Citation : 2012 Latest Caselaw 7176 Del
Judgement Date : 14 December, 2012
*IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 14th December, 2012
+ LPA No.1054/2004
DELHI DEVELOPMENT AUTHORITY ..... Appellant
Through: Ms. Sangeeta Chandra, Adv.
Versus
SUNIL MADNANI ..... Respondent
Through: Mr. Sumit Bansal, with Mr. Ateev
Mathur and Ms. Sumi Anand, Advs.
CORAM :-
HON'BLE THE CHIEF JUSTICE
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
RAJIV SAHAI ENDLAW, J
1. This intra court appeal impugns the judgment dated 18 th August, 2004
of the learned Single Judge allowing WP(C) No.2981/1998 preferred by the
respondent by quashing the letter dated 6th May, 1992 of the appellant DDA
cancelling the bid made by the parents of the respondent for a residential
plot of land bearing 7, New Rajinder Nagar, New Delhi and by directing the
appellant DDA to make a fresh demand on the respondent for the bid price
together with interest at 12% per annum; upon the respondent so making the
payment, the appellant DDA has been further directed to hand over
possession of the plot and execute the conveyance deed with respect thereto
in favour of the respondent.
2. The appeal was admitted for hearing and vide order dated 9 th
November, 2004 the operation of the impugned judgment stayed. The
appellant DDA was also however restrained from reauctioning the said plot
till the disposal of the appeal.
3. The undisputed facts are:
i. that the auction for the aforesaid plot of land admeasuring
121.50 sq. mtr. was held on 14 th January, 1992;
ii. the parents of the respondent namely Smt. Pushpa Madnani
and Sh. Balram Madnani had made the highest bid therefor in
the sum of Rs.15,55,000/-;
iii. in accordance with the auction terms, the parents of the
respondent at the fall of the hammer deposited 25% of the bid
amount i.e. Rs.3,88,750/- with the appellant DDA on 14 th
January, 1992 itself.
iv. that the bid was confirmed on 15th January, 1992 and a demand
for the further amount due of Rs.11,66,295/- payable latest by
14th March, 1992 was raised;
v. no further payment was made by the said date of 14th March,
1992;
vi. a further sum of Rs.25,000/- was deposited on 17th March,
1992 with the appellant DDA;
vii. the appellant DDA vide letter dated 6th May, 1992, for the
failure of the parents of the respondent to pay the balance
amount, cancelled the bid;
viii. a further amount of Rs.5,50,000/- was deposited by the parents
of the respondent on 31st July, 1992, thereby depositing a total
sum of Rs.9,63,750/- as against the bid amount of
Rs.15,55,000/-;
ix. a representation dated 6th August, 1998 was made by the
parents of the respondent to the appellant DDA for revocation
of the cancellation of the bid on the ground that they were
unable to pay the entire bid amount owing to financial
constraints;
x. Smt. Pushpa Madnani died on 2 nd June, 1993 and Sh. Balram
Madnani on 13th June, 1993;
xi. under cover of letter dated 10th January, 1997 the appellant
DDA, after forfeiting the earnest money of Rs.3,88,750/-
refunded a sum of Rs.5,75,000/-;
xii. ultimately in or about June, 1998, the writ petition from which
this appeal arises was filed impugning the letters dated
10.01.1997 and 06.05.1992 aforesaid and seeking a direction to
the appellant DDA to accept the balance payment and allot the
plot.
4. The appellant DDA contested the writ petition inter alia pleading that
the bid stood automatically cancelled on non deposit of the entire amount in
terms of the bid confirmation letter dated 15 th January, 1992. It was further
pleaded that under the terms of auction, the Vice Chairman of the appellant
DDA could extend the time for making payment provided such application
is made at least 7 days prior to the last date of making the payment; no such
application was filed and the amounts of Rs. 25,000/- and 5,50,000/- were
deposited by the parents of the respondent on their own and without seeking
any extension of time.
5. The learned Single Judge allowed the writ petition as aforesaid for the
reason-
i. that during the pendency of the writ petition the respondent had
also sought redressal through the Permanent Lok Adalat of the
DDA, which had passed an order that the Lieutenant Governor
as the Chairman of the DDA should reconsider the matter;
ii. the Permanent Lok Adalat had noted that as per the policy of the
DDA as contained in the Office Order dated
F.100(56)/86/Imp/CL/Pt. dated 1 st May, 1991, restoration could
be done on payment of penalty at Rs.60 per sq. mtr. if the
application for restoration is received more than 60 days after
cancellation but before the expiry of 90 days of the cancellation;
that the mother of the respondent had on 3 rd August, 1992 sought
revocation of the cancellation letter dated 6 th May, 1992 - she
had thus applied within 90 days period for having the bid
cancellation recalled;
iii. that the Lieutenant Governor, in pursuance to the order of the
Permanent Lok Adalat had wrongly rejected the request for
revocation of the bid cancellation order since the restoration was
sought before expiry of 90 days from the date of cancellation
and the appellant DDA as per its policy was duty bound to
restore the allotment by charging Rs.60/- per sq. mtr. as
restoration charges;
iv. that one Shri Ashok Gupta UDC-OSB of the DDA also had in
his note dated 23rd September, 1992 while processing the request
dated 6th August, 1992 of the parents of the respondent for
revocation of the bid had recorded that though they had not
requested for extension of time for making the payment of
balance premium in accordance with the terms of auction but
since had subsequently made such a request, the same should
have been granted subject to payment of interest at the rate of
18% per annum or 15% per annum as DDA had granted
extension of time in similar cases where the request for
extension of time was received; he had in the said note also
referred to the Circular dated 1st May, 1991 (supra) permitting
restoration within 90 days on payment of restoration charges at
the rate of Rs.60/- per sq. mtr.;
v. the Additional Director (OSB) had also while note dated 24 th
September, 1992 recommended restoration of bid subject to
payment of interest and restoration penalty;
vi. however thereafter the file meandered between the officers of
the DDA with a question being raised as to the officer who was
authorized for taking necessary decision for restoration of the
bid and ultimately the letter dated 10th January, 1997 refunding
Rs.5,75,000/- after forfeiting the earnest money was issued;
vii. such action of the DDA was shocking inasmuch as the file
notings showed that the parents of the respondent no.3 were
entitled to restoration of the bid on depositing restoration
charges at Rs.60/- per sq. mtr. and interest at 18% per annum on
account of delayed payment;
viii. that the Lieutenant Governor also while considering the matter
in compliance of the directive of the Permanent Lok Adalat had
rejected restoration without giving any justification for his
decision;
ix. that the issue of extension of time for making payment and the
issue of restoration of cancelled bid are entirely different;
x. that since the parents of the respondent had a right under the
Policy of the DDA to have the cancellation restored and that
right had been violated, the writ petition was entitled to succeed.
The Single Judge however considering the delay on the part of the
respondent from 1993 till 1997, directed that the respondent must pay
interest at the rate of 12% per annum on the balance of the bid amount as
also restoration charges till the filing of the writ petition.
6. The counsel for the appellant and the counsel for the respondent have
been heard between yesterday and today.
7. It is the contention of the counsel for the appellant before us that the
Circular dated 1st May, 1991, on the basis of which it has been held by the
learned Single Judge that the policy of the DDA permits restoration if
applied for within 90 days and on payment of restoration charges, is not
applicable to cancellation of bid. We may in this regard state that since the
complete writ record had not been filed in this appeal, we have called for the
writ record and find the appellant DDA to have therein filed an additional
affidavit dated 11th February, 2002 also stating that the said Circular comes
into operation only when the possession of the plot is handed over to the
purchaser after payment of premium / dues to the DDA and since the
parents of the respondent had not paid the premium / dues, therefore the said
Circular was not applicable to the facts of the case. It was also stated that in
auction cases, the appellant DDA follows only the terms of auction. The
respondent had filed a response affidavit dated 31 st July, 2003 contending
that the Circular dated 1 st May, 1991 nowhere mentions such distinction and
that the DDA had in a number of cases, instances whereof were given,
restored the bids which stood cancelled on account of non payment. We
may however notice that the learned Single Judge has in the impugned
judgment not returned any finding in this regard, though has based his
decision on the Circular dated 1st May, 1991. He has in this regard relied
only on the file notings aforesaid and which had been accepted by the
Permanent Lok Adalat.
8. We are afraid, neither the file notings nor acceptances thereof by the
Permanent Lok Adalat of the DDA could be treated as decisive and in the
face of an express plea by the DDA that the said Circular did not apply, the
learned Single Judge ought to have returned his own finding thereon rather
than relying on the file notings and the order of the Permanent Lok Adalat.
9. As far as the file notings are concerned, it has been held in Sethi Auto
Service Station v. DDA (2009) 1 SCC 180 that internal notings are not
meant for outside exposure and notings in the file culminate into an
executable order affecting the rights of the parties only when it reaches the
final decision making authority in the department, gets his approval and the
final order is communicated to the person concerned. Similarly, in Jasbir
Singh Chhabra v. State of Punjab (2010) 4 SCC 192, it was held that issues
and policy matters which are required to be decided by the Government are
dealt with by several functionaries some of whom may record notings on the
files favoring a particular person, someone may suggest a particular line of
action; however, the final decision is required to be taken by the designated
authority keeping in view the larger public interest. The said views were
recently approved in Union of India v. Vartak Labour Union JT 2011 (3)
SC 110.
10. It is also not as if the Permanent Lok Adalat though presided by a
retired Additional District Judge had independently examined the
applicability of the Circular. The Permanent Lok Adalat merely relied on
the file notings. It is nobody‟s case that the UDC of the DDA who made this
file noting was competent to take a view in this regard.
11. On the contrary we find the Circular dated 1st May, 1991 to be titled
"Sub: Composition Charges For The Late Execution Of Title Deeds And
Delay In Construction Over Residential, Industrial, Commercial And
Institutional Plots And Restoration."
and issued to revise the guidelines for recovery of composition fee for
extension of period of construction on plots and other allied matters. The
same, under Head 1 provides for "Composition Charges For The Belated
Construction" under Head 2 provides for "Late Execution Of Lease/Sub-
Lease Deed" and under Head 3 provides for "Restoration Charges" (and on
which reliance has been placed by the learned Single Judge). The last para of
the Circular is as under:
"If the application is not made for restoration within a period of 90 days the plot will be re-auctioned. However, if before re- allotment/re-auction of the plot the application is received then penalty @Rs.100/- per sq. mtr. is to be charged before restoration is allowed. Further in case where allotments are cancelled on account of breach of the terms and conditions of allotment/misuse, the date of receipt of application for restoration should be reckoned from the date of removal of breach/stoppage."
12. On a reading of the entire Circular and not merely Heading 3 titled
"Restoration Charges", there is no doubt whatsoever that the same applies to
cases where the allottee/auction purchaser though has made payment for the
plot and is in possession thereof but has either delayed raising of
construction on the plot or has delayed the execution of lease deed/sub lease
deed or where allotment has been cancelled on account of breach of terms
and conditions of allotment/misuse. We may in this regard notice that under
Rule 8 of the Delhi Development Authority (Disposal of Developed Nazul
Land) Rules, 1981 the allotment is complete only on making of the entire
payment and not before that. Naturally the question of delay in raising
construction or delay in execution of lease/sub lease arises only after the
allottee/auction purchase has been put into possession and not before that.
In the present case the respondent/his parents chould have been put into
possession only after they had paid the entire auction bid amount and not
before that. The said Circular was thus clearly not applicable and the
learned Single Judge fell in error in relying on the file notings of a UDC of
the DDA in this regard rather than examining the rival pleas as to the
applicability of the said Circular. Since the judgment of the learned Single
Judge is squarely based on the said circular, the judgment is liable to be set
aside on this ground alone.
