Citation : 2011 Latest Caselaw 2379 Del
Judgement Date : 4 May, 2011
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of Judgment: 04.05.2011
+ R.S.A.No. 142/2007
RAMESH LAL ...........Appellant
Through: Mr. B.P. Singh, Advocate.
Versus
MUNICIPAL CORPORATION OF DELHI .........Respondent
Through: Ms. Biji Rajesh along with
Mr. Gaurang Kanth, Advocates.
AND
R.S.A.No. 144/2007
RAMESH LAL ...........Appellant
Through: Mr. B.P. Singh, Advocate.
Versus
MUNICIPAL CORPORATION OF DELHI .........Respondent
Through: Ms. Biji Rajesh along with
Mr. Gaurang Kanth, Advocates.
CORAM:
HON'BLE MS. JUSTICE INDERMEET KAUR
1. Whether the Reporters of local papers may be allowed to
see the judgment?
2. To be referred to the Reporter or not? Yes
3. Whether the judgment should be reported in the Digest?
Yes
RSA Nos. 142/2007 & 144/2007 Page 1 of 10
INDERMEET KAUR, J. (Oral)
1. This appeal has impugned the judgment and decree dated
07.02.2007 which had reversed the finding of the trial judge dated
27.04.2004. Vide judgment and decree dated 27.04.2004, the suit
filed by the plaintiff Sh. Ramesh Lal seeking recovery of amounts
against the defendant/Municipal Corporation of Delhi (MCD) had
been decreed in his favour. The impugned judgment had reversed
the finding of the trial judge. The suit filed by the plaintiff stood
dismissed.
2. Vide the impugned judgment dated 07.02.2007; both the
suits i.e. suit no. 37/2004 and suit no. 39/2004, filed by the
plaintiff had been decided. Both the suits had, in fact, been
consolidated in the trial court itself and had been disposed of by
the impugned judgment.
3. Plaintiff was registered as a contractor with the defendant;
he was engaged in the business of government contract work and
supply of building material. He had conducted works for the MCD
which were found to be satisfactory. The final bill was prepared
by the department and had been passed for payment. The
plaintiff had signified his acceptance and signed the measurement
book as well. These facts are undisputed.
4. The gross value of the work done by the plaintiff in suit no.
37/2004 was to the tune of `2,05,044/-; final bill amounted to
`1,24,750/- of which the amount of `43,133/- was paid to the
plaintiff; security amount had also been released. Balance
recoverable was `81,617/-.
5. In suit no. 39/2004, the gross value of the work done by the
plaintiff amounted to be `3,75,997/-; final bill which had been
passed was of `2,38,102/-. `32,886/- was the security amount.
Amount recoverable was `2,70,988/-.
6. Legal notice dated 11.07.2002 had been issued to the
defendant whereafter the present suits were filed.
7. Suit was accordingly filed for a sum of ` 81,617/- along with
interest at 18% per annum (i.e. a sum of `14,201 w.e.f. 12.06.2001
till 16.09.2002) for the total amount of ` 95,818/-. This was in suit
no. 37/2004.
8. Plaintiff had filed the second suit for recovery of `2,70,988/-
along with the interest at the rate of 18% per annum (w.e.f.
12.06.2001 till 16.09.2002 i.e. the interest amount of `20,001/-)
i.e. the total amount of `2,92,633/-.
9. It is not in dispute that during the pendency of the two suits,
the principal sums of `81,617(in suit no. 37/2004) and `2,70,988/-
(in suit no. 39/2004) have since been paid. The interest amount
i.e. `14,201/- in first suit and `20,001/- in the second suit were the
subject matter of dispute before the courts below.
10. The suit had initially been filed under Order 37 of the Code
of Civil Procedure (hereinafter referred to as ‟Code‟). The trial
judge had noted that the summons in the prescribed format had
been issued. Pursuant to the summons for judgment, the
defendant, however, did not file his application for leave to defend
but instead chose to file an application under Section 8 of the
Arbitration and Conciliation Act, 1996 read with Order 7 Rule 11
of the Code. The contention was that the parties were governed
by an Arbitration Agreement which did not stipulate any interest.
Court was, however, of the view that interest is to be awarded to
the plaintiff and the suit of the plaintiff was accordingly decreed.
11. In appeal, this finding was set aside. The impugned
judgment was of the view that interest is not payable to the
plaintiff. Court was of the view that the parties were governed by
the Arbitration Agreement and Clause 25 of the same was
adverted to. The judgment was accordingly set aside.
12. This is a second appeal. It has been admitted and on
2305.2007, the following substantial question of law had been
formulated:-
" Whether the demand raised by the appellant regarding the
payment of interest is a disputed matter, if so to what its effect
and whether he is entitled to interest or not?"
13. On behalf of the appellant it has been urged that the
judgment suffers from a perversity as there were no disputes or
difference left between the parties; admittedly, the final bill had
been passed for payment; in fact, payment of the principal amount
in terms of the final bill had been released. Part payment had
been released before the filing of the suit and the balance amount
had been paid during the pendency of the suit. This by itself
shows that there was no dispute or difference left between the
parties. The question of invoking the arbitration clause did not
arise.
14. Arguments have been rebutted. It is pointed out that the
impugned judgment suffers from no perversity; the Arbitration
Agreement did not contain any interest clause; interest could not
have been awarded.
15. Record has been perused. The suit had initially been filed
as a suit under Order 37 of the Code. The suit amount was
inclusive of the figures i.e. the amount of Rs. 14,201/-in the first
suit and the sum of Rs. 20,001/- in the second suit. Order 37 is a
complete Code in itself. The procedure contained therein has to
be strictly followed. Once the summons for judgment is served
upon the defendant, the procedural requirement is that the
defendant has to enter his appearance and thereafter file an
application for leave to defend. In the application for leave to
defend all defenses which are permissible under law are
permitted. That is the procedure under Order 37 of the Code.
The plaintiff could not have straightaway filed an application
under Order 7 Rule 11 of the Code or invoked Section 8 of the
Arbitration and Conciliation Act, 1996. The averments made in the
application under Order 7 Rule 11 could well have been made by
him in his application for leave to defend.
16. That apart, the contention of the learned counsel for the
appellant has force. Once the final bill had been passed by the
department; there was no dispute or difference left between the
parties. The question of invoking the arbitration clause did not
arise.
17. The quotient of interest which is now disputed by the
department was not a dispute arising out of the Arbitration
Agreement which is a necessary pre-condition to invoke the
arbitration clause. Even otherwise, the arbitration agreement by
which parties were government clearly in clause 9 stipulated that
the payment of the final bill once it is passed shall as far as
possible be made within the period specified therein i.e. if the
tendered value of the work is up to Rs. 5 lacs, a period of three
months is prescribed and if the tendered work exceeds Rs 5 lacs,
a six months period was prescribed. Admittedly, in this case even
after his stipulated period, complete payment was not released.
Legal notice dated 11.07.2002 which was also after the stipulated
three months period was also not heeded to. The plaintiff was
compelled to resort to litigation. Clause 10 (B) of the Arbitration
Agreement deals with interest and recovery; in this clause, the
mobilization advance paid to the contractor, would carry interest
at the rate of Rs. 18% per annum to be calculated from the date of
payment upto the date of recovery. This clause is admittedly in
favour of the department; nevertheless it does throw light on the
intent of the parties to the agreement; plaintiff had relied upon
this clause to claim interest at 18 % per annum for the intervening
period as in spite of the fact that even after stipulated period of
three months was over, his complete payment had not been made
to him. This clause had been relied upon by the trial judge. The
impugned judgment not granting interest to the plaintiff which
was part of the suit amount which was a suit under Order 37 of
the Code is an illegality. Plaintiff had not invoked the Arbitration
Agreement; he had simplicitor filed a suit for recovery. Question
of the invocation of the Arbitration Agreement did not arise when
admittedly there was no dispute or difference left between the
parties. Payment of final bill was admittedly paid after a delay;
interest was the entitlement of the plaintiff. The award of interest
at the rate of 18 % per annum as aforenoted has been deciphered
from the clause of the agreement itself i.e. Clause 10 (b) read with
Clause 9. Impugned judgment not granting interest to the
plaintiff is a perversity. Plaintiff was rightfully entitled to it.
18. Reliance by the learned counsel for the respondent upon the
judgment reported in (2007) 3 SCC 686 Agri Gold Exims Ltd. Vs.
Sri Lakshmi Knits & Wovens and Ors. as also upon the judgment
reported in (2003) 6 SCC 503 Hindustan Petroleum Corpn. Ltd.
Vs. Pinkcity Midway Petroleums is misplaced. These judgments
are inapplicable. In Agri Gold Exims Ltd. (supra), it was held that
the term „dispute‟ must be given its general meaning. In this
case, the respondents had made payment without prejudice to
their rights and contentions; thus there was a dispute between the
parties. In this case, the final bill had been passed; there was no
dispute left. This ratio is inapplicable. The second judgment of
Hindustan Petroleum Corpn. Ltd. (supra) states the undisputed
proposition that where an arbitration clause exists, the court had
the mandatory duty to refer the disputes arising between the
contracting parties to the Arbitrator. In this case, there was no
dispute which was referable for arbitration. After passing of the
final bill which was an admitted document, there remained no
dispute between the parties.
19. Judgment of 18 (1980) DLT 122 Haryana Breweries Ltd. Vs.
Aluminium Manufacturing Co. Ltd. & Anr. is also distinct. This
judgment has detailed the procedure which has to be followed in a
summary suit under Order 37 of the Code. After the summons for
judgment had been served upon the defendant, an application for
leave to defend has to be filed by him. This was a case where the
leave to defend has been refused only on the ground that it had
been filed before summons for judgment had been served upon
the defendant; this was held to be a curable defect and not a
ground for the dismissal of the application for leave to defend.
20. Substantial question of law is answered in favour of the
appellant and against the respondent. Appeal is allowed. Both
the appeals are disposed of.
INDERMEET KAUR, J.
4th May, 2011 ss
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!