Citation : 2012 Latest Caselaw 2004 Del
Judgement Date : 23 March, 2012
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 23rd March, 2012
+ LPA No.553/2010
% GOVT. OF NCT OF DELHI & ORS. ....Appellants
Through: Ms. Sangeeta Sondhi, Mr. Sanjeev
Narula & Mr. Ashish Virmani, Adv.
Versus
NEW VARIETY TENT HOUSE & ANR ..... Respondents
Through: Mr. J.P. Sengh, Sr. Adv. with Mr.
Mohit Gupta, Sumit Batra & Ms.
Ankita Gupta, Advs. for R-1&2.
CORAM :-
HON'BLE THE ACTING CHIEF JUSTICE
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
JUDGMENT
RAJIV SAHAI ENDLAW, J.
1. This Intra-Court appeal impugns the order dated 23 rd March, 2010 of
the learned Single Judge allowing W.P.(C) No.7225/2007 preferred by the
respondents and consequently directing the appellants to release a sum of
`67,57,072/- to the respondents; the appellants have also been burdened
with interest @ `10% per annum for delay in payment and with costs.
Notice of this appeal was issued and the operation of the impugned order
stayed. The writ record has also been requisitioned. The counsels have been
heard.
2. The respondents had filed the writ petition pleading, that they were /
are engaged in the business of supplying tents / tin sheds and other furniture
on hire; that in the years 1998 to 2000, the Directorate of Education of the
appellants had placed an order on the respondents for erection of tin shed
structures in some of the government schools in Delhi; similar orders were
placed on other tent houses also including one Punjabi Tent House; that
during the year 1999-2000 bills for `4,30,943/-, `57,89,526/- and
`5,30,603/- i.e. for a total sum of `67,57,072/- were raised by the
respondents; that inspite of repeated requests and reminders of the
respondents and promises to pay, the bills were not cleared and the
payments withheld ―due to some audit objections...... during the special
audit conducted in the year 2000‖ ; that the appellants have however never
denied their liability to the respondents; that the respondents on 6 th May,
2004 had made a complaint to the Public Grievances Commission also; that
though payments had been denied to the respondents but the appellant in
pursuance to W.P.(C) No.5900/2003 filed by said M/s. Punjabi Tent House
had paid the withheld amount; that the respondents were similarly placed as
M/s. Punjabi Tent House (supra). Mandamus was thus sought for directing
the appellant to release the payment of `67,57,072/-.
3. Though the respondents had pleaded that the work order aforesaid
was placed on them pursuant to a tender enquiry but along with the writ
petition filed only tender notices and nothing else to show that respondents
had participated in the tender or that any order was so placed on them.
Again, though the respondents claimed that an agreement in this regard had
been executed but only a copy of a draft agreement was filed along with the
writ petition. Though photocopies of the bills raised were filed but the same
do not contain any acknowledgment even of receipt thereon. The copies of
few letters claimed to have been written were filed but the same are again
without any official stamp acknowledging receipt. The respondents however
along with the writ petition filed a copy of the response dated 1 st April, 2003
of the appellants to an RTI query but only to the effect that ―the pending
payment of M/s New Variety Tent House has been withheld due to some
audit objections of Dte. of Audit raised during the special audit conducted
in the year 2000 and the same will be considered after the settlement of
Audit paras by the Dte. of Audit‖. Another response dated 21st May, 2003 to
the same effect to another RTI query was also filed along with the writ
petition.
4. The appellant in its counter affidavit to the writ petition before the
learned Single Judge pleaded that the writ petition qua the contractual claim
was not maintainable; that the appropriate remedy was to file a suit for
recovery of money; that the remedy of suit had got barred by limitation; that
the payments claimed pertained to the period 1999-2000 claim wherefor in
writ petition filed in the year 2007 was palpably barred by time. On merits,
though the receipt of three bills aforesaid for `67,57,072/- was not denied, it
was pleaded that no assurance for payment had been meted out at any time.
5. The learned Single Judge impleaded the Directorate of Audit also as
respondent no.4 to the writ petition. A counter affidavit was filed by the
Controller of Accounts (Audit) of the GNCTD also. It was pleaded therein
that complaints had been received from various schools regarding poor
quality of tents and tin sheds for students; on the basis of the said
complaints a special audit was done and report thereof sent to the
Department of Education undercover of letter dated 14 th September, 2000;
that it was for the Department of Education to see whether any lapse existed
in the quality of the work done.
6. The learned Single Judge vide order dated 29 th January, 2010
requisitioned the audit report and found that there were two specific
objections in relation to the respondents; firstly that the work was awarded
to the respondents without approval of Competent Authority and secondly
that there were complaints regarding poor quality of work and which the
Director of Audit had asked the Directorate of Education to consider.
7. The learned Single Judge in the order impugned before us found that
the Directorate of Education without conducting any inquiry into the
complaints was not justified in withholding payments; that there was
nothing to show that any such inquiry regarding the quality of work had
been conducted.
8. The learned Single Judge further held that non-obtaining prior
approval from the Competent Authority could not erase the entire work
done by the respondents and the respondents could not be denied payment
for omission on the part of appellants to take such approval.
9. Qua the plea of the appellants herein of the claim being barred by
limitation, the learned Single Judge observed that the appellants in the reply
dated 3rd July, 2007 to yet another RTI query by the respondents had not
taken the plea of limitation. It was further held that the appellants were
unable to satisfactorily explain as to how the case of the respondents was
different from the case in W.P.(C) No.6644/2007 in which payments had
been directed to be made.
10. Of the three bills, seeking direction for payment of which the writ
petition was filed, two are dated 27th April, 1999 and the other, 23rd July,
1999. The same are for providing tin structures in government schools from
6th July, 1998 to 31st July, 1998, 1st August, 1998 to 30th April, 1999 and
from 1st May, 1999 to 30 th June, 1999 respectively. In the absence of
anything to show otherwise, under Article 12 of the Schedule to the
Limitation Act, 1963, the limitation for recovery of the said hire charges
was three years from the date when the hire became payable i.e. from the
date of the bill. The said period of three years expired with respect to the
first two bills on 26th April, 2002 and for the third bill on 22 nd July, 2002.
There is nothing to show that the date of payment was agreed to be any
other. The writ petition seeking mandamus was filed only on 28 th
September, 2007. There is nothing to show any acknowledgment of liability
within the meaning of Section 18 of the Limitation Act.
11. We have thus wondered whether money claim, suit for which had
become barred by time/limitation, can be allowed in writ jurisdiction. The
answer obviously is no. The learned Single Judge has brushed aside the
valid plea of the appellant of limitation by referring to the directions issued
in the writ petition being W.P.(C) No.6644/2007 filed by one M/s Ramesh
Kumar Brothers. We are however unable to agree with the said reasoning.
Firstly merely because the time barred claim of another has been allowed
does not constitute a reason for allowing another time barred claim. More
important, there is no ‗decision' in the said order on the aspect of limitation.
Also, a reading of the order shows that the liability therein was
unequivocally admitted and at least part of the amount claimed was the
‗security amount'. It is not so in the present case.
12. The respondents had filed the writ petition agitating the claim stated
to be at par with that of M/s Punjabi Tent House. However Punjabi Tent
House had filed their petition in the year 2003 and the same was allowed on
05.08.2004. The respondents waited for more than three years thereafter
also, for filing their petition. Even if it is to be held that the claim of M/s
Punjabi Tent House was also barred by limitation, wrong decision and more
so on the point of law, as the plea of limitation in the present case is, cannot
constitute a precedent for allowing other time barred claims.
13. The counsel for the appellants has cited State of Madhya Pradesh v.
Bhailal Bhai AIR 1964 SC 1006 to contend that though the provisions of
Limitation Act do not apply to the granting of relief under Article 226
however the maximum period fixed by the Legislature as the time within
which the relief by a suit in a civil court must be brought may ordinarily be
taken to be a reasonable standard by which delay in seeking remedy under
Article 226 can be measured. Reliance is also placed on Binny Ltd. v. V.
Sadasivan AIR 2005 SC 3202 in support of the proposition that contractual
obligations are beyond the zone of judicial review.
14. We may however notice that the judgment (supra) in Bhailal Bhai
has been overruled on another aspect, in Mafatlal Industries Ltd v Union of
India (1997) 5 SCC 536. We may further notice that the Supreme Court in
Tilokchand Motichand v H.B. Munshi (1969) 1 SCC 110 has in the
majority judgment held that the extraordinary remedies under the
Constitution are not intended to enable the claimant to recover monies, the
recovery of which by suit is barred by limitation. It was further held that
where the writ remedy under Article 226 corresponds to a remedy in an
ordinary suit and the latter remedy is subject to the bar of a statute of
limitation, the Court in its writ jurisdiction acts by analogy to the statute,
adopts the statute as its own rule of procedure and in the absence of special
circumstances imposes the same limitation on the summary remedy in writ
jurisdiction.
15. The Supreme Court in Kerala Agro Machinery Corporation Ltd V.
Bijoy Kumar Roy (2002) 3 SCC 165 held that the stage of proceeding has
no relevance so far as the question of limitation is concerned. Similarly in
S.S.Balu V. State of Kerala (2009) 2 SCC 479, it was held that relief on the
ground of delay alone can be denied even though relief is granted to other
person similarly situated.
16. We may also record that for extension of limitation, no reliance can
be placed on response to RTI query. In the present case, the response is not
found to contain any admission of liability so as to extend the period of
limitation.
17. The counsel for the respondents has referred to:-
a. Shankara Co-op. Housing Society Ltd. v. M. Prabhakar AIR 2011
SC 2161 - but which is not found to be applicable;
b. Union of India v. Tantia Construction Pvt. Ltd. 2011 (4) SCALE
745 laying down that the alternative remedy of arbitration is not an absolute
bar to the invocation of writ jurisdiction;
c. Zonal Manager, Central Bank of India v. Devi Ispat Ltd. (2010) 11
SCC 186 to the same effect;
d. Food Corporation of India v. SEIL Ltd. (2008) 3 SCC 440 - on the
scope of interference in writ jurisdiction in contractual matters;
e. Noble Resources Ltd. v. State of Orissa (2006) 10 SCC 236 also
laying down that contractual matters are not totally beyond the scope of
judicial review;
f. A. Angoubi Singh v. State of Manipur AIR 2005 Gauhati 92 - where
direction for discharging contractual obligations was issued in writ
jurisdiction;
g. ABL International Ltd. v. Export Credit Guarantee Corporation of
India Ltd. 2003 (10) SCALE 815 - on the disputed questions of fact
capable of being gone into in writ jurisdiction;
h. Ganga Retreat & Towers Ltd. v. State of Rajasthan (2003) 12 SCC
91 also found to be not applicable;
i. Harbanslal Sahnia v. Indian Oil Corpn. Ltd. (2003) 2 SCC 107 -
also on the rule of alternative remedy being a rule of discretion;
j. Smt. Gunwant Kaur v. Municipal Committee, Bhatinda (1969) 3
SCC 769 laying down that the High Court in exercise of powers under
Article 226 has jurisdiction to determine questions of fact even if they are in
dispute.
We are afraid none of the aforesaid judgments come to the rescue of
the respondents on the aspect of limitation.
18. We may notice that the Apex Court recently in Godavari Sugar Mills
Ltd. Vs. State of Maharashtra (2011) 2 SCC 439 after a consideration of
the entire case law including Suganmal Vs. State of Madhya Pradesh AIR
1965 SC 1741, U.P. Pollution Control Board Vs. Kanoria Industrial Ltd.
(2001) 2 SCC 549 and ABL International Ltd. (supra) , made the legal
proposition clear as under:-
(i) Normally, a petition under Article 226 of the Constitution of
India will not be entertained to enforce a civil liability arising
out of a breach of contract or a tort to pay an amount of money
due to the claimants. The aggrieved party will have to agitate
the question in a civil suit. But an order for payment of money
may be made in a writ proceeding, in enforcement of statutory
functions of the State or its officers;
(ii) If a right has been infringed--whether a fundamental right or a
statutory right and the aggrieved party comes to the Court for
enforcement of the right, it will not be giving complete relief if
the Court merely declares the existence of such right or the fact
that existing right has been infringed. The High Court, while
enforcing fundamental or statutory rights, has the power to give
consequential relief by ordering payment of money realized by
the Government without the authority of law;
(iii) A petition for issue of writ of mandamus will not normally be
entertained for the purpose of merely ordering a refund of
money, to the return of which the petitioner claims a right. The
aggrieved party seeking refund has to approach the Civil Court
for claiming the amount, though the High Courts have the
power to pass appropriate orders in the exercise of powers
conferred under Article 226 for payment of money;
(iv) There is a distinction between cases where a claimant
approaches the High Court seeking the relief of obtaining only
refund and those where refund is sought as a consequential
relief after striking down the order of assessment etc. While a
petition praying for mere issue of writ of mandamus to the
State to refund the money alleged to have been illegally
collected is not ordinarily maintainable, if the allegation is that
the assessment was without a jurisdiction and the tax collected
was without authority of law and therefore the respondents had
no authority to retain the money collected without any
authority of law, the High Court has the power to direct refund
in a writ petition;
(v) It is one thing to say that the High Court has no power under
Article 226 to issue a writ of mandamus for making refund of
the money illegally collected. It is yet another thing to say that
such power can be exercised sparingly depending on facts and
circumstances of each case. For instance, where the facts are
not in dispute, where the collection of money was without
authority of law, there is no good reason to deny a relief of
refund to the citizens;
(vi) Where the lis has a public law character or involves a question
arising out of public law functions on the part of the State or its
authorities, access to justice by way of a public law remedy
will not be denied.
19. In our view the present case does not fall in any of the categories
enumerated above. As far as reliance on ABL International Ltd. is
concerned, a reading of the said judgment shows that the Court on a perusal
of the facts therein found no question which required any oral evidence and
found the dispute in that case to be only as to the interpretation of the
various clauses of the policy subject matter of that petition. However that is
no so here.
20. The Supreme Court in Jagdish Mandal Vs. State of Orissa (2007) 14
SCC 517 held that the power of judicial review will not be permitted to be
invoked to protect private interest at the cost of public interest or to decide
contractual disputes. It was also held that a writ petition in the contractual
matters would be entertained only if there is an element of public interest in
the litigation. No such element of public interest is found in the present case.
21. Recently, the Apex Court in Kisan Sahkari Chini Mills Ltd. Vs.
Vardan Linkers AIR 2008 SC 2160 also reiterated that public law remedy
under Article 226 of the Constitution of India is not available to seek
damages for breach of contract or specific performance of contract unless
the contractual dispute has a public law element. Reference may also be
made to Binny Ltd. Vs. V. Sadasivan (2005) 6 SCC 657 where the Apex
Court held that even in the matter of termination of employment, no public
law element is involved and the remedy of the employees is under the civil
or labour law only. It was further held that the powers under Article 226 are
to be exercised by applying the Constitutional provisions and judicial
guidelines and violation, if any of the fundamental rights and the Court
would be reluctant to exercise the power of judicial review in rights on the
basis of contracts. It was further held that a contract would not become
statutory simply because it has been awarded by a statutory body.
22. Applying the aforesaid principles, the writ petition to enforce the
contractual claim was not maintainable and more so when the claim was
barred by time.
23. We accordingly allow this appeal and set aside the order dated 23rd
March, 2010 impugned herein; axiomatically the writ petition filed by the
respondents is dismissed. No order as to costs.
RAJIV SAHAI ENDLAW, J
ACTING CHIEF JUSTICE
MARCH 23, 2012 ‗pp '
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!