i.e. WP(C)
No. 4781/2011 Sakshi Rail Parcel Services Vs. Union of India also
disposed of on 15th July, 2011 inspite of the complaints of overloading and
imposition of penalty, extension had been granted though only till the
finalization of fresh tenders. On the basis thereof it was opined that
overloading of parcels by the lease holder was not being viewed seriously
by the appellant Railways to deny extension of the lease period. It was
thus held that a singular act of overloading by the respondent could not
form the basis for denying the extension of the contract. Accordingly the
mandamus was issued.
6. The appellant pleads:
i. that the lease agreement admittedly was a terminable contract and thus could not be specifically enforced;
ii. that the policy though framed by the Railway Board was to be implemented and monitored by the Zonal Railways and thus the Northern Zone was entitled to take a policy decision and the Delhi Zone was entitled to take a decision as was taken in September, 2010 not to give extension of the SLR contracts to any of the contractors;
iii. that the contract aforesaid was essentially a commercial contract;
iv. that there is a fundamental difference between a SLR and Parcel Van and though the policy dated 28th March, 2006 covered both SLRs as well as Parcel Vans but vide subsequent circular dated 13th October, 2009 concessions
in penalty were provided only for Parcel Vans and not for SLRs;
v. that overloading in SLRs can lead even to derailment and hence loss of life and property; that while consignments are weighed by the Railway Authorities before loading in the Parcel Van, they are loaded in the SLRs on the basis of declaration by the contractors;
vi. that the revised policy dated 9th February, 2010 is materially different and has done away with the clause for extension of contracts for two years;
vii. that had opportunity been given to the appellant Railways to file counter affidavit, they would have brought on record the incidents of overloading committed by the respondent;
viii. that neither under the 2006 Policy nor under the contract, was the extension mandatory and was only permissible;
ix. that after February, 2011 extension had been refused to all leases without any discrimination;
x. that the whole purpose of granting a lease for a period of three years is frustrated if extension of two years is held to be mandatory.
7. Before we proceed with the matter, notice may be taken of the intra
court appeal preferred by the appellant Railways against the judgment
aforesaid (on the basis whereof the impugned judgment is structured) in
Kishan Freight Forwarders batch of writ petitions being
LPA.No.713/2011 titled Chief Commercial Manager Vs. Kishan Freight
Forwarders and other connected appeals. The same were disposed of by a
Division Bench of this Court vide order dated 1st September, 2011. It is
recorded in that order that there were no allegations against the contractors
in those cases of overloading or of any other kind of irregularities and a
consensus was arrived at between the Railways and the contractors to
extend the contracts. The Division Bench accordingly left the legal
question open for adjudication.
8. We had requisitioned the record of the appellant Railways relating to
the respondent. The same shows that upon receipt of request for extension
from the respondent, a working report highlighting irregularities including
incidences of overloading or under charging, was requisitioned. Though a
report dated 18th August, 2011 was submitted in pursuance thereto and
which cited four incidences of imposition of penalties on the respondent
and which were paid by the respondent but the same, as would be obvious,
is of a date after the rejection letter dated 15 th June, 2011. The record
shows the rejection to be based merely for the monitory reasons i.e. the
likelihood of new tender fetching more rate than would be payable under
the extended contract.
9. What we therefore find is that the position is not very different in
this case than from as prevailing in Kishan Freight Forwarders group of
cases where the appellant Railways before the Division Bench had agreed
to grant the extension.
10. Now that, of the extended period also, only about nine months are
remaining and even if we remand the case to the concerned authority of
appellant Railways for reconsideration of request of the respondent for
extension and even if the appellant Railways, on the basis of report dated
18th August, 2011 refuses such extension, this process and the process of
inviting fresh tenders itself may consume minimum 2-4 months. We in the
exercise of powers under Article 226, do not see any purpose in going into
the other questions. As far as the distinction carved out between the SLRs
and the Parcel Vans is concerned, the same also fades into insignificance
owing to the rejection of the extension being not based on the defaults of
the respondent. Though at one time it was observed that the matter needs
to be adjudicated owing to such questions arising repeatedly but in view of
the change in the policy, we do not feel the need to sit in appeal over the
judgment in Kishan Freight Forwarders group of writ petitions, the
contracts wherein the Railways had itself agreed to extend.
For the aforesaid reasons we dismiss this appeal. No costs.
RAJIV SAHAI ENDLAW, J
ACTING CHIEF JUSTICE th SEPTEMBER 17 , 2012 „M‟
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!