Citation : 2011 Latest Caselaw 4861 Del
Judgement Date : 29 September, 2011
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ LETTERS PATENTS APPEAL 799/2011
% Date of Decision: September 29, 2011
DELHI DEVELOPMENT AUTHORITY ..... Appellant
Through Mr. Ajay Verma and Mr. Manu
Parashar, Advocates.
versus
SURESH GUPTA & ORS. ..... Respondents
Through
CORAM:
HON'BLE THE CHIEF JUSTICE
HON'BLE MR. JUSTICE SANJIV KHANNA
ORDER
SANJIV KHANNA, J.:
CM No. 18271/2011
This is an application for condonation of delay of 221 days
in preferring the appeal.
2. Before issuing notice on the application for condonation of
delay, we have thought it apt to examine the matter on merits.
3. Contention of the appellant-Delhi Development Authority
(DDA) is that the respondent Nos.1 and 2 should be asked to pay
land rates prevalent in 2006. It is submitted that the learned single
Judge in the impugned order dated 10th January, 2011 has erred
in holding that the land rate prevalent as on 1st January, 1993
should be applied. It is submitted that the initial allotment by the
appellant-DDA to one K.D. Sikand vide perpetual sub-lease deed
dated 28th December, 1987 was illegal.
4. Plot No.E-1091, Government School Teacher CHBS was
allotted to K.D. Sikand vide perpetual sub-lease deed dated 28th
December, 1987. She transferred her rights in the plot vide
General Power of Attorney (GPA)/Agreement to Sell dated 18th
March 1988 in favour of Anil Kumar/ Sarla Devi/ Sadhana Devi.
There was another transfer by the said purchasers on 8th
December, 1989 in favour of the respondent Nos.1 and 2. The
said respondents applied to Municipal Corporation of Delhi (MCD)
for sanction of building plan and after approval, constructed a two
and a half storeyed building on the plot in 1990-91.
5. In order to regularize the transfers made on Power of
Attorney basis and convert lease hold rights in the plots into free
hold, appellant-DDA had promoted a conversion scheme.
Respondent No.1 on 20th May, 1992 applied to the DDA for
conversion of the leasehold rights to freehold rights in respect of
the said plot and paid the entire conversion charges. The said
respondent also paid additional penalty charges to the DDA as
the original sub-lessee had transferred/parted with possession of
the plot to third parties contrary to the terms of the sub-lease deed
and the said respondent was the beneficiary.
6. It is not disputed and denied by the appellant that the
respondents were bona fide purchasers for value and were not
aware of any defect or fraud played by the original allotee to
procure allotment. In fact, DDA itself was not aware of any such
fraud.
7. By communicated dated 28th September, 1992, the
appellant informed the respondent No.1 that the original sub-lease
deed dated 28th December 1987 executed in favour of K.D.
Sikand had been cancelled and, therefore, the request for
conversion from lease hold to freehold stood rejected. It was
alleged that K.D. Sikand has failed to disclose that she already
owned a flat and, therefore, was not eligible for allotment of the
plot in 1987. The respondents kept on corresponding with the
DDA but without success and ultimately, as a last resort,
approached the Court by way of W.P.(C) 820/2008, which has
been disposed of by the impugned order dated 10th January,
2011.
8. We have already noticed the facts in detail above. There
cannot be any doubt that the respondent Nos.1 and 2 purchased
the sub-lease rights in respect of the plot, which was originally in
1987 allotted to K.D. Sikand. They paid the entire sale
consideration in 1989 and thereafter constructed a two and a half
storeyed building on the plot. They had in 1992 applied for
conversion of the lease hold rights into free hold and had paid the
conversion charges as well as the penalty charges to regularize
the purchase pursuant to which the lease hold rights and
possession of the plot was transferred.
9. The dispute is whether the said respondents should be
asked to pay the price prevailing as on 1st January, 1993 or in
2006. In our considered opinion, the learned single Judge has
rightly held that the price prevalent as on 1st January, 1993 is
payable by the respondent Nos. 1 and 2 and not the price
prevailing in 2006. The respondents had applied for conversion
from lease hold to free hold in May, 1992 and had also deposited
payment including penalty charges. The said payment has
remained with the appellant. It was for the appellant-DDA to take
a decision in such cases, which are peculiar, as the said
respondents who applied for conversion had deposited the
payment and penalty amount, are not guilty of fraud and if at all
they have also suffered on account of the fraud committed by the
original allottee. There is no explanation why the appellant-DDA
took nearly 14 years from 1992 till 2006 to decide how to deal with
such peculiar cases. Lapse and delay on the part of the appellant
cannot be a ground to enhance liability, which is payable and is
now being demanded from the respondent Nos.1 and 2. The
respondent Nos. 1 and 2 have paid the conversion costs, penalty
amount for illegal transfer, and the purchase price to the sub-
lessee or her attorney. The respondent Nos. 1 and 2 have been
now asked to pay the purchase price to the appellant-DDA.
10. It may be noticed here that the averments made in the
application for condonation of delay of 221 days are vague and
except for stating that the matter was being debated and
examined at various levels, no other reason or ground is given.
11. In view of the aforesaid, there is no justification to issue
notice on the application for condonation of delay and,
accordingly, the application for condonation of delay stands
rejected and as an evitable corollary, the appeal also stands
dismissed in limine.
SANJIV KHANNA, J.
CHIEF JUSTICE September 29, 2011 NA/VKR
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!