Citation : 2012 Latest Caselaw 835 Del
Judgement Date : 7 February, 2012
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ RFA No. 358/2001
% 7th February, 2012
PUNJAB STATE INDUSTRIAL
DEVELOPMENT CORPORATION LIMITED ..... Appellant
Through: Mr. Dalip Mehra, Advocate.
versus
RAIL INDIA TECHNICAL & ECONOMIC
SERVICES & ANR. ..... Respondents
Through: Mr. R.K. Saini, Advocate.
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
To be referred to the Reporter or not?
VALMIKI J. MEHTA, J (ORAL)
1. This is an unfortunate litigation between two Public Sector
Undertakings (PSUs) which never should have come to the Courts in the
first place, inasmuch as, the admitted fact is that the appellant/defendant
No.2 was making a joint venture project with defendant No.1 and for
which, project report was submitted by respondent No.1/plaintiff/Rail India
Technical & Economic Services, a PSU and for which report an amount
was agreed to be paid. There is no dispute that the project report was
prepared by respondent No.1/plaintiff and submitted. There is also no
dispute that the balance payment with respect to the project report was not
made. The suit has therefore been decreed for the balance amount payable.
The project report prepared by the respondent No.1/plaintiff was for a joint
venture project of Coil Spring Manufacturing plant which was to be set up
by the appellant/defendant No.2 with respondent No.2/defendant No.1.
2. The facts of the case are that the appellant/defendant No.2 sought to
set up a joint venture project of a Coil Spring Manufacturing plant with
defendant No.1/respondent No.2/M/s Bombay Motor Trading Company.
With respect to this project the plaintiff/respondent No.1 was called upon
to prepare a project report. The respondent No. 1/plaintiff gave a quotation
to the appellant/defendant No.2 for a sum of Rs.3.5 lakhs vide letter dated
26.6.1987, Ex.P1. The appellant/defendant No.2 requested for reduction
of charges vide letter dated 3.7.1987, Ex.P2, and therefore, the respondent
No.1/plaintiff vide its letter dated 24.7.1987, Ex.P3, reduced the price for
preparing of the project report from Rs.3.5 lakhs to Rs.2.5 lakhs.
3. As per the terms and conditions of the contract, first the draft final
report was to be submitted, and which was submitted by respondent
No.1/plaintiff on 27.3.1989 (Ex.P5). The respondent No.2/defendant No.1
had to give its comments to this draft final report within a fixed period of
time, but the same were not given and, therefore, the final bill was sent.
The respondent No.1/plaintiff hence became entitled to the balance
payment after `50,000/- was paid initially by the defendant
No.1/respondent No.2. The respondent No.1/plaintiff thereafter addressed
its letter dated 25.4.1989 (Ex.P6) asking for the balance payment due of
Rs.1.5 lakhs. Various reminders, thereafter, were sent which are dated
2.5.1989 (Ex.P7), 13.6.1989 (Ex.P9), 4.7.1989 (Ex.P10), 10.11.1989
(Ex.P11), 6.12.1989 (Ex.P12), 15.1.1990 (Ex.P13), and so on. Ultimately,
a legal notice was got served upon the defendants vide notice dated
11.2.1991 (Ex.P17).
4. Defendant No. 1/respondent No.2 remained ex-parte in the trial
Court and the suit was contested by the appellant/defendant No.2. There
were three basic contentions which were raised on behalf of the
appellant/defendant No.2. The first was that there was no privity of
contract between appellant/defendant No.2 and the plaintiff/respondent
No.1. The second defence was of the suit being barred by limitation. The
third defence was that the report was not sent within the period of three
months, as has been mentioned in the offer letter dated 26.6.1987 (Ex.P1).
5. The trial Court after completion of pleadings, framed the following
issues:-
i) Whether the plaintiff is entitled to claim the suit amount from the defendants? OPP
ii) Whether the plaintiff is entitled to claim interest?
If so, at what rate and for what period? OPP.
iii) Whether the suit is time barred? OPD
iv) Whether there is no cause of action in favour of the plaintiff and against the defendants? OPD
v) Whether there is no privity of contract between the parties? OPD
vi) Relief."
6. With respect to the issue of privity of contract, and which was the
subject matter of issue No.5, the trial Court has held that there was a privity
of contract inasmuch as firstly, because the project was to be made for a
joint venture project of both the defendants. Secondly, the letter dated
26.6.1987 (Ex.P1) to prepare the project report, was sent to the
appellant/defendant No.2. Thirdly, a request for reducing the fee for the
project report was also sent by the appellant vide its letter dated 3.7.1987
(Ex.P2) and to which reply was sent giving the necessary concession to the
appellant vide its letter dated 24.7.1987 (Ex.P3) by plaintiff/respondent
No.1. The trial Court in this regard has observed as under:-
"15) Defendant No.2 also wanted to install the plant as a joint venture with defendant No.1 and defendant No.1 had also requested the plaintiff to reduce the fees for the job entrusted to the plaintiff. There is privity of contract as the job done by the plaintiff was for a joint venture. In the letter dated 31.7.87 sent by defendant No.1 to the plaintiff, Ex.P4, there is a mention of project to be sent up in the joint sector with defendant No.1 and has a reference of personal meeting of the General Manager (Projects) of the plaintiff with Assistant General Manager of defendant No.2 and Project Manager of
Punjab Coil Springs Ltd., at the office of the plaintiff in New Delhi. Enquiry and request for reduction in fee by defendant No.2 was not on behalf of defendant No.1 but was made because defendant No.2 wanted to install the plant as a joint venture with defendant No.1 and as such it was on behalf of both the defendants. Defendant No.2 has never informed the plaintiff that defendant No.2 was not liable. There was no occasion for the plaintiff to believe that defendant No.2 has no concern nor defendant No.2 informed so to the plaintiff. Defendant No.2 in reply never stated that defendant No.2 was not liable to make payment.
16) In view of the facts and circumstances of the present suit and testimonies of PW1 and DW1 and DW2 on record and various documents placed and proved on record, I am of the considered opinion that there was privity of contract between the plaintiff and defendants. Issue is decided accordingly in favour of the plaintiff and against the defendants."
7. I completely agree with the findings of the trial Court on issue No.5
inasmuch the aforesaid documents, as also other exhibited documents,
before the trial Court show that the appellant was jointly liable to pay the
costs of the project report, and which were with respect to a joint venture
project which was to be set up by the appellant/defendant No.2 with
respondent No.2/defendant No.1. The trial Court has rightly referred to the
fact that appellant/defendant No.2 never informed respondent No.1/plaintiff
that it was not liable to make the payment because there is no
correspondence on record where such a stand was ever taken up by the
appellant/defendant No.2.
8. The issue with respect to the suit being time barred was issue No.3,
and with respect to which the trial Court has held that the suit is not barred
by time by giving the following observations:-
"20) Issue No.3:- Whether the suit is time barred?
Onus of proving this issue has been placed upon the defendants which they have failed to discharge. Defendants have failed to disclose as to how the suit is barred by time. Even otherwise plaint has been instituted on 6-4-1992. According to the plaintiff the bill were submitted vide letter dated 27-3-1989. Defendants did not sent its comments within 15 days as agreed not made the payment of Rs.1,50,000/-. According to the plaintiff no comments have been received from defendant No.1 even till the date of the filing of the suit. Thus there is a presumption that the report was accepted bY the defendants and plaintiff has been entitled to the final payment as well. It is held that the suit is not barred by time. Issue is decided accordingly."
9. To the aforesaid findings of the trial Court I may add that the final
draft report was given on 27.3.1989 to which comments were to be given
within 15 days, and only whereafter, the final of this draft final report was
to become the final report. It is only on the coming to existence of the final
report, would the entitlement come into being to claim the balance
payment. The 15 days period from 27.3.1987 expired on 12.4.1989, and
since the suit has been filed on 6.4.1992, the suit is very much within
limitation as it was filed within three years from 12.4.1989 i.e. on 6.4.1992.
The findings with respect to issue No.3 are, therefore affirmed with the
additional reasoning as stated above, and which I am entitled to do so in
view of Order 41 Rule 24 CPC.
10. So far as issue that the report was not submitted in time is concerned,
I find that there is no such issue which is framed by the trial Court as to the
claim for payment is disputed because there was breach of contract in not
submitting the report within time. In any case, even assuming if this aspect
is incorporated in the issues framed, however, learned counsel for the
appellant could not dispute that at no point of time, till the final report was
submitted by respondent No.1/plaintiff, was it ever challenged by any of
the defendants, much less the appellant, that the contract stood frustrated on
account of the project report not having been given within time.
11. In view of the aforesaid facts advisedly this issue seems not to have
been pressed before the trial Court.
12. There is, however, one aspect on which I am inclined to give relief to
the appellant/defendant No.2, though this aspect has not been argued before
me. This is with respect to the high rate of pendente lite and future interest
@ 18% per annum granted by the impugned judgment and decree. The
Supreme Court in the recent catena of judgments reported as Rajendra
Construction Co. v. Maharashtra Housing & Area Development
Authority and others, 2005 (6) SCC 678, McDermott International Inc. v.
Burn Standard Co. Ltd. and others, 2006 (11) SCC 181, Rajasthan State
Road Transport Corporation v. Indag Rubber Ltd., (2006) 7 SCC 700,
Krishna Bhagya Jala Nigam Ltd. v. G.Harischandra, 2007 (2) SCC 720
& State of Rajasthan Vs. Ferro Concrete Construction Pvt. Ltd (2009) 3
Arb. LR 140 (SC) has held that in view of the changed economic scenario
where there has been consistent fall in the high rates of interest, Courts
must not grant high rates of interest, more so when the litigation remains
pending for a long time.
13. Accordingly, I hold that the respondent No.1/plaintiff will be entitled
to interest @9% per annum simple pendente lite and future till the decretal
amount is paid.
14. A civil case is decided on balance of probabilities. The balance of
probabilities show that liability was a joint liability of both the defendants
as the Coil Spring Manufacturing plant was proposed to be set up which
was a joint venture project of both the defendants i.e. inclusive of
defendant No.2/appellant. The offer was also given to the appellant who
had asked for reduction and concession, and which was given the said
concession. At no point of time any dispute was ever raised by writing
even a letter by the appellant that it was not liable to make payment of the
suit amount and which is the balance due for the project report submitted.
15. In view of the above, the present appeal is partially accepted, limited
to reducing the pendente lite and future interest to 9% per annum simple.
Parties are left to bear their own costs. Decree sheet be prepared. Trial
Court record be sent back
VALMIKI J. MEHTA, J.
FEBRUARY 07, 2012 AK
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!