Citation : 2011 Latest Caselaw 3652 Del
Judgement Date : 2 August, 2011
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 02.08.2011
+ WP (C) No.4331 of 2011 & CM No. 8869/2011
M/S PATEL ENGINEERING LTD. ...PETITIONER
Through: Mr.Rajiv Nayar, Sr.Advocate
with Mr. Jai Munim, Ms.Shally
Bhasin and Ms.Shikha Sarin,
Advocates.
Versus
UNION OF INDIA & ANR. ...RESPONDENTS
Through: Mr.Neeraj Chaudhri, CGSC
with Mr.Akshay Chandra and
Mr.Mohit Auluck, Advocates
for R-1/UOI.
Mr. Amrinder Sharma, Sr.
Advocate with
Ms. Padma Priya
and
Mr.Somesh Chandra Jha,
Advocates for R-2/NHAI.
CORAM:
HON'BLE MR. JUSTICE SANJAY KISHAN KAUL
HON‟BLE MR. JUSTICE RAJIV SHAKDHER
1. Whether the Reporters of local papers
may be allowed to see the judgment? Yes
________________________________________________________________________________________
WP (C) No.4331 of 2011 Page 1 of 25
2. To be referred to Reporter or not? Yes
3. Whether the judgment should be No
reported in the Digest?
SANJAY KISHAN KAUL, J.
1. The National Highways Authority of India (for short
„NHAI‟)/respondent No.1, issued a request for
qualification in November, 2010 for a six-laning project
of Dhankuni-Kharagpur Section of NH-6 from 17,600 to
1,29,000 in the States of West Bengal and Orissa
under the National Highway Development Projects
Phase-V on design, build, finance, operate, transfer
and toll basis. The petitioner, a public limited
company, submitted its bid on 10.01.2011. The bid
submitted by the petitioner and other bidders were
processed and by a letter of award dated 17.01.2011,
respondent no. 2 informed the petitioner that its bid
had been accepted and that the petitioner should
execute the relevant documents in that regard.
2. It is the say of the petitioner that on account of various
factors including amendments, perceived insufficient
time etc., the bid submitted by the petitioner was ________________________________________________________________________________________
significantly higher than it should have been and thus
the petitioner came to the conclusion on 24.01.2011
that the bid made by it was commercially unviable.
This fact was intimated to respondent no.2 on
24.01.2011 within the period of 7 days prescribed for
the petitioner to execute the necessary documents.
3. As a sequitur to this, respondent no.2 informed other
bidders, and ultimately the contract was awarded to
M/s.Ashoka Buildcon Limited at a much lower premium
of Rs 126.06 crores. We may notice at this stage that
the petitioner had specified a premium of Rs 190.53
crores.
4. All the bidders were to submit a bid security amount of
Rs.13.97 crores. Part „D‟ deals with the bid security
amount. Clause 2.20.6 envisages forfeiture of bid
security amount in the following terms:
"2.20.6 The Authority shall be entitled to forfeit and appropriate the Bid Security as Damages inter alia in any of the events specified in Clause 2.20.7 herein below.
The Bidder, by submitting its Bid pursuant to this RFP, shall be deemed to have acknowledged and confirmed that the Authority will suffer loss and damage on account of withdrawal of its Bid or for any ________________________________________________________________________________________
other default by the Bidder during the period of Bid validity as specified in this RFP. No relaxation of any kind on Bid Security shall be given to any Bidder."
5. The aforesaid amount was agreed as a genuine pre-
estimate of compensation in respect of the eventuality
set out in the clause 2.20.7. The facts of the case fall
within such an eventuality where a contractor fails to
sign and return a duplicate copy of the LOA. Clause
2.20.7 reads as under:
"2.20.7 The Bid Security shall be forfeited and appropriated by the Authority as mutually agreed genuine pre-estimated compensation and damages payable to the Authority for, inter alia, time, cost and effort of the Authority within prejudice to any other right or remedy that may be available to the Authority hereunder or otherwise, under the following conditions:
a) If a Bidder submits a non-responsive Bid, "subject however that in the event of encashment of bid security occurring due to operation of para 2.20.7 (a), the damage so claimed by the authority shall be restricted to 5% of the value of the bid security.;
b) If a Bidder engages in a corrupt practice,
fraudulent practice, coercive practice,
undesirably practice or restrictive practice
as specified in Clause 4 of this RFP;
c) If a Bidder withdraws its Bid during the period of Bid validity as specified in this RFP ________________________________________________________________________________________
and as extended by mutual consent of the respective Bidder(s) and the Authority;
d) In the case of Selected Bidder, if it fails within specified time limit -
i) To sign and return the duplicate
copy of LOA;
ii) To sign the Concession Agreement; or
iii) To furnish the Performance Security within the period prescribed therefor in the Concession Agreement; or
e) In case the Selected Bidder, having signed the Concession Agreement, commits any breach thereof prior to furnishing the Performance Security."
6. It is in view of the aforesaid facts and circumstances
that respondent no.2 took a decision to encash the
bank guarantee furnished towards the bid security
amount; however in the meanwhile petitioner
addressed a letter dated 01.02.2011 volunteering to
make the payment of Rs.13.97 crores in return of the
bank guarantee; which amount was duly paid vide a
demand draft on 03.02.2011. Thus, the issue of
encashment of the bid security amount stood
________________________________________________________________________________________
concluded with the said step and both the parties
accepted the same.
7. The grievance of the petitioner arises out of the
subsequent action taken by respondent no.2 to issue a
show cause notice dated 24.02.2011 to the petitioner
to debar the petitioner for a period of five years from
"pre-qualification, participating or bidding" for future
projects to be undertaken by respondent no.2.
7.1 This show cause notice was replied to by the petitioner
on 01.03.2011, and the impugned letter was issued on
20.05.2011, on the basis of which respondent has
debarred the petitioner for a period of one year
commencing from the date of issue of the letter, i.e.,
20.05.2012 from "pre-qualification, participating or
bidding" for future projects of or to be undertaken by
respondent no.2.
7.2 The petitioner made a representation against such
debarment to the Ministry of Road Transport and
Highways on 28.05.2011, and subsequently filed the
present writ petition on 13.06.2011 under Article 226
________________________________________________________________________________________
of the Constitution of India making a prayer for
quashing of the letter dated 20.05.2011.
8. The aforesaid grievance has naturally been contested
by respondent no.2. Respondent no.1/UOI has not filed
any separate counter affidavit in this matter.
9. We have heard learned counsel for the parties.
10. It is the say of learned senior counsel for the petitioner
that the forfeiture of the bid security amount
concluded the consequence which the petitioner could
be visited with on its failure to convey the acceptance
in respect of the LOA. In other words the petitioner
could not be penalized any further by being debarred
from participation in future projects undertaken by
respondent no. 2. According to the learned counsel
the order of debarment was in the nature of the
petitioner being blacklisted.
11. The learned counsel in this behalf has drawn our
attention to clause 4.2 which forms part of part 4 with
the heading „Fraud and Corrupt Practices‟. Clause 4.2
reads as under:
________________________________________________________________________________________
"Without prejudice to the rights of the Authority under Clause 4.1 hereinabove and the rights and remedies which the Authority may have under the LOA or the Concession Agreement, or otherwise if a Bidder or Concessionaire, as the case may be, is found by the Authority to have directly or indirectly or through an agent, engaged or indulged in any corrupt practice, fraudulent practice, coercive practice, undesirable practice or restrictive practice during the Bidding Process, or after the issue of the LOA or the execution of the Concession Agreement, such Bidder or Concessionaire shall not be eligible to participate in any tender or RFP issued by the Authority during a period of 2(two) years from the date such Bidder or Concessionaire, as the case may be, is found by the Authority to have directly or indirectly or through an agent, engaged or indulged in any corrupt practice, fraudulent practice, coercive practice, undesirable practice, or restrictive practices, as the case may be."
12. Learned senior counsel for the petitioner submitted
that the aforesaid clause applied only if the petitioner
indulged in any "corrupt practice", "fraudulent
practice", "coercive practice", "undesirable practice"
or "restrictive practice" during the bid process or after
the issuance of LOA or on the execution of the
Concession Agreement, and that the definition of each
of these expressions provided in clause 4.3 made this ________________________________________________________________________________________
aspect quite clear. Learned counsel thus submitted
that the case of the petitioner does not fall in any of
the aforementioned practices as defined in clause 4.3
read with clause 4.2.
12.1 A reference was made to following paragraphs of the
show cause notice dated 24.02.2011 to buttress this
point:
"AND WHEREAS subsequent to technical evaluation, Financial Bids were opened on 13.01.2011 in the presence of the Bidders representative and it was noted that M/s Patel Engineering Ltd. had offered the highest premium of Rs.190.53 Crore for the said project. Therefore, as per RFP Volume-I, Clause 3.3.1, M/s Patel Engineering was declared by the NHAI as the Selected Bidder and subsequently was issued the letter of Award (LOA), as per clause 3.3.5 of RFP Volume-I. Copy of letter dated 17.01.2011 is enclosed.
AND WHEREAS, M/s Patel Engineering Ltd., vide letter No.Hyd/181/NHAI-DK BOT/3326 dated 24.01.2001, had expressed their inability to accept the LOA, stating that errors have crept in impacting the bid value significantly. Copy of letter dated 24.01.2011 is enclosed.
AND WHEREAS, as per Clause 2.20.07(d) of the RFP, in case the Selected Bidder fails to accept the LOA, the bid security shall be forfeited and appropriated by NHAI as mutually agreed genuine pre-estimated ________________________________________________________________________________________
compensation as payable to NHAI for, inter- alia, time, cost and effort of NHAI without prejudice to any other right or remedy that may be available to the NHAI thereunder or otherwise.
AND WHEREAS, in view of your conduct which has, inter-alia, resulted in delay of execution of a project of National importance, a view is made out not to deal with you in future for participation and/or award of further projects of NHAI. It needs to be appreciated that the projects being undertaken by NHAI are of huge magnitude and both in terms of manpower and finance besides being of utmost National importance, striking at the root of economic development and prosperity and general public and a nation as a whole, the NHAI cannot afford to deal with entities who fail to perform their obligations as in your case.
AND WHEREAS, in the premises it is proposed to debar above named noticee for a period of five years from pre-qualification, participating or bidding for future projects of/or to be undertaken by NHAI, either directly in your name or indirectly in any other name or in association with any other person entity in which you may choose to carry on your business.
In view of the aforesaid, you are hereby called upon to show cause within 14 days of the receipt of this notice as to why action as aforesaid should not be taken against you. If no reply is received within the said period, it shall be presumed that you have nothing to say against the proposed action of NHAI and NHAI shall be free to take appropriate action as may be deemed fit in the facts and ________________________________________________________________________________________
circumstances of the case and as per applicable law."
13. It was contended that aforesaid extract from the show
cause notice would reveal that as per respondent no.2,
it was the failure on the part of the petitioner to enter
into the contract after being declared a successful
bidder which occasioned delay in execution of the
project propelling respondent no.2 in coming to a
prima facie view that it would not deal with the
petitioner in respect of its future projects for a period
of time, which was tentatively proposed as five years.
13.1 Learned senior counsel for the petitioner submits that
such a show cause notice could not have been issued
for the reason that it was not envisaged under the
terms and conditions of the invitation to offer and no
such decision ought to have been taken de hors the
contract. This was more so according to the learned
counsel as no guidelines had been provided.
13.2 Learned senior counsel for the petitioner has also drew
our attention to the contents of the final order of
debarment dated 20.05.2011, to demonstrate that the ________________________________________________________________________________________
debarment order was passed on grounds which did not
find a mention in the show cause notice. The reason
being, according to the learned counsel, to somehow
bring the order of debarment within the four corners of
clause 4.2 read with clause 4.3 of the ITB.
13.3 It is his say that clause 4.3(e) which defines restrictive
practices cannot bring within its ambit allegations of
"pooling" or "malafides":
"restrictive practice" means forming a cartel or arriving at any understanding or arrangement among Bidders with the objective of restricting or manipulating a full and fair competition in the Bidding Process."
14. In other words it was contended that the allegations
pertaining to "pooling" and "mala fides" were
incorporated in the debarment letter dated 20.05.2011
only as an afterthought with a view to bring the
petitioner with the purview of "restrictive practices".
15. In order to appreciate the aforesaid submission, we
consider it appropriate to reproduce the relevant
portion of the letter of debarment dated 20.05.2011
which reads as under:
________________________________________________________________________________________
" In view of your conduct, Show Cause Notice dated 24.02.2011 was issued to you seeking your explanation as to why action should not be taken to debar above named addresses for a period of five years from prequalification, participating or bidding for future projects of / or to be undertaken by NHAI, either directly in your name or indirectly in any other name or in association with any other person entity in which you may choose to carry out your business. In response to the said Show Cause Notice dated 24.02.2011, you vide letter dtd.01/03/2011, inter-alia, stated that minutes of the pre-bid meeting, which included several amendment/queries, were communicated on website of NHAI on 7.1.2011 while bid submission was kept the next date on 10.01.2011. You also stated that in the light of the above notice in the bid clarification, certain anomalies crept up in bid submission, which were only discovered subsequent to the letter of intent being issued.
It is noted that above submission was also made in your letter dated 24/01/2011, wherein you have accepted the fact that other bidders also participated under the similar circumstances. Further the fact remains that clarification/amendments communicated by NHAI were „minor‟ and cannot be attributed as a cause for occurrence of an „error‟ of „major‟ nature and magnitude. With project facilities clearly spelt out in the RFP document, the project cost gets frozen well in advance and similarly traffic assessment ________________________________________________________________________________________
& projections, which largely impact the financial assessment, are also not expected to be left out for last few days of bid submission. Therefore, stating that an „error‟ of this nature and magnitude occurred is neither correct nor justified. It is to be noted that your actof non-
acceptance of LOA has resulted in huge financial loss, to the tune of Rs.3077 crores, as assessed over the life of concession period, in terms of lower premium, apart from cost of the time and effort, to NHAI. It is further noted that this is the first case where a bidder has not accepted the LOA, and warrants exemplary action to curb any practice of „pooling‟, and „malafide‟ in future.
After considering all material facts, and your reply in response to the Show Cause Notice, NHAI is of the considered view that no justifiable grounds have been made out in support of your action of non-acceptance of LOA. Keeping in view the conduct of the addresses, NHAI find that they are not reliable and trustworthy and have caused huge financial loss to NHAI. Therefore, it is hereby informed that without prejudice to any other rights available to NHAI in terms of the provision of RFP document and/or the applicable law, you the above named addresses are hereby barred from prequalification, participating or bidding for future projects of / or to be undertaken by NHAI, either directly in your name or indirectly in any other name or in association with any other person entity in which you may choose to carry out your business for a period
________________________________________________________________________________________
of one year from the date of issue of this letter."
16. The aforesaid apart, the petitioner is also aggrieved by
the website display of respondent no.2 where the
name of the petitioner is shown with the remark „the
applicant has been debarred by NHAI‟. He thus
submits that this may have an effect on the other
tenders issued by third parties, in which, the petitioner
may want to participate.
17. The last aspect urged by learned counsel for the
petitioner is that without prejudice to the aforesaid,
the punishment imposed on the petitioner is
disproportionate, and such a decision of debarment
can form subject matter of adjudication under Article
226 of the Constitution of India in view of the
judgment of the learned Single Judge of this Court in
M/s V.K.Dewan and Co. v. Municipal Corporation of
Delhi & Ors.; AIR 1994 Delhi 304.
18. On the other hand, learned senior counsel for
respondent no.2 has pointed out to us that all that the
respondent no.2 has done is to take a decision not to ________________________________________________________________________________________
deal with the petitioner for a period of one year on
account of the petitioner having backed out at the last
minute from entering into the contract. The parties
participating in such bids are well experienced and the
petitioner is one such party, which is in fact a public
limited company, and which has been participating in
various tenders including that of respondent no.2. The
difference between the petitioner as H-1 and H-2 to
whom ultimately the contract was awarded is quite
large (i.e., a differential itself amounting to Rs.64
crores). Since the bid security forfeiture term in the
contract provided for a pre-estimate of damages, only
that amount was forfeited, i.e., a sum of Rs.13.97
crores. Learned counsel has referred to the final order
passed by respondent no.2 to contend that it is a first
case where a bidder has not executed LOA, and
respondent no.2 as a prudent commercial party is
entitled to take a decision to discourage such practice
in future by contractors like the petitioner. The
decision taken by respondent no.2 is a prudent
commercial decision not to deal with a contractor like ________________________________________________________________________________________
the petitioner for a limited period of one year and that
the position could be no different only because
respondent no.2 is a public sector enterprise. A
decision, such as the one taken by respondent no. 2,
would not have been called into question if a private
party had decided not to deal with such relcalcitrant
entity.
19. It is the say of learned counsel for respondent no.2
that the debarment is for a short period of time
keeping in mind the nature of contracts which are
entered into by respondent no.2. Learned senior
counsel for respondent no.2 states that clause 4.2 has
no role to play in the present case, and that the
decision taken by it is de hors the same in view of
clause 2.20.7 which states that the encashment of the
bid security amount is „without prejudice to any other
right or remedy that may be available to the
authority".
20. We find the action of respondent no.2 is completely
justified and in accordance with law. The petitioner, a
corporate entity, knew the nature of bid it was making. ________________________________________________________________________________________
It made a bid for RS 190.57 crores. On having found
out that the next highest bid of H-2 was for Rs.126.06
crores (as revised), though the original bid was even
lower, it had a second thought and under the garb of
ostensibly re-visiting a business decision withdrew
from the tender. It naturally bore the financial
consequences of the bid security amount being
forfeited without any demur or protest. What the
petitioner seeks by way of the present writ petition is a
right to continue to participate in the tenders to be
issued of respondent no.2 in the near future despite
the aforesaid conduct. We cannot lose sight of the
fact that respondent no.2 is dealing with highway
projects all over the country which are of critical
national importance both in terms of their economics
and logistical relevance. Expeditious construction of
road links is an important part of infrastructure
development of the country. Any delay in such
infrastructure projects is a national waste. In such a
situation for the petitioner to have withdrawn at the
last minute, ostensibly on the ground of prudent ________________________________________________________________________________________
commercial decision can certainly invite the
consequences of the tenderer declining to deal with
such an entity for a specified period of time. Learned
senior counsel for respondent no.2 has rightly
contended that but for the fact that the said
respondent is a public sector undertaking such a
decision would have passed muster of the court on the
ground of business expediency. The fact that
respondent no.2 is a public sector undertaking ought
not to disable it from taking a commercially prudent
and if you take an expedient decision in its own
interest. It is not the function of this Court to interfere
with such a decision which impinges on its business
efficacy merely because it happens to be taken by a
public sector undertaking which, in the instant case,
happens to be respondent no.2. The order of the
respondent no.2 also notes that this is a first instance
of its kind. The reference of „pooling‟ and „mala fide‟ is
made in that context, and as clarified by learned
counsel for respondent no.2, not to bring it within the
parameters of clause 4.2.
________________________________________________________________________________________
21. In our considered view, such an action by respondent
no.2, in the given facts and circumstances of the case,
is a decision which any prudent businessman placed in
a similar situation would naturally have taken to deter
such like entities from conducting themselves in a
manner, to say the least, which is unbusinessman like.
In such circumstances, it would be both unfair and
unreasonable for the court to issue a direction
requiring respondent no. 2 to deal with a person (i.e.,
the petitioner) who had no qualms in ditching the
project at the nth hour.
22. We are also unable to accept the submission of
learned senior counsel for the petitioner that adequate
opportunity was not granted to the petitioner to
defend its case since an oral hearing was not accorded
to the petitioner. A right of personal hearing is not an
inbuilt right in such like proceedings especially given
the peculiar facts of the case, which stand unrebutted.
In this regard, we draw strength from the observations
of the Supreme Court in Union of India & Anr. v. Jesus
________________________________________________________________________________________
Sales Corporation; (1996) 4 SCC 69 where para 5
reads as under:
5. The High Court has primarily considered the question as to whether denying an opportunity to the appellant to be heard before his prayer to dispense with the deposit of the penalty is rejected, violates and contravenes the principles of natural justice. In that connection, several judgments of this Court have been referred. It need not be pointed out that under different situations and conditions the requirement of compliance of the principles of natural justice vary. The courts cannot insist that under all circumstances and under different statutory provisions personal hearings have to be afforded to the persons concerned. If this principle of affording personal hearing is extended whenever statutory authorities are vested with the power to exercise discretion in connection with statutory appeals, it shall lead to chaotic conditions. Many statutory appeals and applications are disposed of by the competent authorities who have been vested with powers to dispose of the same. Such authorities which shall be deemed to be quasi- judicial authorities are expected to apply their judicial mind over the grievances made by the appellants or applicants concerned, but it cannot be held that before dismissing such appeals or applications in all events the quasi- judicial authorities must hear the appellants or the applicants, as the case may be. When principles of natural justice require an opportunity to be heard before an adverse order is passed on any appeal or application, it does not in all ________________________________________________________________________________________
circumstances mean a personal hearing. The requirement is complied with by affording an opportunity to the person concerned to present his case before such quasi-judicial authority who is expected to apply his judicial mind to the issues involved. Of course, if in his own discretion if he requires the appellant or the applicant to be heard because of special facts and circumstances of the case, then certainly it is always open to such authority to decide the appeal or the application only after affording a personal hearing. But any order passed after taking into consideration the points raised in the appeal or the application shall not be held to be invalid merely on the ground that no personal hearing had been afforded. This is all the more important in the context of taxation and revenue matters. When an authority has determined a tax liability or has imposed a penalty, then the requirement that before the appeal is heard such tax or penalty should be deposited cannot be held to be unreasonable as already pointed out above. In the case of Shyam Kishore v.
Municipal Corporation of Delhi (supra) it has been held by this Court that such requirement cannot be held to be harsh or violative of Article 14 of the Constitution so as to declare the requirement of pre-deposit itself as unconstitutional. In this background, it can be said that normal rule is that before filing the appeal or before the appeal is heard, the person concerned should deposit the amount which he has been directed to deposit as a tax or penalty. The non-deposit of such amount itself is an exception which has been incorporated in different Statutes including the one with which are concerned. Second proviso to Sub-section (1) of Section 4-M says in clear and unambiguous words that an appeal against ________________________________________________________________________________________
an order imposing a penalty shall not be entertained unless the amount of the penalty has been deposited by the appellant.
Thereafter the third proviso vests a discretion in such Appellate authority to dispense with such deposit unconditionally or subject to such conditions as it may impose in its discretion taking into consideration the undue hardship which it is likely to cause to the appellant. As such it can be said that the statutory requirement is that before an appeal is entertained, the amount of penalty has to be deposited by the appellant; an order dispensing with such deposit shall amount to an exception to the said requirement of deposit. In this back- is ground, it is difficult to hold that if the Appellate authority has rejected the prayer of the appellant to dispense with the deposit unconditionally or has dispensed with such deposit subject to some conditions without hearing the appellant, on perusal of the petition filed on behalf of the appellant for the said purpose, the order itself is vitiated and liable to be quashed being violative of principles of natural justice.
(emphasis is ours)
23. We also do not find that the consequences
stipulated in the impugned letter are disproportionate
when examined in the context of the conduct of the
petitioner. The case referred to by learned senior
counsel for the petitioner in V.K.Dewan and Co. v.
Municipal Corporation of Delhi & Ors.‟s case (supra)
was a case where period of debarment imposed was
________________________________________________________________________________________
three years. The aspect of proportionality has to be
examined in the context of the facts and
circumstances arising in a given case. In the present
case, after proposing a debarment for a period of five
years, the decision taken by respondent no.2 is of
debarment of petitioner for a year from participating in
the tenders to be issued by respondent no.2 within the
said time frame. The effect of the petitioner
withdrawing from the contract is that the respondent
no.2 has suffered a loss of Rs 64 crores per year to
begin with, and thereafter, on an extrapolated scale,
spread over a period of 25 years, the loss is pegged at
Rs.3077 crores; as set out in the final order. The
respondent no.2 was thus well within its rights to take
appropriate action against the petitioner, and taking
into consideration the enormity of the loss, we are of
the considered view that respondent no.2 has dealt
with the petitioner rather lightly.
24. Insofar as the display on website is concerned, the
same is only stating a fact that respondent no.2 has
taken a decision to debar the petitioner from further ________________________________________________________________________________________
dealing for a period of one year. It is not a debarment
qua any third party. It is for the third parties to take an
informed decision whether they would like to deal with
the petitioner keeping in mind the conduct of the
petitioner qua respondent no.2. We can only sum up
by noting that the consequences which flowed in this
case pursuant to the conduct of the petitioner are
those, which are of, the petitioner‟s own making; it has
no one else to blame but itself.
25. We find the writ petition devoid of both merit and
substance and hence dismiss the same with costs
quantified at Rs.1,00,000/-.
26. Interim order stands vacated.
SANJAY KISHAN KAUL, J.
AUGUST 02, 2011 RAJIV SHAKDHER, J. dm
________________________________________________________________________________________
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!