Citation : 2011 Latest Caselaw 4320 Del
Judgement Date : 5 September, 2011
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO No.190/2008
% 5th September, 2011
SH. RANJIT SINGH RANA . ......Appellant
Through: Mr. Salil Kumar Jha, Advocate
with Mr. Puneet Rai, Advocate.
VERSUS
PUBLIC WORKS DEPARTMENT & ANR. ...... Respondents
Through: Ms. Ruchi Sindhwani,
Advocate.
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be
allowed to see the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
VALMIKI J. MEHTA, J (ORAL)
1. The challenge by means of this First Appeal under Section 37
of Arbitration & Conciliation Act, 1996 (hereinafter referred to as 'the
Act') is to the impugned order of the Court below dated 22.11.2007 which
has dismissed the objections of the appellant/objector under Section 34
of the Act.
FAO No.190/2008 Page 1 of 6
2. The facts of the case are that the objector was awarded by
the respondents the work of providing fencing on 60 meter right of road
in Dwarka, Delhi, vide agreement dated 14.7.1992. Since the site of
work was not handed over by the DDA to the respondents, the work could
not be executed and therefore the respondents exercising its rights
under Clause 13 of the agreement foreclosed the work. Disputes and
differences arose between the parties whereupon the matter was
referred to arbitration. I may note that the contract in question was
foreclosed way back in the year 1992 and the arbitration in fact
commenced after the series of litigation only when the appellant filed its
statement of claim under the cover of its letter dated 22.5.2006.
3. There were six claims which were raised by the
appellant before the arbitrator. The first claim was for the hire charges of
machinery. While dealing with this claim, the Arbitrator has referred to
the fact that since even the initial construction of the godown and water
tank was not permitted by the DDA officials, therefore, the appellant
should not have unnecessarily mobilized any machinery. Further, the
Arbitrator has held that there was physical verification of only two old
concrete mixers and nothing more. The Arbitrator has also then referred
to the fact that no receipts were filed for payment of hire charges of the
FAO No.190/2008 Page 2 of 6
machineries and in fact claimants removed the machinery without joint
inspection and therefore the claim remained unsubstantiated. A court
hearing objections does not sit as an Appellate Court over the findings
and conclusions of the Award. Merely because two views are possible, the
court hearing objections cannot interfere with the Award. In my opinion,
the Arbitrator has given the aforesaid valid reasons for denying this claim
and I therefore reject the argument with respect to this claim
4. Claim No.2 as made by the appellant was for supervisory
staff and head office expenses. In this regard, the Arbitrator has noted
that no documentary evidence was there with respect to the deployment
of a graduate engineer and with respect to the other staff it could not be
said that the staff was exclusively allocated for the subject work only.
Considering the facts and circumstances, the Arbitrator awarded a sum of
Rs.12,500/-. Issues of appreciation of evidence and determination of an
amount, is in the realm of jurisdiction of the Arbitrator, and a court
hearing objections does not sit as an Appellate Court, unless the findings
are wholly illegal or beyond the provisions of the contract or perverse. In
view of the facts as found by the Arbitrator, there is no illegality or
perversity or any violation of provisions of contract so as to held that
Award with respect to the Claim no.2 is liable to be set aside.
FAO No.190/2008 Page 3 of 6
5. Claim No.3 was the claim for loss of profit. The Arbitrator has
referred to Clause 13 of the agreement which gave a right to the
respondents to foreclose the agreement without any consequential loss
including the claim towards loss of profit. In the present case, since the
site was not made available to the respondents because the DDA refused
to hand over the same the respondents exercised its power under Clause
13 and therefore, the Arbitrator by referring to such Clause as applicable
to the facts of the case has denied compensation towards loss of profit.
Once again, I do not find any illegality or violation of the provisions of the
contract or perversity in the Award for this court to interfere.
6. The only other issue which was urged before this court was
that the interest should have been awarded with respect to Claim Nos. 4
and 6. I may note that the main arbitration proceedings commenced at
the end of May, 2006 and the Award was passed on 14.10.2006. The
Arbitrator in his wisdom has not granted any interest for this short period,
and I do not propose to interfere with the Award on this basis inasmuch
as the complete amount due under the Award has been paid by the
respondents within a period of three months of publishing of the Award.
7. The last claim was the claim of cost of arbitration
proceedings. The claimant had claimed a sum of Rs.10,000/- and the
FAO No.190/2008 Page 4 of 6
Arbitrator has awarded Rs.5000/- as costs of arbitration. Unless the
Award is wholly illegal or perverse, a court hearing objections or the
Appellate Court will not unnecessarily interfere. I do not find any
illegality or perversity in the facts and circumstances of the case and hold
that the grant of costs of Rs.5000/- instead of Rs.10,000/- is in no manner
illegal or perverse.
8. The scope of hearing objections to an Award is limited. If the
scope of hearing objections to an Award is limited, then the scope of
hearing of an appeal against the order dismissing the objections has to
be further limited. Unless there is a gross perversity or gross illegality,
this court cannot interfere in an appeal. In view of the above facts and
conclusions with respect to each of the claim decided, I do not find that
there is any gross illegality or perversity so as to interfere with the
impugned order.
Learned counsel for the appellant states that though the
cheque of the awarded amount was received, the same was not
encashed, and he prays that fresh cheque may now be issued.
Accordingly, let the respondents issue a fresh cheque of the awarded
amount to the appellant within a period of 4 months from today on the
FAO No.190/2008 Page 5 of 6
appellant returning the unencashed cheque within a period of one week
from today.
9. With the aforesaid observations, the appeal stands
dismissed, leaving the parties to bear their own costs.
SEPTEMBER 05, 2011 VALMIKI J. MEHTA, J.
Ne
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!