Citation : 2012 Latest Caselaw 713 Del
Judgement Date : 2 February, 2012
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
20
+ O.M.P. 382/2006
UNION OF INDIA ..... Petitioner
Through Mr. Jaswinder Singh, Advocate.
versus
M/S SUNRISE ENTERPRISES, PANIPAT ..... Respondent
Through Mr. Shiv Khorana, Advocate.
CORAM: JUSTICE S. MURALIDHAR
ORDER
% 02.02.2012 IA No.9086/2006
1. This is an application by the Petitioner seeking condonation of delay in re-
filing the petition being OMP No. 382 of 2006 under Section 34 of the
Arbitration & Conciliation Act, 1996 ('Act').
2. The facts relevant to the present application are that the impugned Award was
passed on 21st February 2006. According to the Petitioner, it received a copy of
the Award on 28th February 2006. In terms of Section 34 (3) of the Act, the
petition for setting aside the Award had to be filed within three months from the
date of receipt of the Award. Admittedly, the OMP was filed within time on
22nd May 2006.
3. The petition was scrutinized and the following defects were pointed out by
the Registry:
(i) Court fee of Rs. 20/- be affixed;
(ii) No annexures filed with the petition;
(iii) Vakalatnama not filed; and
(iv) index should be properly paginated.
4. It appears that the petition was collected from the Registry and re-filed by the
Petitioner first on 30th May 2006 without curing the above objections. The
noting of the Registry on the file of 30th May 2006 was that "all above
objections are still pending". Then for the second time the petition was re-filed
on 5th July 2006. The noting on file of 6th July 2006 reads "all above objections
are still not removed". For the third time, the petition was re-filed by the
Petitioner on 27th July 2006. The noting on file of 30th July 2006 added another
objection "the application seeking condonation of delay for re-filing be filed."
5. It requires to be noticed at this stage that as per the original scrutiny report,
the objections were to be removed and the petition re-filed within one week of
the Registry pointing out the defects. It is stated by Mr. Jaswinder Singh,
learned counsel for the Petitioner that this rule is not rigorously applied by the
Registry and usually an application for condonation of delay for re-filing is
required to be filed only where the delay in re-filing is beyond 30 days. Be that
as it may, in the present case, the re-filing for the fourth time took place on 18th
August 2006 together with an application for condonation of delay.
6. A perusal of the said application, i.e., IA No. 9086 of 2006 reveals that it is
some kind of an omnibus application which is captioned as an application for
"exemption from filing the typed copies of dim annexures". In fact, para 3 talks
of dim annexures and para 4 about inadequate left margins. Para 5 of the
application states: "It is also prayed that this Hon'ble Court may condone delay,
if any, in re-filing of the accompanying OMP." Para 6 again talks of dim
annexures and inadequate left margins. Prayers (a) and (b) are to the same
effect. Prayer (c) reads: "Condone delay, if any, in re-filing of the
accompanying OMP, if any."
7. In effect, therefore, there is absolutely no explanation whatsoever in the
application for the delay in re-filing the OMP.
8. Although the Registry has not computed the actual delay in re-filing, it
should be computed from one week after 23rd May 2006, i.e., 30th May 2006 till
18th August 2006. This is over 75 days.
9. The question that now arises is whether the above delay in re-filing should be
condoned. Mr. Jaswinder Singh, learned counsel for the Petitioner urges that the
delay in re-filing is not considerable and ought to be condoned. To make up for
the absence of an explanation in the application for the delay in re-filing,
learned counsel for the Petitioner prays that one more opportunity should be
given to the Petitioner to file an affidavit to explain the delay. He relies on the
decision of the Supreme Court in Indian Statistical Institute v. M/s. Associated
Builder UJ (SC) 1977 805 to urge that the application for condonation of delay
in re-filing should not be rigorously scrutinized. He submits that as long as the
main petition is within time, the subsequent re-filing would relate back to the
date of the original filing. As long as the delay is not extraordinary, it should be
condoned. He also relies on the decision of the Division Bench of this Court in
D.C. Sankhla v. Ashok Kumar Parmar (1995) 1 AD (Delhi) 753.
10. Mr. Shiv Khorana, learned counsel appearing for the Respondent on the
other hand opposes the application by referring to the decision of the Division
Bench of this Court in The Executive Engineer (Irrigation & Flood Control) v.
Shree Ram Construction Co. 2010 (4) Arb LR 314 (Delhi) (DB) which affirms
the decisions of the learned Single Judge of this Court in Gautam Associates v.
Food Corporation of India 2009 (111) DRJ 744 and Union of India v. M/s.
Harbhagwan Harbhajan Lal 2010 (6) RAJ 310 (Del).
11. The above submissions have been considered. There is, as already noticed,
no explanation whatsoever offered in the application for seeking condonation of
delay in re-filing the present petition. The application was filed way back on
18th August 2006 and has been pending for over five years. During this entire
period, the Petitioner did not seek leave of the Court to file an affidavit to
explain the reasons for the delay. In the circumstances, this Court does not find
any reason to grant the Petitioner any indulgence to do so now. In any event,
even when the application was filed on 18th August 2006, in light of the defect
pointed out by the Registry, the Petitioner was aware that it had to offer some
valid reason for the delay. Considering the number of times that the petition was
collected and re-filed, it is not possible to excuse the totally lackadaisical
manner in which no effort has been made by the Petitioner to offer an
explanation let alone a credible one, for the delay in re-filing the petition.
Clearly, the Petitioner was smug about the delay being condoned by the Court.
12. In The Executive Engineer (Irrigation & Flood Control) v. Shree Ram
Construction Co., the Division Bench of this Court was dealing with a batch of
appeals assailing the orders of the learned Single Judges declining to condone
the delay in re-filing of petitions. Two of the appeals, which were considered by
the Division Bench, concerned condonation of delay in re-filing petitions under
Section 34 of the Act. In FAO (OS) No. 132 of 2009 (Union of India v. Ogilvy
& Mather Limited), the facts were that the original OMP under Section 34 was
filed within time. However, there was a delay of 258 days in re-filing the
petition after curing the defects. After considering the decision of the Supreme
Court in Union of India v. Popular Construction Company (2001) 8 SCC 470
it was observed by the Division Bench that "since this delay crosses the frontier
of the statutory limit, that is, three months and thirty days, we need to consider
whether sufficient cause had been shown for condoning the delay. The conduct
of the party must pass the rigorous test of diligence, else the purpose of
prescribing a definite and inelastic period limitation is rendered futile." On
facts, the Division Bench concurred with the learned Single Judge that no
satisfactory explanation had been furnished for the delay. In FAO (OS) 259 of
2010 (Union of India v. Harbhagwan Harbhajan Lal & Arun Construction
Co.) also, although the OMP under Section 34 of the Act was filed within time
there was a delay of 195 days in re-filing the petition. The decision of the
learned Single Judge declining to condone the delay on the ground that the
deficiencies ought to have been removed "within thirty days as an outer limit",
was affirmed by the Division Bench.
13. It appears that the Court has, in the matter of condonation of delay in re-
filing the petitions under Section 34 of the Act, adopted a stricter scrutiny than
it does while considering an application for condonation of delay filed under
Section 5 of the Limitation Act. What weighs with the Court is the express
legislative intent in Section 34 (3) of the Act, that the total permissible period
within which an application can be permitted to be filed under Section 34 of the
Act, is 90 days plus an additional 30 days. If the delay in re-filing the petition
exceeds the above period, then the scrutiny becomes rigorous. Unless there is a
satisfactory and credible explanation for the delay, the Court would be reluctant
to condone it. Otherwise, the legislative object of not permitting the delay in the
original filing beyond 30 days would get defeated.
14. In the present case, no attempt has been made to explain even a single day's
delay. A delay of 75 days becomes fatal when the Petitioner does not care to
offer any explanation whatsoever. The Court ought not to be taken for granted.
15. This Court is, therefore, not persuaded to condone the delay in re-filing the
present petition. I.A. No. 9086 of 2006 is dismissed.
OMP No. 382 of 2006 & IA Nos. 9085, 9087/2006
16. In view of the dismissal of IA No. 9086 of 2006, this petition and the
pending applications are dismissed.
S. MURALIDHAR, J FEBRUARY 02, 2012 rk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!