Friday, 24, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Delhi Transco Limited vs Techno Electric And Engineering ...
2012 Latest Caselaw 7013 Del

Citation : 2012 Latest Caselaw 7013 Del
Judgement Date : 7 December, 2012

Delhi High Court
Delhi Transco Limited vs Techno Electric And Engineering ... on 7 December, 2012
Author: S. Muralidhar
       IN THE HIGH COURT OF DELHI AT NEW DELHI
                                          (Not reportable)
                   O.M.P. No. 313 of 2007

      DELHI TRANSCO LIMITED                          ..... Petitioner
                    Through: Mr. Rakesh Agarwal with
                             Mr. Pulkit Agarwal, Advocates.

                                versus


       TECHNO ELECTRIC AND ENGINEERING CO.
       LIMITED                                   ..... Respondent
                   Through: Mr. Narender M. Sharma with
                            Mr. Abhishek Sharma and Ms. Aarthy
                            Venkat, Advocates.

        CORAM: JUSTICE S.MURALIDHAR

                            ORDER

% 07.12.2012

1. The challenge in this petition under Section 34 of the Arbitration and

Conciliation Act, 1996 ('Act') is to an Award dated 21st February 2007

passed by the arbitral Tribunal ('AT') in the dispute between the Petitioner,

Delhi Transco Limited ('DTL') and the Respondent, Techno Electrical and

Engineering Limited ('Techno') arising out of an agreement dated 9th

March 1993 entered into between the parties for erection, testing and

commissioning of the 400/220 KV Bamnauli sub-station.

2. Under the agreement, DTL [earlier known as Delhi Vidyut Board

('DVB')] was described as the 'Owner' and Techno was described as the

'Contractor'. The relevant Clause 20 of the Instructions to the Bidder

provided as under:

"The bidders insurance liabilities pertaining to the scope of work are detailed out in clauses titled 'insurance' in Section GCC, Section CSE & Section ECC of Conditions of Contract Volume - I. The Bidders attention is specifically invited to these clauses. The bid price shall include all the costs in pursuance of fulfilling of the insurance liabilities under the contract."

3. The responsibility for taking out insurance policy for both the owner

supplied as well as contractor supplied items was of the Contractor. This

was spelt out in various clauses of the Erection Conditions of Contract

('ECC'), General Terms of Contract ('GTC') as well as Special Conditions

of the Contract ('SCC') which read as under:

"17.1 Insurance (ECC)

The Contractor shall take adequate insurance coverage for all the risks and hazards which will pertain to all the services to be provided under the Contract and pursuant to his employees. The Contractor in all cases will keep the Owner indemnified against any claim resulting from failure of the Contractor to main all necessary insurance coverage to the required extent both in time and in value to take care of all his liabilities, either direct or indirect in pursuance of the contract.

17.2 In addition to the conditions covered under the Clause entitled insurance in General Terms and Conditions of Contract of this Volume I, the following provisions will also apply to the portion of works to be done beyond the Contractor's own or his sub-Contractor's manufacturing works.

19.0 Insurance (GTC)

19.1 The Contractor at his cost shall arrange, secure and maintain all insurance as may be pertinent to the works and

obligatory in terms of law to protect his interest and interests of the owner against all perils detailed herein. The form and the limit of such insurance as defined herein together with the underwriter in each case shall be acceptable to the owner. However, irrespective of such acceptance, the responsibility to maintain adequate insurance coverage at all times during the period of contract shall be of contractor alone. The Contractor's failure in this regard shall not relieve him of any of his contractual responsibilities and obligations. The insurance covers to be taken by the Contractor shall be in a joint name of the Owner and the Contractor. The Contractor shall, however, be authorized to deal directly with Insurance company or Companies and shall be responsible in regard to maintenance of all insurance covers. Further, the insurance should be in freely convertible currency.

