Saturday, 25, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Ssangyong Corporation vs The State Trading Corporation Of ...
2012 Latest Caselaw 3003 Del

Citation : 2012 Latest Caselaw 3003 Del
Judgement Date : 7 May, 2012

Delhi High Court
M/S. Ssangyong Corporation vs The State Trading Corporation Of ... on 7 May, 2012
Author: Valmiki J. Mehta
*              IN THE HIGH COURT OF DELHI AT NEW DELHI

+                    RFA No.345/2004 & RFA No.347/2004

%                                                  7th May, 2012

1. RFA No.345/2004

M/S. SSANGYONG CORPORATION                 ...... Appellant
                 Through: Mr. Sanjeev Anand with
                          Mr. Abhas Kumar, Advs.


                           VERSUS

THE STATE TRADING CORPORATION OF INDIA LIMITED
                                           ...... Respondent
                  Through: Ms.Sumati Anand, Adv.

                                  &

2. RFA No.347/2004

M/S. SSANGYONG CORPORATION                 ...... Appellant
                 Through: Mr. Sanjeev Anand with
                          Mr. Abhas Kumar, Advs.


                           VERSUS

THE STATE TRADING CORPORATION OF INDIA LIMITED
                                           ...... Respondent
                  Through: Ms.Sumati Anand, Adv.

CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA

    To be referred to the Reporter or not? Yes.
RFA No.345/2004 & RFA No.347/2004                    Page 1 of 19
 VALMIKI J. MEHTA, J (ORAL)

1.          This Regular First Appeal filed under Section 96 Code of Civil

Procedure, 1908 (CPC) impugns the judgment of the Trial Court decreeing

the suit of the respondent/plaintiff for recovery of monies paid under a

mistake to the appellant/defendant. The mistake on the basis of which

amounts were found to be payable to the respondent/plaintiff was that in the

Charter Party Agreement, the benefits of certain charges, being the despatch

charges, were to be paid to the respondent/plaintiff calculated on "All Time

Saved" basis (in short „ATS‟) and not "Work Time Saved" basis (in short

„WTS‟) and on which latter basis the payments due were calculated. „ATS‟

unit is a larger unit than the „WTS‟ unit, and therefore when „ATS‟ basis is

taken there would be a higher amount of despatch charges payable to the

respondent/plaintiff by the appellant/defendant instead when the despatch

charges are calculated on „WTS‟ basis.      The expressions of "All Time

Saved" basis and "Work Time Saved" basis are used with respect to the time

taken towards discharge of cargo (being cement in this case), from the hold

of the ship to the vessel on the port/dock. For the sake of completeness I

must state that in fact two suits of the respondent/plaintiff were decreed by

the impugned judgment, however since most of the facts and issues are
RFA No.345/2004 & RFA No.347/2004                          Page 2 of 19
 identical in both the suits, for the sake of convenience I am referring to the

facts of the suit which is the subject matter of RFA No.347/2004.

2.           The facts of the case are that the respondent/plaintiff was

appointed by the Cement Controller of India (now re-designated as DCCI,

Ministry of Industry) as the importer for importing cement in the country.

The respondent/plaintiff therefore entered into contracts with various sellers

of cement, one such seller being the appellant/defendant. In the present

case, the contracts which were entered into between the parties are the

contracts dated 18.11.1977 and 30.11.1977 (two in number), which are

identical in terms except the difference in quantity and the period of

shipments. Under these agreements, the respondent/plaintiff had contracted

to purchase from the appellant/defendant ordinary grey portland cement.

The delivery period was from December, 1977 to January, 1978 under the

agreement dated 18.11.1977 and during December, 1977 to February, 1978

under the agreement dated 30.11.1977.

3.           The appellant/defendant was to arrange the vessels for

transportation of the cement to a port in India.      The cargo was to be

discharged/unloaded from the ship/vessel by the respondent/plaintiff in a

fixed time which was agreed to between the parties and called as "laytime".
RFA No.345/2004 & RFA No.347/2004                           Page 3 of 19
 If extra/additional time was taken for discharge by the respondent/plaintiff

then, the respondent/plaintiff was to pay demurrage charges to the

appellant/defendant, but if the discharge was completed at an earlier date,

the respondent/plaintiff would earn despatch moneys.       The charges for

demurrage were double the charges for despatch, i.e. the demurrage charges

were fixed at US$3,000 and the despatch was at US$1,500/-. Under the first

contract dated 18.11.1977, 97600/- MT cement was to be supplied to the

respondent/plaintiff, and under the contracts dated 30.11.1977, 158900 MT

and 83650 MT of cement was to be supplied. The amount of difference on

account of mutual mistake of fact which was committed by both the parties

by calculating the despatch amount on „WTS‟ basis instead of „ATS‟ basis

came to US$14,052.10 under the contract dated 18.11.77, and under the

contracts dated 30.11.1977 the same came to US$12,369.80 and

US$20,618.75. The relevant contractual Clauses in this case are Clauses 8,

9 and 10 which read as under:-

            8.DISCHARGING RATE:
            Cargo to be discharged by Buyer for their time, risk and
            expenses at an average rate of 1,000 metric tons (One
            Thousand) at Bombay & 800 metric tons (Eight
            Hundred) at Cochin per weather working day of 24
            consecutive hours. Sunday and Holiday excepted unless
            used, if used working time to count as laytime.
RFA No.345/2004 & RFA No.347/2004                         Page 4 of 19
              9. LAYTIME:
             Laytime at discharging port to commence at 1 p.m. if
             Notice of Readiness is given before noon and at 8 a.m.
             next working day if Notice of Readiness is given during
             office hours in afternoon, unless sooner commenced,
             whether in berth or not, time lost in wait for berth to
             count as laytime. The vessel should be in free pratique.
             In case the Buyer or his Agent refuses to accept the
             Notice of Readiness served in the customary manner, it
             shall be deemed to have been served and accepted by the
             Buyer of his Agent if it is served through the local
             telegraph/postal office by cable and/or by Registered
             Post.

             10.DEMURRAGE AND DESPATCH:
             Demurrage money to be paid by Buyer to Seller at the
             rate of US$3,000 (Three Thousand Only) per day or pro-
             rate for all time lost. Despatch money to be paid by
             Seller to Buyer at the rate of US$1,500 (One Thousand
             Five Hundred Only) per day or pro-rata for all time
             saved. Demurrage and despatch payment shall be settled
             within one week from the date of discharging completion
             according to time sheet and statement of fact signed by
             ship master, vessel agent and receivers at discharging
             port. Buyer shall issue a guarantee for weekly settlement
             of demurrage in favour of Indian Shipping or other
             Indian Company nominated by "Seller".

4.           The appellant/defendant laid a two-fold defence.         Its first

defence was that there was agreed modification of the original agreements

between the parties whereby it was agreed that calculation of despatch will

not be on the „ATS‟ basis but will be on „WTS‟ basis. The second defence

was   that   the   suit   was   barred   by   limitation   inasmuch    as   the
RFA No.345/2004 & RFA No.347/2004                           Page 5 of 19
 respondent/plaintiff could have discovered the mistake with due diligence

and therefore the respondent/plaintiff was guilty of negligence and not

mistake.     Once the case is of negligence and not of mistake, the

respondent/plaintiff, it was pleaded by the appellant/defendant, cannot take

the benefit of Section 17(1)(c) of the Limitation Act, 1963.

