Citation : 2012 Latest Caselaw 2154 Del
Judgement Date : 29 March, 2012
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of Judgment:29.3.2012
+ C.R.P. 230/2005
HOUSING & URBAN DEV. COR. LTD ..... Petitioner
Through: Mr.A.K.Singh, Advocate with
Ms.Sheenu Vats, Law Officer.
versus
ANSAL PROPERTIES & IND. LTD ..... Respondent
Through: Ms.Amrita Singh, Advocate.
CORAM:
HON'BLE MS. JUSTICE INDERMEET KAUR
INDERMEET KAUR, J. (Oral)
1 Order impugned is the order dated 15.03.2005. The application
filed by the defendant in the pending suit under Section 8 of the
Arbitration and Conciliation Act (hereinafter referred to as the „said
Act‟) had been allowed; the dispute pending had been referred to the
sole Arbitrator; this was in terms of the arbitration clause contained in
the agreement dated 01.08.1995.
2 Record shows that the plaintiff i.e. Housing & Urban
Development Corporation Ltd. had filed a suit for mandatory injunction
against Ansal Properties; a prayer was made to the effect that the
defendant be directed to demolish the pump room and HT panel
installed in the area depicted in the site plan marked in blue colour and
in red colour. The defendant had offered a consideration of
`1,68,80,93,200/- to the plaintiff for the allotment of shopping arcade
site at HUDCO place, Andrews Ganj, New Delhi on terms and
conditions stipulated in the brochure. On 10.03.1995, the plaintiff had
issued a letter of allotment on the terms and condition contained therein
calling upon the defendant to accept the terms and conditions along with
car parking space for 210 cars; the first installment of 50% of the total
consideration was required to be paid on or before 06.04.1995; balance
was to be paid in two installments as indicated in the allotment letter
dated 10.03.1995. In terms of clause 1 of the agreement, 200 square
meters of this space could be sub-leased for installation of facilities such
as air-conditioning plant and other services. It is not in dispute that 50%
of the first installment was paid by the defendant; the agreement to sub-
lease dated 01.08.1995 was executed; this was a tripartite agreement
between the President of India, the plaintiff and the defendant; the terms
of the allotment letter dated 10.03.1995 was made a part and parcel of
this agreement of sub-lease dated 01.08.1995 physical site was handed
over to the defendant on 10.11.1995. A shopping arcade was
constructed. The respondent was also given 200 square meters in the
plant room on license basis on 10.11.1995 in terms of the letter of
allotment and in terms of the agreement to sub-lease for the purpose of
installation of service facilities such as air-conditioning and other misc.
services. Contention of the plaintiff was that the respondent has
illegality put up an HT Panel in the area under the possession of the
plaintiff. The defendant vide letter dated 03.07.1998 sought permission
of the plaintiff to place water tanks and pumps in the underground
portion as per the location plan; permission was not granted yet the
defendant had installed these tanks as also two pressure pumps;
contention of the plaintiff was that this is an illegal and unauthorized
user of the said premises. Inspite of repeated efforts calling upon the
respondent to remove the HT Panel and to demolish the pump room
which was in terms of the communications of the plaintiff dated
24.03.2000, 13.06.2000, 22.06.2000, 24.08.2000, 13.09.2000 and
11.10.2000, the respondent did not acceded to this request. The legal
notice dated 24.11.2000 was also served upon the defendant as also a
subsequent letter dated 18.01.2001. Left with no alternative, the present
suit for mandatory injunction was filed by the plaintiff.
3 In the course of cross-examination of the witnesses, the present
application under Section 8 of the said Act was filed. The impugned
order had allowed this application on 15.03.2005.
4 Vehement contention of the petitioner before this Court is that
this order suffers from an illegality; provision of Section 8 of the said
Act have not been considered in the correct perspective; this application
should have been filed before the first statement was filed on the
substance of the dispute; the matter was under cross-examination when
this application was filed; the impugned order thus suffers from an
illegality; it is liable to be set aside.
5 Arguments have been countered. 6 Record shows that the issues had been framed on 11.03.2002; issued No. 2 reads herein as under:-
"Whether the suit of the plaintiff is not maintainable in view of arbitration agreement between the parties as mentioned in para 2 of the written statement?
OPD"
7 It was at the stage of the evidence of the plaintiff that the
application under Section 8 of the said Act was filed. Written statement
had been filed in 2001; present application has been filed on 29.10.2004.
8 There is no doubt to the fact that if all the ingredients of Section 8
of the said have been complied with; there is little option left with the
Court but to refer the matter to arbitration. The arbitration clause was
contained in the agreement dated 01.08.1995.
9 Record shows that the written statement was filed on 25.4.2001.
Admittedly a preliminary objection had been taken about the jurisdiction
of the civil court; contention being that since there is an arbitration
clause and the disputes have to be referred to arbitration. However the
averments made in the written statement clearly show that all answers
on the merits of the controversy had been answered in this written
statement; the filing of this written statement clearly shows that the
defendant had submitted himself to the jurisdiction of the civil court.
The application under Section 8 of the said Act was filed only on
29.10.2004.
10 The expression "first statement on the substance of the dispute"
contained in Section 8(1) of the 1996 Act is contra distinct from the
"written statement" it implies the submission of the parties to the
jurisdiction of the judicial authority; there must be a finding that the
party has waived its right to invoke arbitration clause; where the party
has himself submitted itself to the jurisdiction of the civil court as it was
so in the instant case and the written statement filed by the defendant
had answered the merits of the dispute; it is clear that the party in fact
had waived its right to invoke the arbitration clause. Application under
Section 8 of the Arbitration Act was in fact filed much later as noted
supra.
11 In this background impugned judgment referring the disputes of
the parties to the arbitration has committed an illegality. It is
accordingly set aside.
12 Reliance by the learned counsel for the petitioner upon the
judgment of Apex Court reported in AIR 2006 SC 280 Rashtriya Ispat
Nigam Ltd. Vs. Verma Transport Company in this factual scenario is
misplaced.
13 The parties are directed to appear before the District & Sessions
Judge, Tis Hazari on 18.4.2012 at 10.30 AM who shall assign the case
to the concerned court for the disposal of the suit on its merits. With
these directions, petition is disposed of.
INDERMEET KAUR, J MARCH 29, 2012 A/nandan
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!