19.2 Any loss or damage to the equipment during handling transportation, till sixty days after receipt of the equipment and material at site, (in case of supply contracts) and during storage, erection, putting into satisfactory operation and all activities to be performed till such time the plant in 'Taken Over' by the Owner (in case of Supply-cum-Erection Contracts) shall be to the account of the Contractor. The Contractor shall be responsible for preference of all claims and make good the damage or loss by way of repairs and/or replacement of the equipment, damaged or lost. The transfer of title shall not in any way relieve the Contractor of the above responsibilities during the period of Contract. The Contractor shall provide the Owner with copy of all insurance policies and documents taken out by him in pursuance of the Contract. Such copies of documents shall be submitted to the owner immediately after such insurance coverage. The Contractor shall also inform the owner in writing at least sixty (60) days in advance regarding the expiry/cancellation and/or change in any of such documents and ensure revalidation, renewal etc. as may be necessary well in time.

19.3 All costs on account of insurance liabilities covered under the Contract will be on Contractor's account and will be included in Contract Price. However, the Owner may from time to time, during the pendency of the Contract, ask the Contractor in writing to limit the insurance coverage, risks and in such a case, the parties to the Contract will agree for a

mutual settlement, for reduction in Contract Price to the extent of reduced premium amount. The Contractor while arranging the insurance shall ensure to obtain all discounts on premium which may be available for higher volume or for reason of financing arrangement of the Project.

19.4 The clause entitled 'insurance' under the section CSE/ECC of this Volume-I, covers the additional insurance requirements for the portion of the works to be performed at the site.

15.0 Storage-cum-Erection Insurance (SCC)

15.1 All the equipment and materials being supplied by the contractor (as per the relevant clause of Tech. Spec. Vol. II) shall be dept (sic. kept) completely insured by the Contractor at his cost from the time of dispatch from the Bidder's works, up to the completion of erection, testing and commissioning at site and taking over the substation by the Owner in accordance with the contract.

15.2 Further all the equipment and materials being supplied by the Owner for the erection of the substation (as per the relevant clause of Tech. Spec. Vol. II) shall be kept insured by the Contractor against loss, damage, theft, pilferage, fire etc. from the point of unloading up to the time of taking over of substation by the owner including handling, transportation, storage, erection, testing and commissioning etc. The premium paid to the insurance Company by the contractor for such insurance shall be reimbursed by the Owner to the Contractors at actuals against documentary proof to be furnished by the Contractor. The Contractor shall obtain competitive quotations for such insurance and shall take prior approval from the owner before taking the insurance. The insurable value of the equipment being procured by the owner will be intimated to the Contractor for affecting the insurance.

15.3 It will be the responsibility of the Contractor to lodge, pursue and settle all claims with the insurance company in case of any damage, loss, theft, pilferage or fire and the owner shall be kept informed about it.

The contractor shall be responsible for the replacement of loss/

damage etc. in the execution of the contract to any equipment/ material, both owner supplied as well as contractor supplied items irrespective of the time or amount of receipt of insurance claim. Any loss in this shall be to the Contractor's account."

4. It is stated by DTL that initially Techno sought a change in the wording

of Clause 15.3. However this was refused by DTL. Therefore, the said

clause was retained as such. It is not in dispute that on 14th May 1997 there

was a major fire at the store-yard of the Bamnauli Sub-station which was

then under the control of Techno. The material supplied by the DVB to

Techno the approximate worth of which was Rs. 6.5 crores was destroyed

in the fire.

5. Techno had, in terms of the above conditions of contract, taken out the

insurance policy in terms of which such owner supplied materials were

fully insured for any loss. There was a clause in the insurance policy which

provided for 10% towards 'excess deductible'. In response to the claim

lodged with it, the Insurer allowed the claim only to the extent of Rs.

5,07,03,819.70 after adjusting certain deductions including 10% towards

excess clause in terms of the insurance policy. The salvage value was also

deducted.

6. It appears that in terms of the contract, Techno undertook to replace the

equipment that was destroyed in the fire. In addition to the sum of Rs.

5,07,03,819.70 which was received by it from the insurance company on

behalf of DTL, it sought a further payment of Rs. 5,12,30,366.80, being

10% of the value of the material supplied i.e., Rs. 51,23,036.68.

Accordingly, by its letter dated 30th December 1998 Techno requested the

DVB to release a sum of Rs. 50 lakhs. Pursuant thereto, a sum of Rs. 50

lakhs was released by DVB to Techno.

7. It is not in dispute that fresh equipment was purchased and then installed

and commissioned by Techno. The present dispute began with Techno

asking the DVB by its letter dated 8th July 1999 for the salvage which was

valued at Rs. 17.51 lakhs and deducted by the insurance company while

settling the insured claims. At this stage, DVB appears to have raised an

objection that in terms of Clause 15.3 of the SCC any loss on account of the

damage prior to the equipment was to be borne by Techno and therefore,

even the payment of Rs. 50 lakhs should not have been made by it in the

first place to Techno. Accordingly, by its letter dated 25th August 2000

addressed to Techno DVB demanded refund of the sum of Rs. 50 lakhs for

the release of salvage value of the burnt material. It was stated that in the

event that the said sum of Rs. 50 lakhs was not returned to it within 15 days

"the DVB will be free to dispose off the salvage and adjust the amount to

their account."

8. The disputes that resulted were referred to the three-member AT. DTL

filed a statement of claim praying that Techno should be asked to pay Rs.

50 lakhs together with interest @ 24% per annum from 12th March 1999 till

the date of payment. It was stated by DTL that the said amount was

recoverable by DVB from Techno since this amount was short received

from the insurance company against the (initial) 'excess' deductibles to be

borne by the beneficiary under the insurance policy/contract of insurance.

9. The case of DTL was that under Clause 15.3 of the SCC the above

'excess' was to be borne by Techno. Counter claims were filed by Techno

praying that DTL should be asked to release the balance payment of Rs.

6,33,757.76 out of Rs. 56,33,757.76 being the amount not paid by the

insurance company in pursuance of provision of insurance policy.

Additionally, Techno prayed that DTL should be directed to "immediately

release sum of Rs. 17,51,035.72 being the amount deducted by insurance

company towards salvage value of material which is in DVB custody since

July 1999." Techno also claimed interest @ 18% on the above sums.

10. In the impugned Award dated 21st February 2007 the AT held as under:

(i) In respect of the owner supplied equipment, the Contractor acted

as an agent and the responsibilities of the agent are spelt out in

Clause 15.3 of SCC. The responsibility of the Contractor with regard

to the insurance provisions in respect of owner supplied items could

not be same, as in respect of contractor supplied materials,

(ii) In respect of the owner supplied materials, the Contractor was to

act as an agent and insurance premium was to be reimbursed at actual

amount towards excess paid by DTL.

(iii) As regards the excess deductible amount by the insurance

company under the insurance policy this was 'an indeterminate

amount' and could not be passed on the Contractor who was not a

party to the said insurance contract.

(iv) In respect of the words 'loss in this' in Clause 15.3 of the SCC,

"can only be presumed to include such of those liabilities arising out

of a default by the Contractor in his providing the insurance

coordination services or due to any other act of negligence on his

part."

(v) The excess under the insurance policy could not be classified

anything other than a part of total insurance policy cost. The bid

document did not envisage the said cost to be on account of the

Contractor.

(vi) The counter claims of Techno were not time-barred since the

cause of action occurred within three years prior to the date of

Techno making the counter claim, i.e., 27th May 2003.

(vii) The counter claim of Techno for the balance amount of Rs.

6,33,757.76 was allowed together with interest @ 12% per annum

within 30 days after 25th March 2002 till the date of the Award.

Techno was held entitled to salvage value of Rs. 17,51,035.72

together with simple interest @ 12% per annum with effect from 1st

September 1999 till the date of the Award. On both the above

amounts, the post-Award interest was granted at 18% per annum

from the date of the Award till the date of actual payment.

11. This Court has heard the submissions of learned counsel for the parties.

It is submitted on behalf of DTL that the interpretation placed on Clause

15.3 of the SCC by the AT was contrary to the expressed wording of the

said clause which made it unambiguously clear that it is the Contractor who

will be responsible for the replacement of loss/damage etc. in the execution

of the contract and for any equipment/material, both owner supplied as well

as contractor supplied irrespective of the time or amount of receipt of

insurance claim. The said clause further made it clear that "any loss in this

shall be to the Contractor's account." It is further submitted that inasmuch

even as the stage of entering into the contract Techno's suggestion for

amending the above clause was rejected, the said clause had to be

interpreted as meaning that any shortfall in the insurance claim in respect of

the owner supplied equipment had to be made good by Techno.

12. The records show that the insurance company had by its letter dated 16th

August 1999 allowed the claim to the extent of Rs. 5,83,67,857.27 and after

deducting both 10% excess value as well as salvage value settled it for a

sum of Rs. 5,07,03,819.70. At that stage, DTL did not protest. In fact it

directed Techno to receive the amount since in terms of the contract the

policy was to be taken out and claim was also to be lodged only by Techno.

13. In the circumstances, this Court does not find any error committed by

the AT in interpreting the relevant clause to mean that the Contractor was

only acting as an agent of the Owner when it took out an insurance policy

for the owner supplied material. Subsequently it also lodged a claim in

respect of the damage to the said material. As already noted, while making

those purchases, Techno asked DTL to give it an ad hoc payment of Rs. 50

lakhs to make up the differential amount. This was paid by DTL to Techno.

In other words the sum of Rs. 50 lakhs was not relatable to any shortfall of

the insurance claim [which was to the extent of Rs. 56,33,757.76] or to the

salvage value of Rs. 17,51,035.72. It was relatable to the differential

amount in purchasing afresh the owner supplied equipment which came to

be installed and commissioned. It was only at the stage of Techno asking

DTL to compensate for the salvage that DTL asked for refund of Rs. 50

lakhs. It must be noted that under the contract in question, the salvage was

to go to Techno.

14. The letter dated 25th August 2000 written by DTL to Techno (Ex. C-119

in the arbitral proceedings) has been adverted to by the AT as well. The

letter does indicate that DTL did not question that the salvage value was

approx. Rs. 17.51 lakhs and that this was deducted by the insurance

company while settling the claim. The case of DTL was that the said

salvage amount can be released to Techno only if Techno returned to DTL a

sum of Rs. 50 lakhs.

15. The cause of action for Techno to claim the salvage value of approx. Rs.

17.51 lakhs arose with the letter dated 25th August 2000 of DTL.

Consequently, when Techno lodged the counter claims on 27th May 2003

they were certainly within time as rightly held by the AT. In the above

circumstances, this Court is of the view that the conclusion drawn by the

AT on reading of Clause 15.3 of the SCC was a plausible view. In any

event DTL cannot possibly link the sum of Rs. 50 lakhs to the 10% excess

deducted under the insurance policy. There was no reason for DTL to have

limited its claim in that regard to Rs. 50 lakhs.

16. In that view of the matter, this Court is not inclined to interfere with the

impugned Award of the AT to the extent it rejected DTL's claim for refund

of Rs. 50 lakhs. However, this Court finds that the reasons for rejection of

the claim by Techno for the balance amount of Rs. 6,33,757.76 is wholly

inadequate. The AT appears to have overlooked the fact that in relation to

the owner supplied equipment, any shortfall in the insurance claim can at

best be on account of DTL. Title to the said equipment was never passed on

Techno. Consistent with the view that Techno was acting as an agent of

DTL, balance amount of Rs. 6,33,757.76 arising out of the shortfall of the

insurance claims settled could not go to the account of Techno.

Consequently, this Court has no hesitation in setting aside the Award which

directed the payment by DTL to Techno of the sum of Rs. 6,33,757.76

together with simple interest @ 12% per annum from 25th April 2000 till

the date of payment.

17. As regards the salvage value in the sum of Rs. 17,51,035.72 this Court

is not inclined to interfere with the impugned Award as it is consistent with

the clauses of the contract.

18. As a result, the impugned Award to the extent of the award of a sum of

Rs. 6,33,757.76 together with interest @ 12% per annum in favour of

Techno is set aside. The remaining Award is upheld. The petition is

disposed of in the above terms.

S. MURALIDHAR, J DECEMBER 07, 2012 Rk

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter