Citation : 2011 Latest Caselaw 630 Del
Judgement Date : 3 February, 2011
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ ARB.P. NO.275/2010
Date of Decision : 03.02.2011
M/S GEO MILLERAND CROSS OBJECTOR. PVT. LTD.
...... Petitioner
Through: Mr.S.D.Singh, Advocate.
Versus
MUNICIPAL CORPORATION OF DELHI ...... Respondent
Through: Mr.O.P.Saxena, Adv. for respondent no.2.
AND
ARB.P.NO.276/2010
M/S GEO MILLER AND CROSS OBJECTOR. PVT. LTD.
...... Petitioner Through: Mr.S.D.Singh, Advocate.
Versus
MUNICIPAL CORPORATION OF DELHI ...... Respondent Through: Mr.Jitendra Kumar, Adv.
for MCD.
Mr.O.P.Saxena, Adv. for respondent no.2.
CORAM:
HON'BLE MR. JUSTICE V.K. SHALI
1. Whether Reporters of local papers may be allowed to see the judgment? NO
2. To be referred to the Reporter or not ? NO
3. Whether the judgment should be reported in the Digest ? NO
V.K. SHALI, J. (oral)
1. The learned counsel for the respondent no.2 seeks further
time to obtain instructions. The request for the same is
disallowed as the respondent no.2 has already been given
more than sufficient time to obtain instructions or
alternatively file reply.
2. I have heard the learned counsel for the parties and perused
the record.
3. These are petitions filed by the petitioner under Section 11(6)
of the Arbitration and Conciliation Act, 1956 (hereinafter
referred to as an „Act‟) for appointment of an Arbitrator.
4. Briefly stated the facts as averred in the petition are that the
petitioner(s) was awarded a contract known as the „2 MLD
Sewage Treatment Plant at Holambi, Delhi (under Yamuna
Action Plan)‟ vide agreement dated 28.11.2001. The value of
the total contract was fixed at `1,27,70,000/-. The scope of
the work as per the agreement was clearly mentioned to be as
„build, operate and transfer of 2 MLD Capacity Sewage
Treatment Plant at Squarter Resettlement Colony Tikri
Khurd, Delhi (under Yamuna Action Plan)‟ (Annexure P-1). It
is alleged that the petitioner was given the job to operate and
maintain the said plant for a period of five years starting
from 1.2.2003 to 31.1.2008, and having performed his part of
the obligation of commissioning, operating and maintaining
the plant, the petitioner was entitled to get the necessary
payment w.e.f. 1.2.2003.
5. It is alleged by the petitioner that the last amount which was
received by the petitioner was to the tune of `1,44,493/- on
6.8.2007 while as an amount of `41,40,000/- was still due
and payable. On account of this non-payment of the
amount, the petitioner in terms of Clause 25 of the
Agreement wrote a letter to the Superintending Engineer for
settlement of dispute and requested him to release the
aforesaid amount vide letter dated 6.3.2010 (annexure P-2).
6. It is alleged that the Executive Engineer sent an irrelevant
query on 25.3.2010 and made allegations against the release
of payment. On 16.4.2010, the petitioner personally met the
Chief Engineer and filed an appeal in terms of the aforesaid
clause. However, the Appellate Authority namely, the Chief
Engineer, failed to take a decision within 30 days from the
date of filing of appeal which expired on 15.5.2010. It is
alleged by the petitioner that as the petitioner failed to get
any redressal in terms of Clause 25 of the Agreement by
approaching firstly, the Superintending Engineer and then
the Chief Engineer, he was constrained to issue notice dated
10.6.2010 to the competent authority namely, The Municipal
Commissioner, MCD for appointment of an Arbitrator.
7. In the representation, the petitioner had formulated the
question with regard to his grievance and the same were
reiterated in the notice dated 10.6.2010 as required by the
Clause 25 of the Agreement between the parties. The relevant
portion of the said clause reads as under:-
"It is a term of this contract that the party invoking arbitration shall give list of disputes with amounts claimed in respect of each dispute along with the notice for appointment
of arbitrator and giving reference to the rejection by the Chief Engineer of the appeal"
8. Since the respondent/MCD failed to appoint the arbitrator in
terms of Clause 25 of the agreement within 30 days, the
petitioner was constrained to file the present petition on
16.9.2010 for appointment of an arbitrator.
9. The petition came to be listed on 01.10.2010 when notice was
directed to be issued to the Municipal Commissioner, MCD.
10. The learned counsel for the MCD had put in appearance on
11.1.2011 and stated that the Government of NCT of Delhi
had issued a notification according to which w.e.f. 30.8.2010,
the work pertaining to „Slum and JJ Department‟ which was
previously being looked after by the MCD was shifted to Delhi
Urban Shelter Improvement Board under Section 31 of the
Delhi Urban Shelter Improvement Board Act, 2010. In terms
of the said notification, it was urged that the Delhi Urban
Shelter Improvement Board (hereinafter referred to as „Board‟)
was the successor body of the MCD dealing with the contract
in question. It was alleged that the Board may be made as a
party and the respondent no.1 has nothing to do with the
same. A copy of notification has been placed on record. The
petitioner impleaded the Board as respondent no.2 and
accordingly, notice was issued to the Chairman of the Board
also.
11. Mr.O.P.Saxena, learned counsel for the Board appeared on
13.1.2011 and sought time to obtain instructions. Further
time was sought on 20.1.2011 when the matter was directed
to be listed on 3.2.2011.
12. Today again, a request for adjournment has been made,
which has already been turned down. There is no dispute
about the fact that the petitioner had entered into the
contract with the then MCD to build, operate and transfer of
the Sewage Treatment Plant in question and in terms of
Clause 25 of the Agreement, in the event of the grievance of
the petitioner being not adjudicated by the Superintending
Engineer or by the Appellate Authority, the petitioner could
invoke the Arbitration Clause and accordingly, the Municipal
Commissioner was competent to appoint the Arbitrator. The
petitioner had formulated the disputes with regard to his
grievance in the appeal to the Appellate Board, yet the appeal
was not considered within the period of 30 days as envisaged
in the agreement and accordingly, this necessitated the
issuance of notice dated 10.6.2010 to the Municipal
Commissioner.
13. By the learned counsel for the MCD or even for the Board, it
has not been disputed that notice has been issued to them.
The MCD has filed an affidavit to the effect that w.e.f.
30.8.2010 the Board has been constituted and work in
question has been transferred to the Board. The learned
counsel for the Board has neither filed reply nor obtained
instructions with regard to the appointment of an Arbitrator
by the Court. Further, they have even failed to appoint an
Arbitrator. The aforesaid facts clearly show that at the time
when the disputes were raised, the work pertaining to Sewage
Treatment Plant was being dealt with by the „Slum and JJ
Department‟ which was an integral part of the MCD and
therefore, the Municipal Commissioner in terms of Clause 25
of the Agreement, was entitled to appoint an Arbitrator.
According to the averment made, notice dated 10.6.2010 was
sent to the Municipal commissioner, the receipt of which has
not denied by the MCD or by its successor body i.e. the
Board. Therefore, if a reasonable time is excluded for the
service of the notice, it would be assumed that notice was
delivered to the Municipal Commissioner, MCD on or about
12/13 July, 2010 and the Municipal Commissioner was
under an obligation to appoint an Arbitrator within 30 days
from the date of receipt of the said notice. This period of 30
days had lapsed on 12/13 August, 2010 while as the Board
has been constituted on 30.8.2010. Therefore, it was
essentially for the MCD to appoint an arbitrator in terms of
Clause 25 of the Agreement. So far as the disputes are
concerned, they were formulated by the petitioner in the
appeal, which are being reproduced hereinunder:-
" List of Disputes The crux of the disputes between our company and department are being mentioned herein below:
A) Whether the MCD can be justified in not making the payment due and payable to M/s Geo Miler and Co. Pvt. Ltd. arising out of
Contract 2 MLD Sevage Treatment Plant at Holambi bearing agreement no.67/EE (S) DDI/2001-02 dated 28.11.2011. B) Presently a sum of Rs.41.40 lacs along with interest @18% since 1.3.2010 is payable to Geo Miller and Co. Pvt. Ltd. and details whereof are given herein below:-
1) Capital Cost With held in Civil Works 1.16 With held in Mechanical Works 1.67 Security Deposit 1.33 4.16
2) Operation & Maintenance Charges From Sept. 06 to Jan. 08 9.75 Deductions from O & M Bills 10.12 Reimbursement of Service tax 1.46 Reimbursement of WCT 1.30 Retention /Security Deposit 0.64 23.27
3) Interest
On capital cost from 1.3.03 to 28.2.10 5.24 i.e. 7 yrs. @ 18% P.A. on 4.16 lacs On O & M from 1.2.08 to 28.2.10 i.e. 25 months @18% P.A. on 23.7 lacs 8.73 13.97 Total of (1+2+3) 41.40"
14. In view of the aforesaid facts, section 11 (6) of the Act clearly
lays down that:
"Where, under an appointment procedure agreed upon by the parties--
a) a party fails to act as required under that procedure; or
b) ............
c) ............
a party may request the Chief Justice or any person or institution designated by him to take the necessary measures, unless the agreement on the appointment procedure provides other means for securing the appointment."
15. It is pertinent here to mention that relying on the judgment
rendered in Datar Switchgears Ltd. vs. Tata Finance Ltd. & Anr. (2000) 8SCC 151, it was observed by the Supreme Court in Union of India vs. Bharat Battery Manufacturing Co. (P) Ltd. (2007) 7 SCC 684 that
"Once a party files an application under S.11 (6), the other party extinguishes its right to appoint an arbitrator in terms of clause of agreement."
the light of the abovementioned judgments, the
respondent/MCD which was a necessary as well as a proper
party ought to have got an arbitrator appointed latest by
12/13 August, 2010 in furtherance of the notice issued to
them. Since this is not been done till date, either by the MCD
or even by the Board (successor body) which had been given a
reasonable opportunity to appoint an Arbitrator, both of them
are deemed to have forfeited their right to appoint an
Arbitrator in terms of section 11(6) of the Act.
15. I accordingly, allow the petition and appoint Sh. S. M.
Chopra, the learned Additional District Judge (Retired) as the
sole Arbitrator to adjudicate the disputes which are raised by
the petitioner herein.
16. The respondent/ Board shall be free to raise such preliminary
objections including the objections on merit and filing of
counter claim as it may feel necessary. The Arbitrator shall be
governed so far as the payment of fees is concerned by the fee
schedule prescribed by the Delhi High Court Arbitration and
Conciliation Centre.
17. With these directions, the petitions of the petitioner stand
allowed.
V.K. SHALI, J.
FEBRUARY 03, 2011 RN
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!