Thursday, 23, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. S.N.Nandy & Co. vs M/S. Nicco Corporation Ltd.
2011 Latest Caselaw 1075 Del

Citation : 2011 Latest Caselaw 1075 Del
Judgement Date : 23 February, 2011

Delhi High Court
M/S. S.N.Nandy & Co. vs M/S. Nicco Corporation Ltd. on 23 February, 2011
Author: V. K. Jain
         THE HIGH COURT OF DELHI AT NEW DELHI
%             Judgment Reserved on: February 15, 2011
              Judgment Pronounced on: February 23, 2011

+      CS(OS) No. 2448/2000

M/S. S.N.NANDY & CO.                        .....Plaintiff
                           - versus -

M/S. NICCO CORPORATION LTD.                 .....Defendant

Advocates who appeared in this case:
For the Plaintiff:       Mr. S.D.Singh, Ms. Bharti
                        Tyagi, Mr. Rahul Kumar Singh,
                        Ms. Megha Bansiwal, Advs.
For the Defendant:    Mr. Rahul Gupta, Mr. Pinaki
                      Addy and Ms. Ira Gupta, Adv.
CORAM:-
HON'BLE MR JUSTICE V.K. JAIN

1. Whether Reporters of local papers may               Yes
   be allowed to see the judgment?

2. To be referred to the Reporter or not?              Yes

3. Whether the judgment should be reported             Yes
   in Digest?

V.K. JAIN, J

1.     This is a suit for recovery of Rs.92,20,562/-.         The

defendant-company, which was awarded the work for

Biological Oxidation Plant for Coal Chemical Effluents at

Rourkela Steel Plant (hereinafter referred to as "RSP),

assigned the civil work for the aforesaid plant to the plaintiff

for a lump sum amount of Rs.2,87,30,000/- vide Letter of



CS(OS)No.2448/2000                                    Page 1 of 51
 Intent (hereinafter referred to as LOI) dated 15th October,

1992. The scope of work as also the commercial terms for

its execution were annexed to the LOI. It is alleged that in a

meeting held in the last week of February, 1993, among the

plaintiff, defendant and the officials of RSP, some major

changes were made in the nature of civil work which was

assigned to the plaintiff and those changes involved extra

work and extra price implications. Some other extra works

were later entrusted to the plaintiff for execution.        The

plaintiff submitted a claim of Rs.32 lakhs to the defendant

for the extra work executed by it, which was later on

corrected and changed to Rs.42,04,500/-. It is alleged that

a sum of Rs.5 lakhs was paid by the defendant to the

plaintiff in February, 1994, which was adjusted towards

payment for the extra works. The amount payable by the

defendant to the plaintiff towards payment of the extra work

is alleged to have accumulated to Rs.57,18,500/.            The

plaintiff has claimed an amount of Rs.43,51,217/- as

principal sum from the defendant along with interest on

that amount at the rate of 24 % per annum, amounting to

Rs.48,69,345/- - till 31st March, 2000.

2.     The defendant has contested the suit. It has taken a

CS(OS)No.2448/2000                                  Page 2 of 51
 preliminary objection that a full and final payment of

Rs.9,36,900/- was made to the plaintiff on 29.8.1997 and

having accepted that amount, the plaintiff cannot claim any

further amount under the contract in question. The other

preliminary objection taken by the defendant is that the suit

is barred by limitation having been filed on 26.9.2000. On

merits, it has been alleged that the defendant has cleared all

the liabilities which were due to the plaintiff under contract

in question. It is also alleged that extra work claimed by the

plaintiff was already covered in the scope of price breakup

given by it on 15.3.1993 which was subsequently amended

on 19.3.1993.

       The defendant has denied for entrusting extra work to

the plaintiff and having assured payment for the alleged

extra work. It is claimed that the plaintiff, on his own did

the alleged extra work and got the same approved from RSP

because he was fully aware that under the contract he was

required to do that work.

3.     The following issues were framed on the pleadings of

the parties:-

              1.    Whether plaint has been signed and
              verified and suit instituted by a duly


CS(OS)No.2448/2000                                   Page 3 of 51
               authorized        person    on   behalf   of   the
              plaintiff?
              2.   Whether plaintiff executed extra
              work not covered by the letter dated 15th
              October 1992? If answer is in affirmative,
              of what amount?
              3.    Whether plaintiff is entitled to
              interest? If so, on which amount, at
              what rate and for which period?
              4.   Whether amount of Rs.9,36,900/-
              was received by the plaintiff by way of full
              and final payment as alleged in para No.1
              of the preliminary objection of written
              statement?
              5.      Whether suit is barred by time?
              6.    Whether      this    Court     has       no
              territorial jurisdiction to try the suit?
              7.      Relief.


Issue No.6

4.     During        arguments,     the   learned   counsel        for   the

defendant stated that he was not pressing this issue.

Accordingly, this issue is stuck off.

Issue No.1

5.     Mr. S.N.Nandy is the proprietor of S.N.Nandy & Co.

and the plaint has been signed and verified by him.

Institution of suit, and signing and verification of pleadings

by the proprietor of a partnership concern is perfectly legal

and valid. In fact, Mr.S.N.Nandy & Co. is only a trade name

adopted by him and the suit ought to have been filed by Mr


CS(OS)No.2448/2000                                             Page 4 of 51
 S.N. Nandy as its proprietor. The issue is decided against

the plaintiff and in favour of the defendant.

Issue No.2

6.     The plaintiff has examined himself as PW-1 whereas

the defendant has examined one witness Mr. Kartick Kumar

Chatterjee as DW-1.

7.     In his affidavit by way of evidence, the plaintiff has

stated that in the last week of February, 1993, a meeting

was     organized    between   him,   the defendant and      the

department of RSP and certain major changes in the scope

of civil work were made by RSP and accepted by the

defendant.       He accordingly wrote letter dated 2.3.1993 to

the defendant giving details of the extra works as well as the

price implication.       He claimed to have sent another

communication dated 17.6.1993 to the defendant in this

regard and has stated that the defendant had permitted him

to proceed with the work including extra and additional

work with promise and assurance that payment would be

made in due course.        He has further stated that in the

meetings held on 3.1.1994 and 6.1.1994, the defendant

acknowledged the extra works done by the plaintiff and also

accepted his entitlement for payment. He accordingly sent a

CS(OS)No.2448/2000                                   Page 5 of 51
 communication dated 7.1.1994 to the defendant in this

regard. He claimed that the defendant made promises and

assurances to clear his dues but failed to do so. According

to him, in the joint meeting held on 11.3.1994 and

12.3.1994, the issue with regard to extra work was

discussed and the defendant promised to scrutinize the

claim and make payment against the same.              Similar

promise, according to him, was made when he visited the

office of the defendant on 29.6.1994 and 14.7.1994. He has

stated that on 10.11.1994, Deputy Managing Director of the

defendant company came to Delhi and the issue about

payment of extra work was discussed and a promise was

made to make payment.         He further stated that a sum of

Rs.5 lakhs was received by him towards extra work on

15.02.1994.          He maintained that the extra work was

executed at the site with the consent and due information to

the defendant and on their assurance to make payment.

