Citation : 2011 Latest Caselaw 3992 Del
Judgement Date : 17 August, 2011
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Reserved on: 27.07.2011
% Date of decision: 17.08.2011
+ FAO (OS) No.141 of 1998
M/s. MOHAN CONSTRUCTION CO. ...APPELLANT
Through: Mr. Sunil K. Mittal, Mr. Kshitij Mittal
& Mr. Pranav Rishi, Advocates.
Versus
DELHI DEVELOPMENT AUTHORITY & ANR. ...RESPONDENTS
Through: Ms. Anusuya Salwan, Ms. Renuka
Arora & Ms. Neha Mittal, Advocates for
R-1.
CORAM:
HON'BLE MR. JUSTICE SANJAY KISHAN KAUL
HON'BLE MR. JUSTICE RAJIV SHAKDHER
1. Whether the Reporters of local papers
may be allowed to see the judgment? YES
2. To be referred to Reporter or not? YES
3. Whether the judgment should be NO
reported in the Digest?
SANJAY KISHAN KAUL, J.
1. The appellant/contractor was awarded the work of construction of 560
MIG houses at Pitampura, Pocket A(P) including internal development
by the DDA/respondent No.1 vide contract agreement
No.3/EE/N.D.I/85-86. The agreement contained an arbitration clause,
being clause No.25. The appellant/contractor claimed that it concluded __________________________________________________________________________________________
the work satisfactorily though the time period for completion of the
project was greatly extended on account of delay & laches on the part of
respondent No.1 and thus had various claims against respondent No.1.
On the arbitration clause being invoked, disputes were referred to the
sole arbitration of Mr. R.C. Malhotra vide letter dated 20.6.1990.
Subsequently, the DDA also sought reference of certain counter claims
which were also referred to the arbitrator vide letter dated 30.04.1992
and the appellant contractor's additional claims were also referred vide
letter dated 30.06.1992.
2. It may be noticed that as per the original award of work dated 12.3.1985
the work was to be completed within nine (9) months but the time period
for execution of the work was extended and ultimately the work was
completed on 10.3.1988.
3. The arbitrator made and published the award on 29.4.1993. The
appellant/contractor filed an application under Sections 14, 17 & 29 of
the Arbitration Act, 1940 (hereinafter referred to as the said Act) for
making the award rule of the Court. Respondent No.1 filed objections.
These objections were partly allowed in terms of the impugned
judgement dated 27.3.1998 of the learned single Judge against which the
present appeal has been preferred.
4. Learned counsel for the appellant, in view of the aforesaid facts confined
his submissions to the claims awarded by the arbitrator set aside by the
learned Single Judge.
__________________________________________________________________________________________
Claim No.1(a): Refund of Security Deposit
5. The appellant/contractor sought refund of the security deposit which was
deducted by the DDA. The award notes that the provisional completion
certificate was recorded in terms of clause 6 of the contract agreement as
the work was completed on 10.3.1988 and the bill was required to be
finalized within six (6) months of the completion of the work and
security was to be released within one (1) month thereafter, i.e. by
10.10.1988. The defence of respondent No.1 was that as per clause 17
of the contract the security deposit became due for release within six (6)
months after the completion of the work or on the finalization of the bill,
whichever was later, but since there were defects in the work and the
reduction items were yet to be sanctioned, the bill could not be finalized.
The appellant/contractor contended against non-finalization of bill for
long period since action regarding defects, if any, was to be taken within
six (6) months of the completion of the work. This amount was awarded
by the arbitrator.
6. The impugned order, however, proceeds on a different footing as a
defence was sought to be raised by respondent No.1 that the case was
covered under clause 46 of the agreement, which reads as under:
"Security deposit shall not be refunded till clearance certificate from the Labour Officer is obtained by the contractor."
7. It is an undisputed fact that the appellant/contractor had not and till date
has not obtained any clearance certificate from the Labour Officer. It is
__________________________________________________________________________________________
this clause which has weighed with the learned single Judge in recording
a finding that the arbitrator went beyond his jurisdiction by not adhering
to clause 46. However, it has been observed that the moment the
contractor obtains and files certificate in terms of clause 46 from the
Labour Officer, the security deposit would be refunded failing which it
would carry interest.
8. Learned counsel for the appellant pointed out that the aforesaid plea was
raised for the first time in the objections filed under Sections 30 & 33 of
the said Act and had this been the plea before the arbitrator, the
appellant/contractor would have obtained the certificate. He submits
that after lapse of such a long period of time it would be difficult to
obtain the certificate. He also emphasized that the objective of this
clause has to be kept in mind which was to meet an eventuality in case
the Labour Officer lodges any claim which is not even the case of the
DDA.
9. In our considered view, there can be no doubt that the
appellant/contractor was required to furnish such a certificate as per the
terms of the contract (clause 46). Thus, the appellant/contractor should
be aware of the consequences thereof and non-supply of the same would
naturally require respondent No.1 to detain the security deposit.
10. There are, however, two aspects which may be taken note of - the first is
the absence of such a plea before the arbitrator which could have
facilitated the appellant/contractor to obtain the certificate at the relevant
__________________________________________________________________________________________
stage of time, if that was an aspect which was making respondent No.1
detain the security deposit. The second is that on this pretext respondent
No.1 cannot appropriate the security deposit for all times to come. If no
intimation has been received from the Labour Officer for a reasonable
period of time, there can be no question of detaining the security deposit
beyond that time. The work was completed on 10.3.1988. The award
came to be passed on 29.4.1993. Thus, at least, on the award being
made respondent No.1 should have released the security deposit as by
that time more than five (5) years had passed from the date of
completion of the work.
11. We are, thus, of the considered view that keeping in mind all these facts
& circumstances the detention of the security deposit beyond the date of
the award cannot be said to be reasonable or fair especially when
respondent No.1 had not cared to raise a specific plea in this behalf
before the arbitrator. Thus, the appellant is entitled to the amount in
terms of the award on which naturally interest would be payable from
the date of the award.
Claim No.1 (e): Expenses incurred by the appellant/contractor for watch & ward for the period beyond completion of the work
12. The appellant/contractor claimed that there was delay on the part of
respondent No.1 in handing over flats to the allottees and that the
appellant/contractor was required to keep watch and ward staff. The
__________________________________________________________________________________________
liability for this was sought to be fastened on respondent No.1 as this
was not the obligation of the appellant/contractor.
13. The arbitrator has noticed that as per exhibit R-51, which is a completion
certificate, the appellant contractor was required to rectify the defects
which were observed during the allotment of individual houses. The
possession of the flats had to be handed over by respondent No.1 not by
the appellant/contractor. The documents filed before the arbitrator
revealed that the appellant/contractor was required to maintain watch
and ward for some of the flats which was not their responsibility and
therefore the arbitrator allowed a part of the claim for `34,000.00.
14. The learned single Judge came to the conclusion that there can be no
dispute that the liability for the same had to be fastened on respondent
No.1, however, he found that this amount was covered in the claim made
by the appellant/contractor under clause 1(o) and thus no separate award
was required to be made in this behalf. He, thus, set aside this award on
the ground that a double award has been made in respect of the same
claim by awarding the same both as claim No.1(e) and claim No.1(o).
15. Learned counsel for the appellant pointed out to us that claim No.1(o)
was only confined to the period up to 10.3.1988, i.e., the actual date of
completion and thus, there was no overlapping or duplication as found
by the learned single Judge and thus there was no reason to interfere
with the award of this claim.
__________________________________________________________________________________________
16. In order to appreciate this controversy, we have to examine claim
No.1(o). Claim No.1(o) is "infructuous expenditure and damages
sustained by the appellant due to various breaches committed by the by
respondent No.1 during the execution of the work". It was the claim of
the appellant/contractor that on account of breaches of respondent No.1,
the work period was prolonged from nine (9) months to about thirty six
(36) months. The arbitrator found in claim No.1(n) that the delay in
completion of the work was on account of non-fulfilment of contractual
obligations by respondent No.1 and the breaches committed by them.
Thus, the cause for the delay was laid at the door of respondent No.1.
17. It is quite clear to us that claim No.1(o) was on account of infructuous
expenditure and damages sustained by the appellant due to various
breaches committed by respondent No.1resulting in the extension of
period of contract. However, claim 1(e) is for watch and ward staff
beyond the date of completion of work and thus covers a different
period. There is, thus, force in the contention of the learned counsel for
the appellant that there was no reason for the learned single Judge to
interfere with the award of the learned arbitrator. We may also note that
on analysis of the evidence before him the arbitrator awarded only part
of the claim.
Claim No.1(n): Difference of reasonable price and the price actually paid
18. The appellant/contractor claimed a sum of `4,25,476.00 being the
difference of a reasonable price and price paid. This claim was laid by __________________________________________________________________________________________
the contractor as the same is predicated on the plea that on account of
non-fulfilment of contractual obligations by respondent No.1 mainly in
supplying the stipulated material in time and not giving timely decisions,
the appellant/contractor had to pay the enhanced price in purchases.
Respondent No.1 was alleged to have failed to sanction extra and
substituted items in time and payments were delayed abnormally
resulting in prolongation of the period of completion of work from nine
(9) months to thirty-six (36) months. The cost of men and machine
increased tremendously during this period of time causing infrucutous
expenditure. To support this plea, the appellant referred to the various
works awarded by respondent No.1 during the prolongation period and
has justified a reasonable increase of 25 per cent for which a specific
request was made vide exhibit C-68.
19. Respondent No.1, on the other hand, claimed that if the appellant chose,
it could have stopped the work but continued to execute the work, which
implied that the appellant was willing to complete the work at the quoted
rate.
20. The arbitrator having found that the non-fulfilment of the contractual
obligations on the part of respondent No.1 had caused the delay, granted
a 15 per cent increase for the work done making it a sum of
`2,16,448.00. The arbitrator noted that as part of claim No.1(c), increase
in labour wages had been granted as per clause 10(c). This was on
account of the increase in labour rates and an award had been made for a
__________________________________________________________________________________________
sum of `1,28,552.00. Thus, the award under this claim was made over
and above the amount awarded under claim No.1(c) which was
predicated on clause 10(c).
21. This award has been set aside by the learned single Judge on the ground
that it was a condition of the contract, being condition No.1 of the
specifications and conditions of the contract, which reads as under:
"1. The contractor must get acquainted with the proposed site for the works and study specifications and conditions carefully before tendering. The work shall be executed as per programme approved by the Engineer-in-Charge. If part of site is not available for any person (reason) or there is some unavoidable delay in supply of materials stipulated by the Department, the programme of construction shall be modified accordingly and the contractor shall have no claim for any extras or compensation on this account."
22. The aforesaid condition refers to the non-availability of the site or
unavoidable delay in supply of material which would result in the
programme of construction being modified accordingly. This was taken
as a prohibition for avoiding escalation from delay in supply of material.
The learned single Judge found that the clause would imply that both
parties were expecting delays in certain respects and had provided for
that situation and thus allowing compensation for the delay would
amount to paying twice for such rights.
23. Learned counsel for the appellant submitted that condition No.1 referred
to aforesaid only contemplated non-supply of material due to
unavoidable reasons. The finding of the arbitrator was to the contrary.
Respondent No.1 had led no evidence to show there were reasons which
__________________________________________________________________________________________
were unavoidable and the arbitrator had, thus, awarded a part of the
claim. The amount awarded under claim 1(c) was for statutory increase
in labour and wages as per terms of the contract and has nothing to do
with the late supply of material.
24. Learned counsel also emphasized that the judicial view in this behalf is
in his favour by referring to the judgement of the Supreme Court in
Hyderabad Municipal Corporation Vs. M. Krishnaswami Mudaliar &
Anr. AIR 1985 SC 607 where the contractor was required to spread over
work for two years instead of one year and no intimation was sent for
extra payment and contractor had claimed 20% increase in the price of
the work done. It was held that the contractor could be granted extra
payment at increased rates. He also referred to the judgement of the
Supreme Court in P.M. Paul Vs. Union of India AIR 1989 SC 1034
where the award was set aside on ground of mis-conduct by the Court on
account of the arbitrator allowing escalation in contract amount for delay
in completion of the contract. A 20 per cent escalation was allowed by
the arbitrator which was upheld by the Supreme Court and it was
observed that it could not be said that if the work was not completed
within stipulated time, the party has got a right only for extension of
time and not for difference in prices.
25. The submission of the learned counsel for respondent No.1 was based
only on condition 1 of the contract and it was claimed before us that this
aspect was ignored by the arbitrator.
__________________________________________________________________________________________
26. We are unable to accept the reasoning of the learned single Judge in this
behalf. A defaulting party must pay for the consequential sufferance to
the opposite party. The reason for the delay has been laid at the door of
respondent No.1. The fault was of respondent No.1. The delay was
quite substantial, increasing the time period of contract from original
nine (9) months to thirty-six (36) months. The appellant led evidence to
show the increased cost of material during this period of time by
showing the awarded rates to other contractors by respondent No.1. In
fact, increase in labour cost from revision of the labour rates has already
been granted as per claim No.1(c).
27. In our considered view, condition 1 would have no application in the
present case because respondent No.1 failed to establish the sub-stratum
of that condition, i.e. any unavoidable reason. This is not even
apparently a defence originally raised by the respondent No.1. The
arbitrator having weighed these aspects, the learned single Judge ought
not to have acted as a court of appeal. We find the reasoning of the
learned single Judge unsustainable and set aside the interference with the
award of the arbitrator.
Counter Claim No.1(iii): Deduction of TDS by respondent No.1
28. The last aspect is the counter claim No.1(iii) on account of deduction of
TDS of `78,915.00. The learned arbitrator found that respondent No.1
had not submitted any documents to establish as to how this figure was
arrived at. The pre-final bill had showed that no income tax was
__________________________________________________________________________________________
recovered and no evidence was led to show that income tax so deducted
was deposited with the Income Tax Department. Thus, the claim was
rejected. The learned single Judge found that Section 194 (c) of the
Income Tax Act, 1961 puts an obligation on respondent No.1 to deduct
TDS at the time of credit of the sum to the account of the contractor or at
the time of payment thereof. The award has, thus, been held by the
learned single Judge to be in derogation of the mandate of the said
provision of the Income Tax Act.
29. Learned counsel for the appellant/contractor submitted that respondent
No.1 was required to deposit the TDS amount with the Income Tax
Department in the name of the appellant but the fact remains that no
amount was deposited towards such tax ever and thus, respondent No.1
was not entitled to withhold this amount.
30. The written submissions filed by learned counsel for respondent No.1
show that such amount was not deposited by the DDA as it is stated that
the DDA would deposit the TDS on the amounts given under the bills.
31. We are of the considered view that the amount not having been
deposited by the DDA, such amount could have been deducted only at
the time of payment, the DDA was not entitled to the counter claim.
32. The result of the aforesaid is that the impugned judgement of the learned
single Judge dated 27.3.1998 is set aside and the award of the arbitrator
dated 29.4.1993 is made rule of the Court without any modification.
__________________________________________________________________________________________
33. The appeal is accordingly allowed leaving the parties to bear their own
costs.
34. Decree sheet be drawn up accordingly.
SANJAY KISHAN KAUL, J.
AUGUST 17, 2011 RAJIV SHAKDHER, J. b'nesh
__________________________________________________________________________________________
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!