5.            After the pleadings were completed, Trial Court framed the

following issues:-

           "1. Whether the pltf. is entitled to the suit amount? OPP

           2. If so rate of interest to which the plaintiff is entitled?

           3. Whether the suit is not barred by limitation? OPD

           4. Whether the suit is bad for misjoinder of cause of action?

           5. Whether there is no cause of action in view of the fact and
              that accounts between the parties have been finally
              settled as stated in preliminary objection no.3 of the WS
              filed by the defendant? OPD

           6. Whether this court has no territorial jurisdiction to try the
              present suit?

           7. Relief."

6.            The aspect as to whether there was a settlement between the

parties for the respondent/plaintiff to take despatch money on „WTS‟ basis

and not on „ATS‟ basis, has been dealt with by the Trial Court qua issue no.5
RFA No.345/2004 & RFA No.347/2004                                Page 6 of 19
 and while dealing with this issue the Trial Court has held and observed as

under:-

            "7. It has been alleged in the written statement that at
            the time of settling the accounts and even at the time of
            computation of time sheets it was mutually agreed
            between the parties that the basis for computing the
            despatch money would be on WTS band not on ATS. It
            has however, been admitted in the written statement that
            the contracts between the parties provided for
            computation of despatch money on ATS basis.

            8.     The plaintiff is a company fully owned by Govt.
            of India and is a large corporation. Admittedly, the terms
            and conditions settled between eh parties were reduced
            into writing. Admittedly, the written contract between
            the parties, provided for computation of despatch money
            on ATS basis. Therefore, it cannot be accepted that
            there was a subsequent oral agreement between the
            parties whereby written term of the contract as to basis
            for computing the despatch money was modified. Had
            there been any such modification, the modified term
            would definitely have been reduced into writing,
            particularly when the plaintiff is a Govt. company. Had
            there been any modification of the terms of the contact,
            the defendant would definitely have insisted upon
            reducing it into writing instead of taking the risk of the
            plaintiff denying the modification at a later date.

            9.     It has been alleged in the written statement that at
            the time of computation of despatch money and then at
            the time of settling the accounts, it was mutually agreed
            between the parties that the basis for computing the
            despatch money would be WTS and not ATS.
            Admittedly, computation of time-sheets took place much
            earlier than the alleged settlement of accounts. There is
RFA No.345/2004 & RFA No.347/2004                           Page 7 of 19
             no evidence that the officials of the Plaintiff Company
            and defendant company had nay joint meeting before
            computation of time sheets. The written statement does
            not disclose on which date and at which place the parties
            agreed to compute time sheets on WTS basis instead of
            ATS basis. Written statement does not disclose which
            official of the plaintiff company agreed to calculate the
            desptach money on WTS basis instead of ATS basis.
            DW-1 Hyeume Jin Choe is the only witness produced by
            the defendant. In his affidavit also he has not given
            these particulars. In these circumstances, I have no
            hesitation in holding that there was no agreement
            between the parties at the time of computation of time
            sheet that the basis for computing the despatch money
            would be on WTS basis instead of ATS.

            10. Admittedly a meeting took place between the
            officials of the plaintiff company and defendant
            company at New Delhi during October-November‟1984.
            According to DW-1 during discussions, the parties had
            copies of contracts before them and after discussions, it
            was agreed that a net amount of USD 73775.05 was to
            be paid by the defendants to the plaintiff in full and final
            settlement of all claims and counter claims w.r.t
            demurrage and despatch accounts in respect of 5
            contract. He has further stated in his affidavit that at the
            time of settling the accounts it was agreed that despatch
            money shall be computed on WTS basis. On the other
            hand PW-2 Sh. A.S.Dutta, who admittedly attended
            these meetings have specifically stated that there was no
            discussion in the meeting and only calculations were
            available before them. He denied that the parties had
            contacts with them during discussions in October-
            November‟84 and they knew the terms of contract and
            took a conscious decision for calculating the despatch on
            WTS basis. The letter written by the plaintiff company
            to the defendant on 6.11.84 does not give any indication
RFA No.345/2004 & RFA No.347/2004                           Page 8 of 19
             that the parties had consciously agreed to calculate
            despatch money on WTS basis instead of ATS basis.
            There is no contemporaneous document either from the
            defendant or the plaintiff, stating therein that parties had
            consciously agreed, in the meeting held at New Delhi in
            October-Novemeber‟84, to calculate despatch money on
            WTS basis. Therefore, I am not inclined to believe DW-
            1 on this part of his affidavit.

