Citation : 2011 Latest Caselaw 5163 Del
Judgement Date : 20 October, 2011
THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment Pronounced on: 20.10.2011
+ CS(OS) 1676/2007
KAUSHALYA CONTRACTOR & DEVELOPERS (P) LTD.
..... Plaintiff
Through: None.
versus
JASPAL KAUR PUBLIC SCHOOL ..... Defendant
Through: Mr Jasmeet Singh and
Mr Saurabh Tiwari, Advs.
CORAM:-
HON'BLE MR JUSTICE V.K. JAIN
1. Whether Reporters of local papers may
be allowed to see the judgment? No.
2. To be referred to the Reporter or not? No.
3. Whether the judgment should be reported No.
in Digest?
V.K. JAIN, J. (ORAL)
1. This is a suit for recovery of Rs 20,20,326/- and a
counter claim for recovery of Rs 6,42,500/- The defendant
awarded work of renovation of toilet block in the school to
the plaintiff, vide award letter dated 17th May, 2006 and the
work was to be completed by 25th June, 2006. It is alleged
in the plaint that the plaintiff mobilized the machines,
equipments AND labour and started work for renovation of
toilet block of defendant school, but, it was asked to carry
out extra work, to the tune of Rs 8,27,513.35/-, which was
not stipulated in the award letter and, therefore, it could not
meet the deadline fixed in the award letter. This is also the
case of the plaintiff that the awarded work as well as the
extra work was completed by it by the first week of July,
2006. According to the plaintiff, it carried out total work for
Rs 28,93,579.85/- which comprised the awarded work for
Rs 20,66,066.50 and extra work for Rs 8,27,513.35. This is
also the case of the plaintiff that though only a sum of Rs
64,931 was to be deducted towards income tax at source,
the defendant deducted a sum of Rs 1,15,743.49. The
plaintiff accordingly submitted a final bill of Rs
23,21,064.17 after giving adjustment for the advance
payment of Rs 3,91,840/- which it had received from the
defendant. The defendant made payment of Rs 4,88,780/-
to the plaintiff. It is also alleged that the architect appointed
by the defendant informed the plaintiff that a sum of Rs
1,50,000/- had been deducted for rectification of the work
carried out by another contractor. Since the balance
amount was not paid, the plaintiff has claimed the balance
principal sum of Rs 17,35,750.91 along with interest on
that amount, thereby making a total sum of Rs 20,20,326/-
2. The defendant filed written statement contesting
the suit and also filed the above-referred counter claim of
recovery of Rs 6,42,500/-.
The defendant denied the authority of Mr Jagdish
Sharma to instate the suit and sign and verify the pleadings
on behalf of the plaintiff. It was also alleged that time was
the essence of the contract and, therefore, the work was to
be completed at all costs by 25 th June, 2006, the reopening
date for the school being 03rd July, 2006. It is further
alleged that the plaintiff defaulted for adhering to the time
schedule and executed work of a sub-standard nature. It is
also alleged that the plaintiff did not complete even 40% of
the work and raised exaggerated bills. It is claimed that the
architect M/s Myriad Perceptions checked the quality of the
work done by the plaintiff and accordingly a sum of Rs 9
lakh was paid to the plaintiff. Since the work executed by
the plaintiff was sub-standard and defective, the defendant
had to get the same re-done through M/s Mbience Interior
Designer and Furnishers and pay a sum of Rs 12,43,379/-
for the aforesaid rectification and modification and to
complete the balance work which the plaintiff had not
executed. It is also alleged that on account of delay by the
plaintiff in executing the work, the defendant had to install
portable toilets in order to avoid inconvenience to the
children. The defendant claims to have incurred additional
expense of Rs 67,500/-for hiring mobile toilet. According to
the defendant, it is entitled to recover a sum of Rs
5,75,000/- from the plaintiff for the rectification of the sub-
standard and inferior work executed by the plaintiff as also
for building the work which the plaintiff company did not
execute and a sum of Rs 67,500/- paid for hire of mobile
toilets, thereby making a total sum of Rs 6,42,500/-.
3. The following issues were framed on the pleadings
of the parties:-
i. Whether the suit has been instituted and the plaint
signed and verified by a duly authorized person on
behalf of the plaintiff? OPP
ii. Whether the plaintiff is entitled to recover any balance
amount for works done for the defendant and if so how
much? OPP
iii. Whether the plaintiff failed to complete the works
awarded? OPD
iv. Whether the defendant had to get the works completed
and rectified from another party and if so to what effect?
OPD
v. Whether the counter claim has been instituted and
signed and verified by a duly authorized person on
behalf of the defendant? OPD
vi. Whether the defendant is entitled to recover any
amounts from the plaintiff for any works left incomplete
by the plaintiff and/or for rectification of the defective
work done by the plaintiff and/or for delay caused by the
plaintiff and if so what amount? OPD
vii. Whether the party entitled to found recovery of any
monies from the other, entitled to any interest and if so
at what rate and for what period? OPP
viii. Relief
4. No evidence has been let by the plaintiff. The issue
is, therefore, against the plaintiff and in favour of the
defendant.
5. The defendant has placed on record the copy of the
resolution passed in the General Body Meeting of Mata Jai
Kaur Charitable Trust on 3rd October, 2007 whereby
Mr.George Mathew, Principal of Jaspal Kaur Public School,
which is stated to be a school being run by Mata Jai Kaur
Charitable Trust, was authorized to
commence/institute/defend/file cases for and on behalf of
Jaspal Kaur Public School. Since there is no evidence in
rebuttal, I hold that the counter-claim has been signed and
verified and the suit instituted by a competent person on
behalf of Mata Jai Kaur Charitable Trust. The issue is
decided accordingly.
6. These issues are inter-connected and can be
conveniently decided together. The plaintiff has not
produced any evidence and in fact after 20 th January, 2011,
no one has been appearing for the plaintiff. Vide order
dated 20th January, 2011, the Court noted that cost of
Rs.1,000/- was imposed on the plaintiff on 15th December,
2008, cost of Rs.3,000/- was imposed on it on 10 th May,
2010 and cost of Rs.10,000/- was imposed on
22nd September, 2010. It was further noted that the Court
had, while passing the order dated 22nd September, 2010,
also directed that if the plaintiff failed to pay the costs which
were imposed on 15th December, 2008 and 10th May, 2010
as also the cost imposed on that date, the suit shall stand
dismissed for non-prosecution. Since neither the cost were
paid nor any witness was produced by the plaintiff and the
learned counsel appearing for the plaintiff stated on 22nd
January, 2011 that he was not getting any instructions
from the plaintiff, the evidence of the plaintiff was closed.
7. The defendant has filed affidavit of Mr. George
Mathew, Principal of Jaspal Kaur Public School by way of
evidence in the counter-claim. In his affidavit, Mr. George
Mathew has stated that the work carried out by the plaintiff
was not only sub-standard, defective, shabby, but also
below par and far from satisfactory. According to him, the
following defects were found in the work carried out by the
plaintiff:-
(a) The poor workmanship in the shaft area of toilet led to
heavy seepage in all the floors causing substantial damage
to other floors and the concrete.
(b) Due to delay in the contract time, the defendant had to
install portable toilet to avoid inconvenience to the children,
which cost heavily to the school.
(c) The connection pipes used were of substandard quality
as they were already corroding again causing seepage and
damage to the concrete.
(d) Tiles were not laid properly on the floor as no level was
maintained. Due to this, there was water logging on the
floor.
(e) The partitions between the W.C's were not fixed properly,
and were shaking. They had to be refixed again.
Mr. George Mathew also stated that the plaintiff
did not complete even 40% of the work awarded to it and
raised highly exaggerated bills which included bills for the
work which it had not done. He has further stated that
since the plaintiff did not complete the work in time, the
school had engaged the other contractor, namely, Mbience
Interior Designers and Furnishers Delhi, to do the balance
work in which an additional expense of Rs.12,43,379/- was
made towards the costs of rectification of the substandard
work done by the plaintiff. Ex.DW-1/2 & Ex.DW-1/3 are
the invoices raised by M/s. Mbience Interior Designers and
Furnishers in respect of the work executed by it.
Ex.DW-1/4 is the certificate dated 21st November, 2007
issued by Punjab and Sind Bank certifying for the payment
of Rs.12,43,379/- to M/s.Mbience Interior Designers and
Furnishers Delhi. Ex. DW-1/5 is the letter dated 17 th July,
2006 which the Architect of the defendant had returned to
the plaintiff pointing out the work not done by the plaintiff.
According to Mr. George Mathew, the defendant had to hire
mobile toilets for a period of five days after re-opening of the
school, i.e. from 3rd July, 2006 to 7th July, 2006 and Ex.DW-
1/6 is the invoice raised by Superloo in this regard. Ex.DW-
1/7 is the certificate from the bank verifying the payment
made to M/s. Superloo. Mr.Mathew has also stated that the
defendant has already made payment of Rs.8,80,620/- to
the plaintiff, which was verified by the Bank vide certificate
Ex.DW-1/8. I see no reason to disbelieve the unrebutted
testimony of Mr. George Mathew and, therefore, hold that
the work executed by the plaintiff company besides being
incomplete was also sub-standard and defective and,
therefore, the defendant had to incur expenditure of
Rs.12,43,379/- in removing the deficiencies in the work and
completing the work which was left unfinished by the
plaintiff. There is no evidence of any extra work having been
executed by the plaintiff for the defendant. The evidence
shows that even the awarded work was not completed by
the plaintiff. The testimony of Mr. George Mathew also
shows that the defendant has paid a sum of Rs.8,80,620/-
to the plaintiff. It has been admitted in the plaint that the
defendant had deducted a sum of Rs.1,15,743.49 from the
bill of the plaintiff towards income-tax to be deducted at
source. The aggregate of the amount of Rs.12,43379/-
which the defendant paid to M/s. Mbience Interior
Designers and Furnishers, Rs.8,80,620/- paid to the
plaintiff and Rs.1,15,743.49 deducted towards payment of
income-tax comes to Rs.22,39,742.49. The defendant had
to pay a sum of Rs.20,04,240/- to the plaintiff. The
defendant also paid a sum of Rs.67,500/- to M/s.Superloo
on account of the failure of the plaintiff Company to execute
the work within the time stipulated for this purpose. After
deducting the sum of Rs.20,04,240/- which it was required
to pay to the plaintiff, the defendant is entitled to recover
the balance amount of Rs.303002.49 from the plaintiff
Company. The issues are decided accordingly.
ORDER
In view of my findings, the suit is hereby dismissed
with cost.
Counter-Claim 53/2008
A decree for Rs.303002.49 with proportionate costs and
pendente lite and future interest @ 6% per annum is passed
in favour of Mata Jai Kaur Charitable Trust which runs
Jaspal Kaur Public School and against the plaintiff
company.
Decree sheet be drawn accordingly.
(V.K. JAIN) JUDGE OCTOBER 20, 2011 BG/'sn'/'vn'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!