Friday, 24, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Raj Kishan & Company vs National Thermal Power ...
2012 Latest Caselaw 5442 Del

Citation : 2012 Latest Caselaw 5442 Del
Judgement Date : 12 September, 2012

Delhi High Court
M/S. Raj Kishan & Company vs National Thermal Power ... on 12 September, 2012
Author: Vipin Sanghi
*      IN THE HIGH COURT OF DELHI AT NEW DELHI


                     Judgment reserved on:      31.08.2012
%                    Judgment delivered on:      12.09.2012


+      O.M.P. No. 320/2010


       M/S. RAJ KISHAN & COMPANY                              ..... Petitioner
                                Through:   Mr. Chetan Sharma, Sr. Advocate
                                           with Mr. D. Moitra and Mr. Sanjay
                                           Bhaumik, Advocates.
                       versus


       NATIONAL THERMAL POWER CORPORATION..... Respondent
                                Through:   Mr. S. K. Taneja, Sr. Advocate with
                                           Mr. Puneet Taneja, Advocate.
       CORAM:
       HON'BLE MR. JUSTICE VIPIN SANGHI


                                   JUDGMENT

VIPIN SANGHI, J.

1. The present petition under Section 34 of the Arbitration and

Conciliation Act, 1996 (hereinafter referred to as the „Act‟), is directed

against the arbitral award dated 13.11.2009 and the order of modification

dated 22.02.2010 - passed by the Arbitral Tribunal comprising Hon‟ble Mr.

Justice P.K. Bahri (Retd.).

2. The brief facts, leading to the present petition and relevant for the

present purposes, are summarised as under:

2.1. Respondent herein awarded a contract for General Civil Work

Package (4 x 210 MW) at its NCPS (Project) Dadri District, Gautum

Budh Nagar, U.P. to the Petitioner herein. A formal contract was

executed between the parties on 21.03.1989.

2.2. It appears that the petitioner raised certain claims on the respondent

and demanded payments from the respondent vide letter dated

22.02.1999. On 09.08.1999 (vide R-46), the respondent disputed the

said claims. It was alleged that the petitioner had stopped the work

and did not restart the same despite notice. It was also stated that the

respondent had no alternative but to get the balance work executed at

the petitioner‟s risk and cost. It was specifically stated that "there is a

lot of owner issue materials outstanding with M/s RKC which is

required to be returned to NTPC. The detail of the outstanding owner

issue material based on the last RA Bills no.142 is accounted and

enclosed as Annex-I. It is a matter of record that no efforts have been

made to return balance owner issue material inspite of repeated

verbal and written requests". The respondent demanded the petitioner

to return the balance owner issue material. It was stated that the total

recoveries amounted to Rs.283 lacs approximately which includes

recoveries against unaccounted owner issue material. It was stated

that in case the amount of Rs.283 lacs is not paid within 15 days, the

respondent would be constrained to seek arbitration under clause 56 of

the GCC for recoveries. In Annexure III of this letter, the respondent

at serial No.5 claimed an amount of Rs.1,79,81,140 "against FOC

material". The respondent issued a communication dated 06.12.1999

(R-47) to the petitioner in response to the petitioner‟s letter dated

25.08.1999. The respondent in this communication, inter alia, stated:

"....With respect to the release of the payment due, it is pertinent to mention that the same has not been released in order to recover the outstanding advance arisen out of material reconciliation amounting to Rs. 180 lacs approx. For which detailed calculations have already been enclosed in terms of material accounting/reconciliation as per special condition of contract vide our letter dated 9.8.99." (emphasis supplied)

2.3. On 10.05.2000, the petitioner sent a communication to the Manager

(CCD) of the respondent stating that:

"...Disputes and differences arose between M/s. Raj Kishan & Co. And N.T.P.C as the Manager (P.H) N.T. P.C Vidyut Nagar has not made the payment even though notice was sent vide letter no.RKC/HO/SKG/99/2547 dated 22.2.99.

Subsequently, various correspondence have also been made which reconfirms/crystallize that dispute formed earlier could not be amicably settled but remain as a dispute, requiring adjudication, inspite of various efforts made by the parties to reconcile.

However at this stage it is very clear that dispute and difference remain as it is."

The petitioner requested for payment within 15 days failing which, the

petitioner stated that it would be free to approach a forum for sorting

out the dispute.

2.4. On 31.5.2000, the petitioner addressed a communication to Shri V.K.

Srivastava, Sole Arbitrator of the respondent stating that disputes and

differences had arisen between the parties as the Manager of the

respondent had not made payment even though notice was sent vide

letter dated 10.05.2000. The sole Arbitrator was called upon to

adjudicate the disputes thus formed. The disputes and differences

were shown in Annexure A to this communication. On 15.09.2000,

the petitioner sent another communication to the Chairman and

Managing Director of the respondent invoking the arbitration

agreement.

2.5. However, on the respondent‟s failure to appoint an arbitrator as per the

terms of the Contract, the Petitioner filed a petition under Section 11

of the Act before this Court. Vide order dated 25.11.2003, this Court

appointed the aforementioned arbitrator to adjudicate the disputes

between the parties.

2.6. The Arbitral Tribunal vide impugned Award dated 13.11.2009

allowed:

A. Claims of the Petitioner to the following extent:

                     Claim No.     Head                    Amount awarded

                                   Balance amount payable Rs. 17,96,281/-
                         1(a)      to the
                         and       Petitioner/claimant on
                        1(i)(i)    the basis of the
                                   measurements of the
                                   work executed by the
                                   Petitioner/claimant and
                                   duly entered by the
                                   Respondent in its
                                   measurement books.
                                   Balance payment of      Rs. 73,500/-
                        1(i)(ii)   structure steel of
                                   cladding structure
                                   Fitting and fixtures of Rs. 1,69,802/-
                         1(k)      teak wood frames





                                Quantities of Work          Rs. 1,54,28,696/-
                       2       executed beyond the
                               deviation limits in
                               various items of work
                               Escalation charges          Rs. 47,54,047/-

