Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Paharpur Cooling Towers Ltd. vs M/S Ntpc Ltd. & Ors.
2011 Latest Caselaw 3332 Del

Citation : 2011 Latest Caselaw 3332 Del
Judgement Date : 14 July, 2011

Delhi High Court
M/S Paharpur Cooling Towers Ltd. vs M/S Ntpc Ltd. & Ors. on 14 July, 2011
Author: Sanjay Kishan Kaul
*           IN THE HIGH COURT OF DELHI AT NEW DELHI



%                                         Date of decision: 14.07.2011


+                         WP(C) No. 532/2011


M/S PAHARPUR COOLING TOWERS LTD.                                ...PETITIONER


                    Through:            Mr.Rakesh Munjal, Sr.Adv. with
                                        Mr.Amit Prasad and Ms.Ruchika
                                        Pathak, Advocates.

                                Versus


M/S NTPC LTD. & ORS.                                ...RESPONDENTS

                    Through:            Mr.Vikas Singh, Sr.Adv. with
                                        Mr.Bharat Sangal, Ms.Vernika
                                        tomar, Ms.Amrita and Ms.Srijana
                                        Lama, Advocates for R-1/NTPC.

                                        Mr.Ravinder Agarwal, CGSC with
                                        Nitish Gupta, Advocate for R-
                                        2/BRBCL.

                                        Mr.Jayant Bhushan, Sr.Adv. with
                                        Mr.Deepak       Khurana     and
                                        Mr.Shobhit Chandra, Advs. for R-
                                        3/Lanco Infratech Ltd.

CORAM:

HON'BLE MR. JUSTICE SANJAY KISHAN KAUL
HON'BLE MR. JUSTICE RAJIV SHAKDHER

_____________________________________________________________________________________
WPC No.532/2011                                                        Page 1 of 38
 1.      Whether the Reporters of local papers
        may be allowed to see the judgment?

2.      To be referred to Reporter or not?

3.      Whether the judgment should be
        reported in the Digest?


SANJAY KISHAN KAUL, J. (ORAL)

1. In the process of setting up the Nabinagar Thermal

Power Project at Stage-1, respondent no.1 issued an

invitation for bids (ITB) dated 20.08.2008 for an

induced draft cooling tower package (in short, IDCT)

required for the said turnkey project. It is the say of

the petitioner that from 20.08.2008 till 27.10.2009

various clarifications were issued and amendments

made and it is only on 27.10.2009 that the bids

submitted in pursuance to the instructions to bidders

(in short, ITB) were opened. The petitioner was

declared second lowest bidder ( in short, L-2) while

respondent no.3 as lowest bidder ( in short, L-1).

2. The grievance of the petitioner in the present writ

petition under Article 226 of the Constitution of India is

that R-3 was declared as a successful bidder although _____________________________________________________________________________________

it did not possess the necessary and mandatory

qualifying requirements, as contemplated under Clause

8.3(c)(i) of the ITB read with clause 6.1 of the Invitation

for Bids (in short, IFB). The petitioner sent various

representation to respondent no.1 pointing out what

they perceived to be the lack of qualification of

respondent no.3, but to no avail.

3. In order to appreciate the controversy before us, it is

necessary to reproduce the relevant clauses of both

the ITB and IFB.

" 8. Documents Comprising the Bid .......

8.3 Each Bidder shall submit with its bid the following documents:

...

c) Attachment 3: Bidders‟ Qualifications .......

The Bidder shall provide satisfactory evidence that he and/or, where applicable, his collaboration/associate/partner(s) of Joint Venture:

i) is a manufacturer, who regularly manufactures equipment of the type specified and/or undertakes the type of work specified and has adequate technical knowledge and relevant experience for the works covered in the bidding documents."

_____________________________________________________________________________________

"6.0 Qualifying Requirements

6.1 In addition to the satisfactory fulfillment of the requirements stipulated under section ITI ((Instruction to Bidders), the following shall also apply:

6.1.1 The bidder should have designed, constructed and commissioned at least one (1) number Induce Draught Cooling Tower in RCC Construction with splash type fill, of capacity not less than 1300 M3/hr which is in successful operation for at least one (1) year as on date of bid opening.

The reference cooling towers should be of the same type i.e. cross flow splash type Cooling tower or counter flow splash type cooling tower as is being offered by the Bidder.

6.1.2 Bidders who do not fulfill the requirement in clause 6.1.1 above can also participate provided the bidder has designed, constructed and commissioned at lease on (1) number Induced Draught/Force Draught/Natural Draught RCC Cooling Tower having film/splash type fill, of capacity not less than 13000 M3/hr and associates/collaborates with a party fully meeting the requirements of clause 6.1.1 above.

In such a case, the bidder shall furnish an undertaking jointly executed by him and his associate/collaborator as per the format enclosed in the bid document for the satisfactory performance of the Cooling towers. This joint deed of undertaking shall be submitted along with the bid, failing which the bidder shall be disqualified and his bid shall _____________________________________________________________________________________

be rejected. Further, in case of an award, the Bidder‟s associate/collaborator will be required to furnish demand bank guarantee for 1% (one percent) of the total contract price in addition to the contract performance security to be provided by the bidder."

4. The question thus before us is that: whether

respondent no.3 does not meet the qualifying

requirements as per clause 6.0.

5. It is the say of respondents before us that case of

respondent no.3 falls in clause 6.1.2 and it is that

clause which will determine the eligibility of respondent

no.3.

6. If we analyze the aforesaid clauses, we find that as per

clause 6.1.1, the bidder is required to have designed,

constructed and commissioned at least one IDCT in

RCC Construction with splash type fill, of capacity not

less than 13000 M3/hr (cubic metres per hour). We may

note that the cooling tower required by respondent

no.1 is a draught cooling tower with a splash type fill.

Thus, the alternative criteria which is deemed sufficient

to make a bidder eligible is that he may have designed,

constructed and commissioned a draught cooling tower

_____________________________________________________________________________________

of a splash type fill or may have designed, constructed

and commissioned a "forced draught" or "natural

draught" cooling tower either of film or splash type. In

terms of the affidavits filed by respondent no.1 and

respondent no.3, respondent no.3 fulfils this

requirement.

7. Learned counsel for the petitioner has contended

before us that it was incumbent upon the bidder to

have designed, constructed and commissioned the

cooling tower and it is his say (which has also been set

out in the writ petition) that the reliance placed on the

cooling tower stated to have been designed,

constructed and commissioned by respondent no.3 was

actually never designed by respondent no.3.

Respondent no.3 based its experience (which also a

condition of eligibility) on, the setting up of the

Kondapalli-I (in short, K-1) Project. With regard to K-1

project, it is not disputed that the original order qua

the project vis-à-vis the cooling tower(s) was placed on

M/s Lanco Power Limited, which in turn, placed an EPC

on M/s Korea Heavy Industries and Construction Co.Ltd _____________________________________________________________________________________

(Hanjung). Hanjung thereupon awarded the contract to

Encon Services Ltd (ESL). ESL was subsequently

amalgamated with Lanco Infratech Ltd.

8. It is thus the say of the petitioner that respondent no.3

has effectively purchased the alleged qualification

requirements.

9. Learned counsel for the respondents on the other hand

stated that the bid of respondent no.3 as submitted is,

in collaboration and/or association of Ms/ Hammon

Thermal Europe, being part of route-II, which regularly

undertakes execution of cooling tower projects. A

joint undertaking has been submitted both by

respondent no.3 and M/s Hammon Thermal Europe that

they are jointly and severally responsible to respondent

no.1 for the satisfactory performance of the cooling

tower, which includes obligations qua technical

guarantees.

10. Learned counsel for the petitioner submitted that

the design part of the work of K-1 Project was carried

out by Shriram Tower Tech Limited, as would be

apparent as per the work order issued by ESL to _____________________________________________________________________________________

Shriram Tower Tech Limited dated 28.12.1998. In this

behalf, learned counsel invited our attention to clause

2.1.0 under the heading „scope of work‟ to emphasize

that the complete designing work in respect of the

cooling tower was to be carried out by Shriram Tower

Tech Limited. The said clause reads as under:

"2.0.0 SCOPE OF WORK

2.1.0 Design, engineering, manufacture, procurement, stage inspection during manufacture, assembly, inspection at works, performance testing at manufacturers works, dispatching all material required for 1 no.RCC Counter flow Cooling Tower of capacity 26000 m3/hr in 13 cells (12 working + 1 standby), including cold water basin and channel as per the Tender specification and subsequent changes agreed by. The scope shall include Mechanical, Electrical, C&I and Miscellaneous items, consumables, hardware, materials, commissioning spares, and any other items related to the above defined scope and all applicable taxes and duties. The scope of work shall also include and be guided by specifications, drawings, BOQ, amendment/s as applicable."

11. It is the say of the learned counsel for the

petitioner that merely because the legal liability

remained with ESL, does not imply that ESL can be

_____________________________________________________________________________________

stated to have carried out designing work by

implication. Thus, the plea that ESL was involved at

each stage of the project and thus ESL was part of the

designing process is sought to be negated.

12. Learned counsel also sought to draw our

attention amongst others to the Minutes of Meeting (in

short, M.O.M) dated 10.04.1999. It is stated that

Shriram Tower Tech Limited was not even a party to

this M.O.M. A common document referred to by

learned counsel for the petitioner and respondents is a

letter issued by respondent no.1 to respondent no.3

dated 16.12.2009. This arose out of the bid submitted

by respondent no.3 and the clarification sought by

respondent no.1. We consider it appropriate to

reproduce the letter as it is :

"Ref No.01/CS-0270-135-2-PRA M/s Lanco Infratech Limited Plot No.6, Software Units Layout, Hyderabad - 500081 India Attn: Mr.B.Manohar, Director (Operations) Sub: Induced Draft Cooling Tower Package for Nabinagar Thermal Power Project (4x250 MW). Bidding Doc. No.CS- 0270-135-2.

Ref: 1. Your bid proposal dated 27.10.2009.

_____________________________________________________________________________________

2. NTPC letter ref no.01/CS-0270-135-2-PRA dated 12.11.2009 & 09.12.2009

3. Your letter ref LITL/11453x10/2009-10 dated 21.11.2009 & 11.12.2009

Dear Sir,

This has reference to the documents/details furnished vides your letters dated 21.11.2009 & 11.12.2009 on the Qualifying Requirements. On review of these documents, it is observed that there is still need for further details/documents pertaining to the distribution of work between M/s Encon Services Pvt. Ltd (Encon) and M/s Sriram Tower Tech Limited (Sriram) as indicated below:

           Sl.        Area                      Clarifications Required
                 1.   Design                    The        extent      of
                                                involvement of Encon
                                                in the design work for
                                                the execution of the
                                                reference work (i.e.
                                                Induced Draft Cooling
                                                Towers      (IDCT)    for
                                                Kondapalli       Thermal
                                                Power Project).
                 2.   Civil                     From the documents
                      Construction              furnished by you, it is
                                                not clear who has
                                                actually carried out the
                                                civil       construction
                                                works of the reference
                                                work.
                 3.   Commissioning             Who      actually    has
                                                carried       out    the
                                                Commissioning of the
                                                reference      works of
                                                IDCT.

You are required to furnish the necessary information in terms of each of clarifications sought above duly supported by the documentary evidence so as to reach this office latest by 18.12.2009.

Thanking you Yours faithfully _____________________________________________________________________________________

(A.Saha) DGM (CS-II)"

13. Insofar as the issue of designing is concerned,

respondent no.1 sought from respondent no.3 a

clarification about the extent of involvement of

respondent no.3 in the design work for execution of the

K-1 Project, and as to who had carried out the design

work. Respondent no.3 responded to this letter vide

communication dated 17.12.2009. It would suffice to

re-produce the relevant portion of this letter dealing

with the issue of design; the same is extracted

hereinafter :

        No       Area     Clarification required by   Ref.No.    Clarifications by LITL      Remarks
             .            NTPC
        1)       Design   Extend of involvement       1         Involvement of ENCON         Ref. to the
                          of Encon in the design                SERVICES LTD in design       scope of work
                          of IDCT for Kondapalli                of IDCT for Kondapalli       in        the
                          Power Plant                           Power Plant is total.        Agreement
                                                                                             b/w ESL &
                                                                                             Hanjung
                                                                                             already
                                                                                             submitted to
                                                                                             NTPC.
                          Who actually carried                  Basic design in respect of
                          out the design of IDCT                Thermal & Civil was
                          i.e. Thermal design,                  carried out by ESL and
                          Civil, Structural design              Detailed      Engineering
                                                                scope was off loaded to
                                                                the sub contractor M/s
                                                                Shriram Tower Tech
                                                                Limited who in turn
                                                                taken the help of sub
                                                                vendors (approved by
                                                                ENCON / client) like M/s
                                                                ABB, M/s GREAVES, M/s

_____________________________________________________________________________________

PARAG, M/s P &M Construction Co.Pvt. Ltd.

                                                   M/s DANCAL, M/s PETHE
                                                   Brake Motors Pvt. Ltd.,
                                                   M/s    Safetrack,    M/s
                                                   Speed-O-Controls     Pvt.
                                                   Ltd., M/s KGEN/KGEC,
                                                   M/s Crompton Greaves,
                                                   M/s     SRCAST,      M/s
                                                   VANKOS, M/s BRITOOL
                                                   etc.



14. It was clarified vide this letter that the basic

design in respect of thermal and civil work was carried

out by ESL while detailed engineering out of the scope

of work envisaged under the said project was, off

loaded to the sub contractor i.e., Shriram Tower Tech

Limited, which in turn, took the help of various sub

vendors.

15. The aforesaid position is naturally sought to be

disputed by the petitioner by relying upon the

document dealing with division of responsibility

between Hanjung and ESL qua the project of

respondent no.1 with Bihar State Electricity Board,

which is also incidently conceived at Nabinagar

through latter in point of time.

_____________________________________________________________________________________

16. It is the submission of learned counsel for the

petitioner that Clause 7.1 and 7.2 of this document is

identical to clause 6.1.1 and 6.1.2 of the tender in

question. In respect of this other contract, a Sub

Qualification requirement (in short, QR) was issued in

the following terms:

"Sub QR to be included in the Technical Specification

In case the reference cooling tower was designed by a party other than the bidder himself, the bidder shall employ a cooling tower designer/supplier who has independently designed an Induced Draught Cooling Tower of the same type as being offered of capacity not less than 13,000 cum/hr. In RCC Construction with splash type fill which is in successful operation for at least one (1) as on date of bid opening."

17. It is the contention of learned counsel for the

petitioner that this Sub QR envisages a situation where

the designing of the reference cooling tower was

carried out by a party other than the bidder then, in

that eventuality, the bidder is obligated to employ a

cooling tower designer/supplier who has independently

designed and IDCT of the same type.

