Saturday, 25, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sadhu Singh & Company vs National Projects Construction ...
2012 Latest Caselaw 2114 Del

Citation : 2012 Latest Caselaw 2114 Del
Judgement Date : 28 March, 2012

Delhi High Court
Sadhu Singh & Company vs National Projects Construction ... on 28 March, 2012
Author: S. Muralidhar
            IN THE HIGH COURT OF DELHI AT NEW DELHI
                                            (Not reportable)
                         CS(OS) 1421A/2006

                                          Reserved on: February 29, 2012
                                            Decision on: March 28, 2012

         SADHU SINGH & COMPANY                      ..... Petitioner
                      Through: Mr. Girish Aggarwal with
                               Mr. Abhishek Aggarwal, Advocates

                          versus

         NATIONAL PROJECTS CONSTRUCTION
         CORP.                                     ..... Respondent
                      Through: Mr. K.L. Budhiraja with
                               Mr. Neeraj Gupta and
                               Ms. Pruti Sharma, Advocates.

         CORAM: JUSTICE S. MURALIDHAR

                                   JUDGMENT

28.03.2012

1. These are objections by the National Projects Construction

Corporation Limited (NPCC) under Section 30 and 33 of the Arbitration

Act, 1940 ('Act') to an Award dated 5th June 2006.

2. Earlier an Award originally passed by the learned Arbitrator on 25th

April 1996 was questioned in CS (OS) No.1465A of 1996. By an order

dated 20th December 2005 while setting aside the said Award, as it was a

lump sum non-speaking award, the High Court remitted the case to the

Arbitrator for passing a fresh Award giving reasons for each of the claims

after giving an opportunity of hearing to both parties. Thereafter, the

impugned Award dated 5th June 2006 has been passed by the learned sole

Arbitrator giving detailed reasons in regard to each of the claims and

counter claims.

3. NPCC has challenged the award in respect of Claim Nos.1, 3 to 6, 17,

28, 36, 42, 44, 52 to 55, interest and Counter Claim Nos.1 to 4. As

regards 33 claims, the learned Arbitrator has awarded 'Nil' amount.

4. The work in question related to construction of South side portion of

the road over bridge at Seva Nagar. It was awarded by NPCC to M/s.

Sadhu Singh & Company ('Claimant') by Work Order No.186/402 dated

14th November 1981. The work was completed on 12th August 1982.

5. Claim No.1 was for a sum of Rs.10,42,426 plus interest on account of

increased cost due to increased input incurred by the Claimant due to

reduction in the available time for execution of certain elements of the

work necessitated by the delays.

6. The work was to be completed within 12 months from 8th April 1981

i.e. by 7th April 1982. The work was of national importance connected

with Asiad 1982. There were inevitable delays on account of non-

availability of site, delay in issue of materials by NPCC, delay in

providing designs and drawings, increase in the scope of work and

collapse of Span 4-B. The work was completed with a delay of about

seven months. Inter alia, the learned Arbitrator noticed that NPCC had

in its letter (Annexure 1/36) admitted that some portion of the site had

been handed over as late as February 1982. Further, some drawings were

given as late as on 1st April 1982. Documents placed on record by the

Claimant showed that a work order was placed on it by NPCC after the

collapse of Span 4-B for the erection and dismantling of centering of

Span 1A due to change of drawings. The learned Arbitrator, after noting

that the concrete along with reinforcement and erection of centering and

shuttering materials consequent upon collapse of Span 4-B would take

some time, held that the delay of two months claimed by the Claimant in

its correspondence with NPCC was not unreasonable. It was found that

the scope of work did increase by way of letter dated 7th August 1981

issued by NPCC. Further, if delays were occasioned by the Claimant,

NPCC ought to have taken action against it. The learned Arbitrator held

that the delay in execution of the work was on account of aforementioned

hindrances created by the NPCC.

7. The finding of the learned Arbitrator appears to be based on a careful

analysis of the evidence on record. It cannot be held to be perverse or

said to be suffering from an error apparent on the face of the record.