                               „Overhead losses            Rs. 60,04,386/-
                     7 and 9   suffered by the
                               Petitioner/claimant due
                               to under utilisation/
                               partial utilisation of
                               tools, plants, machinery,
                               staff and personnel- for
                               the prolongation of work
                               from the stipulated date
                               of completion‟ AND
                               „Loss of profitability/
                               loss of turnover for
                               prolongation of the
                               work‟
                               Extra expenditure           Rs. 10,50,000/-
                       10      incurred in use of the
                               difference in the
                               theoretical and actual
                               weight of steel
                               Amount of Bank              Rs. 12,00,000/-
                       11      Guarantee enchased by
                               the Respondent
                               Amount of the               Rs. 6,92,924/-
                       18      Construction material
                               belonging to the
                               Petitioner/claimant and
                               taken over by the
                               Respondent
                                                           Rs. 3,11,69,636/-
                                                  Total:

                                                  (emphasis supplied)





        B.      Counter Claim No. 1 of the Respondent- For recovery for

wastage and excess consumption of cement, reinforcement and

structural steel, which were supplied by the Respondent as free

issue material- to the extent of Rs. 1,56,33,435/-.

The Respondent was, thereby, directed to pay the difference amount,

being Rs. 1,55,36,201/- within three months, failing which the

Respondent would pay to the Petitioner interest at the rate of 12% p.a.

on the unpaid amount, from the date of the award till payment.

2.7. Both parties, thereafter, filed applications under Section 33 of the Act-

seeking corrections in the Award. The Award was corrected vide

impugned order dated 22.02.2010- to the extent that the awarded

amount mentioned under Claim No. 2 was stated to be a clerical

mistake in as much, as, Rs.1,47,49.458.70/- out of Rs.1,54,28,696/-,

admittedly, already stood paid by the Respondent to the Petitioner,

which was also taken note off in Para 79 of the Award. The awarded

amount under Claim No. 2 was, thus, held to be Rs.6,79,237.45/-

instead of Rs.1,54,28,696/-.

2.8. At this stage, I may take note of some of the disputes and differences

of which the petitioner sought reference to arbitration. Under Point

No.7, the petitioner sought a "sum of Rs. 75 lakhs being amount

withheld illegally". Under point No.12 (a) and 12 (b), the petitioner

raised the following disputes and differences:

"12.a A sum of Rs. 9 lacs being difference in theoretical and actual weight of steel for the work done up to 31.1.99.

12.b A declaration stating that payment of difference in theoretical and actual weight of steel will continue to accrue, if work is allowed to be done, after 31.1.99 till date of completion."

2.9. Being aggrieved by the Award and the order of modification, the

Petitioner has preferred the present petition.

3. The Petitioner herein has sought to challenge the Arbitral award to the

extent it has allowed Counter Claim No.1 of the Respondent.

Petitioner's Submissions

4. Learned Senior Counsel for the petitioner, Mr. Chetan Sharma,

submitted that the Counter claims of the Respondent could not have been

adjudicated upon as the same were barred by limitation. It is submitted that

the Respondent raised a demand towards material accounting/reconciliation

vide letter dated 06.12.1999. Therefore, the cause of action for the

respondent to initiate recovery proceedings arose on that date and, as such,

the Respondent should have filed its counter claims within 3 years from that

date either by filing a suit or commencing arbitral proceedings in terms of

Section 21 of the Act. Not having done so, the counter claims were barred by

limitation. The Counter claims, for the first time, came to be filed along with

the Statement of defence, on or about June 2004, which was beyond the

prescribed period of limitation. Reliance was placed upon the judgments of

the Supreme Court in State of Goa v. Praveen Enterprises, 2011 STPL

(Web) 561 SC; J.C. Budhiraja v. Chairman, Orissa Mining Corporation

Ltd. & Anr., (2008) 2 SCC 444; S. Rajan v. State of Kerala and Anr., AIR

1992 SC 1918; and the judgment of this Court in Smt. Biba Sethi v. Dyna

Securities Limited, 2009 (6) R.A.J. 454 (Del).

5. It was submitted that, even otherwise, the amount awarded under

Counter Claim No. 1 of the Respondent is in violation of Clause 8.3.1 and

more particularly 8.3.1 (e) of the Contract and, as such, is liable to be set

aside. It was submitted that as per the said clause the outstanding

unaccounted material shall not be more than 10% of the value of the security

deposit i.e. Rs 1,20,000/- (10% of Rs. 12,00,000/-) unless otherwise

permitted in writing by the Engineer In-charge. It was submitted that the

Engineer in-charge had not provided any such written permission.

6. It was further submitted that even going by the contractual rates and

the Respondent‟s documents, the counter claims of the Respondent cannot

go beyond Rs.22,52,370.60/-.

7. As regards the order of modification, it was submitted by the Learned

Senior Counsel that the awarded amount of Rs.1,54,28,696/- (under Claim

No. 2) was in addition to the amount of Rs.1,47,49.458.70/-. It was

submitted that the amount of Rs.1,47,49.458.70/- had been paid way back in

December, 1997 whereas the rate analysis, which is the basis of Claim No. 2,

had been prepared and finalised by the Respondent on 25.10.2001 and no

payment had been after that. Hence, the modification was wholly uncalled

for and unwarranted.

Respondent's Submissions

8. Learned Senior Counsel for the Respondent, Mr. S.K. Taneja, on the

other hand raised a preliminary objection to the maintainability of the

present petition- on the ground that the petitioner is an unregistered

partnership concern and as such is barred, by virtue of Section 69 of the

Partnership Act, 1932, to institute claims and prosecute the same before this

Court or any other forum including before the learned Arbitrator. Placing

reliance on Order XXX Rule 20 of the Code of Civil Procedure, 1908

(hereinafter referred to as the „CPC‟), it was further submitted that present

petition has also not been filed by a duly authorised and competent person.

The locus of the person executing the General Power of Attorney in favour

of the person who has filed the present petition was disputed by the

Respondent

9. Learned senior counsel submitted that limitation is a mixed question

of fact and law. Specific pleading with necessary particulars with regard to

the question of limitation should have been raised before the Arbitral

tribunal. Since such a plea was never raise by the Petitioner before the

tribunal, the Petitioner cannot raise the same before this Court for the first

time in these proceedings. Reliance was placed on the judgment of the

Bombay High Court in Bharat M. Nagori v. Satish Ashok Sabnis & Anr.,

2003 (4) R.A.J. 47 (Bom); Vimal G. Jain v. Vertex Financial Services Pvt.

Ltd., 2007 (4) Arb. LR 18 (Bombay) (DB) and judgment of the Supreme

Court in Balasaria Construction (P) Ltd. v. Hanuman Seva Trust & Ors.,

(2006) 5 SCC 658.

10. It was submitted that even under Order VII Rule 11, CPC, a suit

cannot be dismissed on the ground of limitation without proper pleadings,

framing of issues and taking of evidence. Reference in this regard was made

to the judgment of the Supreme Court in Ramesh B. Desai and Others v.

Bipin Vadilal Mehta and Others, (2006) 5 SCC 638. It was submitted that

this Court while exercising jurisdiction under Section 34 of the Act cannot

re-appreciate the facts and evidence. The Court does not sit in appeal to take

up the issues which were never argued or pleaded before the Arbitral

Tribunal.

11. Learned senior counsel submitted that the counter claims were not

time barred as per the law of limitation. The Petitioner having invoked the

arbitration clause under the contract, there was neither any contractual nor

any legal requirement for the Respondent to invoke arbitration clause again

for its counter claims arising under the same contract between the same

parties. It was therefore submitted that the question of non-invocation of the

arbitration agreement in compliance of Section 21 of the Act does not arise.

12. It was submitted by the Respondent that clause 8.3.1 (e) has no

application in the facts of the case and, therefore, has rightly not been relied

upon by the Arbitral tribunal. It was submitted that merely because as per

clause 8.3.1 (e) the unaccounted outstanding material cannot be beyond 10%

of the value of the security deposit given by the contractor, unless otherwise

permitted by the Engineer In-charge, it does not mean that the counter claim

of the Respondent for the recovery of wastage and excess consumption

cannot, in fact, be beyond 10%. It was submitted that the Petitioner has itself

not disputed the quantum of material issued and consumed and is now,

merely to evade the liability, relying upon a clause which even otherwise has

no application in the facts aforesaid. Such a plea was never set up by the

Petitioner before the Arbitral Tribunal and, therefore, cannot be raised before

this Court in these proceedings.

13. It was submitted that there was no basis for the Petitioner to submit

that the counter claim of the Respondent cannot go beyond

Rs.22,52,370.60/-. It was submitted that the Petitioner cannot be permitted to

so allege, at this stage, when he had not disputed the quantity of materials

issued, consumed, and wastage of materials issued by the respondent owner,

and the only issue raised was of benefit of overweight steel, which was also

accounted for. It was reiterated that the Petitioner cannot be permitted to set

up a new defence in the present proceedings which did not form part of the

pleadings before the Arbitrator.

14. It was submitted that by virtue of the modification order, the Arbitral

tribunal corrected a calculation error with respect to the payment of claim no.

2 and that the same was well within the powers of the Arbitrator under

Section 33 of the Act. It was denied that the Petitioner is entitled to

Rs.1,54,28,696.15/- in addition to the amount of Rs.1,47,49,458.70/-.

According to the Respondent, the same was merely an afterthought. It was

submitted that the entire claim allowed with respect to claim no. 2 was

Rs.1,54,28,696.15/-, which was the amount shown in the final bill (as the

recovery amount could have been worked out only then). After giving

adjustment of the payment made, till the second last running bill of

Rs.1,47,49,458.70/-, the petitioner (under the final bill) was entitled to only

Rs.6,79,237.45/- under claim no. 2.

Petitioner's submissions in Rejoinder

15. The Petitioner in rejoinder arguments denied that the Petitioner is an

unregistered partnership firm. It was submitted that the same objection was

raised by the Respondent before the Arbitral tribunal, to which the Petitioner

had furnished a registration certificate- available on the records of the

Arbitral Tribunal at page C-820. It was further denied that the present

petition had not been duly instituted by an authorised person. Reliance was

placed by the Petitioner on a power of attorney executed in favour of the

person who has instituted the present petition, viz. Shri Jitendra Singh S/o

Late Sh. Khajan Singh. Furthermore, it was submitted that in terms of

Section 19 of the Act, the provisions of the CPC, specifically Order XXX

Rule 1 and 2, are not strictly applicable to the proceedings under the Act and,

as such, the preliminary objection of the Respondent, as regards

maintainability of the present petition, is unsustainable.

16. It was submitted that the question of limitation being a pure question

of law, could be raised at any point of time. Reference in this regard was

made to the judgments of the Supreme Court in The Management of State

Bank of Hyderabad v. Vasudev Anant Bhide etc., 1969 (2) SCC 491, V.M.

Salgaocar & Bros. v. Board of Trustees of Port of Mormugao and

Another, AIR 2005 SC 4138, and Gannmani Anasuya and Others. v.

Parvatini Amarendra Chowdhary and Others, (2007) 10 SCC 296;

judgments of this Court in Ashok K. Khurana v. M/s Steelmen Industries

and Anr., AIR 2000 Delhi 336, Oil & Natural Gas Corporation Ltd. v.

Amtek Geophysical Pvt. Ltd., 2004 (3) R.A.J. 581 (Del), Jammu & Kashmir

Bank Ltd. v. Shree Digvijay Cement, 154 (2008) DLT 80 (DB) and Gannon

Dunkerley and Co. Ltd. v. National Thermal Power Corporation,

MANU/DE/2910/2009; judgment of the High Court of Punjab in Santa

Singh Gopal Singh and Others v. Rajinder Singh Bur Singh and Others,

AIR 1965 Punjab 415 ; judgment of the Calcutta High Court in M/s Orient

Ceramic Products Pvt. Ltd. v. Calcutta Municipal Corporation, AIR 2000

Calcutta 17; and judgment of the Bombay High Court in Sealand Shipping

& Export Pvt. Ltd. Vs. Kinship Services (India) Pvt. Ltd., 2012 (1) R.A.J.