_____________________________________________________________________________________

18. It Is thus submitted that if the say of the

respondents was to be accepted that respondent no.3

could carry out the work of designing through the aegis

of Shriram Tower Tech Limited, then the occasion to

include the sub QR in subsequent tender would not

have arisen. Therefore, the plea in substance is that

because a sub QR has been issued, albeit in a

subsequent tender, it ought to imply that the earlier

tender (which is the tender in question) did not

envisage that the job function of designing be sub

contracted.

19. The other aspect emphasized by learned counsel

for the petitioner is that the certificate submitted by

respondent no.3, on a plain reading, did not refer to

the fact designing work in K-1 project had been carried

out by respondent no.3. There is no reference to the

design contract obtaining between respondent no.3

and Shriram Tower Tech Limited; a reference to that

design contract would show that it is Shriram Tower

Tech Limited which had carried out complete designing

_____________________________________________________________________________________

work of the K-1 project even though the legal

responsibility rested with ESL.

20. In a nutshell, learned counsel for the petitioner

submits that the work of designing has to be carried

out "of its own" resting with respondent no.3 and this

work cannot be delegated to any third party including

Shriram Tower Tech Limited, with mere supervision

and legal responsibility resting with respondent no.3.

21. Learned counsel submits that wherever

respondent no.1 is of the view that such work could be

carried out through another party, the phraseology

used is „designed, constructed and commissioned or

designed or got constructed or got commissioned" as

was the case in WPC No.296/2011 M/s Ansaldo Caldaie

Boilers India Pvt. Ltd. v. Union of India & Anr.; decided

on 01.03.2011; where the expression used was

"designed, engineered, manufactured/got

manufactured, erected or supervised erection,

commission or supervised commission".

22. Learned counsel for the respondents has

emphasized that the restrictive interpretation sought to _____________________________________________________________________________________

be given to clause 6.1.2 is not sustainable as in all such

projects, no single entity carries out the complete

work; but assistance is taken from other experts in the

field. The ultimate responsibility rests with a party to

which the tender is awarded and it cannot escape the

liability or responsibility by putting the burden on such

other party from whom it may have got some part of

the work completed. Learned counsel for respondent

no.1 also emphasized that in the tender in question an

important clause 6.3 was inserted which reads as

under:

"Notwithstanding anything stated above, the Employer reserves the right to assess the capabilities and capacity of the Bidder/his collaborators/associates/subsidiaries/group companies to perform the contract, should the circumstances warrant such assessment in the overall interest of the Employer."

23. It has been thus submitted that respondent no.1

as an employer had reserved the right to assess the

capabilities and capacity of the

bidder/collaborators/associates/subsidiaries/group

companies to perform the contract should the

_____________________________________________________________________________________

circumstances warrant such assessment in the overall

interest of the employer.

24. In the present case, it has been emphasized that

pursuant to the petitioner casting a doubt on the

eligibility of respondent no.3, a Tender Evaluation

Committee (in short, TEC) having technical members

actually went into all the aspects including the matter

in issue and came to a conclusion in favour of

respondent no.3. It is thus submitted that an

inspection has also been carried out to the satisfaction

of respondent no.1 and respondent no.2 about the past

experience and ability of respondent no.3 to carry out

the task assigned to it; and thus, it is submitted that

this Court while exercising the jurisdiction under Article

226 of the Constitution of India cannot be expected to

sit as a court of appeal over the decision of TEC which,

comprised of technical members as well.

25. Learned counsel has also drawn our attention to

clause 8.3(e) of the ITB under the heading "Attachment

5 : Subcontractors Proposed by the Bidder" which deals

with subcontractors proposed by the bidder, to _____________________________________________________________________________________

emphasize that such an delegation of work is

envisaged in the bid itself.

26. The last aspect emphasized by learned counsel

for respondent no.1 is that the petitioner, in any case,

is dis-entitled to any indulgence arising from the delay

in approaching this Court for redressal of its

grievances. In this behalf, it is stated that it was as far

back as on 27.10.2009 that the technical commercial

bids were opened as also the price bids when L-1 was

found to be more competitive, petitioner having quoted

a price of Rs.94,18,00,000/- and respondent no.3

having quoted a price of Rs.90,74,35,000/-. Thus, the

difference in price is about Rs.3.5 crores i.e. about 4%.

The petitioner made a representation challenging the

ability of respondent no.3 on 07.01.2010 followed up

by a number of similar representations. Respondent

no.1 appointed TEC to look into the eligibility issue,

which submitted its report on 02.03.2010. The

petitioner, it was contended, was obviously aware of

the same as it made a further representation on

09.04.2010 seeking a reconsideration. The final _____________________________________________________________________________________

approval was given by a higher management of

respondent no.1 on 30.08.2008 treating the

respondent no.3 as technically qualified, and

thereafter, last representation was made by the

petitioner on 24.11.2010. The work was awarded on

25.01.2011 and the present writ petition was filed a

couple of days thereafter.

27. It is thus submitted that the petitioner should

have approached this Court at least soon after April,

2010 rather than keep making representations for

reconsideration, especially, bearing in mind the prayers

made in the writ petition. Learned counsel for

respondent no.3 has argued more or less on the same

basis as the submissions advanced on behalf of

respondent no.1. Learned counsel emphasized that

the principle of ultimate responsibility and submitted

that it is in view thereof that the sub-contracting of

work was envisaged. Had respondent no.1 required

the designing, construction and commissioning of

working to be strictly carried out by the contracting

entity itself, it would have possibly used the _____________________________________________________________________________________

phraseologies like "by itself". In any case, it is

submitted that the interpretation put forth by the party

making the contract must be given due weightage. It

was also pointed out that (as averred by the said

respondent, in para 19 of the counter affidavit) even

the petitioner has been sub contracting in the past

different job functions of the works awarded to it

including that part of the work which involves

designing.

28. Learned counsel referred to the judgment of the

Supreme Court in Himachal Pradesh Housing and

Urban Development Authority v. Universal Estates and

Anr.; JT 2010(13) SC 57 to emphasize that the scope of

judicial review in such matters is limited and the court

would exercise its discretion only when it is satisfied

that the action of the public authorities is detrimental

to public interest. Furthermore, even if some defects

are found in the decision making process, the court in

exercise of powers under Article 226 of the Constitution

of India would interfere only in furtherance of public

interest and not merely to make out a legal point. _____________________________________________________________________________________

29. We have noticed and examined the aforesaid

contentions though it is our view that the matter is in a

very narrow compass. The short point is whether in

terms of the clause 6.1.2 the work of designing can be

said to not have been carried out by respondent no.3 in

K-1 Project so as to disqualify respondent no.3, as the

substantive part of the design work was executed by

Shriram Tower Tech Limited under the supervision and

overall responsibility of respondent no.3

30. We may note at the threshold that this is a case

where respondent no.3 is L-1. The difference in bid

price between that submitted by the petitioner and

respondent no.3 is approximately Rs.3.5 Crores, which

in percentage terms is nearly 4 percent. The bid of

respondent no.3 is thus undoubtedly commercially

more competitive.

31. The petitioner having lost out in the bid process

now seeks to take recourse to the present proceedings

so as to disqualify respondent no.3 on the aforesaid

plea.

_____________________________________________________________________________________

32. Learned counsel for the petitioner, inter alia,

pleaded that the petitioner was willing to execute the

contract at the price quoted by respondent no.3, but

that, in our considered view, would be no answer to the

fact that the petitioner in its wisdom decided to

possibly keep an additional sum of Rs.3.5 crores as

profit at the time of making the bid even while

respondent no.3 submitted a more competitive bid.

33. Insofar as the aspect of technical qualification is

concerned, no doubt the terms of the tender must be

adhered to, but where there is an element of ambiguity

or even a grey area in ascertaining the intent of parties

weightage will have to be given on how men of

commerce operating in the same field of activity

understand the terms used in a contract. The word

„design‟ used in clause 6.1.2 by itself, in our view does

not exclude the possibility of a bidder employing a

collaborator. The clarification issued by respondent

no.3 vide its letter dated 17.12.2009 quoted by us

above, would show that basic design of IDCT in K-1

project which involved civil and thermal work was with _____________________________________________________________________________________

respondent no.3 while Shriram was off loaded a part of

the job function comprising „detailed engineering‟;

though decidedly the overall supervision and

responsibility was of respondent no.3. This vexed issue

could perhaps be answered by employing the test of

substantiality. Whether the off loaded portion of

design work resulted in a situation of disentitling

respondent no.3 from bidding in respect of the instant

tender is call which the experts had to take. The

experts having decided otherwise. They have come to

a view that respondent no.3 in substantially compliant.

The court cannot supplant that view. It is then open

for the petitioner to contend that the collaboration

route was per se a no-go area. In our view, it cannot

be so contended. As long as the bidder and the

collaborator, are operating broadly in the same line of

business, such a submission is untenable. In today‟s

fast moving era of technology and super specialization,

it would be well nigh impossible for one entity to claim

expertise in any one domain qua projects which are

acutely capital intensive. Segmented parts of a _____________________________________________________________________________________

project, such as design, construction and

commissioning would often require involvement of

multiple agencies and/or entities. It is precisely for this

reason, in order to protect the interest of the employer,

that legal instruments, such as, joint undertaking(s)

have come into existence. In our view, the submission

that because a part of the design work in K-1 project

had been executed by Shriram Tower Tech Limited,

respondent no.3 was ineligible to bid for the instant

tender is misconceived. We thus emphatically reject

this submission. This apart, what cannot be lost sight

of is, assuming all things are equal that a court would

be loathe to supplant its opinion with that of the

experts in the field.

34. In the facts of the present case and the clauses

referred to aforesaid, respondent no.1 and respondent

no.2 were well within their rights to have scrutinized

the capacity and capabilities of the bidders to satisfy

themselves as per clause 6.3. Such an endeavour

possibly would have been made even otherwise in view

of the terms of the contract, but especially taking into _____________________________________________________________________________________

consideration the complaint of the petitioner, a TEC

comprising of technical members was constituted to

examine the matter including inspection of the cooling

towers manufactured, designed and installed by

respondent no.3 at an earlier point in time, and to

satisfy itself with regard to their due performance.

35. That the cooling towers have been working

satisfactorily for a period of 11 years is not seriously

disputed before us. The report of TEC comprising of

technical members has also been shown to us. In TEC‟s

report, the relevant aspects are discussed under the

heading "Capacity and Capability" in para 3.0, para

3.1.5 and 3.1.6. We consider it appropriate to

reproduce the same as under:

"3.1.5 During the discussions with NTPC team, it was informed that Lanco Infratech Limited is an ISO 9001 - 2008 certified company and they are engaged in the field of Engineering, Procurement and Construction (EPC) contracts. The range of projects undertaken by LANCO construction are construction of BOP for thermal power projects, Hydel projects, Power Transmission and Distribution. It is also clarified that Encon Services Limited (ESL) who executed the BOP works including IDCT on sub-

EPC basis from M/s. Hanjung for Kondapalli Power _____________________________________________________________________________________

Corporation Limited Stage-1. It got amalgamated with Lanco Infratech Limited upon the order dated 08th Oct. 2002 of High Court of Andhra Pradesh in order to take up the construction of power plants and other projects on a large scale. It was also clarified that ESL had engaged M/s. Shriram Tower Tech Limited as sub contractor for Design, Engineering, Procurement and Commissioning of IDCT as per the Technical Specifications issued by Owner Company M/s. Kondapalli Power Corporation Limited. LANCO also informed that they had given all the input design data to M/s. Shriram and ensured at various stages that the design was carried out as per TS and got the designhj and drawings approved by the EPC contractors consultant M/s. FICHNER. LANCO also stated that they constructed the civil work of substructure of Cooling Tower and helped M/s. Shriram by issuing the civil construction materials like concrete, reinforcement, shuttering materials etc. LANCO also clarified that they have taken the help of M/s. Shriram for Erection and Commissioning of IDCT and entire project management was done by ESL.

3.1.6 It has been observed that Lanco does not have full fledged engineering set up for carrying out IDCT Package. Lanco informed that, thermal design shall be done and guaranteed by their collaborator M/s Hamon Thermal Belgium and Detailed Design & Engineering shall be carried out by M/s. Hamon Thermal. However, they will employ Consultant for co-ordinating with Hammon and also with their site of this proposed Package of IDCT at Nabinagar. LANCO further clarified that they will carry out all the civil construction, ordering and procurement of _____________________________________________________________________________________

equipment, erection and commissioning since they have all the resources like skilled manpower and equipment for construction, material and equipment procurement, erection and commission of IDCT."

36. A reading of the aforesaid shows that TEC

comprising of technical members fully analyzed the

capability of respondent no.3, and while noticing that it

did not have full-fledged engineering set up relied upon

the work already carried out in the K-1 Project as also

the experience of the collaborator, M/s Hammon

Thermal Europe.

37. We have already noticed that both respondent

no.3 and M/s. Hammon Thermal Europe have given

undertakings for due performance of the contract and

proper functioning of the equipment.

38. At this stage, we may notice with profit the

principles enunciated by the Supreme Court in the case

of Jagdish Mandal v. State of Orissa and Ors.; (2007) 14

SCC 517 in para 22 as under:

"22. Judicial review of administrative action is intended to prevent arbitrariness, irrationality, unreasonableness, bias and _____________________________________________________________________________________

malafides. Its purpose is to check whether choice or decision is made 'lawfully' and not to check whether choice or decision is 'sound'. When the power of judicial review is invoked in matters relating to tenders or award of contracts, certain special features should be borne in mind. A contract is a commercial transaction. Evaluating tenders and awarding contracts are essentially commercial functions. Principles of equity and natural justice stay at a distance. If the decision relating to award of contract is bona fide and is in public interest, courts will not, in exercise of power of judicial review, interfere even if a procedural aberration or error in assessment or prejudice to a tenderer, is made out. The power of judicial review will not be permitted to be invoked to protect private interest at the cost of public interest, or to decide contractual disputes. The tenderer or contractor with a grievance can always seek damages in a civil court. Attempts by unsuccessful tenderers with imaginary grievances, wounded pride and business rivalry, to make mountains out of molehills of some technical/procedural violation or some prejudice to self, and persuade courts to interfere by exercising power of judicial review, should be resisted. Such interferences, either interim or final, may hold up public works for years, or delay relief and succour to thousands and millions and may increase the project cost manifold. Therefore, a court before interfering in tender or contractual matters in exercise of power of judicial review, should pose to itself the following questions :

_____________________________________________________________________________________

i) Whether the process adopted or decision made by the authority is mala fide or intended to favour someone.

OR

Whether the process adopted or decision made is so arbitrary and irrational that the court can say : 'the decision is such that no responsible authority acting reasonably and in accordance with relevant law could have reached.'

ii) Whether public interest is affected.

If the answers are in the negative, there should be no interference under Article 226. Cases involving black-listing or imposition of penal consequences on a tendered/contractor or distribution of state largesse (allotment of sites/shops, grant of licences, dealerships and franchises) stand on a different footing as they may require a higher degree of fairness in action.

39. Having regard to the opinion of the Supreme

Court in the aforesaid case and the court in several

other discussions, we do not think that it is the function

of this court to sit in appeal over the view taken by an

expert body especially called upon to look into the

complaint of the petitioner. This is more so where the

body i.e., TEC comprised of technical experts who

satisfied themselves as to whether respondent no.3 fit

_____________________________________________________________________________________

the bill or not. One cannot but overemphasize as

indicated above that in a contract of this nature,

assistance of experts in the field is often taken to do a

part of the work while, the legal responsibility rests

with the contracting party. So long as the appropriate

experience and technology is available to a contracted

party and the party awarding the contract is satisfied

with the same, the third party cannot insist that the

contract should be read in a particular manner so as to

non-suit the party to whom the contract is to be

awarded. This is exactly what, the petitioner seeks to

do by insisting that respondent no.3 does not have the

experience as in the K-1 Project the designing work

was carried out by Shriram Tower Tech Limited, while

respondent no.3 had only the overall legal

responsibility qua the work in issue.

40. We thus also find force in the contention of

learned counsel of respondent no.3 that the word

„designing‟ used in the contract has to be understood

in the context that this work must be got done

satisfactorily by respondent no.3, and does not mean _____________________________________________________________________________________

that respondent no.3 on a stand alone basis should

execute the work. This, in fact, is the very view we

have taken in the case of M/s Ansaldo Caldaie Boilers

India Pvt. Ltd. v. Union of India & Anr.‟s case (supra),

quite contrary to the submission made by learned

counsel for the petitioner herein. In this context, for

the sake of convenience, the relevant paragraphs

being paragraphs 15.4 to 15.9, are extracted

hereinafter :

"15.4 Therefore, the argument was that while as a whole the reference Steam Generator i.e., TNP plant had been designed, engineered and manufactured by a consortium of which ACS was the leader, the fact that certain parts of the evaporator had been manufactured by BHK/HPE would not make ACS ineligible as a QSGM.

15.5 As against this, Mr.Chandhiok argued to the contrary. He stressed upon the fact that the evaporator being a crucial part of the Steam Generator, it was quite apparent on a plain reading of the relevant clause of the bid documents that ACS would be eligible as a QSGM only if it had also designed, engineered and manufactured the evaporator.

15.6 We may only note at this stage that the writ petitioner's filling up of the bid documents in particular the attachment 3A-4 was less than happy, but what cannot be lost sight of is that there was no attempt on _____________________________________________________________________________________

the part of writ petitioner to mislead NTPC as regards the fact that it was offering an evaporator manufactured by a third party in so far the current tender was concerned. From the extracts which are culled out by us hereinabove, it is quite clear that NTPC was quite aware of the fact that the Siemens AG was the technology owner/licensor of the evaporator which was offered by the writ petitioner in its bid.

15.7 Therefore, this brings us to the question as to whether interpretation placed by the writ petitioner ought to be accepted or not? In our view it is trite law that interpretation is required to be made; whether of contract, document or a statute, only if, there is an ambiguity as to the intent of the parties. Intent has to be construed from the words used in the contract. It is only when the language of a document is ambiguous, should the tools of interpretation be brought into play to gather the intent of the parties. In doing so one should read the document as a whole and not in fragmented parts.

15.8 The word "provide" used in clause 7.1.1 of the IFB/clause I.I.I. of the BDS leaves us no wiser as to the intent of parties. In plain English, the word "provide" would mean supply or furnish (see Concise Oxford Dictionary 9th Edition page 1102). Would it then mean that ACS will stand disqualified as a QSGM if in the reference plant (i.e., the TNP plant), the evaporator was supplied by say BHK. In our view, this interpretation cannot be laid on the said clause, given the manner in which it is structured, especially when it is read in conjunction with other similar clauses (read routes) of the tender. To cite an example, under Route 5, a bidder can qualify as a QSGM if he had in the past had experience of manufacturing a Steam Generator of requisite specification with an evaporator of constant _____________________________________________________________________________________

pressure provided it undertook to supply one with a variable pressure, and in addition furnished a joint deed of undertaking of the owner and/or licensor of such technology. Therefore, on a comparison of QRs for a QSGM (which are common to all five Routes) it appears that in so far as the NTPC was concerned, it was quite prepared to accept a bidder as a QSGM if the evaporator supplied had the backing of the technology owner and/or the licensor of the evaporator.

15.9 In the present case, a consortium appears to have designed and manufactured the TNP Plant of which ACS was the leader. The fact that certain parts of the evaporator (we will assume that they are crucial) were designed and manufactured by BHK would not, on this account alone, disentitle ACS from being categorized as a QSGM, because in our opinion, a reading of the document does not reflect that such was the intent of parties. If NTPC is prepared to accept a joint deed of undertaking of a technology licensor for a Steam Generator with a Variable Pressure evaporator when the referential plant was designed with an evaporator suitable for constant pressure - we see no reason why the word "provide" used in clause 7.1.1 of IFB/clause 1.1.1 of BDS cannot be interpreted to mean that parties did not intend to exclude a person from being categorized as a QSGM only because the evaporator provided in the referential plant was supplied by a third party."

41. We are thus of the considered view that there is

no merit in the challenge laid by the petitioner to the

qualification of Respondent no.3.

_____________________________________________________________________________________

42. The argument of the petitioner that since in the

subsequent tender (by insertion of a sub QR)

respondent no.1 had provided for involvement of a

cooling tower designer / supplier if the reference

cooling tower had been designed by a third party and

hence by implication excluded the possibility of parties

intending that the eligibility condition would stand

complied if a third party was involved in designing a

referential plant (IDCT); is misconceived for the

following reason. Firstly, it proceeds on the premise

that respondent no.3 had no role to play in design work

of K-1 project. Secondly, in our view, incorporation of

a clause in a subsequent tender cannot be used as an

interpretative tool to explain the intent of parties qua

an earlier tender.

43. Now coming to the plea of delay on the part of

the petitioner in approaching the Court, we are unable

to persuade ourselves to agree with the submission of

learned counsel for respondent no.1. The petitioner

showed promptness in making the complaint and this

was followed up by different reminders. There was no _____________________________________________________________________________________

communication to the petitioner but the fact remains

that on 09.04.2010 the petitioner did seek a review of

the decision. Respondent no.1 and respondent no.2 in

their wisdom apparently kept on examining the matter

and withheld their hand till 30.08.2010 when

respondent no.3 was found technically qualified. The

petitioner made the last representation on 24.11.2010

and approached the Court in January, 2011 itself.

44. We are thus of the considered view that there

cannot be said to be any fatal delay on the part of the

petitioner in approaching the Court.

45. We may note in the end that learned counsel for

respondent no.1 prays by relying upon the judgment in

Raunaq International Ltd. v. I.V.R. Construction Ltd. and

Ors.; (1999) 1 SCC 492 that the petitioner having

enjoyed an interim order, respondent no.1 and

respondent no.2 are entitled to be compensated for the

cost escalation arising from the delay in proceeding

with the contract. We may notice that there are some

delays in the contract which have arisen otherwise

than on account of pendency of this petition. The _____________________________________________________________________________________

extension of the bids was sought by respondent no.1

from time to time. Thus, the question arises whether

the continuation of interim order for a period of couple

of months in the present matter has caused any injury

and if so, the extent of it. The observations in para 25

of Raunaq International Ltd. v. I.V.R. Construction Ltd.

and Ors. Raunaq International Ltd. v. I.V.R.

Construction Ltd. and Ors.‟s case (supra) are as under:

"25. Therefore, when such a Stay order is obtained at the instance of a private party or even at the instance of a body litigating in public interest, any interim order which stops the project from proceeding further, must provide for the reimbursement of costs to the public in case ultimately the litigation started by such an individual or body fails. The public must be compensated both for the delay in implementation of the project and the cost escalation resulting from such delay. Unless an adequate provision is made for this in the interim order, the interim order may prove counter-productive."

_____________________________________________________________________________________

46. We are of the considered view that in case the

respondent no.1 so desires, it is for respondent no.1 to

establish in appropriate proceedings that there is

financial implication of the delay occasioned on

account of the interim orders operating for these

couple of months in order to succeed in any monetary

claim in this behalf against the petitioner. The present

dispute is really in the nature of a commercial dispute

between the petitioner and respondent no.3. We are of

the considered view that in such a matter (even though

Mr. Amit Prasad succinctly set out the controversy in

issue while endeavouring to persuade us to his point of

view), the succeeding party must get actual costs.

47. We had asked the parties to file their

respective bills of costs and fees by today. The bill of

costs filed by respondent no.3 for the hearings, senior

counsel‟s fee and drafting expenses are

quantified at Rs.9,13,000/- and that of respondent

no.1 at Rs.12,26,375/-. There has been neither any

_____________________________________________________________________________________

appearance on behalf of respondent no.2 nor has any

bill of costs been filed on behalf of the said respondent.

We thus allow the costs in favour of respondent no.1

and respondent no.3 and against the petitioner in the

aforesaid terms.

48. The writ petition is accordingly dismissed with

costs of Rs.12,26,375/- in favour of R-1 and

Rs.9,13,000/- in favour of R-3.

49. Interim orders dated 10.02.2011 stand vacated.

SANJAY KISHAN KAUL, J.

JULY 14, 2011                                           RAJIV SHAKDHER, J.
dm/yg




_____________________________________________________________________________________

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter