Citation : 2012 Latest Caselaw 2145 Del
Judgement Date : 29 March, 2012
IN THE HIGH COURT OF DELHI AT NEW DELHI
O.M.P. 400/2005
Reserved on: March 1, 2012
Decision on: March 29, 2012
MESCO AIRLINES LTD ..... Petitioner
Through: Mr. Harish Malhotra, Senior Advocate
with Mr. R.K. Modi, Advocate.
versus
M/S. AVIAEXPORT AND ORS ..... Respondents
Through: Mr. Vineet Malhotra with
Mr. Rohan Sharma, Advocates.
CORAM: JUSTICE S. MURALIDHAR
JUDGMENT
29.03.2012
1. The challenge in this petition by Mesco Airlines Limited ('MAL')
under Section 34 of the Arbitration and Conciliation Act, 1996 ('Act') is
to the impugned Award dated 22nd August 2005 being the majority award
of two of the learned Arbitrators constituting the three-member Arbitral
Tribunal ('Tribunal') adjudicating the disputes between the Petitioner and
Respondent No. 1 M/s. AviaExport.
2. It is stated that the Petitioner was to start a new venture of providing
helicopter services to various organizations in India and in particular to
the Oil and Natural Gas Commission ('ONGC'), a Government of India
undertaking, which required helicopters to transport its oil exploration
specialists and stores for off-shore operations in the Mumbai High Sea.
3. The essential requirements stipulated by the Director General of Civil
Aviation ('DGCA') for granting licence for flying an helicopter were as
follows:
(a) The helicopter should have emergency floatation gear; and
(b) It should meet the requirement to operate under outside air
temperature of 35-45 ºC.
4. The Petitioner entered into a contract with Respondent No. 1 for wet
lease of 1 MI-172 helicopter and for sale of 5 MI-172 helicopters.
Contract No.76044/32299 dated 28th April 1994 between the parties
provided "for delivery (by sale) of one MI-172 helicopter to Mesco
Airlines Limited, New Delhi India and lease out of one MI-172 helicopter
to Mesco Airlines Limited, New Delhi, India." Clause 1.1 stipulated that
"the duration of helicopter lease shall be two years. The lease period shall
commence from the day the said helicopter actually commences its
operation for the company." Under Clause 5.14, the date of signing the
said technical acceptance report was considered to be the date of putting
the MI-172 helicopter into operation with the company. However, the
leased helicopter was deemed to have been put into operation "only after
the receipt of necessary approval from the Director General of Civil
Aviation (DGCA) to fly the same in India." Clause 6.2 of the contract
indicated the maintenance schedule of the leased helicopter, and the
inspection time. For 25 hours, there was to be an inspection time of two
hours; for 50 flying hours, the inspection time was one day; for 100 hours,
two days and for 200 flying hours, the inspection time was 3 and half
days. Clause 6.3.1 required that the MI-172 helicopter would fly six days
per week, if weather conditions so permitted and according to the relevant
Indian Flying Rules. The number of working hours for the flying crew
was not to exceed 42 hours per week. Under Clause 6.1.1 for operation of
the leased helicopter, Respondent No. 1 was to provide licenced and
experienced pilots and a maintenance team. The said persons were to be
and remain employees of Respondent No. 1. Under Clause 9.1, the lease
operation and obligations of the parties under the contract "shall be
deemed automatically terminated as soon at the leased helicopters and the
Avia goods involved cross the Indian border". The leased helicopter was
to be operated "during two calendar years of putting it into operation and
upon termination of operation the duration of the contract is to be
extended for the period reasonably required for customer clearance and
demobilization of the helicopter, Avia goods involved and the contractor's
flight and maintenance crews." Clause 14 dealt with the terms of
payment for the leased helicopters. Under Clause 14.1.3 a fixed amount of
US $ 45500 (i.e. for 50 hours at the rate of USD 650) would be
automatically paid by the Petitioner at the end of each 30 day period from
the date of receipt of invoice for each 30 days period after the first three
months of operation till the end of lease period regardless of the actual
hours flown. Under Clause 17 the disputes were to be referred to an
arbitration committee of three Arbitrators appointed by Indian Council of
Arbitration ('ICA').
5. As regards the main contract, the Petitioner herein (Respondent before
the Arbitral Tribunal) was to deposit USD 70,000 with Respondent No. 1
(Claimant before the Arbitral Tribunal) one month prior to the delivery of
the leased helicopter. The said amount was to be deducted from the first
three monthly payment of USD 97500 and thereafter, till the end of the
leased period USD 45,500 was to be charged per month regardless of the
actual hours flown, however, an additional amount of USD 650 per hour
had to be paid if the helicopter flew hours in excess of the period stated in
paras 14.1.2 and 14.1.3 of the contract. All the spares and consumables
were to be supplied by Respondent No. 1 at its own expense. The lease
period was for two years. It was agreed that all fuel consumed during
flight and during any ground running was to be paid by the Petitioner. The
Petitioner was also required to provide a first class bank guarantee of 1
lakh USD in favour of Respondent No. 1 confirming the payments to
Respondent No. 1 of flying charges as agreed between the parties.
6. According to Respondent No. 1, the operation of the leased helicopter
commenced on 11th December 1994. Respondent No. 1 raised several bills
in regard to its balance dues. However, the Petitioner did not pay the
balance lease money and Respondent No. 1 raised a claim of USD
201,529.95 on account of lease money due from July to November 1996.
This formed subject matter of Claim No. 1 before the Arbitral Tribunal.
7. Claim No. 2 was for a sum of USD 1,29,750 in respect of the
helicopter that was sold. The price of the said helicopters was fixed at
USD 25,95,000. In terms of the agreement between the parties, 95% of
the total cost was to be paid by the Petitioner against presentation of the
shipping documents and the balance 5% against presentation of invoice
and technical acceptance report. According to Respondent No. 1, it
received only 95% of the price and the balance 5%, i.e., USD 1,29,750
has still not been paid to Respondent No. 1.
8. Claim No. 3 was for a sum of USD 3,96,017.56 arising out of the
Contract No. 76045/35699 dated 10th February 1995 whereby Respondent
No. 1 agreed to sell the Petitioner five helicopters at a price of USD
1,57,45,709.20. The price of each helicopter was USD 2,980,000 and the
total value of the contract therefore, was reduced to USD 1,57,45,709.20.
According to Respondent No. 1, the goods shipped were more than USD
2,15,385.87. Since the goods shipped were more than the value of the
actual invoices, Respondent No. 1 sent further invoices for payment.
9. According to Respondent No. 1, the Petitioner had to pay for the spare
parts which were supplied under the above contract to the extent of USD
6,62,755.63. Claim No. 4 related to the balance payment towards the
price for spare parts supplied to Respondent No. 1.
10. It was the case of Respondent No. 1 that Petitioner neither paid the
above amounts nor returned the leased helicopter. It is stated that the
leased helicopter was returned only in terms of the orders passed by this
Court. Further, as noted in the order dated 12th September 2000 of this
Court, Respondent No. 1 paid the entire dues of Rs. 13,06,820 to the
Airport Authority of India ('AAI') at the time of release of the helicopter.
11. Before the learned Tribunal, the Petitioner herein filed its counter
claims. The case of the Petitioner was that leased helicopter could be
made operational only on 24th May 1995. According to the Petitioner, due
to lack of maintenance, operations of the leased helicopter had come to a
grinding halt and the liquidated damages ('LD') had to be paid to Pawan
Hans. It is contended that the date of commencement of lease was 24th
May 1995 and not 11th December 1994. Respondent No. 1 had not
adjusted the amount for the period during which the helicopter was not
flying. It was claimed that what was due to Respondent No. 1 was USD
2,01,529.95 minus USD 40,932.00 = USD 1,60,660.95. Even this
payment was to be made by the Petitioner only after adjustment of the
losses incurred by Petitioner on account of breaches of the contract by
Respondent No. 1.
12. The Petitioner claimed Rs. 5,99,03,400 towards LD (Counter Claim
No.1), Rs. 13,06,820/- towards housing and parking charges of the leased
helicopter (Counter Claim No.2) and Rs. 5,00,71,600 towards losses due
to idling of helicopter during warranty period due to failed component and
their delayed/non-replacements (Counter Claim No.3). The Petitioner
also claimed interest @ 24% on the above amounts with past and
pendente lite interest (Counter Claim No.4) and Rs. 5 lakhs as cost of
arbitration (Counter Claim No.5). It was also prayed that the claim made
in Rupees may be converted into USD. Consequently, before the learned
Tribunal Respondent No. 1 filed four claims and the Petitioner filed five
counter claims. Affidavits by way of evidence were filed by both the
witnesses.
13. As regards Claim No. 1 by Respondent No. 1 for USD 2,01,529.95
towards balance lease rentals of the leased helicopter, the principal
question that arose for determination was the date from which the lease
rentals for the leased helicopter became payable. The Tribunal referred to
two letters dated 1st July 1995 and 7th August 1995 written by the
Petitioner to Respondent No. 1 admitting that the helicopter had started its
operation on 12th December 1994. By its letter dated 21st January 1996
written by the Petitioner to the Reserve Bank of India ('RBI'), the
Petitioner stated that the certificate of airworthiness was issued to the
helicopter on 11th December 1994 and that the period of lease commenced
on that date itself. The Tribunal also noted that during the month of May
1996 the Respondent No. 1 had raised a bill for 69.81 hours where the
actual flying hours were 72.03 hours. In March 1996 the helicopter had
flown for 81.40 hours whereas Respondent No. 1 raised the bill only for
77.52 hours. For August and September 1996 again the actual flying
hours were for more than the bills raised by Respondent No. 1. Even the
admitted liability for of USD 16,060.95 had not been paid by the
Petitioner to Respondent No. 1. It was held that since the Petitioner had
flown the helicopter for more than 70 hours per month which was the
minimum guarantee flying hours under Clause 14.1.3 of the contract,
there was no question of any deduction of USD 10,06,000.
14. Assailing the above finding, it was submitted by Mr. Harish
Malhotra, learned Senior counsel for the Petitioner, that Clause 6.3.1 of
the contract which related to the working hours for the flying crew was
mandatory and the helicopter could not fly beyond those hours per week.
He submitted that the DGCA granted final clearance for the helicopter
only from 24th May 1995. According to him, Clause 14.1.3 of the
contract dated 28th April 1994 talked of the liability of the Petitioner for a
fixed amount in respect of the actual number of flying hours. He referred
to the letter dated 19th April 1996 written by the Petitioner to Respondent
No. 1 and pointed out that Petitioner had stated clearly therein that the
helicopter had flown in the month of March 1996 for 77 hours 52 minutes.
The helicopter was grounded for five days from 6th to 10th March 1996
and therefore, an amount of USD 2274 had to be deducted. Likewise the
Petitioner by its letter dated 10th October 1996 pointed out that the
helicopter had been grounded for seven days from 4th to 9th September
1996 and on 15th September 1996 and accordingly claimed USD 10,612
as deduction. By a letter dated 5th November 1996 the Petitioner pointed
out that during October 1996 the helicopter had been grounded for six
days and USD 9096 was claimed as deduction.
15. Mr. Vineet Malhotra, learned counsel for the Respondents on the
other hand relied upon two letters of the Petitioner which clearly showed
that commercial operations of the leased helicopter had commenced on
12th December 1994. He referred to each of the flying logs of the
helicopter, which had been referred to in the majority Award, to show that
actual bills were raised by Respondent No.1 for less than the actual flying
hours. The Award of the dissenting member had accepted the contention
of the Petitioner herein that under Clause 6.3.1 there was a restriction on
the Petitioner flying more than 42 hours and therefore, the Petitioner was
justified in claiming reduction for the period of grounding of the
helicopter for more than what was authorized under the contract and
which deductions were never refuted by the Respondent No.1.
16. The above submissions as regards Claim No.1 have been considered.
The claim turns on the interpretation of two clauses of the contract, i.e.,
Clause 6.3.1 under which the number of flying hours for the crew was not
to exceed 42 hours and Clause 14.1.3 which talks of the minimum
guarantee to be paid by the Petitioner.
17. As regards the first plea of the Petitioner that lease had commenced
only from 24th May 1995, the majority Award correctly deduced from the
Petitioner's own letter dated 7th August 1995 to Respondent No. 1 and the
letter dated 10th December 1996 to the RBI that even according to the
Petitioner, commercial operation of the leased helicopter commenced on
12th December 1994. The relevant portion of letter dated 7th August 1995
reads as under:
"Following has been the schedule of the helicopter's operations in chronological order:
1. Operations commenced on 12th December 1994.
2. Helicopter in operation from 12th December 1994 till 23rd of February.
3. Helicopter grounded due to non-availability of the air (Capt. Said hospitalized) from 23rd February to 5th March 1995.
4. Helicopter grounded due to fitment of floatation system, ELT and Two ULBs from 5th March to 28th April 1995."
18. The cross-examination of the witness, Mr. D.V.S. Trehan, for the
Petitioner also indicates that the first flight of the leased helicopter did
take place on 11th December 1994. The relevant question and answers to
this regard as under:
"Q. Is it correct the first flight took place on 11th December 1994 in regard to the lease helicopter?
A. Yes. The first air test flight took place on 11th December 1994 as recorded in page 82 in Volume-I."
19. The view taken by the majority Award cannot therefore be said to be
contrary to the evidence placed on record.
20. As regards deduction claimed by the Petitioner, one has to go by the
actual flying log (Ex.30). The learned Tribunal has rightly pointed out that
examination of invoices does show that as compared to the actual flying
time, the total flying hours that were billed for each month from May
1995 onwards till November 1996 were less. As rightly held by the
majority Award, the claim for any further reduction was, therefore,
misconceived.
21. As regards the actual date of return of the leased helicopter, the letter
dated 10th December 1996 written by the Petitioner to the RBI indicates
that even as on that date, it was not yet returned. Para (b) of the said letter
reads as under:
"b. With regard to the period of lease, it is reiterated that the helicopter was received on 7th September 1994 and the certificate of airworthiness was issued to the helicopter on 11th December 1994. As per clause 1.1 of the agreement No. 76-044/32299 dated 28th April 1994 the period of lease commenced from the date of C of A which is 11th December 1994. As such the lease agreement expires on 10th December 1996. Therefore, we request that GR waiver for re-export of this helicopter may please be issued urgently."
22. The fact remains that the leased helicopter was not returned till much
later. This is evident from the letter dated 11th September 1998 written by
the Petitioner to the RBI requesting for GR waiver for re-export of leased
helicopter. It is not disputed that it was only after an application filed by
the Respondent No.1 under Section 9 of the Act in this Court that the
leased helicopter was returned. Further, there was no clause in the
contract that actually provided for reduction of lease rentals for non-flying
hours, or even for damages for days of the non-flying. The majority
Award in regard to Claim No. 1 was based on the correct interpretation of
the clauses of the contract as well as the evidence on record and,
therefore, calls for no interference.
23. Claim No. 2 concerned the helicopter which was to be sold under the
contract dated 24th April 1994. While the Petitioner paid 95% of the price,
it had not paid the balance amount. The admission of the Petitioner in the
written submission was that balance amount, i.e., 5% was payable only
after adjustment of its claims, i.e., losses and LD suffered by it. Since this
was virtually an admission by the Petitioner, the decision to allow Claim
No.2, in the majority Award was justified. No interference is called for
with the Award in regard to Claim No. 2.
24. Claim No. 3 related to the second contract dated 10th February 1995
in relation to the four invoices under which the Respondent No.1 claimed
USD 3,96,017.56. The Tribunal referred to the letter of agreement dated
18th February 1997 as well as the evidence of Mr. Nikolai V. Dulin on
behalf of Respondent No. 1. The contention of Mr. Harish Malhotra,
learned Senior counsel for the Petitioner was that no details were
furnished by Respondent No. 1 nor any evidence led by it in support of
the claim. Whatever was the value of the goods, as shown in the invoices,
was duly paid by the Petitioner. The addendums to the agreement were of
no consequence as they were consequently treated to be cancelled.
25. Mr. Vineet Malhotra, learned counsel for Respondent No.1, on the
other hand pointed out that liability to pay the amount under Claim No.3
was based on invoices and was admitted by the Petitioner in the letter of
agreement dated 18th February 1997.
26. A perusal of the letter of agreement dated 18th February 1997 shows
that the Petitioner admitted its liability in respect of the four invoices
under the contract dated 10th February 1995 for USD 3,96,017.56. This
document has been signed by both the parties. Mr. Dulin, a witness of
Respondent No. 1, in his evidence spoke about this letter. Mr. Dulin,
specifically referred to the addendum and in para 25 of the affidavit by
way of evidence referred to the amount due under the contract dated 10th
February 1995. In para 26 it was specifically stated that the said amount
was also admitted by the Petitioner in the letter of agreement dated 18th
February 1997. The cross-examination of Mr. Dulin does not indicate that
any question was asked in relation to the LOA. In the circumstances, this
Court finds no error having been committed by the majority Award in
allowing Claim No. 3 of Respondent No. 1.
27. Claim No. 4 related to the balance amount towards the price for spare
parts. A reference was made in this regard again to the LOA dated 18th
February 1997. Therefore, this claim had also to be allowed to the extent
of USD 6,39,911.47.
28. Counter claim No. 1 of the Petitioner was premised on the contention
that the lease of the helicopter commenced only on 24th May 1995 and
was valid up to 23rd May 1997. The evidence on record, as has already
been discussed, showed that even according to the Petitioner, the
operation of the helicopter commenced on 12th December 1994 and ended
in November 1996. Therefore, the very basis of this claim stood refuted
by the evidence of the Petitioner itself. Rejection of Counter Claim No. 1
by majority award cannot therefore be faulted.
29. Counter claim No. 2 was for parking charges of the helicopter.
Despite the lease having expired in November 1996, the helicopter was
not returned by the Petitioner. Ultimately, the helicopter was released to
Respondent No. 1 by this Court's order. At the time of release, the
parking charges had been paid by Respondent No. 1 to the AAI.
Consequently, there is no merit and Counter claim No. 2 was rightly
rejected by the majority Award.
30. As regards Counter claim No. 3 for losses due to idling of helicopter,
the majority Award pointed out that no evidence was placed on record by
the Petitioner to establish any part of this counter claim. In the absence of
any evidence in support of such counter claim, it was rightly rejected by
the majority Award. Counter Claim Nos. 4 and 5 are also rejected.
31. As regards claims of Respondent No. 1, the Tribunal has awarded
only 6% interest per annum which is reasonable. The cost of arbitration
awarded can also not be unreasonable.
32. No ground has been made out for interference with the impugned
Award of the Tribunal. The petition is dismissed with costs of Rs.
20,000/- which will be paid by the Petitioner to Respondent No. 1 within
a period of four weeks.
S. MURALIDHAR, J.
MARCH 29, 2012 rk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!