       He further stated that the defendant sent a cheque of

Rs.9,36,900/- being last 5% of the original contract value

and the payment towards extra work remained payable to

him. He has proved the comparative statement Ex.PW-1/51

prepared by him. Ex.PW-1/52, according to him are details

CS(OS)No.2448/2000                                  Page 6 of 51
 of change in scope of work.

8.     In rebuttal, Mr. Kartick Kumar Chatterjee who was

examined as DW-1 has stated that the plaintiff was

entrusted the work of design, construction and maintenance

of civil work in the Biological Oxidation Plant for coal

chemical effluents of RSP on turnkey basis, for a total lump

sum price of Rs.2,87,30,000/- as per the terms and

conditions stipulated in the LOI dated 15.10.1992. The LOI,

according to him, did not contemplate any extra work with

extra price implication nor did it contain any price variation

clause.      He has also proved the letter dated 15.3.1993

written by the plaintiff giving detailed item-wise price-wise

breakup and has stated that complete full and final

payment under the contract and LOI was made to the

plaintiff vide receipt dated 29.8.1997.      According to him,

nothing is left due to the plaintiff. He maintained that the

plaintiff never executed any extra item or extra work.

9.     Ex.PW-1/4 is the offer made by the plaintiff to the

defendant company for civil work of BOD plant at RSP.

Paras 2 and 3 of the letter read as under:-

              "We have gone through the entire scope of
              civil work and specifications furnished to
              us along with the enquiry. Our lumpsum

CS(OS)No.2448/2000                                     Page 7 of 51
               offer for entire civil work is based on M/s.
              NCL's scope of work, specifications and
              layout, and Flow diagram drawings sent
              to us.

              Our total lumpsum price consideration for
              the above job shall be Rs.275 lacks
              (Rupees two hundred seventy five lacs
              only) includes design, execution and
              supervision.   Our lumpsum price also
              includes cost of all materials and
              manpower required for the job. The price
              implication of WCT is not considered, by
              us."

10.    Ex.PW-1/5 is the letter of the plaintiff dated 6.8.1992

whereby, he submitted lump sum price quotation for

Earthern Sludge lagoon for a covered area of 800 sqm. and

providing       one   metre   wide   pavement.       A   sum        of

Rs.2,55,000/- was quoted for the sludge lagoon and

Rs.3,35,000/- was quoted for the pavement. Ex.PW-1/6 is

the letter dated 15.10.1992 whereby the work for the

design, engineering, drawing, construction and maintenance

of all the civil works in the Biological Oxidation Plant for

coal chemicals effluents etc. at RSP was awarded to the

plaintiff for a lump sum price of Rs.2,87,30,000/-.              The

scope of work covered by the letter and major chemical

terms and conditions were also enclosed to this letter. The

scope of work as defined in the annexure to this document


CS(OS)No.2448/2000                                       Page 8 of 51
 reads as under:-


              "SCOPE OF WORKS

                    The scope of work of this LOI covers
              the Design. Engineering preparation of
              Arrangement and Detailed Drawings,
              obtaining approval from RSP, construction
              in    accordance   with   the    approved
              drawings, Specifications and Instructions
              of RSP/NCL and maintenance of all the
              Civil-Works involved in the Biological
              Oxidation Plant for Coal Chemical
              Effluents at RSP.
                    The list of items of Civil-Works
              involved in the above project is shown in
              the enclosed Annexure No.1."


       Annexure-I gave detailed breakup of the scope of work

awarded to the plaintiff.

11.      It would thus be noticed that though the initial offer

made by the plaintiff was for Rs.2,75,00,000/-, the work

was     awarded        to   him     for   Rs.2,87,30,000/-   which      is

Rs.12,30,000/- more than the quotation given by him and

the difference between the price and the price at which the

work      was        awarded   is     more    than   the   amount       of

Rs.5,90,000/- which the plaintiff had claimed for extra

items/earthern sludge lagoon and bituminous pavement,

vide letter Ex.PW-1/5. This becomes important since

contention of the learned counsel for the defendant was that

CS(OS)No.2448/2000                                           Page 9 of 51
 value of the work was enhanced in order to pay for the extra

work involved in the execution of contract.

12.    Ex.DW-1/P-1 is the letter of the plaintiff dated

15.3.1993 whereby he sent detailed price breakup for the

civil work awarded to him. This breakup was sent by the

plaintiff in order to facilitate progressive payment to him

during the execution of the work. A perusal of the annexure

to this letter would show that the plaintiff had divided the

amount of Rs.2,87,30,000/- into various heads and sub-

heads.     This break up is important as no item-wise value

was given either in the quotation of the plaintiff or in the

LOI issued to him by the defendant. It is not open to the

plaintiff to say that the items mentioned in this break up

were not included in the scope of work awarded to him, nor

can he claim any amount higher than the amount assessed

by him for each item mentioned in this document.

13.    Admittedly, the work was awarded to the plaintiff on

turnkey basis and a composite amount of Rs.2,87,30,000/-

was to be paid to him for the whole of the work. Unless the

plaintiff is able to show that the work claimed by him as

extra work was beyond the scope of the composite work

awarded to him on turnkey basis, he will not be entitled to

CS(OS)No.2448/2000                                 Page 10 of 51
 any extra payment.     Since the break-up submitted by the

plaintiff as annexure to his letter Exhibit DW1/P1 was

based on the awarded amount, which was higher than the

amount initially awarded by him, he can claim payment

only for that work, which was not included in the break up

sent by him to the defendant.       Of course, he would be

entitled to payment of the work, which was not included in

the break-up given by him to the defendant as well as for

the quantity which exceeded the quantity indicated in the

break-up, provided he is able to make out either a

contractual obligation or a statutory obligation on the part

of the defendant to pay to him for that extra work/extra

quantity.

14.    The case of the plaintiff is that the extra works were

executed by him on the instructions of the defendant. The

case of the defendant, however, is that no extra work was

entrusted by it to the plaintiff and the works claimed as

extra work were included within the scope of the work

awarded to the plaintiff.

15.    In his cross-examination, the plaintiff has admitted

that no prior permission was taken before executing the

extra works. The next question which then comes up is as

CS(OS)No.2448/2000                                  Page 11 of 51
 to whether the defendant had impliedly consented to pay for

the works. Exhibit PW1/9 is the letter sent by the plaintiff

to the defendant on 2nd March, 1993, referring to the

discussions held with various departments of RSP and

stating therein that the defendant had agreed for some

major changes/incorporations in the scope of civil work

having substantial extra price implication on the agreed

lump sum value.      The details of the additional work with

extra price implications were annexed as Annexure A to this

letter. The items mentioned and included in Annexure A to

this letter were sludge drying beds in place of sludge

lagoons, treated effluent sump for increased capacity,

screed concrete in channels and plaster with WPC in all

RCC tank floors, providing anti-forming system, providing

fencing around MCC/Transformer rooms with gates and

bituminous pavement, providing additional aprons around

RCC tanks and pathways as approach to units and two

coats of Epoxy Paint inside Equalization tanks. Out of these

items, screed concrete in channels and plaster with WPC in

all RCC tank floors, anti-foaming system, fencing around

MCC/Transformer rooms and pathways as approach to

units and two coats of Epoxy Paint inside Equalization

CS(OS)No.2448/2000                                 Page 12 of 51
 tanks have not been shown either in Exhibit PW1/51 or in

Exhibit PW1/128, which indicates that either these works

were not actually executed or were treated to be within the

scope of the awarded work and that is why the plaintiff has

not claimed any payment from the defendant for these

works.     Exhibit PW1/12 is the letter of the plaintiff dated

17th June, 1993, informing the defendant that the works

mentioned in the letter would be treated as extra works and

payment for them shall have to be made separately to him

over and above the agreed lump sum value. The two items

mentioned in this letter were dry pump house attached with

the sump size of 5.00 M X 5.00 M and providing necessary

support foundation and walkway platform suitable for

installation of Cooling Tower Device on the top of the sump.

However, neither of these items has been claimed in Exhibit

PW1/51 or PW1/128. Vide letter dated 7th January, 1994,

which is exhibit PW1/17, the plaintiff sought outstanding

payment along with finalization of extra work, which were

claimed to be worth Rs.32 lakhs.       Vide letter dated 25 th

July, 1994, which is exhibit PW1/21, the plaintiff again

sought payment for the extra claim raised by him.          Vide

letter dated 30th September, 1994, which is exhibit PW1/26,

CS(OS)No.2448/2000                                   Page 13 of 51
 the plaintiff again requested the defendant for finalization of

his extra claims, which he had submitted on 31 st December,

1993. This request was reiterated vide fax massage dated

9th November, 1994, which is exhibit PW1/27, fax message

dated 29th November, 1994, which is exhibit PW1/29 and

fax letter dated 12th December, 1994, which is exhibit

PW1/33.

16.    A payment of Rs.5 lakhs was made by the defendant to

the plaintiff vide cheque No.251361 dated 15 th February,

1994 drawn on Hong Kong Bank.          Vide letter dated 30th

May, 1995, which is Exhibit PW1/D-2, the defendant

claimed that this payment was to be adjusted against

further R/A bills commencing from 10 th R/A bill onwards

but inadvertently that was not done.             The plaintiff

immediately replied to this letter vide his response dated 2nd

June, 1995, which is Exhibit PW1/35 and claimed that the

payment of Rs.5 lakhs was made as advance against extra

work carried out by him and had been released after he had

submitted his claim of Rs.41 lakhs towards extra work. He

maintained that this amount could be adjusted against

payment of extra work.     There was no response from the

defendant to this letter, which leads to the inference that

CS(OS)No.2448/2000                                   Page 14 of 51
 this payment was made towards extra work. Vide letter

dated 5th August, 1997, which is Exhibit PW1/44, the

plaintiff sought payment for the extra work executed by

him.     Vide fax message dated 18th July, 1996, which is

Exhibit PW1/38, the plaintiff again sought payment for the

extra work.          Vide letter dated 17 th June, 1997, which is

Exhibit      PW1/43,       the   plaintiff   demanded   a   sum        of

Rs.51,34,500/- from the defendant towards price of extra

work after deducting a sum of Rs.5 lakhs already received

by him as advance towards these extra works. The above

referred correspondence clearly indicates that some extra

works were executed by the plaintiff to the knowledge of the

defendant. Had the defendant not given an implied consent

to any extra work, it would have adequately responded to

the letters of the plaintiff and would not have paid Rs 5

lakhs to the plaintiff towards payment of extra works.

Silence on the part of the defendant, despite repeated

correspondence and claims from the plaintiff for the extra

works alleged to have been executed by him gives an

indication of an implied consent for some payment for the

extra works by him.

17.    Assuming, however, that the extra works claimed by

CS(OS)No.2448/2000                                          Page 15 of 51
 the plaintiff were not authorized by the defendant and,

therefore, the defendant is under no contractual obligation

to pay for those works, the plaintiff is entitled to get

reasonable payment for these works in view of the

provisions contained in Section 70 of the Contract Act,

1872, which reads as under:-

                     "70.    Obligation      of    person
                     enjoying      benefit     of    non-
                     gratuitous act.-- Where a person
                     lawfully does anything for another
                     person, or delivers anything to him
                     not intending to do so gratuitously,
                     and such other person enjoys the
                     benefit thereof, the latter is bound
                     to make compensation to the
                     former in respect of, or to restore,
                     the thing so done or delivered."

18.    A bare perusal of the above referred Section would

show that three conditions need to be fulfilled before benefit

of this provision can be invoked by a person.           The first

condition is that the claimant should either lawfully do

something for another person or deliver something to him.

The second condition is that while doing or delivering

something, the claimant must not be acting gratuitously

and thirdly, the person for whom something is done or to

whom something is delivered must enjoy the thing done for

or delivered to him as the case may be.

CS(OS)No.2448/2000                                      Page 16 of 51
         Invocation of Section 70 of the Contract Act was

disputed by learned counsel for the defendant on the

ground      that     the   plaintiff   has   not   pleaded   essential

requirement of the Section.            In support of his contention

that pleading ingredients of Section 70 is a pre-condition for

its invocation, the learned counsel for the defendant has

referred to Kotah Match Factory Kotah v. State of

Rajasthan, AIR 1970 Rajasthan 118, Hansraj Gupta &

Co. v. Union of India, AIR 1973 SC 2724, Union of India

v. Sita Ram Jaiswal, AIR 1977 SC 329 and Devi Sahai

Palliwal v. Union of India and another, AIR 1977 SC

2082.

19.    In Kotah Match Factory (supra), the Rajasthan High

Court noted that the plaintiff did not raise the plea for

compensation under Section 70 of the Contract Act nor was

any issue framed, nor were the parties given an opportunity

to lead any evidence on the point.            It was found that the

case of the appellant before the Court was based upon an

agreement. It was held that since the parties had not gone

on trial on the question of compensation under Section 70

of the Contract Act, if the benefit of the aforesaid provision

is allowed at this stage, it would amount to taking the

CS(OS)No.2448/2000                                           Page 17 of 51
 opposite party by surprise.          In    Hansraj Gupta &

Co.(supra), the Supreme Court was of the view that the

conditions for the applicability of the Section 70 must at

least be set out in the pleadings and proved. In Sita Ram

Jaiswal (supra), the Supreme Court, inter alia, observed as

under:-

                     "6.      The three ingredients to
                     support the cause of action under
                     Section 70 of the Indian Contract
                     Act are these: First, the goods to
                     be delivered lawfully or anything
                     has to be done for another person
                     lawfully. Second, the thing done
                     or the goods delivered is so done
                     or delivered "not intending to do so
                     gratuitously." Third, the person to
                     whom the goods are delivered
                     "enjoys the benefit thereof." It is
                     only when the three ingredients
                     are pleaded in the plaint that a
                     cause of action is constituted
                     under Section 70 of the Indian
                     Contract Act.      If any plaintiff
                     pleads the three ingredients and
                     proves the three features the
                     defendant is then bound to make
                     compensation in respect of or to
                     restore the things so done or
                     delivered."

        In Devi Sahai Palliwal (supra), the Supreme Court

found that there was no allegation in the plaint to support

any pleading in proceeding under Section 70 of the Indian

Contract Act. Relying upon its earlier decision in Sitaram

CS(OS)No.2448/2000                                      Page 18 of 51
 Jaiswal (supra), it was held that in the absence of proper

pleadings under Section 70 of the Indian Contract Act, the

plaint should not be entertained.

20.    The learned counsel for the plaintiff on the other hand

has referred to State of West Bengal v. M/s B.K. Mondal

and Sons, AIR 1962 SC 779, V.R. Subramanyam v. B.

Thayappa and others, 3 SCR 663 and Food Corporation

of India & Others v. Vikas Majdoor Kamdas Sahkari

Mandli Ltd., 2007 (13) Scale 126.               In the case of B.K.

Mondal and Sons (supra), the Supreme Court, after

reiterating the three conditions, which need to be satisfied

before invoking Section 70 of the Contract Act, was of the

view that when these conditions are satisfied, Section 70

imposes upon the person for whom something is done or to

whom       something    is   delivered,   the    liability   to   make

compensation in respect of or restore the thing done for or

delivered to him.      During the course of the judgment, the

Court, inter alia, observed as under:-

              "14.......If a person delivers something to
              another it would be open to the latter
              person to refuse to accept the thing or to
              return it; in that case S. 70 would not
              come into operation. Similarly, if a person
              does something for another it would be
              open to the latter person not to accept

CS(OS)No.2448/2000                                           Page 19 of 51
               what has been done by the former; in that
              case again S. 70 would not apply. In other
              words, the person said to be made liable
              under S. 70 always has the option not to
              accept the thing or to return it. It is only
              where he voluntarily accepts the thing or
              enjoys the work done that the liability
              under S. 70 arises. Taking the facts in the
              case before us, after the respondent

constructed the warehouse, for instance, it was open to the appellant to refuse to accept the said warehouse and to have the benefit of it. It could have called upon the respondent to demolish the said warehouse and take away the materials used by it in constructing it; but, if the appellant accepted the said warehouse and used it and enjoyed its benefit then different considerations come into play and S. 70 can be invoked. Section 70 occurs in Chapter V which deals with certain relations resembling those created by contract. In other words, this chapter does not deal with the rights or liabilities accruing from the contract. It deals with the rights and liabilities accruing from relations which resemble those created by contract..........Therefore, in cases falling under S. 70 the person doing something for another or delivering something to another cannot sue for the specific performance of the contract nor ask for damages for the breach of the contract for the simple reason that there is no contract between him and the other person for whom he does something or to whom be delivers something. All that Section 70 provides is that if the goods delivered are accepted or the work done is voluntarily enjoyed then the liability to pay compensation for the enjoyment of the said goods or the acceptance of the said work arises. Thus, where a claim for

compensation is made by one person against another under S. 70, it is not on the basis of any subsisting contract between the parties, it is on the basis of the fact that something was done by the party for another and the said work so done has been voluntarily accepted by the other party. That broadly stated is the effect of the conditions prescribed by S.

70."

21. In V.R. Subramanyam (supra), the Court reiteratd the

settled proposition of law that if a party of a contract

rendered service to other not intending to do so gratuitously

and another person had obtained some benefit, the former

is entitled to compensation for the value of the services

rendered by him. It was further held that even if a person

has failed to prove an express agreement in this regard , the

Court may still award him compensation under Section 70

of the Contract Act and such a decree for compensation

would be under the statute and not under a contract.

22. In Food Corporation of India (supra), the Supreme

Court, inter alia, observed as under:-

"12.....A person who does work or who supplies goods under a contract, if no price is fixed, is entitled to be paid a reasonable sum for his labour and the goods supplied. If the work is outside the contract, the terms of the contract can have no application; and the contractor is entitled

to be paid a reasonable price for such work as was done by him.

13. If a party to a contract has done additional construction for another not intending to do it gratuitously and such other has obtained benefit, the former is entitled to compensation for the additional work not covered by the contract. If an oral agreement is pleaded, which is not proved, he will be entitled to compensation under Section 70. Payment under this section can also be claimed for work done beyond the terms of the contract, when the benefit of the work has been availed of by the defendant."

23. In the case before this Court, though the plaintiff has

not specifically pleaded the provisions of Section 70 of the

Contract Act, nor has any issue been framed by the Court

on its applicability, he has pleaded all the ingredients

necessary for invocation of the aforesaid statutory provision.

In the plaint, the plaintiff has repeatedly alleged execution

of extra work for the defendant. In fact, his entire claim in

the suit is based on the extra works alleged to have been

executed by him for the defendant. In para 7 of the plaint,

he alleged that since changes in the scope of work involved

extra work and extra price implications, the letter dated 2 nd

March, 1993 was written by him giving details of additional

work and price implication. In para 9 of the plaint, he

alleged that in his letter dated 17th June, 1993, he had

clearly pointed out about the payment of extra work over

and above the value of the contract. Thus, the plaintiff has

made it quite clear in the plaint that the extra works were

not executed gratuitously and that the defendant was

obliged to make payment for those works. In para 19 of the

plaint, it is alleged that the extra work executed by him was

duly accepted by the defendant. In para 21, he again

alleged that all the works executed by him were accepted by

the parties. In para 27 of the plaint, the plaintiff reiterated

that the extra work was duly executed by him and accepted

by the defendant. The plaintiff has, thus, pleaded all the

necessary ingredients of Section 70 of the Contract Act by

claiming that (i) he had executed extra works for the

defendant; (2) extra works executed by him were accepted

by the defendant and (3) he had not executed extra work

gratuitously. The defendant could have refused to accept

the extra works/extra quantities executed by the plaintiff. In

that event, it would not have been liable to pay for them.

But, the defendant failed to do so and accepted these works.

Therefore, even if it is presumed that the defendant had not

consented to pay for the extra work by the plaintiff, it is

obliged in law to compensate him for the extra works, which

were accepted by it, without any protest and without

claiming that the plaintiff will not be paid for those works.

24. Ex.PW-1/51 is the comparative charge filed by the

plaintiff showing change in scope of work in various units.

The charts reads as under:-

"BOD PLANT AT RSP, ROURKELA
CHANGE OF SCOPE IN VARIOUS UNITS



Sl.No.    Units                   Original   Revised     Difference
                                  Scope      Scope
1         Pump House-I            128 m2     86.45 m2    (-)41.55 m2
2         Pump House-II           192 m2     90.00 m2    (-) 102.00 m2
3.        Office-cum-Lab          300 m2     330.77 m2   (+) 30.77 m2
4.        DAF Building            Nil        255.79 m2   (+) 255.79 m2
5.        MCC Building            Nil        200.16 m2   (+) 200.16 m2

                                                         343.17 m2
6.        Treated      Effluent   40 m3      100 m3      (+) 60 m2
          Sump
7.        Sludge                  800 m2     1080 m2     (+) 280 m2
          Lagoon/Drying Bed
8.        Influent Sump           Nil        35 m3       (+) 35 m2
9.        Pump      House    at              Nil 33 m2   (+)Nil 33 m2
          Common Catch Pit
10.       Cooling Tower Basin     Nil        30.67 m2    31 m2
          Over Common Catch
          Pit



Pump House I & II

25. A perusal of the above-referred chart would show

that as far as item No.1 and 2 viz. Pump House-I and Pump

House-II are concerned, there was reduction in the quantity

of the work, for which credit has to be given to the

defendant.

As per Ex.PW-1/51, the quantity of Pump House-I as

per the original scope of work is 128 sq.mt. but, on revision

the quantity was reduced to 86.45 sq.mt. Since the plaintiff

is claiming payment for the extra work as well as extra

quantity executed by him, he is required to give adjustment

to the defendant for the lesser quantity executed by him. A

perusal of Ex.DW-1/P1 would show that the plaintiff had

quoted Rs.4 Lacs for Pump House-I. If the value of 128

sq.mt was Rs.4 Lacs, the value of 41.55 sq. mt. which is the

difference between the original quantity and the revised

quantity comes to Rs.129843/-. The plaintiff is required to

give adjustment of this amount to the plaintiff on account of

reduction in the quantity of the work for Pump House-I.

The plaintiff had assessed the value of Pump House-II

at Rs.3,50,000/- for 192 m2 in Ex.DW-1/P1. If the value of

192 sq.mt. was Rs.3,50,000/-, the value of difference

between the original quantity and the revised quantity of

102 sq.mt. comes to Rs.185937/-. The plaintiff is required

to give adjustment for this amount to the defendant.

DAF Building

26. As regards item No.4 DAF Building in chart Ex.

PW1/51, the case of the plaintiff as indicated in the Chart is

that this item was not included in the scope of work

awarded to him. However, a perusal of the Annexure to

plaintiff‟s letter Ex.DW-1/P-1 would show that DAF Unit

was shown as item No.5 whereas DAF Dosing Pump House

was shown as item No. 15 and the plaintiff had assessed

value of DAF Unit at Rs.50,000/- and that of DAF Dosing

Pump House at Rs.7 lakhs. There is no evidence on record

to indicate that DAF Building was different from DAF unit

and DAF Dosing Pump House. Nowhere has it been alleged

in the plaint that DAF Building was a work different from

DAF Unit and DAF Dosing Pump. In fact, the plaintiff has

not specified any alleged extra item in the plaint. As a

result, the defendant had no opportunity to rebut the case

of plaintiff in respect of each item claimed to be extra item.

In his affidavit, the plaintiff did not say that DAF Building

was different from DAF Unit and DAF Housing Pump. No

other evidence was led by him to prove that these are

different items. Since the defendant had claimed that all the

works executed by plaintiff were included in the scope of

LOI, it was incumbent upon the plaintiff to prove that this

was a work different from the works included in Ex DW-

1/P1. In fact, there is no evidence during trial to even prove

that any such work was actually executed by the plaintiff.

27. It was contended by the learned counsel for the

plaintiff that since there is no cross-examination of the

plaintiff in this regard, it is not open to the defendant to

dispute the execution of the extra works or to say that these

works were not extra works. In support of his contention, he

has relied upon the decision of this Court in Uttam Kumar

vs. State 2010(3) JCC 1946 and the decision of Punjab High

Court in Chuni Lal Dwarka Nath v. Hartford Fire

Insurance Co. Ltd. and Anr. AIR 1950 Punjab 440. In the

case of Uttam Kumar (supra), which was a criminal appeal

against conviction, it was found that no question was put to

the police officer as to why he took six police men along with

him. Observing, that without questioning a witness on a

point of controversy and eliciting a response, no argument

can be built on said controversy by hinging the controversy

on surmises and conjectures, this Court felt that had the

witness been asked, an answer would have come and then

there could have been some scope for a debate. It was also

found that another witness Vibhor was not cross-examined

with respect to the essential portion of his testimony, which

had virtually gone unrebutted. This Court, then, referred to

the observations made by Punjab High Court in Chuni Lal

Dwarka Nath (supra) that a party should put to each of his

opponent witness so much of his case as concerns that

particular witness and if no such questions are put, the

Court presumes that the witness account has been

accepted. However, these judgments are of no help to the

plaintiff for the simple reasons that in his affidavit by way of

evidence, the plaintiff did not even depose with respect to

execution of the alleged extra works. He did not say that

DAF building was different from DAF Unit and DAF Dosing

respectively in Ex.DW-1/P1. Had the plaintiff stated that he

had constructed DAF Building and that work was different

from DAF Unit and DAF Dosing Pump House, only then

failure of the defendant to cross-examine him in this regard

could have proved detrimental to the defendant and could

have accrued to the benefit of the plaintiff. The case of the

defendant has all along been that all the alleged extra work

was within the scope of the work awarded to the plaintiff.

Moreover, during the course of arguments, I gave an

opportunity to the learned counsel for the plaintiff to satisfy

me, from the drawings, if available on record that DAF

Building was different from DAF Unit and DAF Dosing

Pump House shown in Ex.DW-1/P1. No such attempt was,

however, made. Hence, DAF Building cannot be considered

to be an extra item and the plaintiff is not entitled to any

extra amount for this work.

MCC BUILDING

28. Item No.4 shown in chart Ex.PW-1/51 is MCC

Building. A perusal of the annexure to plaintiff‟s letter

Ex.DW-1/P-1 would show that MCC-cum-transformer room

was shown as item No.18 in this document and the plaintiff

had assessed the value of this work at Rs.8 lakhs. Again,

there is no material on record to indicate that MCC Building

was different from MCC-transformer room. Also, there is no

evidence produced during trial, to prove execution of this

work. The plaintiff did not say about execution of this work

in his affidavit. He did not claim that MCC Building was

different from MCC Transformer Room. No attempt was

made to satisfy me, from drawings, etc. that these were two

separate works. Consequently, this work cannot be treated

as extra item and the plaintiff is not entitled to any amount

from the defendant towards payment of this work.

OFFICE CUM LAB

29. As regards office-cum-lab which is item No.3 in the

Chart Ex.PW-1/51, according to the plaintiff there has been

increase in the scope of work since the quantity had

increased from 300 sq.m. to 330.77 sq.m., the increase

being 30.77 sqm. The plaintiff had assessed the value of

office-cum-lab building at Rs.11 lakhs in the annexure to

his letter Ex.DW-1/P-1. If the cost of 300 sqm. was Rs.11

lakhs, the cost of the extra quantity measuring 30.77

quantity would come to about Rs.1,10,000/-. The plaintiff

therefore cannot claim more than Rs.1,10,000/- for this

extra work. Though in his affidavit, the plaintiff did not

specifically say that the quantity of this item had increased

from 300 m2 to 330.77m2, I do not propose to deny the

payment, since during the course of arguments before me,

the contention of the learned counsel for the defendant was

that the plaintiff can claim for extra quantity, only as per

value assessed in Ex.DW-1/P1. This was not his contention

that in fact the quantity did not exceed 300 m 2.

TREATED EFFLUENT SUMP

30. As regards Treated Effluent Sump which is item No. 6

in the Chart Ex.PW-1/51, the quantity according to the

plaintiff had increased from 40 cubic metre to 100 cubic

metre, the increase being 60 cubic metre. The plaintiff has

in annexure to letter Ex.DW-1/P-1 assessed the value for

Treated Effluent Sump at Rs.2 lakhs. If this was the value

for 40 cubic metre, he is entitled to only Rs.3 lakhs towards

payment of the extra quantity. Though in his affidavit by

way of evidence, the plaintiff did not refer to execution of

extra quantity of this item, I am granting this payment to

him, as the contention before me was that he cannot claim

at a value higher than estimated by him, and this was not

the contention that there was no excess quantity of this

item.

SLUDGE LAGOON/DRYING BED

31. Item No.7 shown in the Chart Ex.PW-1/51 is sludge

lagoon/Drying Bed. The quantity is alleged to have

increased from 800 sqm. to 1080 sqm. the increase being

280 sqm. The case of the plaintiff is that he had given value

of Rs.2,50,000/- for 800 sqm. for sludge lagoon whereas he

has constructed sludge lagoon/ sludge drying bed

measuring 1080 sqm., price of which comes to

Rs.17,28,000/-. The first question which comes up for

consideration in this regard is whether sludge

lagoon/sludge drawing bed is different from the sludge

lagoon shown in Ex.DW-1/P-1 and if so, whether the

plaintiff is entitled to any extra payment for this item. The

heading of item No.14 in the annexure to letter Ex.DW-1/P-

1 is sludge lagoon/drawing bed. Same is the heading given

in the comparative chart. The plaintiff, therefore, cannot

say that the work executed by him was different from the

work for which break up was given by him. By quoting Rs.3

lakhs for sludge lagoon/drawing beds, the plaintiff clearly

indicated that there were alternative works and valued this

work at Rs.3 lakhs irrespective of whether it was to be

sludge lagoon or drawing bed.

The plaintiff has not told the Court how drawing beds

are different from the sludge lagoons. More importantly, the

work indicated in EX.DW-1/P-1 is not sludge lagoon but

sludge lagoon/drawing bed and same is the work alleged to

have been executed by the plaintiff. Therefore, the plaintiff

is entitled only to the extra quantity measuring 280 sqm.

Calculated at the value assessed by the plaintiff himself in

Ex.DW-1/P-1, the price for the extra quantity measuring

280 sqm. would come to Rs.1,05,000/-. The plaintiff is

entitled to recover only this much amount in respect of this

extra quantity. Here also, though the plaintiff did not claim

execution of extra quantity, in his affidavit by way of

evidence, I am inclined to allow payment for extra quantity

as this was not the contention before me that no extra

quantity was executed.

INFLUENT SUMP

32. Item No.8 in chart Ex.PW-1/51 is Influent Sump which

the plaintiff claims to be a new item. However a perusal of

annexure to letter Ex.DW-1/P1 would show that influent

sump was shown as items No.3 in this document and the

plaintiff had assessed its value at Rs.1,00,000/-. There is

neither any pleading nor evidence before the Court to show

that more than one influent sump were constructed by the

plaintiff. NO attempt was made to show from drawings etc.

that the plaintiff had constructed an additional influent

sump. Therefore he is not entitled to any amount towards

this item.

PUMP HOUSE AT COMMON CATCH PIT

33. Item No.9 in chart Ex.PW-1/51 is Pump House at

Common Catch Pit. Though Common Catch Pit has been

shown as item No.21 in annexure to letter Ex.DW1/P1, the

breakup of this item does not indicate any Pump House.

Therefore, if the plaintiff had constructed a Pump House at

Common Catch Pit, it would be an extra item and the

plaintiff would be entitled to payment for this item. During

arguments, this was not the contention of the defendant

that no pump house at common catch pit was constructed

by the plaintiff. The plaintiff has claimed a sum of

Rs.1,85,000/- for this extra item. No evidence has been led

by the defendant to prove that the value of this extra item

would be less than Rs.1,85,000/-. I, therefore, hold that

the plaintiff is entitled to recover a sum of Rs.1,85,000/-

from the defendant towards payment of this extra item.

COOLING TOWER BASIN OVER COMMON CATCH PIT

34. Item No.10 shown in chart Ex.PW-1/51 is Cooling

Tower Basin over Common Catch Pit, which is not included

in the work indicated under item No.2, Common Catch Pit

in annexure to letter Ex.DW1/P1. Again this was not the

contention of the defendant that no Cooling Tower Basin

was constructed by the plaintiff over Common Catch Pit.

The plaintiff, therefore, is entitled to payment towards this

extra item. He has claimed a sum of Rs.1,20,000/- for this

extra item. There is no evidence led by the defendant to

show that the cost of this extra item was less than

Rs.1,20,000/-. I, therefore, see no reason to disbelieve the

unrebutted evidence of the plaintiff in this regard and also

that he is entitled to recover a sum of Rs.1,20,000/- from

the defendant towards payment of this extra item.

APRON AROUND RCC TANK

35. In his comparative statement Ex.PW-1/128, the

plaintiff has also claimed Rs.80,000/- towards payment for

Apron around the RCC Tank. A perusal of annexure to

letter Ex.DW-1/P1 would show that the plaintiff was to

construct Equalization Tank-TO1B, Aeration Tank-I T05

and Aeration Tank-II T07. Apron has been shown as one of

the sub items of Equalization Tank-TO1A. The plaintiff had

assessed its value at Rs.50,000/-. Aprons are also shows as

a part of Equalization Tank-TO1B and its value has been

assessed at Rs.50,000/- Aprons has also been included in

the work shown under the heading Aeration Tank-I and the

plaintiff has assessed its value at Rs.92,000/- for the

aprons/finishing. Aprons/finishing has also been shown

under Aeration Tank-II against item No.10 and the plaintiff

has assessed its value at Rs.1,68,000/-. The plaintiff has

not told the Court how the Apron around the RCC Tank

shown by him at item No.21 in Ex.PW-1/128 is an extra

item when examined in the light of the fact that he has

already included aprons while giving detailed breakup of

Equalization Tank-TO1B, Aeration Tank-I T05 and Aeration

Tank-II T07. No evidence has been led by the plaintiff to

show how many aprons he was to construct in terms of the

LOI and how many were actually constructed by him. No

attempt was made to satisfy me from the drawings that the

any additional apron was constructed by the plaintiff. He

has, therefore, failed to prove that aprons around the RCC

Tank were extra items. I, therefore, hold that the plaintiff is

not entitled to any payment for Apron around the RCC

Tank.

BOUNDARY WALL (EXTRA QUANTITY)

36. At serial No.22 of Ex.PW-1/128, the plaintiff has

claimed a sum of Rs.75,000/- towards excess quantity

measuring 25 RM of boundary wall. The chart indicates

that the quantity as per the work order was 345 RM

whereas the quantity as per the approved drawing was 370

RM. During arguments, there was no claim by the

defendant that the actual quantity was not 370RM. A

perusal of annexure to letter Ex.DW-1/P1 would show that

the plaintiff had assessed the value of boundary wall,

gates/guard room at Rs.5 Lacs. The breakup of this item

would show that a sum of Rs.25,000/- was claimed towards

design and drawing, Rs.50,000/- towards guard rooms and

Rs.20,000/- towards gates. This would mean that the value

of the boundary wall was Rs.4,05,000/- (Rs.5Lac -

Rs.25,000/- - Rs.50,000/- - Rs.20,000/-). If the value of

345 RM is taken as Rs.4,05,000/- the value of the excess

quantity measuring 25 RM would come to Rs.29,347/-. The

plaintiff is entitled to recovery of this amount from the

defendant towards excess quantity of boundary wall.

RECONSTRUCTION OF BOUNDARY WALL

37. In Ex.PW-1/128, the plaintiff has claimed

Rs.153217.50 towards reconstruction of boundary wall in

terms of his letter dated 30 th November 1994. A perusal of

Ex.PW-1/23, which is the letter written by the plaintiff to

defendant on 27th August 1994 shows that there was some

verbal discussion between the parties regarding

reconstruction of boundary wall and Bio-Oxidation plant

and the plaintiff quoted a price of Rs.1,55,000/- for this

work. He also gave details of the price quoted by him for this

item. A perusal of Ex.PW-1/25, which is the letter sent by

the defendant to the plaintiff on 31st August 1994, shows

that on receipt of the letter dated 27th August 1994, the

defendant requested the plaintiff to start the reconstruction

of boundary wall with immediate effect. This letter does not

indicate that reconstruction of boundary wall was

necessitated on account of some defect in the boundary wall

earlier constructed by the plaintiff. Since the plaintiff

quoted a sum of Rs.1,55,000/- for reconstruction of the

boundary wall and the defendant asked him to go ahead

with the work, the defendant is liable to pay for this work

which has to be treated as an extra work. I, therefore, hold

that the plaintiff is entitled to recover a sum of

Rs.153217.50 from the defendant for reconstruction of the

boundary wall.

38. Thus the plaintiff is entitled to recover a sum of Rs

1,10,000/- for the extra quantity of the work involved in

office-cum-lab, Rs 3 lakhs for the extra quantity of the work

involved in Treated Effluent Sump. Rs 1,05,000/- for the

extra work involved in Sludge Lagoon/Drying Bed. Rs

1,85,000 for the Pump House at Common Catch Pit. Rs

1,20,000 for Cooling Tower Basin over Common Catch Pit.

Rs 29,347/- for the extra quantity of boundary wall and Rs

1,53,217.50/- for reconstruction of boundary wall. He is

entitled to give adjustment of Rs 1,29,843/-to the defendant

towards revised quantity of the work involved in Pump

House-I and Rs 1,85,937/- towards reduction in the

quantity of work involved in Pump House-II. The balance

amount payable to the plaintiff for the extra work thus

comes to Rs 6,86,784.50/-

39. This is plaintiff‟s own case that he had received a sum

of Rs.5 lakhs from the defendant as an advance towards the

extra work executed by him. After deducting the aforesaid

amount of Rs.5 lakhs from the amount of Rs 6,86,784.50/-

found payable to the plaintiff. The balance principal sum

payable to him comes to Rs 1,86,784.50. The issue is

decided accordingly.

ISSUE NO.4

40. Relying upon the receipt dated 27th August, 1997,

which is exhibit PW-1/D1 the defendant has claimed that

payment of Rs.9,36,900/- was accepted by the plaintiff in

full and final settlement of all his claims and having done

so, he is now estopped from claiming any further amount

from it towards payment of the extra works. The receipt

Exhibit PW1/D1 reads as under:-

" "RECEIPT"

Received with thanks the full and final payment of Rs.936900.00 (being last 5% of our contract value) vide cheque no.668151, dated: 28-08-97 drawn on Allahabad Bank, Calcutta against Civil Works of our original contract value of Rs.2,87,30,000.00

for S.N. Nandy & Co.

              Date: 29-08-97           Sd/-
                                           (S.N. Nandy)
                                             Proprietor"

41. This document, to my mind, contains an admission

that the plaintiff had received Rs.9,36,900/- from the

defendant towards full and final payment of the work to the

extent it was covered under the LOI Exhibit PW1/6 dated

15th October, 1992. This document does not apply to the

claim of the plaintiff for the extra works executed by him to

the extent those works were beyond the scope of the LOI

dated 15th October, 1992. On receipt of this payment, the

plaintiff had no claim left against the defendant with respect

to those works, which were included in the scope of work

awarded vide LOI dated 15.10.1992, but, it does not

preclude the plaintiff from making claim for payment of

extra works, which he executed for the defendant. While

executing this receipt, the plaintiff did not say that he had

no claim left against the defendant company with respect to

civil work for Biological Oxidation Plant at R.S.P. Rourkela

nor did he say that he had received payment for whole of

the work executed by him at the above referred plant. The

scope of the receipt was confined to the civil works, which

were awarded to him vide LOI dated 15th October, 1992 and

there is no justification for enlarging the scope of this

document beyond what is evident from its plain and natural

reading. Use of the expression "being last 5% of our

contract value" and "contract value of Rs.2,87,30,000/-" in

this receipt clearly indicates that what the plaintiff

acknowledged was full and final payment of the contracted

value and not the price of the extra works, which he had

executed for the defendant.

In Bharat Coking Coal Ltd. V. Annapurna

Construction, (2003) 8 SCC 154, the respondent before

the Supreme Court had accepted the final bill. It was

contended on behalf of the appellant that the respondent

having accepted the final bill, a further claim by it was

inadmissible. Rejecting the contention, it was held that

acceptance of final bill would not mean that the respondent

was not entitled to raise any claim since the respondent had

not unequivocally stated that it would not raise any further

claim. The Court was of the view that in the absence of

such a declaration, the respondent cannot be held to be

estopped or precluded from raising any claim.

In Pandit Construction Company v. Delhi

Development Authority and another, 143 (2007) DLT

270, the petitioner had made the endorsement „accepted in

full and final‟ on the final bill submitted to the DDA. The

claim of the petitioner was rejected by the Arbitrator on the

ground that the final bill had been accepted by the

petitioner as full and final settlement. The petitioner,

however, maintained that this was not full and final

settlement of accounts. Accepting the contention of the

petitioner, this Court held that a settlement, to be binding,

must be recorded in clear and unambiguous terms. The

Court was of the view that the endorsement „accepted in full

and final‟ could also be read to mean that the amount

received was in respect of full amount of the bill on which

endorsement was made.

The issue is accordingly decided in favour of the

plaintiff and against the defendant.

ISSUE NO.5

42. Admittedly, the defendant company had been making

payment to the plaintiff from time to time. The documents

filed by the plaintiff show that the payments used to be

made by cheques. The following payments were made by

the defendant to the plaintiff between 1994-1997 :-

      Cheque No.            Date              Amount
                                                (Rs.)
       527145            18.01.1994          4,00,000/-
       527175            27.01.2994          5,43,670/-
       527338            04.02.1994          5,32,421/-
       527431            18.02.1994          5,00,000/-
       038274            15.03.1994          5,00,000/-
       038339            23.03.1994          4,00,000/-
       038628            20.04.1994          9,49,762/-
       490273            27.05.1994          3,27,945/-
       446810            04.08.1994          5,65,023/-



        575449            13.10.1995           15,00,000/-
       575430            11.10.1995           3,00,000/-
       575450            13.10.1995           3,20,162/-
       212246            10.11.1995           2,54,749/-
       212247            10.11.1995           4,00,000/-
       650410            23.07.1996            83,659/-
       668151            28.08.1997           9,36,500/-



43. Section 19 of the Limitation Act, to the extent it is

relevant, provides that where payment on account of a debt

is made before the expiration of the prescribed period, by

the person liable to pay the debt or by his agent duly

authorized in this behalf, a fresh period of limitation would

be computed from the time when the payment was made.

The last payment having been made by the defendant is on

28th August, 1997, a fresh period of limitation if computed

from this date would expire on 28th August, 2000. The suit

having been filed on 26th May, 2000 is, therefore, well within

time. Though it was contended by the learned counsel for

the defendant that the payment on 28th August, 1997 was

made after the limitation prescribed for filing a suit of this

nature had expired, that obviously is incorrect since

payments by way of cheques were made by the defendant

from time to time and at no occasion there was gap of three

or more years between the two payments. In this regard, it

would be pertinent to note that though the extra works

executed by the plaintiff were out of the scope of work

contained in the LOI dated 15th October, 1992, the amount

payable by the defendant to the plaintiff towards the civil

work executed by him at Biological Oxidation Plant at R.S.P.

Rourkela was one debt and though having two components,

one for the works covered in the scope of LOI and the other

for the works which were beyond the scope of LOI cannot be

said that the payment for the work included in the scope of

work awarded vide LOI dated 15 th October, 1992 was one

debt and payment for the extra work executed by the

plaintiff was another debt. The project executed by the

defendant for the plaintiff was one project, i.e., civil work at

Biological Oxidation Plant at R.S.P. Rourkela and, therefore,

payment for the entire quantity irrespective of whether for

the work included within the scope of work indicated in the

LOI or for the work beyond the scope of LOI, constituted one

debt, which the defendant owed to the plaintiff. Therefore,

even the payment was made by the defendant to the plaintiff

towards price of the contractual work, which was included

in the LOI it would extend the period of limitation also for

the extra work executed by the plaintiff while carrying out

civil work at Biological Oxidation Plant at R.S.P. Rourkela.

It would also be pertinent to note here that this is not the

requirement of law that while making a payment, the debtor

must make it towards part payment. Any payment,

irrespective of, whether it is made as part payment or

otherwise, would extend the period of limitation under

Section 19 of the Limitation Act. In this regard I may refer

to the decision of the Privy Council in Rama Shah v. Lal

Chand, AIR 1940 Privy Council 63 where the Court, inter

alia, observed as under:-

"In the Limitation Act, Section 19, which deals with acknowledgments, is not to be read as based upon the theory of implied promise: and it is difficult to see why Section 20, which deals with payments, should be regarded as based upon a theory of acknowledgment. The Indian Legislature may well have thought that a payment if made on account of the debt and evidenced by writing gave the creditor some excuse for further delay in suing, or was sufficient new proof of the original debt to make it safe to entertain an action upon it at a later date than would otherwise have been desirable. The words in Section 20 by which the matter must be judged are "where part of the principal of a debt is paid". As it is not prescribed by the Section that the payment should be intended by the debtor to go towards the principal debt at all, the words 'as such'

having no place in this part of the Section, it is not in their Lordships' view correct to require that the payment should have been made of part as part."

44. In support of his contention that the suit is barred by

limitation, learned counsel for the defendant has referred to

Major (Retd.) Inder Singh Rekhi v. Delhi Development

Authority, (1988) 2 SCC 338, Satender Kumar v.

Municipal Corporation of Delhi and another, 168 (2010)

DLT 15, and Hansa Vision Pvt. Ltd. V. Dabur (India)

Limited & Ors, 168 (2010) DLT 562.

45. In the case of Inder Singh Rekhi (supra), the Court

was dealing with a petition under Section 20 of the

Arbitration Act, 1940. During the course of judgment, the

court observed that on completion of the work a right to get

payment would normally arise but where the final bills have

not been prepared, the cause of action would arise from the

date when the assertion of the claim was made. It was

further observed that a party cannot postpone the accrual of

cause of action by writing reminders or sending reminders

but where the bill has not finally prepared, the claim made

by the claimant is the accrual of cause of action.

In the case of Satender Kumar (supra), this Court,

after referring to the decision of the Supreme Court in the

case of Inder Singh Rekhi (supra), inter alia, held as

under:-

"16(iii) As regards contracts for execution of building work, Article 18 comes into play in that when no specific date for payment is fixed, limitation commences and the cause of action accrues for the purpose of limitation on the completion of work.

(iv) In its application, Article 18 will cause different dates for accrual of causes of action in building works when a time period is fixed for submitting of a bill by the contractor and to which there is no response to the owner. Where a final bill is submitted and liability under the same, even if, in part, is admitted or some payment is made then such actions extend limitation in terms of Section 18 of the Limitation Act."

In the case of Hansa Vision Pvt. Ltd. (supra), this

Court, referring to Article 113 of the Limitation Act, 1963,

observed that the period of limitation is 3 years to be

computed from the date when right to sue accrues,

wherever the aforesaid Article applies.

All these judgments tend to support the contention of

the learned counsel for the defendant that in a suit for price

of work executed by contractor, Article 18 of the Limitation

Act would be the relevant Article, which provides a period of

limitation of 3 years from the date when the work is done,

where no time has fixed for payment. They also support his

contention that a party cannot postpone the accrual of

cause of action by writing letters and reminders seeking

payment from the other party and once the period of

limitation starts running, mere sending reminders would

not postpone the accrual of cause of action even if the

defendant does not dispute his liability in this regard.

However, the benefit of Section 19 of Limitation Act cannot

be denied to the plaintiff even if Article 18 of the Limitation

Act is applied to the case. The issue is decided against the

defendant and in favour of the plaintiff.

ISSUE NO.3

46. The plaintiff has claimed interest @ 18% per annum

for the period from 31st December, 1993 to 31st March, 2000

on the amount of Rs.41,98,000/- and from 30th November,

1994 to 31st March, 2000 on the amount of Rs.1,53,217/-

thereby making a total sum of Rs.48,69,345/- towards

interest. The plaint does not disclose the basis on which

interest has been claimed by the plaintiff. Admittedly, there

is no agreement between the parties for payment of interest.

No custom or usage of trade with respect to payment of

interest has either been pleaded or proved by the plaintiff.

It is settled proposition of law that in a civil suit interest

cannot be awarded as damages. However, interest can be

awarded by the Court under the provisions of the Interest

Act, 1978. Section 3 of the Interest Act, 1978, to the extent

it is relevant, provides that in any proceedings for the

recovery of any debt in which the claim of interest in respect

of any debt is made, the Court may, if it thinks fit, allow

interest to the person entitled to the debt on a rate not

exceeding the current rate of interest. If the proceedings

relate to a debt, which is not payable by virtue of a written

instrument at a certain time, interest can be awarded for

the period from the date mentioned in this regard in a

written notice given by the person entitled or making the

claim to the person liable that interest will be claimed, till

the date of institution of the proceedings. Vide his letter

dated 18th July, 1996, the plaintiff informed the defendant

that the losses incurred by him were being worked out in

terms of interest and the same shall be intimated to it. The

details of interest were then sent by the plaintiff to the

defendant vide its letter dated 20th July, 1996, which is

Exhibit PW1/39. He claimed interest @ 24% per annum. I,

therefore, feel that interest should be awarded to the

plaintiff from 20th July, 1996 till the date of filing of this suit

at the rate of 12% per annum. Calculating accordingly the

amount of interest at the rate of 12% per annum on the

principal amount of Rs.1,86,784.50/-, interest for the

period from 20th July, 1996 to 26th May, 2000 comes to

Rs.86,294.44p. The plaintiff is entitled to recover total

amount of Rs.2,72,078.94p from the defendant.

ORDER

For the reasons given in the preceding paragraphs,

a decree for a sum of Rs.2,72,078.94p with proportionate

costs and pendente lite and future interest at the rate of

12% per annum is passed in favour of the plaintiff and

against the defendant.

Decree sheet be prepared accordingly.

(V.K. JAIN) JUDGE FEBRUARY 23, 2011 bg/sn/AG/vkm'

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter