Thursday, 23, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Rama Construction Company vs Municipal Corporation Of Delhi
2011 Latest Caselaw 6249 Del

Citation : 2011 Latest Caselaw 6249 Del
Judgement Date : 20 December, 2011

Delhi High Court
Rama Construction Company vs Municipal Corporation Of Delhi on 20 December, 2011
Author: V. K. Jain
         THE HIGH COURT OF DELHI AT NEW DELHI

%                    Judgment Reserved on: 05.12.2011
                     Judgment Pronounced on: 20.12.2011

+ CS(OS) 921/2005 & IA 5040/2005

RAMA CONSTRUCTION COMPANY             ..... Plaintiff
               Through: Mr. A.K.Trivedi, Adv.

                     versus

MUNICIPAL CORPORATION OF DELHI        .... Defendant
                Through: Ms. Mini Pushkarna, Adv.

CORAM:-
HON'BLE MR JUSTICE V.K. JAIN

V.K. JAIN, J

1.          This is a suit for declaration, perpetual injunction

and mandatory injunction. The plaintiff was awarded work

for construction of live stock marketing for sheep, goat and

buffalo at Gazipur Dairy Farm, vide work order dated

18th March, 2003, which the plaintiff claims to have received

on 31st March, 2003. The work was to be completed within

fifteen months and the time allowed for carrying out the

work was to be reckoned from the tenth day of the work

order. Admittedly, the work was not completed within the

period of fifteen months stipulated in the order irrespective

of whether the period is reckoned from the tenth day of the



CS(OS)No.921.05                                       Page 1 of 50
 issue of the order, i.e. 18th March, 2003 or it is reckoned

from tenth day of the date on which the plaintiff claims to

have received the work order.

            Clause 2 of the agreement between the parties

provided that if the Contractor failed to maintain the

required progress in terms of clause 5 or to complete the

work and clear the site on or before the Contract or

extended date of completion, he shall pay, as agreed

compensation, at the rate of 1% per day or such smaller

amount as the Superintending Engineer may decide, on the

tendered value of the work, for every completed day, the

work remained incomplete or the progress remained below

that specified in clause 5 of the Contract. It provides that

the total amount of compensation for the delay would not

exceed 10% of the tendered value of the work. The decision

of the Superintending Engineer in this regard has been

made final and binding. Clause 5.1 of the Contract, to the

extent it is relevant provided that the Contractor shall

submit a time and progress chart and get it approved from

the department.     It further provided that the Contractor

shall, in all cases in which the time allowed for any work

exceeds one month complete 1/8 th of the whole of work

CS(OS)No.921.05                                    Page 2 of 50
 before 1/4th of the whole time allowed in the contract has

elapsed, 3/8th of the work before one-half of such time has

elapsed and 3/4th of the work before 3/4th of such time has

elapsed. A show-cause notice dated 11th March, 2004 was,

therefore, issued by the defendant to the plaintiff.             The

defendant vide notice dated 11th March, 2004, intimated the

plaintiff that since the progress of the work was not

proportionate to the time that had elapsed, he had rendered

himself liable to pay compensation.             He was, therefore,

asked to show-cause why the compensation be not levied.

The plaintiff replied to the show-cause notice, but the reply

was     not       found   satisfactory.   The     defendant,     vide

communication dated 4th March, 2005,                 informed the

plaintiff that the Competent Authority under clause 2 of the

agreement had determined that he was liable to pay

Rs.19,04,703/- as compensation.           The aforesaid action of

the defendant has been challenged by the plaintiff primarily

on the grounds that (i) the compensation was levied after

the contract had already lapsed and (ii) the delay in

completion of the work was not attributable to him. This is

also the case of the plaintiff that it was the defendant which

had failed to provide lay-out plan and get the connect the

CS(OS)No.921.05                                          Page 3 of 50
 electricity connection and further had also failed to remove

the hindrance created by legal people at the site where the

work was to be executed.          The defendant has also taken

action under clause 3 of the agreement and published a

fresh tender for work to be executed at the risk and cost of

the plaintiff. The plaintiff has now sought a declaration that

the order levying compensation and taking action for re-

tender at the risk and cost of the plaintiff, is null and void.

The plaintiff has also sought an injunction restraining the

defendant from taking action for recovering the amount of

compensation and debarring or blacklisting him from the

department.           The plaintiff has also sought mandatory

injunction directing the defendant not to circulate any letter

with respect to recovery of aforesaid amount to any other

divisioned branch.

2.          In its written statement, the defendant has alleged

that the plaintiff had stopped the work right from the very

beginning on flimsy grounds and to hide his own short-

comings.          He completed only 16% of the work during the

stipulated period of 15 months to complete the work,

though there was no hindrance in the execution of the work.

It is also alleged that six other agencies worked round the

CS(OS)No.921.05                                       Page 4 of 50
 clock on the adjacent land completed the work of temporary

live stock market, construction of link road etc. without any

public resistance from June, 2003 to March, 2004.                          It is

claimed that the plaintiff raised bogus dispute on one

pretext or the other which not only caused delay but also

caused losses to the public exchequer. He accepted various

provisional extensions but did not complete the work. The

following table, according to the defendant, would clear the

picture:-

S.No./Item        No.   of   the Quantity     as      per Quantity executed
schedule                         Schedule                 by the contractor
Item
                                 Qty.          %     of Qty.              % of
                                               Total                      Total
                                               work                       work


1/15        Brick work 1:6       547.24        3.34        629.66 M3 3.84
            in foundation
2/16        Brick work 1:6       546.71            3.74    334.07         2.28
            in         super
            structure
3/132       Random               306.31 M3         1.78    329.83 M3 1.92
            Rubble
            masonry
4/136       Washed stone         452.10            0.64    3243.53        4.63
            grit plaster         SQ.M.
5/13        Reinforcement        140800 Kg.    14.24       35861.53       3.63

6/36        Steelwork   in 70000Kg             8.60        24691.12       3.03
            grating
7/119       Supply     and 7506 M3                 1.67    341.91M3       0.07
            stacking     of
            good earth
8/129       Ready      mix 1879.61M3               16.91   334.00 M3 3.00
            concrete




CS(OS)No.921.05                                                     Page 5 of 50
             It is alleged that items at serial No.1 to 4 were of

interest to the plaintiff and covered upto 9.5% of total cost

but the plaintiff went on to execute these item upto 12.67%

of the total cost of the contract. On the other hand, he was

not interested in items at serial No.5 to 8 which constituted

upto 41.42% of the total cost of the contract. The plaintiff,

however, executed these items only upto the extent of

9.73%.       The following table, according to the defendant,

indicates the delay in progress of the work at the site:-

S.No.    Running     Date of Time          % of the    % work Cumulative
         Account     Bill    elapsed       total       done      Hindrance
         Bill (gross                       work        (actually
         amount                            required    at site)
         upto date)                        to    be
                                           done (as
                                           per
                                           contract)
1        1st    R.A.    30.6.0   3 month   20%         2.19%      19 days
         Bill       -   3
         4,17,525/-
2        Upto     2nd   23.10.   7 month   46%         3.71%      27 days
         R.A.Bill       03
         2,89,830/-



            It is also alleged that in fact this project was a loss-

making contract for the plaintiff on account of abnormally

low rates quoted by him and that is why he did not execute

the work in terms of his agreement with the defendant. It is

also alleged that the contract had not expired at the time



CS(OS)No.921.05                                                Page 6 of 50
      compensation was levied, since MCD had granted two

     extensions upto 27th April, 2005 and the plaintiff also

     continued to work at the site till 14 th January, 2005.

                 The following table, according to the defendant

     indicates the progress of work during the entire period of

     execution of work:-

S.No.     Running      M.B.No./P   Date       of    Gross           %    of   Hindranc    %     of
          Actt. Bill   age         billing          Amount of       work      e           work to
          No.                                       accepted bill   done                  be done
1.        1st          415/88      30.06.03         4,17,525/-      2.19%     19 days     20%
          Running
          Account
          Bill
2.        2nd          1817/6      23.10.03         2,89,830/-      3.71%     27 days     46%
          Running
          Account
          Bill
3.        3rd          1817/73     31.7.04          23,31,698/-     15.95     27 days     100%
          Running                                                   %
          Account
          Bill
          1817/7
          3
4.        4th          1817/87     27.8.04          14,50,504/-     23.57     27days      100%
          Running                                                   %
          Account
          Bill



                 The       defendant          has      justified        the      levy      of

     compensation on the ground that the plaintiff had failed to

     complete the work even in the extended period of contract.

     Regarding delay in dispatch of the work order, it is alleged

     that the plaintiff despite being aware of the awarded work to

     him and site having been shown to him did not collect the

     turn over and despite it, it has been handed over to him on


     CS(OS)No.921.05                                                            Page 7 of 50
 21st March, 2003.

            It is also alleged that the approach to the site was

not available only for eight days starting from 11th August,

2003 as was duly recorded in the hindrance register but the

plaintiff did not complete the work despite site being

available free from all encumbrances and any hindrance.

Approach to the site, according to the plaintiff was provided

by creating another entry by filling up the drain passing in

front of the site. It is also alleged that after two provisional

extensions upto 24th April, 2005, the plaintiff was also given

another extension upto 27th June, 2005. It is alleged that

there was a total hindrance of 57 days which was duly

recorded in the hindrance register maintained at the site,

and the hindrance was not for 299 days from 11 th August,

2003 to 4th June, 2004, as is claimed by the plaintiff.

3.          The following issues were framed on the pleadings

of the parties:-

              1.     Whether MCD was right in levying
              compensation of Rs.19,04,703/- under
              Clause 2 of the contract vide order dated
              4th March, 2005?         OPD.

              2.      Whether MCD was right in
              rescinding the contract under clause 3 of
              the Agreement by order dated 10th May,
              2005?

CS(OS)No.921.05                                       Page 8 of 50
               3.      Whether MCD was right in
              issuing Tender dated 13th May, 2005 at
              the risk and cost of the plaintiff firm?
              OPD.

              4.     Whether MCD was right in
              issuing show-cause notice dated 19th
              May, 2005?     OPD.

              5.      Whether the hindrances existing
              at site were such as to lead to non-
              execution of the contract? OPP.

              6.     Whether the plaintiff is entitled to
              decree of declaration and injunction?
                     OPP.
              7.     Relief."


Issues No.1 to 5:

            These issues are inter-connected and can be

conveniently decided together.


4.          In M/s J.G.Engineers Pvt. Ltd. v. Union of India

& Anr. AIR 2011 SC 2477, Supreme Court considering a

clause identical to clause 2 of the agreement between the

parties to this suit, inter alia held as under:

       14. Thus what is made final and conclusive by
       clauses (2) and (3) of the agreement is not the
       decision of any authority on the issue whether
       the contractor was responsible for the delay or
       the department was responsible for the delay or
       on the question whether termination/rescission
       is valid or illegal. What is made final, is the
       decisions on consequential issues relating to

CS(OS)No.921.05                                        Page 9 of 50
        quantification, if there is no dispute as to who
       committed breach. That is, if the contractor
       admits that he is in breach, or if the Arbitrator
       finds that the contractor is in breach by being
       responsible for the delay, the decision of the
       Superintending Engineer will be final in regard
       to two issues. The first is the percentage
       (whether it should be 1% or less) of the value of
       the work that is to be levied as liquidated
       damages per day.            The second is the
       determination of the actual excess cost in
       getting the work completed through an
       alternative agency. The decisions as to who is
       responsible for the delay in execution and who
       committed breach is not made subject to any
       decision of the respondents or its officers, nor

excepted from arbitration under any provision of the contract.

Supreme Court in this regard also referred to the

following view taken by it in Bharat Sanchar Nigam

Limited v. Motorola India Limited (2009) 2 SCC 337:

x x x The decision contemplated under Clause 16.2 of the agreement is the decision regarding the quantification of the liquidated damages and not any decision regarding the fixing of the liability of the supplier. It is necessary as a condition precedent to find that there has been a delay on the part of the supplier in discharging his obligation for delivery under the agreement.

5. It would thus be seen that in the present case, it is

for this Court to decide whether delay in execution of the

work within the time stipulated in the agreement is

attributable to the plaintiff or to the defendant. If the Court

finds that the delay is attributable solely to the defendant,

the decision of the Superintending Engineer levying

compensation on the plaintiff is liable to be held without

jurisdiction. On the other hand, if the Court finds that the

delay is attributable to the plaintiff, the decision of the

Superintending Engineer in respect of the quantum of

compensation to be levied on the plaintiff would be final and

binding on the parties and it would not be open to the Court

to review the decision of the Superintending Engineer with

respect to quantum of compensation and take a view

contrary to the view taken by the Superintending Engineer.

Similarly, if the Court finds that the Contractor failed to

maintain progress of the work in terms of clause 5 of the

agreement and the defendant was not responsible for the

failure of the plaintiff to maintain the required progress, it

would not be open to the Court to interfere with the amount

of compensation levied by the Superintending Engineer, his

decision with respect to quantification of the compensation

being final and binding on the parties.