            11. Another important aspect in this regard is that if
            the parties had already agreed at the time of computation
            of time sheets, to calculate despatch on WTS basis as
            alleged in the written statement there would have been
            no occasion for them to take a similar decision in the
            meeting held in October-Novemebr‟84. In my view this
            is yet another circumstance which falsifies the plea
            taken by the defendant in this regard.

            12. I have gone through the correspondence between
            the parties. None of the letters suggest that there was a
            conscious agreement between the parties to modify the
            written terms of the contract and to calculate despatch
            money on WTS instead of ATS basis. Had there been
            any such agreement, either at the time of computation of
            time sheets or at the time of meetings which took place
            in October-Novmeber‟84, some indication of that would
            have been found in correspondence between the parties.
            In fact when the plaintiff sent revised calculations to the
            defendant, on ATS basis after discovering the mistake,
            the plea taken by the defendant was altogether different.
            Therefore, I hold that there was no oral agreement
            between the parties to calculate desptach money on
            WTS basis instead of ATS basis.
            .........

.........

The issue is decided against the Defendant and in favour of plaintiff." (underlining added)

7. A reference to the aforesaid paragraphs shows that the Trial

Court arrived at the following salient conclusions to hold that there was no

settlement as was urged by the appellant/defendant:-

i) If there was a modification of the contract, considering that the

respondent/plaintiff is a Government Company, the modification

would surely have been reduced in writing. In fact, even the

appellant/defendant instead of taking risk would have insisted for the

modification to be reduced in writing.

ii) The written statement does not disclose the date and place

where the agreement was entered into to show that the despatch

moneys will be calculated on „WTS‟ basis and not on „ATS‟ basis.

The written statement also did not disclose which official of the

respondent/plaintiff agreed to calculate the despatch money on „WTS‟

basis and not on „ATS‟ basis.

iii) The correspondence between the parties do not suggest any

conscious agreement to reduce the calculation of despatch charges

from „ATS‟ basis to „WTS‟ basis.

8. I do not find any absurdity, perversity or illegality in the

aforesaid findings and conclusions of the Trial Court. Surely, when the

consequences of a modification would run into lacs of rupees, the

respondent/plaintiff being a public sector undertaking, none of its officers

would have taken the risk of giving monetary benefit to the

appellant/defendant by calculation of despatch money on „WTS‟ basis

instead of „ATS‟ basis without bringing the modification of the contract into

writing and more so without the necessary sanction of the appropriate higher

authorities. I am therefore of the opinion that there was no settlement as

alleged by the appellant/defendant to make payment of despatch money on

„WTS‟ basis instead of contractual „ATS‟ basis.

9. On the issue as to whether the suit was barred by time, the Trial

Court has held that it cannot be said that the suit is time barred in view of the

provision of Section 17 of the Limitation Act, 1963 inasmuch as the mistake

was such which could not have been discovered earlier than 6.2.1985. Trial

Court has held that in every mistake there is always some built-in amount of

negligence, however, the negligence so as to be such to take the case out of

„lack of due diligence‟, is not found in the facts of the present case for it to

be held that the respondent/plaintiff cannot be entitled to the benefit of

Section 72 of the Contract Act, 1872. The Trial Court has held that the

actions of the respondent/plaintiff amount to mistake in the facts of the

present case and the mistake committed by the respondent/plaintiff was

discovered only when the letter dated 6.2.1985, Ex.P-1 was sent to it by the

office of the Cement Controller, Government of India. If the period of

limitation is computed from 6.2.1985, the suit having been filed within 3

years thereafter i.e. on 27.1.1988, the same would be within limitation.

Trial Court has also referred to the fact that merely because the accounts of

the respondent/plaintiff are audited cannot mean that in every case a mistake

must necessarily be discovered. Finally, the Trial Court has concluded that

there is no evidence that the respondent/plaintiff could have discovered the

mistake before the receipt of letter dated 6.2.1985 from the Cement

Controller, Govt. of India.

10. Sitting as a First Court of Appeal, I am entitled to reappraise

both findings of fact and law of the Court below. I have examined the

evidence which was led in this case in the form of lay-day sheets, statements

of facts and time sheets, and which are documents drawn up on the

completion of discharge from the vessel. It is thereafter that the facts and

figures were/are calculated and the same were sent by the

appellant/defendant to the respondent/plaintiff. These documents have been

exhibited in the Trial Court as exhibit PW2/51 to PW2/63. When we look at

the time sheets which have been sent by the appellant/defendant to the

respondent/plaintiff, the same show that the calculations have been shown to

be made on „ATS‟ basis, although in reality it was on „WTS‟ basis without

so being mentioned. The final calculation specifically refers to only „ATS‟

basis and not „WTS‟ basis. In the time sheets sent by the

appellant/defendant to the respondent/plaintiff, there is absolutely no

narration of calculation on „WTS‟ basis. The contract provided for

calculation of despatch charges on „ATS‟ basis, and once time sheets are

prepared by the appellant/defendant stating the same to be on „ATS‟ basis,

and not on „WTS‟ basis, surely, there may be some amount of overlooking

or an implied trust of the respondent/plaintiff in taking the „ATS‟ figures

contained in time sheets as „ATS‟ figures only and not „WTS‟ figures which

they actually were, however, the same would be a mistake and not

negligence for it to be argued that there is a lack of due diligence on behalf

of the respondent/plaintiff. The position would have been different if the

time sheets had shown both the calculations on „WTS‟ basis and on the

„ATS‟ basis, but the final figures of despatch thereafter would have been

shown only payable on „WTS‟ basis, and in which circumstances it could

have been open to the appellant/defendant to contend lack of due diligence

because the contract specifically provided for calculation of despatch money

only on „ATS‟ basis but the time sheets in that theoretical case would be

showing payment of despatch money on „WTS‟ basis and not „ATS‟ basis,

in which case the negligence would have writ large on the face of the record,

however, that theoretical position has not emerged in actual fact. On the

contrary what has happened in this case is that there is a single calculation

on „ATS‟ basis and therefore its consequent acceptance on behalf of the

respondent/plaintiff as the contract provided for „ATS‟ basis and surely this

is therefore only a mistake because the respondent/plaintiff accepted the

time sheets as they were presuming that calculations made therein are

actually on „ATS‟ basis and which is the basis of calculation as per the

contract and not on „WTS‟ basis on which the calculations were made

although the heading was „ATS‟ basis. Once the basis of calculation was as

per the contract on „ATS‟ basis, surely, a mere mistake in not ensuring to

check that actually the figures were on „WTS‟ basis and not on „ATS‟ basis

as apparently stated, in my opinion, is definitely not such position for it to be

called lack of due diligence as per S.17(1) of he Limitation Act. In fact, as

held by the Trial Court, some amount of negligence is always implicit when

a mistake is committed, however, the negligence must be of that order so as

to take the case out of the concept by lack of due diligence. In the facts of

the present case, considering the fact that the time sheets were prepared by

the appellant/defendant on „ATS‟ basis, and which is the calculation as per

the contract which provided for calculation on „ATS‟ basis, I hold that there

is no negligence on behalf of the respondent/plaintiff so as to decline it the

benefit of Section 72 of the Contract Act, 1872. The mistake cannot be

called such that it could have been discovered with „due diligence‟ as per

Section 17 of the Limitation Act, 1963.

11. Learned counsel for the appellant/defendant has sought to rely

upon the Division Bench judgment of this Court in the case of Life

Insurance Corporation vs. Raghunath Prasad Almal & Ors., 44(1991)

DLT 521 to argue that once there is negligence i.e. lack of due diligence, the

respondent/plaintiff should not be entitled to the benefit of Section 17 of the

Limitation Act, 1963. In fact this judgment was also cited before the Trial

Court and which has distinguished the said judgment on facts. All I need to

say is that the law with respect to whether an act is a mistake or negligence,

i.e. lack of due diligence necessarily has to be facts specific. Whereas the

facts in one case may show that there is only a mistake, facts in another case

may show that the mistake could have been discovered due to due diligence

and therefore the mistake is not a mistake as is known to the law but is in

fact gross negligence. In the facts of the present the factual context was that

the time sheets which were provided by the appellant/defendant to the

respondent/plaintiff mentioned calculation of despatch money on „ATS‟

basis and it was this „ATS‟ basis which was the unit to be applied in terms of

the contract causing the respondent/plaintiff to commit mistake by taking he

figures as „ATS‟ calculations, where in reality, though shown as „ATS‟

calculations, they were in fact „WTS‟ calculations. As already stated

hereinabove, and reiterated herein, if the time sheets would have specified

two methods of calculation on „WTS‟ basis and „ATS‟ basis and thereafter

the „WTS‟ calculations were claimed, then, the respondent/plaintiff may

have been guilty of negligence and lack of due diligence, however, once

only one basis of calculation of despatch money viz „ATS‟ basis is given in

the time sheets, there resulted an implied trust and acceptance thereof by the

respondent/plaintiff, and which can only be termed as a mistake and

definitely not negligence.

12. A civil case is decided on balance of probabilities. The balance

of probabilities in this case makes it more than abundantly clear that the

appellant/defendant is seeking to take advantage of unjust enrichment and

retaining moneys with it which were not due to it. The appellant/defendant

took up a case of an alleged agreed modification, and which the Trial Court

has for valid reasons held that there was no such agreement for modification

of the contract for acceptance of despatch money on „WTS‟ basis instead of

on „ATS‟ basis. An Appellate Court will not interfere with the findings and

conclusions of the Trial Court, unless the conclusions of the Trial Court are

illegal or perverse. In addition to the reasoning given by the Trial Court, I

have given an additional reasoning, and which I am entitled to do so under

Order 41 Rule 24 CPC, the additional reasoning being based on the time

sheets which have been sent by the appellant/defendant itself to the

respondent/plaintiff.

13. In view of the above, I do not find any merit in the appeal

which is accordingly dismissed, leaving the parties to bear their own costs.

RFA No.345/2004

14. The facts of this case and the issues in this case are more or less

identical with the facts of RFA No.347/2004 which has been disposed of by

me above. There may be some difference in facts and figures qua this case,

however, the basic issues decided in both the cases are the same. The only

additional argument urged on behalf of the appellant in this case is that

between the parties there were arbitration proceedings and in which

arbitration proceedings, it was held that there was an agreement between the

parties to make payment on „WTS‟ basis and not on „ATS‟ basis and which

Award has been upheld by this Court even including at the stage of appeal

and thus it must be held that there was an agreement for „WTS‟ basis. I may

state that unfortunately law with respect to challenge of an Award is

different than law as applicable when I am sitting as an Appellate Court

under Order 41 CPC. Ordinarily, Courts do not interfere with an Award,

once reasons are given in the Award, unless the Award is in violation of the

public policy under Section 34 of the Arbitration and Conciliation Act, 1996,

A Court which hears objections under Section 34 of the said Act ordinarily

does not interfere with an Award. If the original Court does not interfere

with the Award, the Appellate Court hearing appeal against the judgment

dismissing the objections, has further limited scope. Therefore, I do not

think any judgment in arbitration proceedings between the parties, can have

any bearing on the result of this appeal, as my jurisdiction sitting as an

Appellate Court under Section 96 of CPC (with other relevant provisions)

read with Order 41 CPC is different. The present appeal is also therefore

dismissed leaving the parties to bear their own costs.

VALMIKI J. MEHTA, J MAY 07, 2012 ak

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter