Citation : 2011 Latest Caselaw 1084 Del
Judgement Date : 23 February, 2011
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CONT. APP. (c) No. 27/2010
% Date of Decision: 23rd February, 2011
VIKRAM BAKSHI & OTHERS .... PETITIONERS
Through: Mr. Anand M. Mishra, Advocate.
Versus
MRS. SONIA KHOSLA AND OTHERS ...RESPONDENTS
Through: Mr. Deepak Khosla, R-2 in person.
CORAM:
HON'BLE MR. JUSTICE A.K.SIKRI
HON'BLE MR. JUSTICE M.L.MEHTA
1. Whether the Reporters of local papers
may be allowed to see the judgment? No
2. To be referred to Reporter or not? No
3. Whether the judgment should be
reported in the Digest? No
M.L.MEHTA, J. (Oral)
C.M. No. 13701/2010 (delay) In CONT. APP. (c) No. 27/2010
1. Vide this order, the aforesaid application for condonation of
delay is being disposed of.
2. The appellants have filed contempt appeal being 27 of 2010
on 13th July, 2010, against the order dated 26th April, 2010,
passed by the learned Single Judge in CCP No. 2 of 2010. The
instant application, is filed for seeking condonation of delay in
filing the said appeal. The statutory limitation period for filing
the appeal was admittedly 30 days from the date of the order.
The appeal, filed on 13th July, 2010, admittedly, appears to be
time barred.
3. It is stated that order dated 26th April, 2010 was ex-parte
against the appellants and they got the copy of the order only
on 17th May, 2010. The same was handed over to the counsel
for the appellants during last week of May, 2010 for taking
necessary steps and for preparing the present appeal. Since
the Courts were about to close for summer vacations, learned
counsel for the appellant was busy in attending other matters
between the parties. It is averred that during summer
vacations, learned counsel for the appellants was out of
station and returned on 30th June, 2010. He prepared a draft
appeal and sent the same to the appellants for finalizing the
same on 4th July, 2010, but since appellant No. 1 was out of
station uptill 10th July, 2010, the same was signed by him only
on 12th July, 2010. It is averred that the delay in filing the
present appeal is neither intentional nor deliberate, but for
bona fide reasons.
4. The application was opposed and contested by Mr. Deepak
Khosla, respondent No. 2 in person. He submitted that the
counsel for the appellants had the knowledge of the orders
passed on 26th April, 2010, as he was present in the Court on
that date in some other case between the parties. He also
submitted that copy of the order was also given to learned
counsel for the appellants on 27th April, 2010 i.e., on the next
day and that the counsel was also informed about the passing
of the order by e-mail. He further submitted that the period of
thirty days was to be calculated from the day of knowledge of
the order dated 24th April, 2010. Mr. Deepak Khosla relied
upon the case of Khemchand Agrawal v. Commissioner,
Irrigation, Government of Orissa, 2004 Law Suit (Ori) 28.
5. This fact was not denied by learned counsel for the appellants
that Mr. Khosla informed him about the passing of the order of
26th April, 2010 in the Court when he was present in some
other matter. However, it is denied that the copy of the order
was supplied to him on that day.
6. There is no dispute that the order of learned Single Judge
dated 26th April, 2010 was ex-parte against the appellants.
Mr. Deepak Khosla informed the learned counsel for the
appellants about the passing of the aforesaid order in the
Court on 26th April, 2010. A copy of the same was also given
to him on the next day i.e. 27th April, 2010 (though denied).
The admitted fact is that the appellants received the copy of
the order on 17th May, 2010 with the notice of the contempt
petition dated 26th April, 2010. The aforesaid judgment relied
upon by Mr. Deepak Khosla is not applicable in the present
case, inasmuch as, in the said case, no application for
condonation of delay was filed along with the main petition,
but was filed later on. In any case, that case related to
applicability of Section 20 of Contempt of Courts Act, 1971
which provided for limitation of one year for initiation of
contempt proceedings. It was in that context that Section 5 of
the Limitation Act, 1963 was held to have no applicability to
the proceedings under the Contempt of Courts Act. There are
catena of judgments which have held that 'sufficient cause'
required to be established for condonation of delay should
receive a liberal construction so as to advance substantial
justice when no negligence or inaction or bona fides is
imputable to a party. Whether explanation furnished would
constitute 'sufficient cause' or not will depend upon the facts
of each case. There cannot be a straitjacket formula for
accepting or rejecting explanation furnished for the delay
caused in taking steps. The Courts should not proceed with
the tendency of finding fault with the cause shown and reject
the petition by slipshod order. Acceptance of explanation
furnished should be the rule and refusal an exception more so
when no negligence or inaction or want of bona fide can be
imputed to the defaulting party. A liberal approach is to be
adopted and sufficient cause must be made out in a pragmatic
manner and a pedantic approach calling upon a party to
explain each days delay is to be avoided.
6. Reference in this regard is made to Collector, Land
Acquisition, Anantnag v. Katiji, AIR 1987 SC 1353 and
G.Ramagowda v. Special Land Acquisition Officer, AIR
1988 SC 897.
7. The instant application is supported with the affidavits of all
the appellants. The period of limitation is to be calculated not
from the day of the knowledge but form the day of receipt of
copy of the order. That being the case, the period is to be
calculated from 17th May, 2010. In this view of matter, the
limitation period was to expire on 16th June, 2010. Admittedly,
the Courts were closed for summer vacations during this
period and re-opened on 1st July, 2010. The appeal is filed on
13th July, 2010. Therefore, the delay is of 13 days i.e., from 1st
July to 13th July, 2010. The appellants have explained that
appellant No. 1 was out of station from 4th to 10th July, 2010
due to some business engagements and returned on 10th July.
Apparently, there was some element of carelessness on the
part of the appellants in not filing the appeal between 1 st to 4th
July, 2010 or on 11th/12th July, 2010. Keeping in view the
entire gamut of litigation pending between the parties and
consequential effects of the order dated 26th April, 2010
restraining the appellants, it could not be said that the
appellants inaction was deliberate or intentional.
8. Keeping in view the principals of law regarding condonation of
delay, as noted above, and large ongoing litigation and
contest being made by the parties against each other, we are
inclined to exercise our discretion and condone the delay in
filing the instant application. The same is, hereby, allowed.
M.L.MEHTA (JUDGE)
A.K.SIKRI (JUDGE) FEBRUARY 23, 2011 AK
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!