Citation : 2011 Latest Caselaw 3337 Del
Judgement Date : 14 July, 2011
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ RFA No.8/2002
% 14th July, 2011
M/S. LUCKY ENGINEERING WORKS (REGD.) & ANR. ...... Appellants
Through: Mr. Pankaj Batra, Advocate.
VERSUS
SHRI G.S. CHADHA ...... Respondent
Through: Mr. K.D. Kaushal, Advocate.
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be
allowed to see the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
VALMIKI J. MEHTA, J (ORAL)
1. The challenge by means of this Regular First Appeal under
Section 96 of Code of Civil Procedure, 1908 (CPC) is to the impugned
judgment and decree dated 29.11.2001 by which the suit of the
respondent/plaintiff for recovery of advance price paid to the
appellants/defendants with respect to a machine (which was not
supplied) was decreed. The suit has been decreed for Rs.3,80,885/-
alongwith costs and interest @ 12% per annum.
2. The facts of the case are that there was a contract between
the parties on 24.8.1998, Ex.PW1/1, by which the
appellants/defendants agreed to supply a machine " 30 inch working
width Roto Gravier Single Colour printing machine with single station
RFA No.8/02 Page 1 of 5
coating machine roll to roll". The total price of the machine agreed to
be paid was Rs.4,80,000/- and of which a sum of Rs.2 lacs was received
in advance. The balance payment was Rs.2,80,000/-. The delivery
period was six weeks.
3. It was not disputed before the trial Court that the
appellants/defendants have in fact received total amount of
Rs.3,50,000/- from the respondent/plaintiff/buyer i.e. Rs.2 lacs
originally and thereafter two sums of Rs.1 lakh and Rs.50,000/-
respectively. The issue which was urged before me was that time of
performance was not the essence of the contract and there was no
breach on the part of the appellant as the appellant/defendant was
ready to deliver the machine for the first time in February, 1999 as
stated in Ex.PW1/3, but which delivery was not taken. Subsequent to
the letter Ex.PW1/3 dated 13.2.1999, there was certain correspondence
exchanged between the parties, including Ex.PW1/4 dated 23.2.1999.
In support of his argument learned counsel for the appellants also
relies upon a judgment of the Supreme Court in the case of Arosan
Enterprises Limited Vs. Union of India 1999 (9) SCC 449.
4. The fact of the matter is that the appellants could not
manufacture and produce the machine within the contractual period of
six weeks. The respondent/plaintiff was forced to pay an additional
amount of Rs.1 lakh on 16.9.1998 although the contract Ex.PW1/1
dated 24.8.1998 did not require any further payment to be made till
RFA No.8/02 Page 2 of 5
the supply of the machine inasmuch as the balance payment was
Rs.2,80,000/- with delivery period of six weeks meaning thereby that
the balance payment would only be payable on delivery. Not only the
appellants managed to extract an additional amount of Rs.1 lakh
beyond as stipulated in the contract (and which the respondent/plaintiff
paid inasmuch as it had already parted with a substantial amount of
Rs.2 lacs, yet, the appellants did not supply the machine), the
respondent/plaintiff thereafter was again forced to make payment of
Rs.50,000/- through cheque No.228816 dated 29.10.1998. The period
of delivery had expired in the meanwhile by about 7.10.1998. During
this entire period and in fact till February, 1999 i.e. a period of 24
weeks, instead of six weeks, there was never offer of the
appellants/defendants to deliver the machine. Even assuming that the
time of performance is not the essence of the contract, the fact of the
matter is that there cannot be interminable delay in supply of machine.
Learned counsel for the appellants stressed the fact that once the time
was not the essence of the contract, and the appellants vide Ex.PW1/3
dated 13.2.1999 offered to give the machine, it should be held that it
was the respondent/plaintiff who was guilty of breach of contract. I
may note that except writing Ex. PW1/3, there is no proof which was
proved by the appellants that the machine was in fact ready when the
notice dated 13.2.1999 Ex.PW1/3 was sent. The fact that the machine
was in fact not ready even when Ex.PW1/3 dated 13.2.1999 was sent
RFA No.8/02 Page 3 of 5
becomes clear from the fact that the appellants disputed that certain
parts of machinery were in fact not to be supplied, though, the contract
is exhaustive so far as the machine to be supplied.
In view of the fact that the machine was really not ready
and false stand was taken up that the machine was ready clearly
shows that there is no scope for applicability of the judgment in the
case of Arosan Enterprises Limited (supra) as cited by the learned
counsel for the appellants.
A reference to para 5 of the written statement shows that
the appellant/defendant admitted that by the end of November a heat
control panel and 5 HPS. Motor with panel had not been fixed with the
machine and which parts still had to be purchased by the
appellant/defendant. This stand in the written statement shows
therefore that the complete machine was in fact not ready in 1st week
of November, 1998 and therefore clearly what was therefore the letter
dated 13.2.1999 Ex.PW1/3 was only a ruse as nothing has been filed by
the appellant thereafter to show that these parts were purchased.
5. In my opinion, one determinative issue which arose during
the course of arguments in the present appeal was that the respondent
agreed to make the payment of the balance amount of the machine
even today so that the appellants should give the machine on payment
of the complete price. When this was put to the appellant No.2, who is
RFA No.8/02 Page 4 of 5
present in person, he outrightly refused on the ground that machine
was no longer available as the same was burnt in a fire. Further, when
another proposal was put to the appellant No.2 as to whether he is
ready to refund the amount received with reasonable interest, the
appellant No.2 stated that he is not ready to return even a single
rupee.
6. This Court is entitled to interfere with the impugned
judgment and decree only if the trial Court takes one view which is
illegal and which causes grave injustice which now is not so in the facts
of the present case. The facts show that not only the machine was not
ready, but, the respondent/plaintiff was forced to part with additional
monies in the hope that he will receive the machine. Even before this
Court, the appellants have taken a totally unacceptable stand of not
being ready to supply the machine on payment of balance price or not
agreeing to refund the advance price received with respect to the
machinery with a reasonable rate of interest. The respondent was
ready to accept any reasonable amount because he had already parted
with monies to the appellants.
7. In view of the above, there is no merit whatsoever in the
appeal. The appeal is accordingly dismissed, leaving the parties to
bear their own costs. Trial Court record be sent back.
JULY 14, 2011 VALMIKI J. MEHTA, J.
Ne
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!