Citation : 2011 Latest Caselaw 5509 Del
Judgement Date : 16 November, 2011
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ RFA No.509/2002
% November 16, 2011
RAKESH KUMAR ..... Appellant
Through: Mr. C.B.N. Babu, Advocate
Versus
THE NUCLEAR SCIENCE CENTRE & ORS. ..... Respondents
Through: Mr. A. Konar, Advocate
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be
allowed to see the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
VALMIKI J. MEHTA, J. (ORAL)
1. This Regular First Appeal filed under Section 96 of the Civil
Procedure Code, 1908 (CPC) impugns the judgment and decree of the trial
court dated 02.04.2002 by which the suit of the appellant/plaintiff for
recovery of ` 3,50,963/- was dismissed.
RFA No. 509/02 Page 1
2. The facts of the case are that the appellant-contractor was awarded a
contract for making a New Bitumen Road for the respondent No. 1/Nuclear
Science Centre vide letter of intent dated 01.03.2000. The total estimate of
the work to be done was ` 12,42,000/- and bills were to be submitted as per
the actual measurement of work done from time to time. The work relating
to seal coat was to be done @ ` 20/- per square meter. The
appellant/plaintiff claims to have completed the work and submitted a final
bill. After giving due adjustment for payment made, it was claimed that an
amount of ` 2,24,798/- was due. It was stated that the
respondents/defendants through their letter dated 11.05.2000 pointed out
certain defects which were rectified by the appellant/plaintiff. The
appellant/plaintiff also claimed that an extra work to the tune of ` 39,632/-
was done. The subject suit came to be filed for recovery of ` 2,24,798/- as
the balance payment of the work done, an amount of ` 83,517/- as security
deposit and ` 42,648/- as interest @ 24% per annum totaling to `
3,50,963/-.
3. The respondents/defendants contested the suit and pleaded that as per
the joint inspection carried out between the parties on 08.05.2000 it became
RFA No. 509/02 Page 2 apparent that the work of the appellant/plaintiff was not satisfactory and
therefore a detailed list of works to be rectified was supplied to the
plaintiff/appellant vide letter dated 11.05.2000. Though the
appellant/plaintiff by its letter dated 22.05.2000 claimed that deficiencies
were removed, however, when the representatives of the Central Roads
Research Institute (CRRI) visited the site on 25.05.2000 it was found that
there were deficiencies in the work and which were pointed out to the
appellant/plaintiff vide a letter dated 31.05.2000. The appellant/plaintiff by
means of two letters dated 07.06.2000 (Ex. DW-1/2) and 19.06.2000 (Ex.
DW-1/3) admitted the defects in the work and promised to rectify the same,
however, the work which was to be done after a rainy season was not done
by the appellant/plaintiff and therefore this was notified to the
appellant/plaintiff by the respondent No. 1/defendant No. 1 vide its letter
dated 26.09.2000 (Ex. DW-1/1). It was also pleaded that the
appellant/plaintiff relied upon a report of the CRRI dated 26.07.2000 (Ex.
PW-1/12), however, that report only dealt with the content of the Bitumen in
the seal coat but not with respect to the issue of the defective nature of work.
4. The trial court after the pleadings were completed framed the
RFA No. 509/02 Page 3 following issues:
"1. Whether plaintiff has not performed the contract to the satisfaction of the defendant, if so its effects? OPD
2. Whether defendants have made payment in respect of the agreement to the plaintiff save and except the final bill which could not have been paid until the works were completed satisfactorily and the defects rectified? OPD
3. Whether the defendants are entitled to with-hold the amount of contract of seal-coating alongwith security deposit? OPD
4. Whether plaintiff is entitled to amount claimed? OPP
5. Relief."
5. The trial court has dismissed the suit by holding that the admitted
documents Ex. DW-1/2 dated 07.06.2000 and Ex. DW-1/3 dated
19.06.2000, being the letters of the appellant/plaintiff himself, admitted the
defective work, which admittedly was not rectified and, therefore, the
appellant/plaintiff was not entitled to suit amount.
6. Learned counsel for the appellant argued that the report of the CRRI
dated 26.07.2000 (Ex. PW-1/12) clearly showed that there was no defect in
the work and, therefore, the suit ought to have been decreed. It was argued
that letters of the appellant/plaintiff to the defendants dated 07.06.2000 and
RFA No. 509/02 Page 4 19.06.2000, Ex. DW-1/2 and Ex. DW-1/3 respectively, were got signed
under coercion and pressure and, therefore, cannot be relied upon.
7. In order to appreciate the first contention of the appellant/plaintiff, it
was necessary to refer to the document Ex. PW-1/12 which is relied upon by
the appellant/plaintiff to claim that there is no defective work. This report is
in fact a letter from CRRI to the respondent No. 1 and the same reads as
under:
"F.P. 3D(2)/331 Dated : 26th July, 2000
To
Shri M.K. Gupta,
S.E. (Civil),
Nuclear Science Centre
Post Box No. 10502,
Aruna Asaf Ali Marg
New Delhi - 110067 (India)
Sir,
Kindly refer to your letter No. NSC/9.85 dated 10 th July, 2000. The sample of seal coat sent by your department has been tested.
The test results are as under:
1. Bitumen Content 8.89%
By weight of Mix
RFA No. 509/02 Page 5
2. Sieve Analysis 2.36mm. - 100% Passing
180 Micron - 100% Rtd.
Thanking you,
Yours faithfully,
(Dr. Sunil Bose)
Flexible Pavements Division"
A reading of this letter quite clearly shows that this letter has nothing to do
with whether the work done by appellant/plaintiff was defective or not and
this letter only talks of the Bitumen Content. Even if the Bitumen Content is
as per the desired parameters that does not mean that the work done by the
appellant/plaintiff was not defective, and as admitted by him vide Ex. DW-
1/2 and Ex. DW-1/3.
8. The argument raised on behalf of the appellant/plaintiff that the
appellant's letters Ex. DW-1/2 and Ex. DW-1/3 were got signed under
coercion and pressure is an argument without any substance whatsoever
because if these letters were written on account of any pressure or coercion,
the appellant/plaintiff would have thereafter withdrawn these letters,
however, these letters were never withdrawn. In fact, the respondent No. 1
after the rainy season wrote its letter dated 26.9.2000 (Ex. DW-1/1) which
RFA No. 509/02 Page 6 reminded the appellant/plaintiff to rectify the defective work, however, the
rectification was not done.
9. A civil case is decided on balance of probabilities. The balance of
probabilities shows that in the present case the work done by the
appellant/plaintiff was defective in as much as the appellant/plaintiff on his
own letterheads and in his own handwriting admitted the work done to be
defective vide Ex. DW-1/2 and Ex. DW-1/3. I have, therefore, no reason to
interfere with the impugned judgment and the decree dismissing the suit of
the appellant/plaintiff.
10. In view of the above, the appeal, being without merit, is dismissed,
leaving the parties to bear their own costs. Trial court record be sent back.
VALMIKI J. MEHTA, J.
NOVEMBER 16, 2011 godara RFA No. 509/02 Page 7
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!