589 (Bom).

17. In view of the above referred pronouncements, it was submitted that

mere failure to raise the plea of limitation would not be fatal, as it was the

duty of the Arbitral tribunal to deal with the same. It was submitted that the

Limitation Act, 1963 applies to arbitrations under the Act, as it applies to

proceedings in Court. Relying upon Section 28(1)(a) of the Act, it was

submitted that in an arbitration (other than an international commercial

arbitration), which takes place in India, the arbitral tribunal is bound to

decide the dispute submitted to arbitration in accordance with the substantive

law for the time being in force in India. It was submitted that Section 4 of the

Act applies only to derogable provisions under the Act, such as, Section

12(3), 19(2), 20(1), 22 etc., and the said provision (Section 4), therefore,

cannot be invoked to render Section 28 of the Act and Section 3 of the

Limitation Act otiose. The Tribunal would, therefore, be obliged to decide

the dispute in accordance with the Substantive law in force in India.

18. It was submitted that the „Counter Claims‟ are also „Claims‟ raised by

a Respondent. Hence, the provision of Section 21 of the Act is squarely

applicable and, consequently, until and unless a notice is served upon the

claimant, the question of Arbitral proceeding, in respect of the counter claim,

commencing would not arise.

19. It was submitted that the Arbitral tribunal being a creature of the

contract between the parties, cannot ignore the provisions of the contract and

more specifically, clause 8.3.1 (e) in the present case. It was submitted that

the counter claim allowed was beyond the scope of the contract and as such

was liable to be set aside.

20. The Petitioner denied to have not disputed the quantity of materials

issued, consumed and wasted. It was submitted that the Learned Arbitrator,

under the garb of Section 33 of the Act, has re-written the Award against

claim No.2 as an adjustment- which is not permissible under the law.

Discussion

21. The primary question to be determined in the present petition is,

whether, the petitioner can be permitted to urge for the first time in these

proceedings that the counter claims of the Respondent were barred by

limitation. However, before I examine the same, I shall first deal with the

preliminary objection raised by the Respondent with regards to

maintainability of the present objections/petition.

22. The petitioner, on this objection being raised before the learned

Arbitrator had placed (at page C-820 of the arbitral record), a copy of the

Certificate of Registration of the petitioner firm which shows, inter alia, Shri

Ashwini Kumar Gupta as one of the partners. The copy of the Power of

Attorney given to Shri Jatindra Singh - who has instituted the objection

petition- duly authorised him to institute legal proceedings on behalf of the

petitioner firm, and the same has been filed along with the rejoinder. The

learned Arbitrator has not allowed the aforesaid preliminary objection of the

respondent. Therefore, in view of the aforesaid, I find no merit in the

respondent‟s objection either on the ground that the petitioner is not a

registered firm, or that the present petition has not been instituted by a

competent person.

23. The petitioner claims that the counter claims of the respondent was

barred by limitation on the premise that, since the respondent raised a

demand towards material accounting/reconciliation vide letter dated

06.12.1999, the cause of action arose on that date and, as such, the

Respondent should have filed its counter claims within 3 years from that

date, either by filing a suit or commencing arbitral proceedings in terms of

Section 21 of the Act. Not having done so, the counter claims were barred by

limitation. To fortify its submission, the petitioner referred to the judgment

of the Supreme Court in State of Goa v. Praveen Enterprises (supra), and

more specifically to the following observation:

"17. As far as counter claims are concerned, there is no room for ambiguity in regard to the relevant date for determining the limitation. Section 3(2)(b) of Limitation Act, 1963 provides that in regard to a counter claim in suits, the date on which the counter claim is made in court shall be deemed to be the date of institution of the counter claim. As Limitation Act, 1963 is made applicable to arbitrations, in the case of a counter claim by a respondent in an arbitral proceedings, the date on which the counter claim is made before the arbitrator will be the date of "institution" in so far as counter claim is concerned. There is, therefore, no need to provide a date of „commencement‟ as in the case of claims of a claimant. Section 21 of the Act is therefore not relevant for counter claims. There is however one exception. Where the respondent against whom a claim is made, had also made a claim against the claimant and sought arbitration by serving a notice to the claimant but subsequently raises that claim as a counter claim in the arbitration proceedings initiated by the claimant, instead of filing a separate application under section 11 of the Act, the limitation for such counter claim should be computed, as on the date of service of notice of such claim on the claimant and not on the date of filing of the counter claim."

24. The issues which arose before the Supreme Court for consideration,

and which the Supreme Court was dealing with were not the same as the one

raised by the petitioner. The issue raised and considered by the Supreme

Court was "Whether the respondent in an arbitration proceedings is

precluded from making a counter-claim, unless a) it had served a notice

upon the claimant requesting that the disputes relating to that counter-claim

be referred to arbitration and the claimant had concurred in referring the

counter claim to the same arbitrator; and/or b) it had set out the said

counter claim in its reply statement to the application under section 11 of the

Act and the Chief Justice or his designate refers such counter claim also to

arbitration". Therefore, the issue was not of limitation for filing a counter

claim, but of the maintainability thereof without giving notice therefor.

25. The judgment of the Supreme Court in S. Ranjan (Supra), also does

not advance the case of the petitioner. In that case, the question before the

Supreme Court was when did the right to apply under Section 20 of the

Arbitration Act, 1940, for appointment of arbitrator, accrue- for the purpose

of deciding the maintainability of the application under Section 20 on the

issue of limitation. The Supreme Court observed that, reading Article 137 of

the Limitation Act and sub-section (1) of Section 20 of the Arbitration Act

together, the right to apply accrues when differences arise between the

parties. The same being a question of fact has to be determined having

regard to the facts of the case.

26. Petitioner‟s reliance upon the judgment of this Court in Smt. Biba

Sethi (supra) is entirely misplaced. The question before the Court was

whether the period of limitation to prefer claims as provided for under the

byelaws of NSE would override the law of limitation. In other words, the

issue before the Court was whether an arbitration, under the Byelaws of

NSE, is an arbitration under any other enactment, within the meaning of

Section 2(4) of the Arbitration Act, so as to make Section 43 thereof- and,

consequently, the Limitation Act inapplicable to such arbitration. The Court

held that the legislative intent was not to empower the State Government to,

while framing rules, prescribe the period of limitation for preferring claims.

The byelaw to that extent was held to be purely contractual and, in view of

Section 28 of the Contract Act, the same was declared to be void.

27. The judgment of the Supreme Court in J.C. Budhiraja (supra) also

does not bolster the submissions of the petitioner herein, since the same dealt

with an entirely different issue. In that case, the Supreme Court set aside the

finding/assumption of the Arbitrator that if the application for appointment

of arbitrator was made in time, then all claims made in the claim statement

filed before the appointed arbitrator are also in time. The Supreme Court

held that Section 37(3) of the Arbitration Act 1940 provides that for the

purpose of the Limitation Act, an arbitration is deemed to have been

commenced when one party to the arbitration agreement serves on the other

party thereto, a notice requiring the appointment of an arbitrator. Such a

notice having been served, it has to be seen whether the claims were in time

as on that date. If the claims are barred by limitation on that date, it follows

that the claims had to be rejected by the Arbitrator on the ground that the

claims were barred by limitation. The said period of limitation has nothing to

do with the period of limitation for filing a petition under Section 8(2) of the

Arbitration Act, 1940 for appointment of an arbitrator- as the cause of action

in that case would arise when the other party fails to comply with the notice

invoking arbitration.

28. For the purposes of deciding the question whether the counter claims

were barred by limitation, the starting point of institution of counter claim

would have to be the date of institution of counter claims before the Arbitral

tribunal. If the said date was within the period of limitation when taken from

the date on which the cause of action to institute the counter claims last

arose, then the same would not be barred by limitation and if not so, then it

would be barred.

29. There can be no quarrel with the above proposition. But what is to be

examined in each case, as a matter of fact and of law is - when the cause of

action last arose in respect of a particular claim/counter claim. Since the

primary issue, i.e. when the cause of action last arose for raising the counter

claim, is a mixed question of fact and law, the issue of limitation cannot be

raised in proceedings under Section 34 of the Act for the first time.

30. In Santa Singh (supra), the full bench of the Punjab High Court

permitted the raising of the plea of limitation, though the same had not been

raised before the trial court, as the same was not altogether a new issue in the

facts of the case. It was observed that the no new facts had to be proved, and

all that had to be seen was whether, according to the pleadings of the parties

and the findings which have been given and which are binding on them, the

suit was barred by limitation. In Management of State Bank of Hyderabad

(supra), the Supreme Court permitted the appellant to raise a plea of

limitation for the first time since no fresh facts had to be investigated and the

matter could be dealt with as a pure question of law. In Ashok K. Khurana

(Supra), the appellant had assailed the order of trial court- dismissing the

appellant‟s suit for recovery, filed against the respondent, on the ground that

the same was barred by limitation. The respondent/defendant had it in its

written statement, inter-alia, raised a preliminary objection that the suit was

barred by limitation. On the basis of the pleadings the trial court framed the

preliminary issue- whether the suit is within the period of limitation. The

trial court decided the same in favour of the respondent/defendant and

dismissed the suit. In appeal, this Court observed that the question of

limitation, in the case at hand, was a question of fact and the

appellant/plaintiff could not be non-suited without a trial. The order of the

trial court was accordingly set aside and the suit was remanded back to the

trial.

31. The last three decisions referred to above do not advance the

petitioner‟s submissions for the reason that in all those cases, the Court

which permitted the raising of the issue of limitation for the first time was

acting as the appellate Court. It is well settled that an appeal is a

continuation of the original proceedings. The entire matter is at large before

an appellate Court. The same is not true about a Court hearing objections to

an arbitral award under Section 34 of the Act. The arbitrator is the final

judge of facts. The Court while hearing objections does not scrutinize the

award as an appellate forum.

32. Reliance placed on Orient Ceramic Products Pvt. Ltd. (supra) also

seems to be misplaced. In this case, the defendant sought to set up a counter

claim. The Court, after examination of the facts before it, as pleaded in the

application, whereby the counter claim was sought to be set up, came to a

definite conclusion that the same was barred by limitation. It was on this

account that the Court did not permit the counter claim to be filed by the

defendant. Moreover, the counter claim was sought to be set up after the

filing of the written statement and without furnishing any justification for not

raising the same when the written statement was filed.

33. In Bharat M. Nagori (Supra), the issue before the Bombay High

Court was whether it is open for the petitioner to raise a plea of limitation, in

a case where the plea was not raised before the Arbitrator, while assailing the

award. The Court observed that the issue of limitation, pleaded on facts,

would be mixed question of fact and law and as such considering the

pleadings, in the case at hand, it was not possible to hold that the claim filed

is barred by limitation. The High Court also took note of the judgment of the

Supreme Court in Oil & Natural Gas Commission v. M.C. Clelland

Engineers S.A., 1994 (4) SCC 327, wherein the Supreme Court while

dealing with the contention of limitation raised before it, observed that when

no foundation has been laid in the course of the proceedings before the

Arbitrator either in the pleadings or in the evidence, it would be difficult to

examine the plea as raised.

34. Oil & Natural Gas Corporation Ltd. v. Amtek Geophysical Pvt. Ltd.

(supra), is a decision rendered in its own facts and does not advance the

petitioner‟s case. The petitioner assailed the award of the Arbitral tribunal

dismissing the counter claim filed by it on the ground that the same was

barred by limitation. Therefore, the issue of limitation was raised before, and

considered by the Arbitral Tribunal, which is not the position in the case at

hand.

35. V.M. Salgaocar (supra) too has no relevance for the simple reason

that the plea of limitation had been squarely raised by the defendant in the

written statement. The issue examined by the Court was whether the

defendant had waived the said plea, as a partial decree had been passed on

admission under Order 12 Rule 6 C.P.C. The Supreme Court held that the

plea of waiver was not a pure question of law, and could not be permitted to

be raised at a later stage. Therefore, the issue of limitation had to be

examined. As aforesaid, in the present case the issue of limitation qua the

counter claim was never raised by the petitioner before the Arbitral Tribunal.

It cannot be said that the counter claim was ex-facie barred by limitation.

Consequently, this case is of no avail to the petitioner.

36. In Balasaria Construction (P) Ltd. (Supra), the Supreme Court took

the view that the "suit could not be dismissed as barred by limitation without

proper pleadings, framing of an issue of limitation and taking of evidence.

Question of limitation is a mixed question of law and fact. Ex facie in the

present case on the reading of the plaint it cannot be held that the suit is

barred by time."

37. In Ramesh B. Desai (Supra), the appellants had filed a company

petition under Section 155 of the Companies Act, 1956. Respondent no. 1

and 2 moved an application to dismiss the petition on the ground that the

same was barred by limitation. The application was allowed by the Ld.

Company Judge and the order was affirmed in appeal by a Division Bench of

the High Court. The Supreme Court, in appeal, observed that "A plea of

limitation cannot be decided as an abstract principle of law divorced from

facts as in every given case the starting point of limitation has to be

ascertained which is entirely a question of fact. A plea of limitation is a

mixed question of law and fact". Relying upon the principle laid down in its

earlier judgment, in Balasaria Construction (P) Ltd. (Supra), it observed

that "unless it becomes apparent from the reading of the company petition

that the same is barred by limitation, the petition cannot be rejected under

Order VII Rule 11 (d) CPC". After considering the contents of the petition

and having regard to the provisions of the Limitation Act, 1963, the Supreme

Court observed that the company petition could not have been thrown out at

the preliminary stage- as being barred by limitation without giving

opportunity to the appellants to lead evidence.

38. In Vimal G. Jain (supra), a Division Bench of the Bombay High Court

observed that on a conjoint reading of Section 4 and 16(2) of the Act it

would appear that a party to the arbitration proceedings seeking to raise the

point of bar of limitation for initiating the arbitration proceedings should

raise the issue at the earliest opportunity and, in any case, not later than the

submission of the statement of defence, otherwise it would be deemed to

have been waived. Referring to the decision of the Supreme Court in

Narayan Prasad Lohia v. Nikunj Kumar Lohia, (2002) 3 SCC 572,-

wherein it has been held that unless the objection in terms of section 16(2) is

raised within the time prescribed under the said Section, it would be deemed

to have been waived in terms of section 4 of the said Act- the Bombay High

Court held that since the point regarding the bar of limitation was never

raised before the learned arbitrator, the same should be deemed to have been

waived.

39. In Jammu & Kashmir Bank Ltd. (Supra), the appellant, assailed the

judgment of the learned Single Judge, inter alia, on the ground that the suit

instituted by the Respondent was barred by limitation. The Division Bench

observed that "An issue of limitation does not arise as a pure question of

law. It is always a mixed question of fact and law. In order to decide the

issue of limitation, the Court has to perforce appreciate the facts and

evidence, unless from a plain reading of the plaint, the suit appears to be

unambiguously barred by limitation". This Court further observed that "In

such a case, the appellate Court may set aside the decree and dismiss the

suit on the ground of limitation on the basis of the evidence and record

available if, from such record and evidence, without more, the suit appears

to be struck by the law of limitation. However, if the question of limitation is

allowed without examining the relevant facts and evidence, or if the appeal,

in which the plea has been raised for the first time, is allowed and suit is

dismissed without giving an opportunity to the plaintiff to oppose it on the

facts and evidence, it may cause prejudice to some of the parties to the suit."

The situation, in a case like the present, is still worse for the party raising a

belated plea of limitation because the Court, as aforesaid, is not an appellate

forum qua the arbitral award. As aforesaid, an appeal is a continuation of an

original suit proceeding. Therefore, it is possible to amend the plaint even

during the pendency of an appeal. It is also possible to lead additional

evidence at the appellate stage. But this facility is not available before the

Court hearing objections to an arbitral award. For the aforesaid reason, the

decision in Gannmani Anasuya (supra), has no relevance.

40. In Gannon Dunkerley (Supra), this Court allowed the plea of

limitation to be raised for the first time in a petition/objections under Section

16, 30 and 33 of the Arbitration Act, 1940 against an arbitral award, as the

facts of the case were not disputed and the issue of limitation appeared on

the face of the record. As aforesaid, that does not appear to be the position

in the present case.

41. In Tamil Nadu Water Supply and Drainage Board v. N. Abdul

Kareem and Ors., (2010) Arb. LR 581 (Madras) (DB), the Division Bench

of the Madras High Court upheld the order of the Ld. Single Judge wherein,

the plea of limitation, having been raised for the first time in the

petition/objections under Section 34 of the Act, had been rejected. It was

observed that specific pleading with necessary particulars with regard to the

question of limitation could have been made before the arbitral tribunal.

Considering that the question of limitation is a mixed question of law and

facts, the High Court, in view of the lack of evidence on record, observed

that the same could not be decided at this stage.

42. The decision in Sealand Shipping & Export Pvt. Ltd. (supra), in my

view, has no application for various reasons. Firstly, this decision does not

take note of the Division Bench decision of the same High Court in Vimal G.

Jain (supra). Secondly, the fact situation in that case was materially

different. The plea of limitation had been raised before the Arbitral

Tribunal, however, the Tribunal did not frame an issue on this plea and did

not decide the same. In the present case, admittedly, no plea of limitation

was raised by the petitioner. Pertinently, the respondent raised the plea of

limitation in respect of the petitioner‟s claim. Inspite of this, the petitioner

did not raise the plea of limitation in respect of the counter claim.

43. Last but not least, I may take note of the decision of this Court

rendered inter partes in M/s Raj Kishan & Company Vs. National Thermal

Power Corporation Limited, O.M.P. No. 333/2004 decided on 13.03.2012.

In that case as well, the petitioner herein did not raise the plea of the

respondent/NTPC‟s claim being barred by limitation before the Arbitral

Tribunal. The only difference is that, whereas, in the present case this plea

has been raised in these proceedings, in O.M.P. No. 333/2004 it was not

even raised in the objection petition. The learned Single Judge rejected the

said plea by holding as follows:

"This ground has been raised only at the time of the arguments. It is a settled position of law that plea of limitation cannot be decided as an abstract plea of law divorced from the facts. As explained in Ramesh B. Desai v. Vipin Vadilal Mehta 2006 (5) SCC 638 "a plea of limitation is a mixed question of law and fact." Consequently, unless the plea of limitation is raised at the earliest point in time before the learned Arbitrator, it cannot be adjudicated upon as a mixed question of law and fact. In Oil and Natural Gas Corporation Limited vs. Mc Chemical Engineers, 1999 (2) Raj. 149 (SC) the Supreme Court negatived the plea of limitation raised for the first time in the course of challenge to the award before the Court. In Tamil Nadu Water Supply v. M. Abdul Karim, 2010 (4) ALR 581 (Madras) it was again held that without a proper foundation of facts laid before the learned Arbitrator to demonstrate that the claims were barred by limitation, a plea to that effect cannot be raised for the first time in Court. A Division Bench of Bombay High Court in Vimal G. Jain v. Vertex Financial Services Pvt. Ltd., 2007 (4) Arb LR 18 (Bombay) held that if the point regarding the bar of limitation is not raised before the Arbitrator, it should be deemed to have been waived. Consequently, "the question of entertaining such point in proceedings under Section 34 of the Act or in an appeal arising from the order passed therein cannot arise." This Court has held to the same effect in M/s. Uppal Engineering Corporation v. C.W.C., 2009 (3) Raj. 666 (Del.) and M. Sons Enterprises

Pvt. Limited v. Shri Suresh Jagasia and Anr. 2011(123) DRJ

266. In that view of the matter, the Petitioner cannot be permitted to urge the ground regarding limitation for the first time during arguments."

44. It is not for this Court to speculate with regard to the possible defences

that the respondent may have been in a position to raise and may have raised,

as also all the defences which may have been accepted by the learned

Arbitrator in answer to the bar of limitation that the petitioner could have

raised but failed to raise. However, to deal with the petitioner‟s submission

that the present case is an open & shut case in which the respondent could

possibly not have raised any defence to the plea of limitation in respect of

the respondents counter-claim and that, therefore, this Court should entertain

the said plea even at this stage, I may only demonstrate what all pleas the

respondent could and might have raised, had the petitioner raised the plea of

limitation, which defences may have been accepted by the Arbitral Tribunal,

which come to my mind.

45. On the basis of the correspondence exchanged between the parties, as

referred to in para 2.2 and 2.3 above, the respondent could have contended

that what the respondent nomenclatured as a counter claim was, in fact, an

already undertaken adjustment of the amount due to it from the petitioner on

account of owner issued materials. The respondent could have contended

that since the amount adjusted on this account was less than the amount due

from the respondent to the petitioner, there was no need or occasion for the

respondent to have invoked the arbitration agreement, and to seek reference

of the said dispute to arbitration. It could have been argued that the

respondent could well have waited for the petitioner to invoke the arbitration

agreement to claim the amounts due to it, and in such proceedings to set up

its defence to seek adjustment of the amount due from the petitioner to the

respondent towards owner issued materials. One possible view that the

tribunal could have taken, could be that the limitation did not run against the

respondent, as such a defence could be raised at any point of time, as and

when the claim is made against the respondent. The respondent could also

have argued that when the petitioner invoked the arbitration agreement, the

petitioner itself sought to raise the issue of adjustment sought to be made by

the respondent on account of owner issued material, by placing reliance on

the communication dated 10.05.2000 extracted in para 2.3 above. The

respondent could have also contended that the petitioner itself sought

reference of the disputes with regard to the amount adjusted by the

respondent to arbitration, as that was the justification offered by the

respondent to not pay the dues of the petitioner under the contract. It

appears, that because the issue of limitation was never raised by the

petitioner, the tribunal could not examine whether the counter claim was in

the nature of an adjustment. Even if the said counter claim was not in

respect of an adjustment but an independent counter claim, the learned

Arbitrator was precluded from considering the issue as to when the cause of

action last arose in favour of the respondent, and when the period of

limitation for making the said counter claim started to run against the

respondent. This was a mixed question of facts and law. The tribunal could

also not consider the issue, whether in terms of the arbitration agreement, it

was incumbent for the respondent to have raised the claim and also

demanded arbitration before preferring the counter claim.

46. Lastly, the tribunal was also precluded from considering whether the

said issue of adjustment/counter claim of the respondent was covered by the

invocation of the arbitration agreement by the petitioner.

47. Consequently, I find no merit in the petitioner‟s objection that the

counter-claim of the respondent was barred by limitation. This plea is not

open to the petitioner to raise at this stage as the same was never raised

before the Arbitral Tribunal.

48. The objection of the petitioner that the award made by the learned

Arbitrator qua recovery for wastage and excess amounts of cement,

reinforcement steel and structural steel is contrary to the contractual terms

also has no merit. The petitioner has placed reliance on Clause 8.3.1 (e) of

the contract, which reads as follows:

"At any point of time, the material outstanding as unaccounted for, shall be limited to 10% of the value of the security deposit given by the contractor for the materials unless & otherwise permitted in writing by Engineer Incharge."

49. The petitioner‟s submission is that since no permission was given by

the Engineer-in-Charge permitting the petitioner to retain the material in

value terms beyond the limit of 10% of the security deposit, it could not be

accepted that the petitioner, in fact, was holding or had consumed excess

amounts of cement, reinforcement steel or structural steel.

50. The Arbitral Tribunal has dealt with the submission of the petitioner

and interpreted Clause 8.3.1(e) in the award in paragraphs 195 to 198. The

learned Arbitrator notes that the said clause requires reconciliation of

material on quarterly basis on the execution of works up to the specified

percentages including at the final stage. He also notes that there was no

evidence or averment of the respondent that the procedure had been followed

by the Engineer-in-Charge. He thereafter goes on to observe as follows:

"196. However, the claimant cannot be allowed to get undue enrichment, if on getting the details from the documents, the respondent is able to prove that the respondent is entitled to make recovery in accordance with the provisions of the contract for excess/less consumption of material is enumerated in the contract, which is not in dispute.

197. I will first take up the recovery in respect of Reinforcement Steel. Although in the statement of counter claim, the amount claimed in respect of this material was Rs. 1,49,89,462/-. Yet, in the details filed by the respondent during the proceedings on 24.5.2007, which were furnished to the counsel for the claimant at that time but filed on the record on 31.1.2009, show that the respondent is now claiming Rs.1,27,70,884/-. There is no dispute with regard to the quantity of material issued to the claimant.

198. The claimant however, has endeavored to show that the steel so issued was over weight. The respondent in its calculation has given due account of the overweight material as appeared on the record. The claimant on the other hand has assumed without any basis that over weight found in respect of particular quantity of steel should be spread over by average in a generalized manner in respect of the entire quantity of the steel issued to the claimant. There is no basis for the same. It can be seen at page 151 of Book No.5 (Vol.XXX), the claimant had mentioned about the weight difference at Sl No.3.Col.No.3 for the quantity of steel issued for section 16mm dia, whereas, the store issue voucher (SI V) at C-682 (Book No.6) Vol.XIV, the steel of section 16 mm dia is underweight i.e. 1.56 kg/mt as compared to theoretical weight of 1.58 kg/mt and similarly, in C-697, the claimant is getting the weight certified in respect of the steel of section 20 mm dia and not of 16 mm dia, when it is to the knowledge of the claimant that steel of 16 mm dia issued

to the claimant was under weight. The respondent has taken out the actual issued material and the weight so recorded and whenever so desired by the claimant for giving its calculation. There is no reason to doubt the correctness of the details given by the respondent, hence, I allow Rs.1,27,70,884/- as recovery on the rates fixed in the contract, which are not in dispute."

51. The Respondent under counter claim no. 1 claimed Rs. 2,83,38,453/-

(which thereafter, on 31.01.2009, was claimed to be Rs. 1,27,70,884/- ) as a

recovery for wastage and excess consumption of cement, reinforcement steel

and structural steel, which were supplied by the respondent as free issue

material. The petitioner herein refuted the counter claim and also denied the

correctness of the details given in respect of the counter claim.

52. As per clause 8.3.1. (a) of the GCC, the re-conciliation of the actual

consumption and the theoretical consumption of the material so issued, was

to done as directed by the Engineer-in-charge on quarterly basis and also at

different stages of the works in accordance with the procedure prescribed

therefor. However, as noted by the arbitrator, there was no averment or

evidence that such procedure had been followed by the Engineer-in-charge.

53. The same, however, as observed by the Ld. Arbitrator, and rightly so,

would not entitle/allow the petitioner to get undue enrichment. Mere non-

obsservance of the procedure prescribed in clause 8.3.1(e) could not efface

the factual position as it was found to be existing on the record. The said

clause does not say that if the said procedure is not adopted, the respondent

would not be entitled to claim any amount in excess of 10% of the security

deposit or that the remaining claim of the respondent would be barred or

stand waived. The Arbitrator has returned a finding of fact that the

respondent was able to prove that there was excess consumption of free issue

material. The aspects of the method of calculating the consumption of

material, as enumerated in the contract, and the quantity of material issued to

the petitioner- were not disputed. These aspect, therefore, do not call for

interference in these proceedings.

54. The petitioner herein, however, tried to wash its hands of the said

liability by endeavouring to show that the steel issued by the respondent was

over-weight. The Ld. Arbitrator, while returning a finding of fact, rejected

the said defence on the ground that the petitioner assumed, without any

basis, that the over weight found in respect of particular quantity of steel

should be spread over by average in a generalised manner in respect of the

entire quantity of the steel issued to the claimant. The respondent, on the

other hand, as taken note of in the award, gave a due account of the

overweight material and the material actually issued along with its recorded

weight and the corresponding calculation- to stake its counter claim.

Consequently, the Ld. Arbitrator found no reason to doubt the correctness of

the details given by the respondent and accordingly allowed the counter

claim. The reasons given by the Ld. Arbitrator while dealing with the

counter claim of the respondent appear to be logical and plausible. There is

nothing to suggest that the interpretation of clause 8.3.1 of the contract is

perverse or contrary to the contractual terms. This objection of the

petitioner, accordingly, stands rejected.

55. The petitioner has assailed the aforementioned modification of the

award, as noticed in para 2.7 above, not on the ground that the amount of the

second last running bill was not paid to it by the respondent, but on an

entirely new ground i.e. that the amount of Rs. 1,54,28,696/- under Claim

No. 2 was in addition to the amount of Rs. 1,47,49.458.70/-. It was submitted

that the amount of Rs. 1,47,49.458.70/- had been paid way back in

December, 1997, whereas the rate analysis, which is the basis of Claim No.

2, had been prepared and finalised by the Respondent on 25.10.2001 and no

payment had been made thereafter. The raising of such entirely new grounds,

obviously, cannot be permitted at this stage.

56. The said plea is otherwise also unsustainable as, before the arbitrator

(at the time of the order of modification) it was pleaded that the said amount

had not been paid. However, the petitioner in the present proceedings admits

to have received the same - and that too, way back in December 1997. The

petitioner cannot be permitted to blow hot and cold at the same time and take

frivolous stands, just to somehow defeat the claim of the respondent. The

same is, accordingly, dismissed.

57. Accordingly, the present objection petition is dismissed with costs

quantified at Rs.30,000/-, to be paid by the petitioner to the respondent.

(VIPIN SANGHI) JUDGE SEPTEMBER 12, 2012 BSR/sr

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter