Citation : 2012 Latest Caselaw 2093 Del
Judgement Date : 27 March, 2012
IN THE HIGH COURT OF DELHI AT NEW DELHI
O.M.P. 158/2009
Reserved on: 28th February 2012
Decision on: 27th March 2012
DELHI DEVELOPMENT AUTHORITY ..... Petitioner
Through: Mr. Bhupesh Narula, Advocate.
Versus
M/S JAGDISH CHANDER KHANNA AND SONS
ENGINEERS AND CONTRACTORS ..... Respondent
Through: Mr. S.K. Jain with Mr. Rajeev
Kapoor, Advocates.
AND
O.M.P. 159/2009
DELHI DEVELOPMENT AUTHORITY ..... Petitioner
Through: Mr. Bhupesh Narula, Advocate.
Versus
M/S JAGDISH CHANDER KHANNA AND SONS
ENGINEERS AND CONTRACTORS ..... Respondent
Through: Mr. S.K. Jain with Mr. Rajeev
Kapoor, Advocates.
CORAM: JUSTICE S. MURALIDHAR
JUDGMENT
27.03.2012
1. These are two petitions under Section 34 of the Arbitration and
Conciliation Act, 1996 ('Act') against an Award dated 31st October 2008
passed by the sole Arbitrator in the disputes arising between the Delhi
Development Authority ('DDA') and M/s. Jagdish Chander Khanna & Sons
Engineers and Contractors ('Claimant') which was awarded by the DDA for
the work of construction of a Local Shopping Centre at Ashok Vihar, Phase-
III, Pocket-B under the Agreement No.2/EE/ND-10/DDA/94-95.
2. The date of the start of the work was 23rd June 1994. It was to be
completed within 15 months i.e. by 22nd September 1995. According to the
Claimant the work remained incomplete as a result of the breaches
committed by the DDA. The DDA rescinded the contract by a letter dated
15th May 1996 and decided to get the remaining work executed at the risk
and cost of the Claimant. Compensation in the sum of Rs.3,69,578 was also
levied. Before the learned sole Arbitrator the Claimant filed seven items of
claim and the DDA filed five of its counter-claims against the Claimant.
3. By the first impugned Award, disposing of the Claimant's claims, the
learned Arbitrator awarded against Claim No.1, a sum of Rs.21,125 as part
rates of different items of work. Against Claim No.2 for a sum of Rs.46,519
towards the work done but not paid, the Claimant was awarded Rs.30,208.
Against Claim No.3 for Rs.52,000 as part rates in extra items, the learned
Arbitrator awarded Rs.11,493. Against Claim No.4 for refund of security
deposit of Rs.60,000 was allowed. Against Claim No.5 for Rs.80,000 under
Clause 10-CC, the learned Arbitrator awarded Rs.79,437. Against Claim
Nos.6 & 7 a for sum of Rs.2,50,000 on account of loss and profit and
Rs.2,00,000 on account of damages, the learned Arbitrator awarded
Rs.4,17,263. Against Claim No.8, the learned Arbitrator awarded simple
interest at 12% per annum pendente lite together with costs of Rs.50,000.
4. By the second impugned Award in deciding the DDA's claims, the
learned Arbitrator rejected Claim No.1 for recovery of Rs.15,01,011 on
account of differential increase of the balance work to be done at the risk
and cost of the Claimant. Claim No.2 for Rs.24,053 for defective work was
also rejected. Claim No.3(a) for sum of Rs.1,62,185 on account of tor steel
not returned by the Claimant and Claim No.3(b) for Rs.4,000 on account of
cement used in the work more than the permissible limit, were also rejected.
He also rejected DDA's Claim No.4 for the sum of Rs.9,000 on account of
non-deployment of graduate engineer and Claim No.5 for the sum of
Rs.3,69,578 towards the compensation levied under Clause 2 of the
agreement were also rejected.
5. It is contended by the DDA that the site for work had been handed over
to the Claimant on 23rd June 1994. The Claimant was to construct a godown
for the stocking of cement, steel etc. and to make arrangement of water for
drinking and construction purposes. The architectural and structural
drawings were made available to the Claimant. However, the Claimant
failed to show the required progress of the work. Despite directions of the
Executive Engineer ('EE') on 2nd September 1995, the Claimant did not
submit a programme for completion of the work. The inspection by the
Chief Engineer (Quality Control) revealed that the work was extremely
poor. The work performed was highly defective. These were communicated
to the Claimant by the letter of the EE dated 29th February 1996. The
Engineer In-charge ('EIC') inspected the site on 5th October 1995.
According to the DDA on 1st December 1995, the Claimant abandoned the
work site and had by then completed only 10% of the work. On 13th March
1996, the EE issued a show cause notice to the Claimant as to why the work
should not be rescinded and got executed at the risk and costs of the
Claimant. A final notice was served on 12th April 1996. Finally, the contract
was rescinded on 15th May 1996.
6. The above facts are, however, disputed by the Claimant. It is pointed out
that no site was handed over to the Claimant and only a site was shown on
23rd June 1994. Even till 25th January 1995 a clear site was not handed over.
Therefore, there was a wastage of six months. There was no possibility of
starting the work before 3rd December 1994. According to the Claimant the
provisional extension of time granted to it was unilateral without any
request made in that behalf by it to the DDA. It was denied that the
Claimant had abandoned the work site. The receipt of the letter dated 21st
March 1996 is also denied.
7. The learned Arbitrator observed that the work had to be executed as
multi-storey building and single storey stalls. The failure on the part of
DDA to issue to structural drawings of the site resulted in non-completion
of the work. Consequently, the original time limit of 15 months for
completion of the work could not be adhered to. The record also showed
that provisional extension of time was granted by the DDA to the Claimant
just to keep alive the contract so that it could ultimately terminate the
contract.
8. As regards Claim No.1, the learned Arbitrator held that DDA failed to
issue the complete structural drawings in good time and this resulted in the
non-completion of the work. This is a finding of fact. The DDA has been
unable to show when the complete structural drawings were ultimately
issued, if at all, to the Claimant. The Award cannot be said to be contrary to
the evidence on record or to the contractual provisions. The reliance placed
by the DDA on Clause 13 of the agreement was misconceived, since the
question was not one of change of drawings but non-supply of the complete
structural drawings. As there had been extension of time granted by the
DDA till 31st May 1996 it could not be said that time was still the essence of
the contract. As regards Claim No.1, it was on the basis of the admission of
the DDA that the sum of Rs.21,125 was withheld from the Claimant's bill.
After rescinding the contract, the DDA failed to undertake joint
measurement of the work done in the presence of the Claimant. The
measurements were recorded by DDA unilaterally. In the circumstances,
while the DDA's claim in this regard was rejected, the admitted sum of
Rs.21,125 was awarded to the Claimant. The above findings are factual,
based on the evidence on record, and do not call for interference.
9. Claim No.2 was awarded on the basis of an admission by the DDA that
Rs.30,208 was due to the Claimant. Claim No.3 for part rates in extra items
was allowed only to the extent of 11,493 to the extent admitted by the DDA.
Claim No.4 towards refund of security deposit had to follow the finding that
the termination of the contract by the DDA was illegal. As Regards Claim
No.5 on account of Clause 10-CC, DDA objected only to the index adopted
by the Claimant. However DDA did not supply the correct index. The
learned Arbitrator found that the Claimant was entitled to Rs.79,347. The
award of Rs.4,17,263 against Claim No.6 (loss of profit) and Claim No.7
(damages) was also based on a proper analysis of the evidence on record.
The reasons given are cogent. This Court, therefore, does not find any
ground having been made to set aside the impugned Award to the extent it
allows the claims of the Claimant.
10. As regards the claim of the DDA, Claim No.1 for the differential
increase of balance work had to be rejected in view of the finding that it was
the DDA which was in breach of the agreement and had illegally terminated
the contract. As regards claim No.2 for defective work, the learned
Arbitrator found that the inspection was carried out by the SE on 16th
August 1995 and the reduction item was approved by the SE on 22nd
September, 1999. It was conveyed to the Claimant on 8th October 2008.
DDA failed to justify the claim and even in the demand notice it was not
mentioned. Rejection by the learned Arbitrator of this claim cannot be held
to be unjustified. DDA's Claim Nos.3(a) & (b) about the Claimant not
handing back for steel used it was held that the notice required to be issued
under Clause 42 of the agreement was in fact not issued. Consequently, the
rejection of this claim also cannot be held to be unjustified. As regards
Claim No.4 of the DDA, the learned Arbitrator found that the site order
book did not record anything about the non-deployment of a graduate
engineer and, therefore, not recorded in the 4th R.A. bill which was paid. As
regards Claim No.5, since it was concluded that the termination of the
contract was illegal, the question of awarding compensation to the DDA did
not arise. This finding too does not call for interference.
11. This Court finds no ground having been made out by the DDA for
interference with either of the impugned Awards. Both petitions are
accordingly dismissed but in the circumstances, no order as to costs.
S. MURALIDHAR, J.
MARCH 27, 2012 bs
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!