13. The counsel for the appellant DDA has however also drawn our
attention to V.K. Khosla Vs. Union of India 71(1998) DLT 642 which was
also a case of cancellation of auction bid on account of non payment of the
balance deed amount within time. Reliance in that case was placed besides
on the Circular dated 1 st May, 1991 (supra), also on Circular dated 20th July,
1982 laying down rates of penalty on account of restoration of
allomtnet/auction bid/lease deed. It was held, that though the Circular dated
20th July, 1982 referred to restoration of the auction bids also but a complete
reading thereof showed that the same was applicable only in case where the
purchase had been completed by the payment of the entire price and was not
applicable when the entire bid amount had not been paid; that the Circular
dated 20th July, 1982 and 1st May, 1991 were not issued by the Central
Government or under the authority of the Central Government as required in
terms of Section 22(3) of the Delhi Development Act and were merely
instructions and did not partake character of the terms issued by the Central
Government; that the said Circulars in any case are in conflict with Rule 29
of the Nazul Rules; that if the Circular dated 1 st May, 1991 were to be held
to entitle a party to seek restoration of the auction bid at any time prior to re-
auction, it would be in conflict with Rule 29 of the Nazul Rules and cannot
hold the field.
14. We are in respectful agreement with the said judgment.
15. The learned Single Judge in the impugned judgment though noted the
delay on the part of the respondent from 1993 to 1998 when the writ petition
was filed and for the said reason held the respondent liable for interest at
12% but did not consider that the said delay on the part of the respondent
was rather fatal to the writ petition. We have carefully perused the writ
petition. In the writ petition, in this regard, we do not find any explanation
whatsoever for the period from 1993 to 1997 and the respondent claims to
have learnt of the bid made by his parents only on receipt of letter dated 10 th
January, 1997 of the DDA. The respondent thus had clearly slept over his
rights, if any, inherited from his parents and was after lapse of five years
from automatic cancellation of the deed on 14 th March, 1992 not entitled to
challenge the said cancellation. We are of the opinion that the writ petition
ought to have been dismissed on this ground alone.
16. The counsel for the respondent has contended that the parents of the
respondent who had made bid were old and ailing and died soon thereafter
and delay ought to have been condoned. He has in this regard again relied
upon the order of the Permanent Lok Adalat.
17. We are unable to agree. The auction terms were clear and no right
came into existence in favour of the bidder till the entire amount was paid.
It thus cannot be said that there was even an agreement to sell in favour of
the bidder which could be specifically enforced. Upon the entire payment
not having been made the bid itself stood cancelled and no right thereunder
remained in favour of the bidder. Moreover, it has been held by a Division
Bench of this Court in the judgment/order dated 2 nd September, 1993 in
CWP No.2395/1990 titled Kailash Nath & Associates Vs. Union of India
and the Supreme Court in Meerut Development Authority Vs. Association
of Management Studies (2009) 6 SCC 171 that the exercise of writ
jurisdiction in such matters is not appropriate. Mention may also be made of
Kisan Sahkari Chini Mills Ltd. Vs. Vardan Linkers (2008) 12 SCC 500
laying down that the writ remedy in contractual matters can be allowed only
where an element of public law is involved. As aforesaid, no case of
arbitrariness in the action of the appellant DDA is made out.
18. The counsel for the respondent in the written submission handed over
at the time of hearing though has referred to Vishwa Raj Saxena vs. DDA
MANU/DE/0041/2008 and Ashok Kumar Kanojia Vs. Delhi Development
Authority 117 (2005) DLT 648 but has in oral submissions not even referred
to the said judgments nor alongwith the written submission bothered to file
copies thereof. In these circumstances need is not felt to deal therewith.
19. We accordingly allow the appeal and vacate the interim order
restraining DDA from auctioning the said plot and set aside the judgment
dated 18th August, 2004 of the learned Single Judge. Axiomatically the writ
petition from which this appeal arises stands dismissed. The respondent is
also directed to pay costs of litigation of Rs.25,000/- to the appellant DDA
by depositing the same in this Court within two weeks and whereafter the
DDA shall be entitled to withdraw the same.
RAJIV SAHAI ENDLAW, J
CHIEF JUSTICE DECEMBER 14, 2012 „M‟
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!