8. As was urged before the learned Arbitrator, it has been urged on

behalf of NPCC in this Court that no amount should have been awarded

under Claim No.1 on account of Clauses 18 and 20 of the Special

Conditions of Contract ('SCC'). It is also submitted that there could be

no claim entertained for extra wages in view of Clause 20 of the SCC.

Further, Section 73 of the Contract Act had no relevance as the claim did

not pertain to compensation for breach of contract.

9. The reasoning of the learned Arbitrator while awarding Rs.3,29,660 in

respect of Claim No.1, as contained in para 5.8.2 of the impugned Award

reads as under:

"5.8.2. The Claimant had done a total work of Rs.34,94,753 after 9-12-81 and Rs.16,83,247/- from 12-4-1981 to 9-12-81 and has claimed Rs.10,48,426/- plus interest on account of increased inputs after 9-12-81. Clause 18 and 20 of contract referred to by the respondent have been misinterpreted by the respondent and do not bar compensation due to the claimant on account of increased cost imposed on him due to respondent's failures and as such are not relevant to this claim. After going through the records made available I accept the claim of the claimant only to the extent of additional costs incurred by him due to increased inputs necessitated to speed up the work to make up for the lost time on the basis of certified details by the Chartered Accountant as given under:-

Incentives and overtime paid during the period claimed to speed up the work as per the Chartered Accountant's certificate Rs.2,99,691/-

         Labour Agent's commission

          limited to 10% of the above                Rs. 29,969/-
                                                    ------------------
                                                    Rs.3,29,660/-"

10. Once it was found that the delay caused was on account of actions of

the NPCC, then Clauses 18 and 20 of SCC would have to be interpreted

accordingly. While in terms of the original time schedule for completion

of the work no escalation was permitted under Clause 18 SCC, that

obviously cannot be the position where the delay was occasioned by the

NPCC. The Claimant had to engage additional labour to complete the

project as quickly as possible. Clearly therefore the claim for

compensation under Section 73 of the Contract Act was maintainable.

The learned Arbitrator has found that the Claimant did a substantial

amount of work after 9th December 1981 and based on payments made by

NPCC after 24th December 1981, the Claimant claimed 30% of the said

amount. The reliance on the certificate of the Chartered Accountant was

only to prove exact details concerning the overtime paid to the workmen

for speeding up the work.

11. This Court is unable to find any illegality having been committed by

the learned Arbitrator in deciding Claim No.1 in the above manner. The

objection in this regard is hereby rejected.

12. The next objection is to Claim No.3 which was for a sum of

Rs.2,19,694 plus interest. This was a claim basically for idle labour.

13. The Claimant was able to demonstrate that after the collapse of Span

4-B, the work was stopped by NPCC as drawings and designs had to be

revised as per the Inquiry Committee Report. This in turn compelled the

Claimant to keep the labour and supervisory staff idle during the period

from 10th December 1981 to 28th January 1982. The total expenditure

incurred worked out to Rs.1,91,325. The balance amount claimed under

this head was for the stoppage of work for short periods between 16th

April 1981 and 26th November 1981.

14. The learned Arbitrator discussed the entire evidence in detail. NPCC

objected to the above claim on the basis of Clause 29 of the Contract

which stated that the work allotted was of a total nature and the

contractor should make his own arrangements for haul roads, godowns

and such like requirements for execution at his own cost. The

interpretation placed by NPCC on Clause 29 was not accepted by the

learned Arbitrator. He reasoned as under:

"Clause 29 is not correctly interpreted by the Respondent. Since the Contract is based on Work Order with Schedule of quantities mentioning the items of work briefly, it is the intention of the Contract Clause 29 to make it clear that the rates quoted by the Claimant would include arrangements for haul roads, godowns and such like requirements needed to execute the work and nothing extra would be payable on this account. Such requirements would be done by the Claimant at its own cost. This has no relevance to the present claim. The respondent is

liable to reimburse the cost of idle labour to the Claimant as under:-

Amount claimed by Rs.2,21,916/- plus interest.

      the Claimant

      Amount awarded               Rs.1,91,325/-

      plus interest which is dealt with separately"


15. The objection of NPCC to Claim No.3 is without merit. Once the

learned Arbitrator found as it was NPCC which was responsible for the

hindrances caused including the delays on account of the collapse of

Span 4-B, the Claimant was entitled to be compensated for idle labour

which was one of the consequences. The learned Arbitrator has

entertained the claim for idle labour only for the period after 10th

December 1981.

16. Claim No.4 was for a sum of Rs.3,62,050 for the work done in

relation to the collapsed Span 4-B. Significantly, in a letter dated 24th

February 1983, NPCC informed the Claimant that its claim in this regard

"has already been sent to the Northern Railways for their consideration.

As this claim is linked with our claim to Railways, as per Clause 30 of

the Agreement condition, this can only be released after it is released to

NPCC." Therefore, NPCC initially did not deny its responsibility.

However, before the learned Arbitrator as well as this Court, NPCC has

placed reliance on Clause 29 to urge the rejection of the said claim. Once

the contract itself made it clear that the erection had to be strictly in

accordance with the directions of the Engineer In-charge ('EIC'), the

NPCC had to bear the consequence of the collapse of Span 4-B. The

Enquiry Committee which went into the said incident - recommended

that the entire centering be redesigned as such. Prior to the collapse, the

concreting was still in progress in the final stages and all the centering

and scaffolding as erected were still in position. The collapse occurred

due to collapse of centering. The responsibility for removal of the faulty

concrete as a result of collapse of Span 4-B could not obviously be

fastened upon the Claimant by resorting to Clause 29. Once it was

established that the very design was faulty, as per the Report of the

Enquiry Committee, the claim of the Claimant could not be rejected.

17. The objections as regards Claim No.4 are hereby rejected.

18. Claim No.5 was for a sum of Rs.13,52,020 which was for the extra

expenses incurred for the increased sleepers after the collapse of Span 4-

B. This again had to be allowed on the same reasoning as Claim No.4.

However, the learned Arbitrator has not allowed the entire claim. He has

concluded, after examining the evidence, that the increase in the number

of sleepers required to be compensated was 1600 but they were

retrievable and usable after use. Therefore, only a part of these additional

sleepers was awarded i.e. to the extent of 50%. As regards batons and

additional vertical supports, 10% was deducted for salvage. The Award

is a well reasoned one. There is no merit in the objection to the Award in

relation to Claim No.5.

19. Claim No.6 was for a sum of Rs.1,30,742 towards freight charges for

the cribs and centering material to be supplied by NPCC on hire. Again,

NPCC relied on Clause 29 of the SCC and Clause 5 of the SCC which

permitted recoveries to be made by it.

20. The learned Arbitrator discussed the above claim at great length with

particular reference to Annexure R-5 being the letter dated 5th April 1982

of NPCC. The reliance placed on Clause 29 was rejected since it did not

apply. Additional costs claimed by the Claimant were necessitated due to

the change in the programme which resulted in additional freight due to

delays caused by NPCC. The impugned Award in this regard is well

reasoned. The objection to the Award in respect of Claim No.6 is hereby

rejected.

21. Under Section II of the Claims, the Claimant submitted 46 claims.

Claim Nos. 7 to 52 were titled as "Extra Items". NPCC objected to the

impugned Award in respect of Claim No.17. The learned Arbitrator

explained his approach as under:

"Keeping in view all the records, pleadings, written and oral

submissions of both the parties I conclude that these claims have not been paid or adjusted or credited as stated by the respondent. I also conclude that the rates already accepted by the parties in terms of Annexure II/14 and II/15 are reasonable and allow claimant for these extra items at these rates. I restrict the payment to the Claimant of these claim items, to the respondent's recorded quantities in the Measurement Book and since these have not been paid I treat these as payable to the claimant by the respondent. Accordingly I proceed Claim wise first in respect of Claim Nos.7, 8, 9, 10, 11, 12, 15, 17, 18, 19 and 20 as under. Other extra item claim are dealt separately later."

22. Thereafter, with particular reference to Claim No.17, which was for

providing water spouts, the learned Arbitrator awarded Rs.1600 as per

the record of measurement of NPCC itself. This Court is unable to find

any illegality in the above approach of the learned Arbitrator or the

decision in respect of Claim No.17.

23. Claim No.28 was for rectification of the shuttering plates. According

to NPCC, under Clause 6 of the SCC the Claimant was required to return

the shuttering plates to the NPCC in good usable condition. It is

submitted that since the Claimant had admitted that all drawings as well

as the site were handed over in June 1981, the claim was untenable.

24. The reasoning of the learned Arbitrator in this regard is as under:

"The claimants in their rejoinder have stated that drawings for

pre stressed concrete beams had not been received and shuttering for six numbers bottoms of beams and two number sides of the beams had been fabricated as directed. Design of shuttering had been changed. Shuttering had been rectified on the receipt of the drawings for pre-stressed beams, due to change in design, Rectification of shuttering under the circumstances is an additional item payable separately. The claimants have referred to their letter to the respondents written on 14-8-1981 (Annexure II/34), 17-8-1981 (Annexure II/35) and 31-8-1981 (Annexure II/36).

The respondent in its letter Annexure II/14 has not rejected this claim but recorded as approximately two beam fabrication "details of work done awaited from contractor."

I agree with the Claimant that this item is payable to him and is not covered as stated by the respondent in its reply. This item has arisen due to change in the design of beams by the respondent. After considering all the records made available and oral submissions and considering the extent of rectification required and the wastage on account of rectification I allow Rs.26,100 to be paid by the respondent to the claimant plus interest for two beams fabrication."

25. This Court is unable to find any illegality in the learned Arbitrator

allowing Claim No.28 to the above extent.

26. The next objection is in respect of the Award of Claim No.36

towards railing. The design of the precast hand railing had undergone

change. The changed design was complicated and involved complicated

shuttering. The claim for extra item was on this account. The learned

Arbitrator, on examination of the evidence, found that the drawings

which were issued six months after commencement of work were more

complicated as curved shuttering was involved. After adjudicating the

rate fixed for items, the learned Arbitrator considered a sum of

Rs.1,03,346.50 as being reasonable. After accounting for the sum

already included in the final bill on this account, an additional amount of

Rs.49,924 plus interest was held payable by NPCC to the Claimant.

27. No fault can be found with the above reasoning or conclusion of the

learned Arbitrator which is based on the evidence on record.

28. The next objection is to the Award in respect of Claim No.42, being

the extra item on account of erection of precast end blocks for Span 8B.

The learned Arbitrator found, as a matter of fact, that the said item had

not been included in the final bill and no payment towards the said item

had been made by the NPCC. The learned Arbitrator allowed Rs.330 per

metric tonne for the said item and this worked out to Rs.1188. The

objection in regard to Claim No.42 is rejected.

29. Claim No.44 was towards supply of labour. A bill amounting to

Rs.8657 had been submitted on 4th February 1983. A further bill of

Rs.958.30 was submitted on 4th February 1983 for skilled and unskilled

labour. The documents were produced before the learned Arbitrator and,

on checking the documents, he held the claim to be proved. Again, there

is no merit whatsoever in the said objection.

30. Claim No.52 was for refund of excess recovery made for supply of

R.S.J. for leveling of shuttering and centering in the sum of Rs.4750 plus

interest. The claim was allowed after examining the records. It was held

that excess recovery of Rs.4,000 was refundable to the Claimant. Again,

there is no ground made out for setting aside the Award in respect of

Claim No.52.

31. Claim No.53 was for refund of security deposit for labour in the sum

of Rs.3750. The reasoning of the learned Arbitrator was under:

"I have examined the Final bill filed by the respondent on 3.5.1991 and have noticed that a recovery of legal expenses amounting to Rs.9196.00 has already been made from the claimant therein. Respondent's contention that the Security Deposit is adjusted legal expenses incurred by respondent is neither supported by any document nor reflected in the final bill. The respondent is also not denying that an amount of Rs.3,750.00 was deducted as Security Deposit of 8th running bill of the Claimant.

In view of the above I disagree with the respondent's contention and Claimants are entitled for refund of this Security Deposit.

I therefore, allow the Claimants a refund of Rs.3,750/- payable by the respondent plus interest which is dealt separately."

32. This Court is unable to find any error having been committed by the

learned Arbitrator in regard to Claim No.53.

33. Claim No.54 was for interest on mobilization advance in the sum of

Rs.15,830. The reasoning of the learned Arbitrator was as under:

"I have gone through all the records placed before me and the oral submissions and I conclude that the respondent as per contract was required to pay the claimant twice every calendar month (Special Condition no.4), one measured bill within first 10 days and other advance bill in third week of every month. The claimant's advance bearing interest was adjusted with the first bill. The claimant has rightly asked for refund of excess recovery of interest due to delay in payments. Claimant has worked out the details beyond 10th of each month the due date of payment vis-à-vis actual date of payment which has been checked to be correct as per records seen. I therefore allow refund of Rs.15,830/- plus interest. Issue of interest is dealt separately."

34. No error can be found in the above reasoning or conclusion of the

learned Arbitrator. It is based on the evidence on record. The objection

in this regard is rejected.

35. The next objection is to the Award in respect of Claim No.55 in the

sum of Rs.2,25,022.83 as regards the balance amount towards the final

bill. The learned Arbitrator has carefully analysed the evidence on record

and held that there was no justification in the NPCC withholding a sum

of Rs.2,21,875.98 from the final bill. Likewise, the withholding of

Rs.3,146.85 pertaining to repairing of the wearing coat was also not held

to be justified. The objection in this regard is rejected.

36. As regards the award of interest it is submitted that the learned

Arbitrator had no jurisdiction to award pendente lite and future interest.

Alternatively, it is submitted that the rate of interest awarded is on the

higher side. The learned Arbitrator allowed 12% interest during the pre-

suit and pendente lite periods and future interest at 18% per annum from

the date of the Award till date of payment.

37. Going by the decision of the Supreme Court in Krishna Bhagya Jala

Nigam Ltd. v. G. Harischandra Reddy, AIR 2007 SC 817, this Court

considers the interest rate to be on the higher side considering that the

claim is an old one and the litigation has been pending for over three

decades. Accordingly, the interest rate is reduced to 9% per annum

simple interest at all stages, pre-reference, pendente lite and post-Award.

38. Counter claim No.1 by the NPCC was on account of losses suffered

by it due to collapse of Span 4-B. There is no justification whatsoever

for the NPCC to require the Claimant to compensate NPCC for this loss.

In fact, the letter dated 22nd April 1983 of the NPCC showed that it had

preferred this very claim from the Railways. The Enquiry Committee's

Report affirmed that the design of Span 4-B was faulty and required to be

revised. Consequently, the rejection by the learned Arbitrator of Counter

Claim No.1 cannot be said to be erroneous.

39. For the same reason, Counter Claim No.2 of NPCC against the

Claimant on account of damages for loss of reputation and prestige

caused to NPCC on account of collapse of Span 4-B cannot be allowed.

40. Counter claim No.3 was for Rs.1,96,250 being the amount incurred

for repairs done by the Railway Department to rectify some defects and

deficiencies noticed in the work. The learned Arbitrator found that

NPCC failed to show which defect in the work was pointed out by it or

the Railways. No letter or document was written by the NPCC to the

Claimant to this effect during the period of construction or during the

period of six months after completion. Accordingly, the Counter Claim

No.3 was rightly rejected by the learned Arbitrator.

41. Counter Claim No.4 was for a sum of Rs.91,244.24 on account of

failure of the Claimant to return certain tools and plants. The learned

Arbitrator observed that NPCC had not proved which plants and tools

were retained by the Claimant. No details were provided. The rejection

of Counter Claim No.4 was also, therefore, not erroneous.

42. With the counter claims having been rightly rejected, the question of

payment of interest thereon did not arise.

43. For the aforementioned reasons, this Court upholds the impugned

Award of the learned Arbitrator with only one modification regarding the

rate of interest. The rate of interest on the sums awarded by the learned

Arbitrator is uniformly reduced to 9% simple interest per annum for all

the periods for which the interest has been awarded. Subject to this one

modification, the impugned Award is upheld as such.

44. The impugned Award, modified to the above limited extent, is made

rule of the Court. The suit is disposed of. Decree sheet be drawn

accordingly.

S. MURALIDHAR, J.

March 28, 2012 s.pal

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter