Citation : 2011 Latest Caselaw 3865 Del
Judgement Date : 10 August, 2011
*IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 10th August, 2011
+ W.P.(C) 5724/2011
M/S HYDRO AIR TECTONICS (PCD) LTD ..... Petitioner
Through: Mr. Pawan Bahl, Mr. Kamlakshi
Singh & Mr. Saundarya Singh, Adv.
Versus
M/S NATIONAL BUILDINGS CONSTRUCTION
CORPORATION LTD. AND ANR. .... Respondents
Through: Mr. Himanshu Bajaj, Adv. for R-3.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may Yes
be allowed to see the judgment?
2. To be referred to the reporter or not? Yes
3. Whether the judgment should be reported Yes
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. The petition impugns the communication dated 27th July, 2011 of
the respondent no.1 National Buildings Construction Corporation Ltd.
(NBCC), in pursuance to the show cause notice issued to the petitioner,
rescinding the contract given to the petitioner for construction of Medical
College/Retrofitting work of existing ESIC Hospital at Parel, Mumbai
(Maharashtra).
2. There was admitted delay in execution of the work which led to the
issuance of the show cause notice. The contention of the counsel for the
petitioner however is that the delay is not attributable to the petitioner but
owing to the impediments in execution of the work, the works being
required to be carried out in an existing/operating/running hospital.
3. It has been enquired from the counsel for the petitioner as to how
writ jurisdiction can be invoked in such a purely contractual matter.
4. The counsel for the petitioner relies upon Kisan Sahkari Chini Mills
Ltd. v. Vardan Linkers (2008) 12 SCC 500 which also lays down that the
writ jurisdiction ought not to be exercised in contractual matters unless
there is a public law element; it is contended that the letter dated 27th July,
2011 merely states that the reply of the petitioner to the show cause notice
had not been found satisfactory and does not give any reasons as to why
the same was not found satisfactory; that thus the writ petition would be
maintainable. Reliance in this regard is also placed on Kranti Associates
Pvt. Ltd. v. Masood Ahmed Khan (2010) 9 SCC 496 & Oryx Fisheries
Pvt. Ltd. v. Union of India (2010) 13 SCC 427 where the duty to give
reasons has been emphasized. Though the counsel for the petitioner has
also relied upon the order dated 21st May, 2010 of this Court in W.P.(C)
3447/2010 titled Vichitra Constructions Pvt. Ltd. v. Delhi Jal Board but
the same is found to be a consent order and thus cannot be cited as a
precedent.
5. The duty to give reasons has to be seen in the context. The Supreme
Court in Maharashtra State Board of Secondary & Higher Secondary
Education v. K.S. Gandhi (1991) 2 SCC 716 held that omission to record
reasons is not necessarily illegal or violative of natural justice and depends
upon the nature of enquiry and the effect of the decision on the rights of
the person and attendant circumstances. As has often been said, the
principles of natural justice cannot be applied in a vacuum without
reference to the relevant facts and circumstances. In fact doubts have been
expressed whether duty to give reasons is a part of the principles of natural
justice.
6. The respondent no.1 NBCC in the matter of rescinding of the
contract was not exercising any judicial or quasi judicial function. A power
to deal with a contractual matter and a power of the statutory authority to
exercise its statutory power in determining the rights and liabilities of the
parties are distinct and different. Whereas reasons are required to be
assigned in a case where civil or evil consequences may ensue, the same
may not be necessary where it is contractual in nature (see Ramchandra
Murarilal Bhattad v. State of Maharashtra (2007) 2 SCC 588). The
Courts in contractual matters have insisted on giving of reasons only where
the action impugned is apparently contrary to logic i.e. say where the
highest bid is not accepted. This Court in Integrated Techno Systems Pvt.
Ltd. v. NDMC MANU/DE/8339/2007 held that the Court in judicial
review proceedings under Article 226 is more concerned with the process
of decision making rather than the merits of the decision; the Court does
not don the hat of the decision maker and does not act as a super appellate
administrative body to examine the soundness of the action; the duty of the
Court is only to see whether the decision was arrived at after following a
fair procedure considering the relevant factors and ignoring the irrelevant
facts.
7. It is not in dispute that the respondent no.1 NBCC was under the
contract, for the reason of delay, entitled to rescind the contract. It is not in
dispute that the work was not completed within the time stipulated in the
agreement for completion of the work. The action of respondent no.1
NBCC is thus not apparently illogical. The question which arises is,
whether the respondent no.1 NBCC was required to deal with each and
every contention in the reply of the petitioner as in a judgment of the
Court. I am unable to hold so. The Engineers/Officers of respondent no.1
NBCC who deal with such matters have hands-on experience of the work.
Such Engineers/Officers of respondent no.1 NBCC are of the view that the
delay in execution of the work is attributable to the petitioner and that the
petitioner would be unable to complete the work within the time extended
by the ESIC also. This Court cannot in exercise of powers of judicial
review sit in appeal over the opinion so formed by such
Engineers/Officers. The principles of natural justice have been complied
with by issuance of a show cause notice.
8. The counsel for the petitioner has with reference to several
documents sought to contend that the decision of the respondent no.1
NBCC is arbitrary. Attention in this regard is invited to the satisfaction
recorded on 10th October, 2010 by the Medical Superintendent of the
Hospital of the work being undertaken, to a letter dated 14 th January, 2011
of the respondent no.1 NBCC to ESIC seeking extension of time for
completion of work, quoting the hindrances and to the pert charts also
referring to hindrances. However none of the said documents persuade me
to interfere with the decision. The Medical Superintendent of the Hospital
was not concerned with the reasons for delay and such procured documents
have no weightage. Similarly, what was written by the respondent no.1
NBCC while seeking extension of time from ESIC cannot be used against
the respondent no.1 NBCC. The respondent no.1 NBCC in writing the said
letter was interested in obtaining the extension to avoid claims and
damages which may have been made against it. Yet further, the pert charts
were relied upon by the petitioner in its reply to the show cause notice and
there is nothing to indicate that the same were not considered. Moreover,
this Court is not exercising appellate power.
9. There is another aspect of the matter. Even if it were to be held that
the action of the respondent no.1 NBCC is erroneous, the contract which
has been terminated was not specifically enforceable. If the petitioner, in
an appropriate proceedings, succeeds in establishing that the delay is not
attributable to it and the contract has been wrongfully rescinded, it will be
entitled to compensation/damages. On the contrary if this Court interferes
and which would necessarily entail restraining respondent no.1 NBCC
from awarding the work to anyone else (and which relief has been sought
by the petitioner), the same would inordinately delay the works aforesaid
and which are public works and on account of delay whereof the public at
large will suffer. For this reason also, it is not deemed appropriate to
entertain this challenge.
10. It is also felt that the adjudication as this Court is called upon to do
entails factual controversy, best left for decision in a suit or in arbitration
as the case may be.
11. The counsel for the petitioner has contended that a direction may be
given to respondent no.1 NBCC to reconsider the matter giving reasons.
However, the same would also entail, at least till then, restraining NBCC
from awarding the contract to another and which course, for reasons
aforesaid is not found appropriate.
12. The writ petition is therefore not maintainable and is dismissed with
liberty to the petitioner to take appropriate remedies in law. The
observations herein shall not come in the way of the petitioner, in
appropriate proceedings establishing its claim for compensation/damages.
No order as to costs.
Dasti.
CM No.11676/2011 (for exemption).
Allowed, subject to just exceptions.
RAJIV SAHAI ENDLAW (JUDGE) AUGST 10, 2011 PP
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!