6. The plaintiff has filed his own affidavit by way of

evidence and has examined one more witness Shri Harmir

Singh from Police Station Kalyanpuri. The defendant has

examined one witness Mr. Alok Tiwari. In his affidavit by

way of evidence Mr. Alok Tiwari who was earlier working as

Assistant Engineer in Division 27 of MCD has stated that

there was hindrance at the site from 18th March, 2003 to 4th

April, 2003 as was noted in the hindrance register.

According to him, thereafter there was no obstruction on

the site upto 9th October, 2004 due to any public resistance.

He has alleged that the plaintiff had completed only 16% of

the work during the stipulated period of 15 months to

complete the work, despite there being no hindrance in

execution of the work. The plaintiff, according to him, was

from the very beginning trying to avoid execution of the

items which were loss making items for him. He wanted a

replacement of stone masonry, brick masonry on boundary

wall, Dholpur Stone finish on boundary wall with blue grit

stone finish and ready mix concrete by designs mix

concrete, in execution of the work. The defendant, though

not bound to do so, accorded replacement of the first two

items since the plaintiff promised to expedite the work and

complete it within the stipulated period. He was also

allowed to execute small concrete work using design mix at

the site but permission to replace whole of ready mix

concrete by design mix concrete was denied since ready mix

concrete is rated highest grit concrete by everyone.

According to him, the plaintiff executed excess work in

respect of the items which are profitable to him but failed to

execute very little work in respect of the items which were

not profitable to him. He has claimed that the items which

were not profitable to the plaintiff constituted 41.42% of the

total cost of the contract but the plaintiff executed them

upto the extent of 9.73%. On the other hand, the items

which were profitable to him and constituted 9.5% total cost

of the work were executed upto 12.6% of the total cost of

the work. He has also claimed that the plaintiff was

provided police protection by approaching the police

whenever he made complaint though first such complaint

was made only on 9th September, 2004. He has alleged that

the progress of the work executed by the plaintiff never

commensurate with the time that had elapsed. The plaintiff

was required to execute 20% of the work in first three

months and 46% of the work in first seven months. As

against this, he executed only 2.19% of the work during

first three months and 31% during first seven months

though the cumulative hindrance during this period was 90

days and 27 days respectively. He has alleged that

approach to the site was not available only for eight days

and another entry was provided to the plaintiff by filling up

the drain passing in front of the site and the plaintiff,

therefore, did not have any valid reason for slow progress of

the work. He has also alleged that the plaintiff himself

signed the cement register till 30th January, 2005 and the

cement was issued to him till 14th January, 2005, till he

demolished the cement godown and site office and removed

all the cement from the site, without knowledge of the

department.

7. The plaintiff, in his affidavit by way of evidence has

stated that the work order posted on 29th March, 2003 was

received by him by 31st March, 2003 and immediately

thereafter he had written a letter to the defendant

requesting that the date of start of work may be taken as

10th April, 2003 since the work order was received by him

only on 31st March, 2003. Referring to the correspondence

between the parties, he has stated that he had been writing

to the defendant to complete the work required to be done

on its part. According to him, he had also requested for

replacement of coursed rubble stone masonry with brick

work since mining of stone was banned by Supreme Court.

He also stated that the defendant also failed to make

payment to him despite repeated requests from him. He

has alleged that the work was stopped by the residents from

the first day of September, 2004 and when the situation did

not come under control despite efforts made by him as well

as by officers of the defendant, the matter was reported to

the police, which was requested to remove the hindrances at

the site. He has stated that the Executive Engineer has

passed an order on behalf of the Commissioner

imposing/levy Rs. 19,04,703/- as compensation on him,

which was against the norms of clause 2 of the agreement

as well as the principles of natural justice. He has also

alleged that the defendant knowingly did not record the

hindrances which were beyond his control. He has claimed

that the defendant was not competent to rescind the

contract under clause 3 of the agreement since the contract

had already come to an end on 9 th July, 2004 whereas the

contract was repudiated vide letter dated 9th December,

2004.

8. Admittedly, the time stipulated in the Contract for

completion of the work awarded to the plaintiff was

15 months. The case of the plaintiff is that since the work

order was received by him only on 30 th March, 2003, the

time for commencement of the work should be taken as 10 th

April, 2003. Computed from 10th April, 2003, the work

ought to have been completed by 9th July, 2004, which

admittedly has not been done. The case of the plaintiff is

that the work could not be completed by him on account of

hindrances at the site. The case of the defendant, as noted

earlier, is that the initial hindrance on the site was only

from18th March, 2003 to 4th April, 2003. There is no

credible evidence of any hindrance on the site between 10 th

April, 2003 and 9th July, 2004. It has come in the

testimony of DW-1 that for 8 days, an approach to the

site was not available and, therefore, another entry was

provided by them to the plaintiff by filling up the drain

passing in front of the site. Thus, the site was approachable

10th April, 2003 onwards and the plaintiff, therefore, had no

justification not to complete the work by 9th July, 2004.

It has come in evidence that the plaintiff wanted

replacement of stone masonry, brick masonry on boundary

wall, Dholpur Stone finish on boundary wall with blue grit

stone finish and ready mix concrete by designs mix

concrete, in execution of the work. It is an admitted case

that though it was not bound to do so, the defendant

approved replacement of the two items. The plaintiff was

also allowed to execute small concrete work using design

mix at the site. It is true that permission to replace whole of

the ready mix concrete by design mix concrete was refused

to the plaintiff but, since ready mix concrete definitely is far

superior than a design mix and as stated by DW1, it is

considered as the highest grit concrete, the defendant was

well within its right in refusing to permit replacement of

whole of the ready mix concrete by design mix concrete.

Refusal of the defendant to permit replacement of the whole

of the RMC by DMC therefore did not justify delay in

completion of the work. There is no evidence of any

agitation by local people at its site, between 10 th April, 2003

and 9th July, 2004. The agitation started only in September,

2004 whereas the time to complete the construction had

expired much earlier. The plaintiff himself has stated in the

Court that the work was stopped by residents from first day

of September, 2004. This is not his claim that the local

residents had also stopped the work at any time between

10th April, 2003 and 9th July, 2004. A perusal of the

complaint made by DW-1 Shri Alok Tiwari to the Police

(Ex.P-20) would show that the hindrance at this site started

only about ten days before this letter was written by him,

which would mean that it started on or before 30 th August,

2004. There is no evidence of any agitation at this site prior

to 30th August, 2004.Therefore, the agitation by local people

did not justify failure of the plaintiff to complete the work

within the time stipulated in the Contract. A perusal of the

letter dated 24th November, 2004 (Ex.P-29) and letter dated

9th December, 2004(Ex.P-30) would show that the plaintiff

was insisting on payment of price difference in terms of

clause 10cc of the Contract, in order to complete the

balance work. The alleged hindrance, therefore, was not the

true reason for the failure of the plaintiff to complete the

work within the stipulated period. In fact the letters dated

18th August, 2003(Ex.P-8), 27th October, 2003(Ex.P-9), 14th

November, 2003(Ex.P-10), 10th December, 2003(Ex.P-11)

and 6th September, 2004(Ex.P-19) written by the plaintiff to

the defendant indicate that the reason given by the plaintiff

for delay in completion of the work was non-payment of bills

and not any such hindrance which could have been

prevented the execution of the work at this site. In fact, no

hindrance at all was claimed by the plaintiff in these letters.

Vide letter dated 2nd April, 2003, Ex.P-3, the

plaintiff had requested the defendant to make available (i)

lay-out plan of the project; (ii) location of hand pump/tube

well; (iii) letter to DVB for temporary electricity connection;

(iv) all architectural as well as structural designs. Vide

letter dated 3rd April, 2003(wrongly dated as 4th March,

2003) which is Ex.P-4 and is an admitted document, the

defendant informed the plaintiff that (i) lay-out plan can be

had from the office of the AE/JE concerned; (ii) location of

hand pump should be marked by him himself in the lay-

out, plan considering the building infrastructure; (iii) for

electricity connection, he should apply in a prescribed form

and his application should be forwarded to the concerned

Electric Engineer and (iv) all the architectural as well as

structural designs can be had from the office of Executive

Engineer(or concerned Assistant Engineer). Thus, the

defendant immediately responded to the requirement of the

plaintiff and this response was sent seven days before 10 th

April, 2003 which I am taking as the date for

commencement of work. In fact the defendant vide a

separate letter dated 3rd April, 2003(Ex.P-4/A) which again

is an admitted document, requested the plaintiff to start the

work immediately since it was of great importance being

necessary, to implement an order passed by the Supreme

Court. A perusal of the documents would show that the

defendant had continuously been requesting the plaintiff to

speed up the work and complete it in time. The letters

whereby the plaintiff was requested to speed up the work

are dated 23rd July, 2003 (Ex.PW-1/6), 20th February,

2004(Ex.P-12), dated 25th February, 2004(Ex.PW-12/A),

dated 11th March, 2004(Ex.P-14), dated 27th September,

2004(Ex.P-25 & Ex.P-76), dated 14th January, 2005(Ex.P-

31), and dated 20th January, 2005(Ex.P-34).

I, therefore, have no hesitation in holding that the

plaintiff was squarely responsible for not completing the

work within the stipulated period of 15 months computed

from 10th April, 2003, and, thereby he rendered himself

liable to levy of compensation under clause 2 of the

Contract between the parties.

9. The work completed by the plaintiff in the first 15

months was to the extent of only 16%, which was wholly

unjustified and amounted to breach of the contract on the

part of the plaintiff. As noted earlier, in terms of clause 5 of

the Contract, the plaintiff was required to execute 1/8th of

the work before 1/4th of the time allowed for completing the

work, 3/8th of the work before half of the time stipulated for

completing the work and 3/4th of the work before expiry of

3/4th of the stipulated time. As against this, the plaintiff

executed 2.19% of the work during first three months and

31% during first 7 months. In fact, this is not at all in

dispute as the plaintiff did not maintain progress of the

work in terms of his agreement with the defendant.

10. During the course of arguments, it was contended

by the learned counsel for the plaintiff that the defendant

was not competent either to levy compensation or to rescind

the Contract, after the Contract had already expired by

efflux of time. The case of the defendant, on the other hand,

is that the compensation can be levied even after the time

for execution of the work expired and in any case the time

was extended by the defendant first upto 27 th December,

2004 vide letter dated 28th June, 2004, then upto 27th April,

2005. Vide letter dated 24th December, 2004 and thereafter

after 27th June, 2005, vide letter dated 19th April, 2005. The

plaintiff has denied receipt of the letters dated 28 th June,

2004, 24th December, 2004 from the defendant, though

receipt of the letter 19th April, 2005(Ex.D-11) has been

admitted by the plaintiff. A copy of this letter has also been

filed by the plaintiff as Ex.P-44. The plaintiff himself has

filed a copy of the letter dated 25th April, 2005 Ex.P-45 sent

to him by the defendant. Even in this letter, there is

reference to extension of time upto 27th June, 2005.

Ex.PW-1/D is the cement register which was

maintained at the site. A perusal of the document would

show that cement was regularly issued to the plaintiff even

after 27th June, 2004. The plaintiff took cement on

numerous dates, the last delivery having been taken by him

on 14th January, 2005. In fact the last seven deliveries of

cement were taken in January, 2005, whereas cement was

taken 17 times in December, 2004 and 18 times in

November, 2004. It had also been taken on a number of

dates in October, September, July and June, 2004. Had the

defendant not extended time beyond 27th June 2004 and

the plaintiff not accepted extension of work from time to

time, there would have been no occasion for him to take

delivery of cement from the site, after the initial date

stipulated for completion of the work had expired. Had the

plaintiff not received the letter dated 28 th June, 2004

extending the time for completion of the work upto 27 th

December, 2004, he would not have taken delivery of

cement after June 2004. Similarly had he not received the

letter dated 24th December, 2004 extending the time upto

27th April, 2005, he would not have taken delivery of cement

after December, 2004. In his deposition, the plaintiff has

claimed that he stopped the work on the site on 31 st August,

2004 but, delivery of cement taken by him from time to

time, even after 31st August, 2004 clearly shows that his

statement in this regard is not correct. It would be

pertinent to note here that the plaintiff has admitted that

the cement which is stored at the godown at the site was

under joint custody of the parties and whenever it was

taken out from the godown, enty used to be made in cement

register before taking cement out of the godown. He has

also admitted the cement register (Ex.PW-1/DA) filed by the

defendant and has expressly admitted his signatures at

mark „A‟ to mark „G‟. Mark „G‟ shows the issue of cement in

December, 2004 and January, 2005, mark „F‟ shows

delivery of cement to the plaintiff between September, 2004

and December, 2004 and mark „E‟ shows delivery of cement

to him between August, 2004 and September, 2004. The

conduct of the plaintiff in taking delivery of cement beyond

27th December, 2004, clearly indicates that the parties had

treated the contract as subsisting even beyond 27 th

December, 2004, and that is why the plaintiff got the

cement issued to him from the godown, and presumably to

carry out further work. The site register Ex.PW-1/DB has

also been admitted by the plaintiff. It bears signature of the

site Engineer of the plaintiff on 17th January, 2005 wherein

it is recorded that after demolishing the cement godown and

site office, the plaintiff had removed all the cement from the

site, without permission of the department. These

documents totally be lie the case set up by the plaintiff and

clearly show extension of time by the defendant.

11. Referring to various extensions of time granted to

the plaintiff for completing the work and the terms of the

contract providing for levy of compensation on account of

delay in execution of the work, it was contended by The

learned counsel for the plaintiff that since time was not the

essence of the contract, the defendant was not justified in

rescinding the contract and awarding the work for execution

by another agency at the risk and cost of the plaintiff. In

support of his contention, the learned counsel for the

plaintiff has relied upon the decision of Supreme Court in

Hind Construction Contractors vs. State of Maharashtra

AIR 1979 Supreme Court 720. In the above-referred case,

the period for completion of the work was fixed as 12

months from the date of commencement of the work. The

plaintiff/appellant did not complete the work within the

stipulated time, whereupon the contract was rescinded by

the respondent and the security deposited by the appellant

was forfeited. The case of the appellant before Supreme

Court was that time was not the essence of the contract, the

completion of the work was delayed on account of reasons

beyond his control and though extension of time was

permissible under the contract, it was wrongfully refused by

the respondent, though his request for extension of time

made before expiry of the time stipulated for completion of

the work was pending with the respondent. The contention

was that the respondent/defendant ought to have granted

some reasonable time to the plaintiff/appellant for

completing the work undertaken by him and making the

time essence of the contract and only if the work was not

completed by him within that time, the contract could have

been rescinded on the ground that the plaintiff/appellant

had committed breach of the contract. Dealing with the

contention Supreme Court, inter alia, observed as under:

"X X X It will be clear from the aforesaid statement of law that even where the parties have expressly provided that time is of the essence of the contract such a stipulation will have to be read along with other provisions of the contract and such other provisions may, on construction of the contract, exclude the inference that the completion of the work by a particular date was intended to be fundamental; for instance, if the contract were to include clauses providing for extension of time in certain contingencies or for payment of fine or penalty for every day or week the work undertaken remains unfinished on the expiry of the time provided in the contract such clauses would be construed as rendering ineffective the express provision relating to the time being of the essence of contract.

X X X If time was not of the essence of the contract or if the stipulation as to the time fixed for completion had, by reason of the waiver, ceased to be applicable then the only course open to the respondent was to fix some time making it the essence and if within the time so fixed the appellant-plaintiff had failed to complete the work, the respondent-defendant could have rescinded the contract.

X X X Long before the expiry of the period of 12 months the appellant-

plaintiff had by his letter dated June 6, 1956 (Ex. 68) requested for extension of period of completion up to the end of December, 1956; this request was repeated by another letter dated June 23, 1956 (Ex. 69). May be the reasons or grounds on which the request was made may not have appealed to the Superintending Engineer but some reasonable time making it the essence ought to have been granted. In this behalf it may be stated that the S.D.O. by his letter (Ex. 69) had recommended extension up to December 1956 as sought while by his letter dated June 23, 1956."

In the facts and circumstances of the case before this

Court, this judgment would be of no help to the plaintiff.

This is not the case of the plaintiff that he had asked for

extension of time to complete the work, but the defendant

had unjustifiably refused the same. It is rather the case of

the defendant that they had extended the time for

completion of the contract; firstly up to 27 th June, 2004,

then up to 27th December, 2004 and lastly up to 27th June,

2005. The plaintiff himself wrote letters to the defendant

stating therein that he was not interested in executing the

balance work. During his deposition in the Court, the

plaintiff claimed that he had stopped work at the site in

August, 2004. In his letter dated 09th December, 2004

(Ex.P-30), the plaintiff alleged that he had never applied for

extension of time and in fact he was rescinding/repudiating

the contract w.e.f. 09th December, 2004. In his legal notice

dated 10th February, 2005, the plaintiff again referred to his

letter dated 09th December, 2004. In the legal notice dated

21st March, 2004 (Ex.P-37), the plaintiff again alleged that

he had vide letter dated 09th December, 2004, rescinded the

contract. This was again reiterated in his reply dated 04th

April, 2005 (Ex.P-42), representation dated 12th April, 2005

(Ex.P-43) and notice dated 25th May, 2005 (Ex.P-51). Since

the plaintiff abandoned the work, did not apply for

extension of time and even did not offer to complete the

work within the time, which was extended by the defendant

from time to time, the defendant, in my view, was justified

in rescinding the contract and awarding the work to another

agency to be executed at the risk and cost of the plaintiff.

In any case, even if I presume, despite my finding

to the contrary, that rescission of the contract was wrong in

law on account of time being not essence of the contract

that would have no bearing on the compensation levied

upon the plaintiff under clause 2 of the Contract.

12. It was contended by the learned counsel for the

plaintiff that though under Clause 2 of the contract, the

compensation can be levied only by Superintending

Engineer, the levy of compensation to the plaintiff was

conveyed by the Executive Engineer and neither the

Superintending Engineer has been produced in the witness

box nor has any documentary evidence been produced by

the defendant to prove that the compensation was levied by

Superintending Engineer.

A perusal of Ex.P-36, which is the letter dated 04th

March, 2005, conveying levy of compensation to the

plaintiff, shows that the compensation was levied by the

Competent Authority. Though the letter does not indicate,

who the Competent Authority was, since the compensation

under Clause 2 of the Contract could be levied only by the

Superintending Engineer, the reference to the Competent

Authority in the letter dated 04th March, 2005, obviously,

would be only to the Superintending Engineer. Hence, it

cannot be said that the compensation was not levied by the

Superintending Engineer. In my view, since the letter dated

04th March, 2005 clearly conveyed that compensation was

levied by Competent Authority, it was not necessary for the

defendant to produce the Superintending Engineer in the

witness-box to prove that the compensation was levied by

him.

13. Relying upon the decision of this Court in Delhi

Development Authority vs. Construction & Design

Services, UP Jal Nigam, 165 (2009) Delhi Law Times 208, it

was contended by the learned counsel for the plaintiff that

since the communication dated 04th March, 2005 did not

disclose any reason as to why maximum compensation was

levied on the plaintiff, the order levying compensation is

liable to be declared null and void. I, however, find no merit

in this contention. As noted earlier, Supreme Court, in M/s

J.G.Engineers Pvt. Ltd. (supra), and Bharat Sanchar

Nigam Limited (supra) has clearly held that decision of the

Superintending Engineer with respect to quantification of

the compensation is final and what has to be seen for

adjudication is only as to whether the contractor was

responsible for the delay or not. A purpose of requiring a

decision making authority to disclose the reasons for his

decision is that in the event of his decision being

challenged, the reviewing authority or the Court, as the case

may be, may scrutinize the reasons given by him, to decide

whether the decision is based on cogent and germane

reasons or was influenced by extraneous considerations.

Since the decision of the Superintending Engineer with

respect to quantum of damage is final and binding on the

parties and, therefore, cannot be questioned in any

proceedings, including a civil suit, absence of reasons for

levying the maximum penalty cannot be a ground for

declaring the levy of compensation null and void.

14. It was also contended by the learned counsel for

the plaintiff that since the defendant has failed to prove the

actual damages, it is not entitled to recovery of any

compensation from the plaintiff. Again, he has relied upon

the decision of this Court in Construction & Design

Services, UP Jal Nigam (supra), where this Court was of

the view that the plaintiff before the Court having not

treated the time as essence of the contract, cannot fall back

on a presumptive condition to impose the maximum

compensation leviable; enforcement of such action would be

giving effect to a penalty clause. As regards reasonable

compensation, this Court observed that the plaintiff had not

shown even the basis for levying compensation which it did

in that case, despite its being aware of the extent to which

the contract was performed as well as the exact extent of

loss in monetary terms, either by way of payment to another

contractor or the amount spent for completing the work.

15. In BSNL vs. Reliance Communication Ltd.

(2011) 1 SCC 394 and ONGC vs. Saw Pipes Ltd AIR 2003

SC 2629. In Saw Pipes Ltd (supra), the respondent offered

to supply casing pipes to the appellant, who accepted the

offer and issued a detailed order containing terms and

conditions of which the goods were to be supplied on or

before 14th November, 1996. The contract provided for

payment of liquidity damages to the appellant. After

referring to Sections 73 and 74 of the Contract Act,

Supreme Court, inter alia, observed as under:

"Under Section 73, when a contract has been broken, the party who suffers by such breach is entitled to receive compensation for any loss caused to him which the parties knew when they made the contract to be likely to result from the breach of it. This Section is to be read with Section 74, which deals with penalty stipulated in the contract, inter alia [relevant for the present case] provides that when a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, the party complaining of breach is entitled, whether or not actual loss is proved to have been caused, thereby to receive from the party who has broken

the contract reasonable compensation not exceeding the amount so named. Section 74 emphasizes that in case of breach of contract, the party complaining of the breach is entitled to receive reasonable compensation whether or not actual loss is proved to have been caused by such breach. Therefore, the emphasis is on reasonable compensation. If the compensation named in the contract is by way of penalty, consideration would be different and the party is only entitled to reasonable compensation for the loss suffered. But if the compensation named in the contract for such breach is genuine pre-estimate of loss which the parties knew when they made the contract to be likely to result from the breach of it, there is no question of proving such loss or such party is not required to lead evidence to prove actual loss suffered by him. Burden is on the other party to lead evidence for proving that no loss is likely to occur by such breach. Take for illustration: if the parties have agreed to purchase cotton bales and the same were only to be kept as a stock-in-trade. Such bales are not delivered on the due date and thereafter the bales are delivered beyond the stipulated time, hence there is breach of the contract. Question which would arise for consideration is--whether by such breach party has suffered any loss. If the price of cotton bales fluctuated during that time, loss or gain could easily be proved. But if cotton bales are to be

purchased for manufacturing yarn, consideration would be different (emphasis supplied)

....Take for illustration construction of a

road or a bridge. If there is delay in completing the construction of road or bridge within stipulated time, then it would be difficult to prove how much loss is suffered by the Society/State. Similarly in the present case, delay took place in deployment of rigs and on that basis actual production of gas from platform B- 121 had to be changed. It is undoubtedly true that the witness has stated that redeployment plan was made keeping in mind several constraints including shortage of casing pipes. Arbitral Tribunal, therefore, took into consideration the aforesaid statement volunteered by the witness that shortage of casing pipes was only one of the several reasons and not the only reason which led to change in deployment of plan or redeployment of rigs Trident-II platform B-121. In our view, in such a contract, it would be difficult to prove exact loss or damage which the parties suffer because of the breach thereof. In such a situation, if the parties have pre-

estimated such loss after clear understanding, it would be totally unjustified to arrive at the conclusion that party who has committed breach of the contract is not liable to pay compensation. It would be against the specific provisions of Section 73 and 74 of the Indian Contract Act. There was nothing on record that compensation contemplated by the parties was in any way unreasonable."

In para 69 of the judgment, the Court, inter alia,

concluded as under:

"(1) Terms of the contract are required to

be taken into consideration before arriving at the conclusion whether the party claiming damages is entitled to the same;

(2) If the terms are clear and unambiguous stipulating the liquidated damages in case of the breach of the contract unless it is held that such estimate of damages/compensation is unreasonable or is by way of penalty, party who has committed the breach is required to pay such compensation and that is what is provided in Section 73 of the Contract Act.

(3) Section 74 is to be read along with Section 73 and, therefore, in every case of breach of contract, the person aggrieved by the breach is not required to prove actual loss or damage suffered by him before he can claim a decree. The Court is competent to award reasonable compensation in case of breach even if no actual damage is proved to have been suffered in consequence of the breach of a contract.

(4) In some contracts, it would be impossible for the Court to assess the compensation arising from breach and if the compensation contemplated is not by way of penalty or unreasonable, Court can award the same if it is genuine pre- estimate by the parties as the measure of reasonable compensation."

In BSNL (supra), the contract between the parties

provided for payment of liquidity damages to the appellant.

On the question as to whether a sum named in the contract

is a pre-estimate of reasonable compensation for the loss or

by way of penalty, Supreme Court referred to the following

extract from Law of Contract (10th Edn.):

"a payment stipulated as in terrorem of the offending party to force him to perform the contract. If, on the other hand, the clause is an attempt to estimate in advance the loss which will result from the breach, it is a liquidated damages clause. The question whether a clause is penal or pre-estimate of damages depends on its construction and on the surrounding circumstances at the time of entering into the contract".

As regards the liquidity damages, the Court

observed as under:

"Lastly, it may be noted that liquidated damages serve the useful purpose of avoiding litigation and promoting commercial certainty and, therefore, the court should not be astute to categorize as penalties the clauses described as liquidated damages. This principle is relevant to regulatory regimes. It is important to bear in mind that while categorizing damages as "penal" or "liquidated 68 damages", one must keep in mind the concept of pricing of these contracts and the level playing field provided to the operators because it is on costing and pricing that the loss to BSNL is measured and, therefore, all calls

during the relevant period have to be seen."

In case of Saw Pipes Ltd (supra) the contract

pertained to supply of pipes required for deployment of rigs

which were to be used for production of gas and the plan for

redeployment and a revised plan had to be made for

deployment of rigs on account of various constraints

including shortage of casing pipes which were to be

supplied by Saw Pipes Ltd. and shortage of casing pipes

being only one of the several reasons leading to delay in

deployment of rigs, the actual damages on account of delay

in supply of casing pipes could not have been ascertained

by the Court. In case of BSNL vs. Reliance

Communication Ltd. (supra), there was an interconnection

agreement between the parties which provided for payment

of liquidated damages and considering that the telecom

services in India are operating under regulatory regime

where all service providers are to be afforded level playing

field. The Court was of the view that the compensation

claimed by BSNL was pre-estimate of damages and was not

penal in nature.

In Shiva Jute Baling Ltd vs. Hindley and

Company Ltd, AIR 1959 SC 1357, the appellant company

entered into a contract with the respondent company for

supply of 500 bales of jute. The contract proved that in the

event of default of tender or delivery, the seller shall pay to

the buyer as and for liquidated damages, Rs 10 per ton plus

the excess (if any) of the market value over the contract

price, the market value being that of jute contracted for on

the day following the date of default. On the appellant

taking the stand that the contract had stood cancelled, the

respondent claimed default on the part of the appellant and

the matter was referred for arbitration. Upholding the

compensation awarded by the Arbitrator in terms of the

contract between the parties, Supreme Court, inter alia,

observed as under:-

"The argument under this head is that the liquidated damages provided under clause (12) of the contract include not only the difference between the contract price and the market price on the date of default but also a further sum of 10s. per ton. Reference in this connection is made to Sections 73 and 74 of the Indian Contract Act, and it is said that the extra amount of 10s. per ton included in the sum of liquidated damages is against the provision of these section and therefore the award being against the law of India

is bad on the face of it and should not be enforced in India. Section 73 provides for compensation for loss or damage caused by breach of contract. It lays down that when a contract has been broken, the party who suffers by such breach is entitled to receive from the party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from such breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it. Section 74 provides for breach of contract where penalty is stipulated for or a sum is named and lays down that when a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for. What clause (12) of the contract provides in this case is the measure of liquidated damages and that consists of two things, namely, (i) the difference between the contract price and the market price on the date default and

(ii) an addition of 10s. per ton above that.

There is nothing in s. 73 or s. 74 of the contract Act, which makes the award of such liquidated damages illegal. Assuming that the case is covered by s. 74, it is provided therein that reasonable compensation may be awarded for breach of contract subject to the maximum amount named in the contract. What the

arbitrators have done is to award the maximum amount named in the contract. If the appellant wanted to challenge the reasonableness of that provision in clause (12) it should have appeared before the arbitrators and represented its case. It cannot now be heard to say that simply because clause (12) provided for a further sum of 10s. per ton over and above the difference between the contract price and the market price on the date of the default, this was per se unreasonable and was therefore bad accordingly to the law of India as laid down in Sections 73 and 74 of the Contract Act. Both these sections provide for reasonable compensation and s. 74 contemplates that the maximum reasonable compensation may be the amount which may be named in the contract. In this case the arbitrators have awarded the maximum amount so named and nothing more. Their award in the circumstances cannot be said to be bad on the face of it, nor can it be said to be against the law of India as contained in these sections of the Contract Act."

16. The propositions of law which emerge from the

statutory provisions contained in Section 73 & 74 of the

Indian Contract Act when examined in the light of a

cumulative reading of aforesaid decisions of Supreme Court

can be summarized as under:

a) If a party to the contract commits breach of the

contract, the party who suffers loss/damage on

account of such breach is entitled to receive such

compensation from the party in breach of the contract

which naturally arose in usual course of business, on

account of such breach or which the parties to the

contract knew, at the time of making the contract, to

be likely to result on account of its breach. However,

the party suffering on account of the breach is entitled

to recover only such loss or damage which arose

directly and is not entitled to damages which can be

said to be remote.

b) In case the agreement between the parties provides for

payment of liquidated damages, the party suffering on

account of breach of the contract even if it does not

prove the actual loss/damage suffered by it, is entitled

to reasonable damages unless it is proved that no loss

or damage was caused on account of breach of the

contract. In such a case, the amount of reasonable

damages cannot exceed the amount of liquidated

damages stipulated in the contract.

Any other interpretation would render the words

"whether or not actual damage or loss is proved to

have been caused thereby" appearing in Section 74 of

the Indian Contract Act absolutely redundant and

therefore the Court needs to eschew such an

interpretation.

c) If the amount stipulated in the contract, for payment

by party in breach of the contract, to the party

suffering on account of breach of the contract is shown

to be by way of penalty, the party suffering on account

of the breach is entitled only to a reasonable

compensation and not the amount stipulated in the

contract. If it is shown by the party in breach of the

contract that no loss or damage was suffered by the

other party on account of breach of the contract, the

party in breach of the contract is not liable to pay any

amount as compensation to the other party.

d) If the nature of the contract between the parties is

such that it is not reasonably possibly to assess the

damages suffered on account of breach of the contract,

the amount stipulated in the contract, for payment by

the party in breach should normally be accepted as a

fair and reasonable pre-estimate of damages likely to

be suffered on account of breach of the contract and

should be awarded.

17. In FAO(OS) No. 06/2008 & FAO(OS) No.07/2008

Oil & Natural Gas Corporation Ltd. v. Mitra Guha Builder

(India) Company decided on 16th February, 2009 damages

were levied in exercise of power conferred on the

Superintending Engineer under an identical clause. The

Arbitrator however, concluded that the clause permitting

levy of penalty was impermissible in law and it was not a

clause levying liquidated damages being a pre-estimate of

damages. The view taken by the Arbitrator was upheld by

the learned Single Judge noticing that the petitioner cannot

deny liability to make payment by adjusting admitted

amount against the damages/penalty when a substantive

part of delay (367 days) was attributable to the petitioner

and there was a smaller part of delay (273 days), which was

attributable to the respondent. The Division Bench of this

Court held that the view taken by the Arbitrator was not

correct since mere absence of a recital in the clause of the

agreement to the effect that the parties agree that the

liquidated damages are genuine pre-estimate, would not

lead to the conclusion that the parties had provided for levy

of penalty and not liquidated damages. The Court was of

the view that the reasoning adopted by the Supreme Court

in ONGC v. SAW Pipes (supra) was applicable and the

learned Single Judge had disregarded the same.

In Pure Pharma Limited v. Union of India,

2008(3) Arb. L.R. 57 (Delhi), the agreement between the

parties contained an identical clause. One of the grounds

taken by the petitioner in that case was that the clause

pertaining to liquidated damages could not be invoked

unless and until the exact extent of loss was proved. It was

also contended that the aforesaid clause did not reflect the

genuine pre-estimate of damages but was in the nature of a

penalty and therefore it was incumbent upon the

respondent to prove the loss incurred by it on account of the

alleged breach. The petitioner before the Court relied upon

the decision of Supreme Court in ONGC v. SAW Pipes

(supra) as well as the decision in Haryana Telecom Ltd. v.

Union of India 2006 (2) Arb.L.R. 293. After considering the

decisions relied upon by the learned Counsel for the

petitioner, this Court noted that the Arbitrator had

interpreted the aforesaid clause to be a genuine pre-

estimate of the loss which was likely to occur on account of

delayed supplies and also held that the compensation

provided in the said clause was not unreasonable since no

evidence had been led by the claimant to establish that the

stipulated condition was by way of penalty. It was also

observed that the claimant was not able to demonstrate

either before the Arbitrator or before the Court that on

account of delay in the supply of goods no legal injury was

or would be suffered by the respondent or no loss was likely

to occur on account of the delayed supplies. The petition

challenging the award was therefore dismissed.

18. A Division Bench of this Court having held in

Mitra Guha Builder (India) Company (supra) that such a

levy was by way of liquidated damages and similar view

having been taken in Pure Pharma Limited (supra), I am

unable to accept the contention that the levy of

compensation under Clause 2 of the Contract was not by

way of liquidated damages envisaged in Section 74 of the

Act. In Sudhir Genset Limited vs. Indian Oil Corporation

Ltd. 177 (2011) DLT 438, this Court, dealing with a clause

which provided for payment by the vendor to the defendant

by way of liquidated damages, an amount equal to ½ per

cent of arterial, delayed by the vendor for each week or part

thereof subject to a maximum of 10% of the price, rejected

the contention that in order to claim damages, the

respondent was required to prove the actual loss suffered by

it. In taking this view, this Court, particularly relied upon

the decision of Supreme Court in the ONGC (supra). The

Court was of the view that when the parties had agreed to

fix liability in terms of Clause 13 for payment of damages as

per the formula contained in that clause, it was not a case

of penalty but what was recovered is the amount of damages

pre-fixed by the parties with regard to loss suffered by the

respondent on account of delay in supplying the equipment.

In such circumstances, it was not necessary for the

respondent to prove actual damages.

19. The learned counsel for the plaintiff has also

submitted copies of the decisions in Vishwanath Sood vs.

Union of India, AIR 1989 SC 952, B.W.L. Ltd. vs. MTNL

and Others 2000 Arb. W.L.J. 450, J.S. Chaudhary vs.

Vice-Chairman, DDA and Anr. 183 (2011) Delhi Law Times

723.

I have perused these judgments and none of them

is of any help to the plaintiff. In the case of Vishwanath

Sood (supra), Supreme Court held that levy of

compensation was conditioned on some default or

negligence on the part of the contractor and the relevant

clause in the Court provides for discretion to the

Superintending Engineer to reduce the rate of penalty from

one per cent. It was observed that nay moderation which

may be done by the Superintending Engineer would depend

on the circumstances, the nature, the period of default and

the degree of negligence or default that could be attributed

to the contractor. It was also observed that the decision of

Superintending Engineer was in the nature of a considered

decision which he has arrived at after considering the

various mitigating circumstances that may be pleaded by

the contractor and the question regarding amount of

compensation has to be decided only by the Superintending

Engineer and no one else.

However, in the case before this Court, it has been

proved that it was the plaintiff who was responsible for

delay in execution of the work and in fact he abundant the

work despite various extensions of time granted by the

defendant. A show-cause notice dated 11th March, 2004

(Ex.P-13) was admittedly issued to the plaintiff and was also

replied by him vide letter dated 19th March, 2004 (Ex.P-16).

However, since he has failed to complete the work,

compensation was levied on him and conveyed vide letter

dated 04th March, 2005. The presumption is that while

levying the compensation, the Superintending Engineer had

considered all the facts and circumstances of the case,

including the reply submitted by the plaintiff to the show-

cause notice. As noted earlier, since the decision of the

Superintending Engineer with respect to quantification of

the compensation is final and binding on the parties, it was

not necessary for the Superintending Engineer to pass a

speaking order dealing with each and every plea taken by

the plaintiff in his reply to the show cause notice.

In B.W.L. Ltd. (supra), this Court held that before

levying the liquidated damages, it was necessary to prove

that there was delay by the supplier in performance of its

obligations the agreement did not clothe the respondent

with the power to arrive at a unilateral finding in this regard

and that even independent of Section 74 of the Contract

Act, it was necessary that adjudication takes place on the

question who was responsible and liable for the delay. This

judgment does not help the plaintiff since this Court has

gone into this aspect and has come to the conclusion that

the plaintiff was squarely responsible for the delay in

execution of the work. This Court was also of the view that

the respondent could not take a decision with respect to

levy of compensation in violation of the rule of audi alteram

partem. Again, this judgment does not help the plaintiff

since a show-cause notice was duly given to the plaintiff

before levying the compensation.

In J.S. Chaudhary (supra), the plaintiff had file a

suit claiming certain amounts from DDA. I do not find any

such proposition of law in this judgment which can be

applied to the case before this Court.

The learned counsel for the plaintiff has also relied

upon clauses 28.1 to 28.8.3 and clause 32.1 of CPWD

Works Manual, but I find nothing in the above-referred

provisions of the Manual, which would be of any help to the

plaintiff.

20. In the case before this Court, there is nothing on

record to indicate that the compensation contemplated by

the parties under clause 2 of the Contract was in any way

unreasonable. No evidence has been led by the plaintiff to

establish that levy of compensation envisaged in clause 2 of

the Contract was by way of penalty or that the

compensation contemplated therein was unreasonable. No

evidence has been led by the plaintiff to prove that there

was no legal injury to the defendant on account of his

failure to complete the contract. The challenge to levy of

compensation, therefore, must fail. The issues are decided

against the plaintiff and in favour of the defendant.

21. In view of my findings on issues No.1 to 5, the

plaintiff is not entitled to the declaration or injunction

sought by him.

ORDER

In view of my findings on issues, the suit is

dismissed with costs.

Decree sheet be drawn accordingly.

(V.K. JAIN) JUDGE DECEMBER 20, 2011 'sn'/vn/bg

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter