Citation : 2011 Latest Caselaw 3932 Del
Judgement Date : 12 August, 2011
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Date of Decision: 12.08.2011
% O.M.P. 735/2010
M/S V.K. SOOD ENGINEERS & CONTRACTORS
DDS JV ..... Petitioner
Through: Mr. Vishnu Mehra and Ms. Sakshi
Gupta, Advocates
versus
PUNJAB NATIONAL BANK & ORS ..... Respondent
Through: Mr. M.U. Khan, Adv. for R-1 Bank
Mr. Arun Khosla and Mr. Shreeanka
Kakkar, Advocates
CORAM:
HON'BLE MR. JUSTICE VIPIN SANGHI
1. Whether the Reporters of local papers may
be allowed to see the judgment? : No
2. To be referred to Reporter or not? : No
3. Whether the judgment should be reported
in the Digest? : No
VIPIN SANGHI, J. (Oral)
1. This petition has been preferred under Section 9 of the
Arbitration and Conciliation Act to seek a restraint against the
encashment of various bank guarantees furnished at the instance of
the petitioner by Punjab National Bank - respondent no.1 in favour of
respondent no.2, Ircon International Ltd.
2. When the matter was taken up by this Court on 10.12.2010, a
detailed ex-parte order came to be passed recording the reasons for
granting ad-interim measures. The said order reads as follows:
" Issue notice to the respondents, returnable on 28.03.2011.
My attention is drawn to Clause 9 of the GCC which reads as follows:-
"9.0 PERFORMANCE BANK GUARANTEE
Within 28 days from the date of issue of Acceptance Letter by IRCON but before signing of the agreement, the contractor shall submit a Performance Bank Guarantee to IRCON for 3% value of the contract sum issued by Nationalized/Scheduled Bank on a format issued/approved by IRCON. The Performance Bank Guarantee shall be kept valid for the entire contract period which shall be the duration of the execution of the contract works. Thus the validity period of Performance Bank Guarantee shall be until issue of completion certificate by the Engineer-in-charge. The contractor shall revalidate, if needed, the Performance Bank Guarantee to cover the period until issue of completion certificate."
Learned counsel for the petitioner has referred to the completion certificate issued by respondent No.2 dated 26.10.2009, according to which, the date of actual completion of work in respect of the three projects namely, Zone Br.17A, Zone Br.17B and Zone Br.17A (Additional) is stated to be 31.03.2009, 28.02.2007 and 31.3.2009 respectively. It is also stated in the certificate that the extension of time has been granted on administrative grounds, and not on the contractor's account. The certificate also records that the work stands completed satisfactorily. It is, therefore, argued that in terms of Clause 9 of the GCC, the petitioner, after completion of the works on the aforesaid dates was not obliged to keep the performance bank guarantees alive. The petitioner seeks restraint against invocation of the following bank guarantees:-
S. B.G.No Zone/ Purpose Date of Amount Extended
No issue (`) upto
Package
1 ILG-203 BR-17A Performance 18.08.2003 5,00,000/- 13.08.2008
2 ILG-303 BR-17B Performance 16.08.2003 5,00,000/- 13.08.2008
3 ILG-503 BR-17A Performance 27.12.2003 39,83,363/- 25.12.2008
4 ILG-904 BR-17A Security 02.06.2004 61,38,938/- 25.12.2008
5 ILG-1005 BR-17A Security 09.11.2005 65,00,000/- 07.11.2008
6 ILG-505 BR-17A Mobilization 18.05.2005 64,96,517/- 17.11.2008
7 ILG-605 BR-17A Mobilization 18.05.2005 64,96,517/- 17.11.2008
8 ILG-705 BR-17A Mobilization 18.05.2005 64,96,517/- 17.11.2008
9 ILG-805 BR-17A Mobilization 18.05.2005 64,96,517/- 17.11.2008
10 ILG-807 BR-17B Performance 20.08.2007 78,87,173/- 19.08.2008
11 ILG-807 BR-17B Performance 21.08.2007 30,10,967/- 20.11.2008
12 ILG-1507 BR-17B Performance 24.12.2007 45,18,277/- 23.09.2008
My attention is also drawn to three awards made by the learned Arbitral Tribunal in respect of each of the aforesaid contracts. The respondent IRCON International Ltd. had preferred counter claims before the Arbitral Tribunal. The counter claims preferred in relation to Contract No. Zone Br.17B have been adjusted in the final award. In respect of the awards arising out of contract No.17A and 17A (Addl.), none of the counter claim of the respondent was allowed. My attention is also drawn to order dated 4.8.2010 passed in OMP No.425/2010, OMP No.426/2010 and OMP No.427/2010 (these objections were preferred by the petitioner). However, no objections were preferred to the three awards. On the contrary, on 04.08.2010, the respondent had made a statement that the respondent had accepted the awards and that they would be making payment of the awarded amounts within 15 days.
In view of the aforesaid position, in my view, to permit invocation of the aforesaid bank guarantees at this stage would be wholly improper and may amount to a fraud upon the petitioner and the issuing Bank. Accordingly, the invocation of the aforesaid bank guarantees shall remain stayed till the next date.
DASTI."
3. The respondents have filed their reply, and the matter has
been heard at considerable length.
4. The respondent nos.2 and 3 have vehemently argued that the
petitioner is guilty of gross suppression and mis-statement of relevant
facts. It is stated that during the execution of the works under the
three contracts in question, the petitioner faced acute shortage of
funds and repeatedly sought financial help of the said respondents. At
the instance of the petitioner, respondent no.1 Punjab National Bank
issued three communications, two dated 23.02.2007 in relation to bank
guarantee no.5/05 dated 18.05.2005 and bank guarantee no.6/05
dated 18.05.2005 stating that, at the request of the petitioner, an
amount of Rs.64,96,517/- (in respect of each of the aforesaid two
guarantees) is covered for the recovery of steel purchase from SAIL.
Another letter was issued by the bank in relation to bank guarantee
no.7/05 dated 18.05.2005 stating that the bank covers security deposit
upto the amount of Rs.64,96,517/- for fabrication as per contract dated
10.05.2005 and LOI dated 05.12.2003.
5. The petitioner once again approached respondent no.2 to seek
further assistance to complete the balance supply of steel of Qty. 2500
MTS. To provide comfort to the said respondents, and secure the
advances made by them to SAIL for purchase of steel, the petitioner
issued a communication dated 07.08.2007, inter alia, stating as
follows:
"5. As also discussed in the meeting at Corporate Office with higher IRCON management on 6.8.2007 we will extend and cover BGs total amount of advance taken in the form of steel advance which is presently Rs.3.27 crores plus interest accrued.
6. We will also extend the performance bond for BR-17A & BR-17A (Addl.) in operation as per conditions of the contract.
If the above help is given to us we undertake to complete the entire work of fabricating girders by 31.10.2007 and supply within November, 2007.
We shall keep the BGs alive/extended for the equivalent amount of steel advance given to us for recovery if any. At the close of contract, adjustment of advances shall be made from the payments due to us including the payable payments of extra/NS items. Balance, if any, shall be adjusted against the BGs after giving us a notice period of 15 days to arrange the funds and clear the advances." (emphasis supplied)
6. On 29.09.2007, the petitioner issued another communication
to respondent no.2 stating that they had completed the work relating
to contract BR 17-B, i.e. fabrication and supply of steel Girders for
various Bridges under on Qazigund-Baramulla section of Kashmir Rail
(J&K), and also received the final payment. It was stated that the bank
guarantee No.ILG 303 for Rs.5,00,000/-, bank guarantee No.ILG 804 for
Rs.45,18,277/- and bank guarantee No.ILG 807 for Rs.30,10,967/-,
which stands released, are offered for recovery of steel advance given
to the petitioner against contract No.BR 17A and BR 17A (Additional).
7. On 30.10.2007, the petitioner issued yet another
communication to respondent no.2 inviting the respondents attention
towards condition no.4 sub para (vi) of allotment letter dated
10.05.2005, wherein it was provided that adjustment of bank
guarantee from earlier works may be considered towards enhanced
scope of work. As order for additional girders on emergent basis had
been placed on the petitioner vide letter dated 22.10.2007, the
petitioners submitted the bank guarantees lying with the respondent in
relation to the virtually completed work under BR 17A, for adjustments
against material advances of BR 17A (Additional) to cover the advance
payment for purchase of materials for additional girders from SAIL on
emergent basis.
8. Mr. Khosla submits that none of the aforesaid documents were
produced by the petitioner before this Court at the time of filing of the
petition. It is also submitted that on 18.07.2008, the respondent
IRCON had demanded an amount of Rs.4,57,41,310/- as the amount
outstanding against steel advances for package 17A and 17A
(Additional). The petitioner was called upon to deposit the amount by
26.07.2008. Alongwith this communication, the respondent annexed
the breakup of the amount claimed by it in the said communication.
9. The petitioner sent it is reply to this communication on
01.08.2008 stating that they need time for making arrangement of
funds. They further stated that they are regularly paying interest on
all advances and "our Bank Guarantees are valid and we will extend
these guarantees further". The petitioner sought three months
extension for payment of advances and also requested the respondent
"not to insist on encashment of BGs at this stage which will make our
account NPA with the Bank and cause major upset to us in our future
business with our clients, including Railways and IRCON".
10. The respondent issued another communication on 03.03.2009
raising a demand of Rs.6,21,88,361.44/-. With this communication as
well, the summary of recovery of dues from the petitioner was
enclosed which also gave computation of the steel advances paid to
the petitioner. As per the said statement, Rs.3,05,19,835/- was the
balance recoverable on account of steel recovery, and Rs.51,11,530/-
was recoverable on account of balance of Rivets advance. These
documents were also not placed before the Court by the petitioner.
11. Mr. Mehra, learned counsel for the petitioner submits that
there was no concealment made by the petitioner inasmuch, as, in
para 21 and 22 of the petition, the petitioner had made the following
averments:
"21. That as per terms and conditions of the Contract, the Petitioner had to purchase Steel from Steel Authority of India in respect of Zone BR-17A and Zone BR-17A (Additional). However, due to financial difficulties created by the Respondent No. 2, the Petitioner by their letter dated 07.08.2007, requested for financial help from the Respondent No. 2 for purchase of the steel from Steel Authority of India. The request of the Petitioner was accepted by the Respondent No. 2. The steel purchased was paid for by the Respondent No. 2 which was treated as Steel Advance by the Respondent No. 2 and it was agreed that the payment made had to be adjusted against the final bill of the Petitioner in respect of Zone BR-17A and Zone BR-17A (Additional). It may be clarified that there was no such clause either in the tender documents or in the Allotment/Acceptance Letter or even in the Contract Agreement.
22. That it may stated here that though after the completion of work in respect of Zone BR-17B, the Guarantees stood released. However, at the request of the Respondent No. 2, the Petitioner by their letter dated 29.09.2007 offered only the 3 Bank Guarantees, namely ILG-303, ILG-807 and ILG-804 submitted for the said Zone BR-17B. The remaining 9 Bank Guarantees were, however, not offered."
12. Mr. Mehra submits that the advance granted for procurement
of steel is not covered by the contracts in question. The said
arrangement was a separate arrangement. He submits that the letters
of invocation of the said bank guarantees issued by the respondent did
not even make a reference to the alleged recovery sought to be made
on account of advances for steel. The letters of invocation alleged that
the petitioner has failed to fulfill its contractual obligations. He submits
that this statement of the respondent IRCON, in the various letters of
invocation, is patently false in the face of the completion certificate
issued by the respondent on 26.10.2009 in relation to all the three
packages. He, therefore, submits that there is no concealment of any
material or fact by the petitioner from this Court while filing this
petition.
13. Having heard learned counsels for the parties, I am of the view
that the petitioner has indeed sought to misled this Court into passing
the ex-parte order of injunction, by not placing before this Court the
complete scenario and the correspondence exchanged between the
parties in relation to advances for steel and the petitioners own
representation that the said advances would be secured by the bank
guarantees furnished at the instance of the petitioner by the
respondent bank in relation to the three contracts.
14. From the correspondence placed on record by the respondent,
it is evident that the petitioner was in urgent need of funds. Since the
petitioner could not procure the steel required to execute the works
under the contracts, the petitioner requested the respondent to pay for
the same. Firstly, at the instance of the petitioner, the Punjab National
Bank issued express communications on 23.02.2007 and 05.03.2007 in
relation to bank guarantee nos.5/05 and 6/05 and 7/05 all dated
18.05.2005 extending the scope of these bank guarantees to cover the
recovery of steel purchased for the petitioner from SAIL, and to cover
for security deposit for fabrication as per contract dated 10.05.2005
and LOA dated 05.12.2003. Secondly, to provide comfort to the
respondent, on 07.08.2007, the petitioner even assured that the bank
guarantees furnished by the petitioner under the contracts, which by
then had been released on account of completion of some of the
works, would be kept alive to secure the amounts advanced by the
respondent for the purchase of steel.
15. When the respondent raised its demand vide letter dated
18.07.2008, on 01.08.2008 the petitioner pleaded the respondent not
to encash the bank guarantees as the said bank guarantees were
being extended, and the interest was being paid on all advances.
16. The averments made in the petition, as extracted above,
conceal more than what they disclose. Without the relevant documents
being placed on record, the purport of the said averments could
possibly not have been fully appreciated. Moreover, the averment that
only three bank guarantees bearing nos. ILG 303, 807 and 804 were
offered (without stating what they were offered for), and that the
remaining nine bank guarantees were not offered is also not a
completely accurate statement, inasmuch, as, the petitioner in its
communications dated 07.08.2007, 30.10.2007 and 01.08.2008 clearly
represented to the respondent that all its bank guarantees given under
the contracts in question were valid and extended to cover the
respondents dues for advances for steel.
17. It is not in dispute that the aspect of advances for steel was
not the subject matter of any of the arbitration proceedings, and the
said dues are not covered by three arbitration awards passed in favour
of the petitioner. The said amounts stand admitted by the petitioner in
its communication dated 07.08.2007, and the computation furnished
by the respondent IRCON has not been denied in the subsequent
communication dated 01.08.2008.
18. The petitioner has filed this petition to invoke the discretionary
jurisdiction of this Court. The petitioner was expected to come with
clean hands, and to make a full and complete disclosure of facts and
circumstances which may have a bearing on the decision of the Court.
By merely stating that only three bank guarantees had been offered
(presumably to cover advances on steel), and by stating that the
invocation of the bank guarantee has been made on the basis that the
works under the contract are not complete (which is stated to be
factually not true), the petitioner has concealed from this Court the
aforesaid relevant and material facts and circumstances. Had a
complete disclosure been made and full picture presented before the
Court at the time when the petition was taken up for ex-parte hearing,
this Court certainly would not have granted the injunction as it did,
considering the fact that there are admittedly very large liability owed
by the petitioner to the respondent, and the petitioner had repeatedly
represented to the respondent that the said liabilities are covered by
the various bank guarantees offered under the three contracts.
19. I am, therefore, not inclined to continue the interim order any
further. I vacate the same and dismiss this petition.
20. Considering the conduct of the petitioner, I subject the
petitioner to costs quantified at Rs.3 lacs. Costs be paid within two
weeks.
VIPIN SANGHI, J AUGUST 12, 2011 sr
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!