Citation : 2012 Latest Caselaw 1351 Del
Judgement Date : 28 February, 2012
* IN THE HIGH COURT OF DELHI AT NEW DELHI
LPA No. 167 OF 2012
% Judgment Delivered on: 28.02.2012
RASHTRIYA ISPAT NIGAM LTD. . . . APPELLANT
Through : Mr. N.K. Kaul, Sr. Adv. with
Mr. Pratap Venugopal,
Ms. Surekha Raman, Mr. Varun
Singh, Mr. Gaurav Nair, Advs.
VERSUS
DELHI DEVELOPMENT AUTHORITY ... RESPONDENT
Through: Mr. Ajay Verma with Mr. Munesh Kumar, Advs.
CORAM :-
HON'BLE MR. JUSTICE A.K. SIKRI HON'BLE MR. RAJIV SAHAI ENDLAW
A.K. SIKRI, ACTING CHIEF JUSTICE:
1. A notice to show cause dated 17th December, 2007 was issued by the
DDA to the appellant herein as to why damages of `6,25,71,881/- be not
imposed upon it for unauthorized use and occupation of commercial premises
measuring 22 bighas and 10 biswas in Village - Barwala, Delhi for the period
from 6th October, 2005 to 31st December, 2006. The appellant disputed the
liability. However, order under Section 7 of the Public Premises (Eviction of
Unauthorised Occupants) Act, 1971 (hereinafter referred to as "PP Act") was
passed by the Estate Officer imposing the aforesaid damages. The appellant
filed appeal there against questioning the liability on various grounds. This
appeal was dismissed by the appellate authority vide order dated 15th
November, 2010. Thereafter, appellant preferred writ petition assailing the
order of the appellate authority. In this writ petition mainly three grounds
were raised by the appellant, namely :
(i) There was an inordinate delay of two years in passing the order
by the Estate Officer;
(ii) No positive evidence was led by the DDA to justify the
imposition of the exorbitant damages and no opportunity was
granted to the appellant to lead evidence ; and
(iii) The appellant was not responsible to pay any damages and the
liability if any was that of M/s. VTC Transport Limited
(hereinafter referred to as „VTC‟) which had been awarded
consignment agency by the appellant and the aforesaid premises
were taken on rent by VTC from the landlord before the land was
acquired by the DDA.
2. The learned Single Judge has accepted the contention of the appellant
that there was no positive evidence led by the DDA to establish the quantum
of damages. On this ground, the orders of the authorities below have been set
aside and matter is remanded back to the Estate Officer for a prompt decision
afresh after the respondent is permitted to lead the evidence. Because of this
reason first ground of delay also does not survive. However, insofar as the
question of liability of appellant is concerned, the learned Single Judge has
held that the liability to pay the damages, which would be determined, would
be that of the appellant. It is this part of the order which is not palatable to the
appellant and, therefore, present appeal is preferred on this limited aspect.
3. Before we take note of the contention of the parties and appreciate the
same, we would like to give some background under which the use and
occupation of the aforesaid premises became unauthorized. In June 2000, the
appellant had awarded consignment agency on certain terms and conditions
for which agreement was entered between the appellant and the VTC. VTC
had represented that it had taken the aforesaid premises from a landlord on
rent which was available for handling and storage of iron and steel material of
the appellant, which is a public sector undertaking. The material belonging to
the appellant was kept in the said premises known as stockyard/stock
warehouse of the VTC which was appointed as consignment agent. As per
the agreement VTC was supposed to handle the arrivals, storage including
security, stacking with tonnage and deliveries of iron and steel materials
dispatched to the said yard as directed by the appellant. The VTC was also to
provide handling/transportation equipment i.e. minimum number of mobile
cranes, trucks/ trailers equipment for bending/cutting and requisite minimum
labour as well. VTC was to perform all the work involved from the stage of
dispatch from the plant, receipt and clearing of consignment arriving by
rail/road, their unloading, loading into trucks/trailers, transportation, stack
with tonnage, storage in the yard, bending and cutting when required and
delivery through rail or road as advised by the appellant. For undertaking this
job various other incidental jobs to be carried out by the VTC were also
mentioned in the agreement. Clause 27 which is relevant for us provides as
under:-
"Clause 27
a) The ownership of the material consigned to the Consignment Agent and received in the yard shall always remain with the company and the Consignment Agent shall only hold some trust for the Company. In case of any dispute or claim arising from either side in respect of the provisions of the agreement or otherwise, the Consignment Agent shall not at any time refuse permission to the Company or its authorized officers to entry into the yard and/ or in effecting/ arranging disposal of the materials or take possession of the material in the yard as the Company may deem fit. The Consignment Agent or any one claiming through or under him shall not set up any claim or title on or in respect of the materials consigned to and received in the yard, adverse to the company, during the subsistence of the agreement and/ or on expiry of termination as long the materials are not fully delivered to the Company, shall not allow or suffer the sad
materials to be attached or sold in any court proceedings or any receiver or special offer to be appointed in respect of them.
b) The Consignment Agent shall not hypothecate and/ or pledge and/ or encumber in any manner whatsoever the materials dispatched to him either in full or part to any bank, financial institution or association or Company or firm or person as Security or otherwise.
c) The Consignment Agent shall not suffer any injunction and/or attachment and/or appointment of receiver in respect of the materials dispatched to him?
4. The land in question was acquired and after acquisition it was placed at
the disposal of the DDA. DDA thus became entitled to take possession of the
said land. Compensation was paid to the landlord/original owner. When
DDA wanted to take possession, request was made to DDA by VTC as well
as appellant not to take immediate possession and give some time to enable
the shifting of goods from the said place to some other place. This is how the
premises remained under occupation from 6th October, 2005 to 31st
December, 2006 and this occupation has been treated as unauthorized use by
the DDA which compelled DDA to take out the proceedings under the PP
Act.
5. Consistent stand of the appellant, questioning its liability to pay the
damages, has been that it is the VTC who was to provide the stockyard at
Delhi in terms of agreement entered into between VTC and the appellant and,
therefore, the liability if any is that of VTC. It was argued that in September,
2005 VTC had informed the appellant that the land in question had been
sealed by the DDA and the material of the appellant had been stored therein.
It was also argued that it is VTC who requested the DDA to grant time and,
therefore, there was no liability of the appellant.
6. The learned Single Judge on interpreting Clause 27 referred to above,
came to the conclusion that the material in question was exclusively the
material of the appellant and VTC was merely an agent therefore
unauthorized use of the said stockyard was by the appellant whose material
was lying there and it was the appellant who had sought time from the DDA
to clear the materials, therefore, liability to pay the damages is that of the
appellant.
7. We are in agreement with the view taken by the learned Single Judge.
Not only the material was that of the appellant, correspondence placed on
record in fact clinches the issue. The appellant on coming to know that the
land had been acquired and the DDA was going to seal the stockyard, wrote a
letter dated 8th June, 2006 to the DDA. In this letter reference was made to
the communication of VTC stating that DDA was going to seal the premises
and request was made not to seal the premises and to give to the appellant 6-7
months‟ time in order to take the alternate action. The relevant portion of the
said letter is extracted below:
"M/s. VTC Transport Limited have brought the acquisition of land by DDA to the knowledge of RINL on 27.09.2005 and they stated that the yard would be sealed by DDA. As the steel sections stocked at this yard belong to the Government of India Enterprise which is 100% Government owned, in larger public interest, Regional Manager (North) of RINL wrote a letter to The Commissioner(Land), DDA vide Ref. No.VSP/GZB/MKTG/05- 06/776 dated September 27th, 2005 requesting DDA not to seal the yard and to give RINL 6-7 months time in order to take the alternate action. The copy of this letter has been sent to your office also."
In the last para, it was stated that:
"Hence I request your goodself not to seal the yard and kindly grant another extension of 6-7 months enabling M/s. Rashtriya Ispat Nigam Limited, a Government of India Enterprise, to serve the customers at Delhi, in larger public interest."
8. Thus, it is the appellant who wanted 6-7 months time to take alternate
action and it also stated that this period would enable the appellant to serve
the customers at Delhi and would also secure larger public interest. The
above letter was followed by another letter dated 27th September, 2005 which
is of significance. It was written to the DDA by the appellant in which
appellant stated that the steel materials of the appellant valuing over `30
crores was stacked in the said stockyard and sealing of the premises would
affect the appellant and the appellant again requested for 6-7 months time in
order to take alternate action by making following request:
"You will very kindly agree that shifting of steel materials being approximately 9 to 10 thousand MT requires considerable time. Further, shifting of Weigh Bridge and other infrastructures may also take quite some time. Sealing of the Yard will put RINL, the Government of India Enterprises, under the administrative control of Ministry of Steels will affect the RINL and as such request your goodself to consider and give us atleast 6-7 months time in order to take the alternate action."
9. We are of the opinion that the damages under Section 7 are leviable for
unauthorized use and occupation of the public premises. Use of the said
premises was by the appellant which is not only clear from the agreement in
question but also from the conduct of the appellant itself. Therefore, liability
to pay the damages which are to be determined shall be that of the appellant.
Finding no merit in this appeal, the same is dismissed.
ACTING CHIEF JUSTICE
(RAJIV SAHAI ENDLAW) JUDGE FEBRUARY28, 2012 dk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!