Thursday, 23, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Prakash Industries Ltd. vs Union Of India & Ors.
2010 Latest Caselaw 2632 Del

Citation : 2010 Latest Caselaw 2632 Del
Judgement Date : 18 May, 2010

Delhi High Court
Prakash Industries Ltd. vs Union Of India & Ors. on 18 May, 2010
Author: S. Muralidhar
IN THE HIGH COURT OF DELHI AT NEW DELHI

        W.P.(C) No. 7135 of 2008 & CMs 13784/08,
                    5035, 13945/2009

                             Reserved on: 23rd March 2010
                             Decision on: 18th May, 2010

PRAKASH INDUSTRIES LTD.             ..... Petitioners
             Through: Mr. A. Sharan Sr. Advocate with
             Mr. B.R. Menon, Mr. Alok Singh,
             Ms. Divya Kesar and
             Mr. Ashwini Kumar, Advocates.

                        Versus

UNION OF INDIA & ORS.                    ..... Respondents
              Through: Ms. Anjana Gosain with
              Ms. S. Fatima, Advocates for UOI.
              Mr. Atul Jha, Advocate for
              Respondent No.3.
              Mr. Kailash Vasdev, Sr. Advocate with
              Mr. Manoj Sharma, Mr. Kapil Kaushik and
              Mr. Sumit Bhardwaj, Advocates for
              Respondent No.4.
              Mr. Arvind Nigam, Sr. Advocate with
              Mr. S.K. Mishra, Mr. Adil Ali and
              Mr. Ashutosh, Advocates for
              proposed Respondent No.5.

CORAM: JUSTICE S. MURALIDHAR

   1.     Whether reporters of the local newspapers be
          allowed to see the Judgment?                      No
   2.     To be referred to the Reporter or not?            Yes
   3.     Whether the Judgment should be reported
          in the Digest?                                    Yes


                             JUDGMENT

18.05.2010

1. The challenge in this petition under Article 226 of the

Constitution by Prakash Industries Ltd. (`PIL‟) is to a letter

dated 6th February, 2008 issued by the Government of India,

Ministry of Coal allocating 73.85 MT of coal reserves to M/s W.P.(C) Nos. 7135 of 2008 page 1 of 33 S.K.S. Ispat & Power Ltd. (`SKS‟), Respondent No.4 herein.

The further prayer is for a direction to the Ministry of Coal to

allocate the non-coking coal block to both the Petitioner, PIL

and Respondent No.4 (on the basis of the capacity of the

proposed power plant) as recommended by the Government of

Chhattisgarh (Respondent No.3) on 18th June, 2007.

Background Facts

2. The background facts are that on 6th November, 2006,

Respondent No.1 through Ministry of Coal advertised a list of

38 coal blocks for captive coal mining for allocation to

companies engaged in the generation of power, production of

iron and steel and production of cement. 15 out of the 38 coal

blocks were earmarked for power generation. The remaining

23 blocks were to be made available for other specified end-

uses like production of iron and steel and production of

cement.

3. PIL states that it was incorporated in the year 1980, and is

engaged in the business of manufacturing sponge iron, power

co-generation, steel (blooms and billets) etc. PIL states that it

has developed a fully integrated Steel Plant at Champa in

Chhattisgarh which commenced production in 1993. The

original installed capacity was 4 LTPA of sponge iron, 1.6

LTPA of liquid steel, 1.5 LTPA of structural steel along with

12 MW power co-generation.

W.P.(C) Nos. 7135 of 2008 page 2 of 33

4. On 7th January, 2005, PIL entered into a Memorandum of

Understanding (MOU) with the Government of Chhattisgarh

(Respondent No.3) for setting up of a 190 MW coal based

captive power plant with a proposed investment of Rs. 1017

crores.

5. Pursuant to an advertisement issued by Respondent No.1,

the Petitioner on 12th January 2007 applied for allocation of

non-coking coal block for its proposed power plant at

Fatehpur, in Chhattisgarh. In its application PIL indicated that

the coal was required for meeting its part requirement for the

power plant of 625 MW capacity. The power plant project was

to be executed in phases. The first phase of 250 MW was to be

commissioned in April 2010 and second phase of 250 MW in

April 2011.

6. On 12th January, 2007 Respondent No.4 SKS also applied

pursuant to the same advertisement dated 6th November 2006

for allocation of a non-coking coal block. It was indicated in

the application that the power generation capacity of its

proposed power plant was 1000 MW+100 MW, i.e., 1100

MW.

7. PIL planned to expand its facilities in Chhattisgarh where it

proposed to set up a coal based thermal power plant having a

power generation capacity of 500 MW thus having a combined W.P.(C) Nos. 7135 of 2008 page 3 of 33 capacity of 690 MW at an approximate project cost of Rs.

3,218.75 crores. Accordingly, another MOU was entered into

by PIL with Respondent No. 3 on 18th June, 2007 for an

integrated steel plant with additional annual capacity/unit of

1.2 mTPA at a cost of Rs. 440 crores and a captive power plant

(thermal) of 500 MW at a cost of Rs. 1625 crores.

8. In the meanwhile on 24th January 2007, Respondent No. 4

entered into an MOU with Respondent No. 3 for setting up of a

power plant having a capacity of 600 MW.

9. Respondent No.1 appointed a Screening Committee,

Respondent No.2 herein, to examine the applications made

pursuant to the advertisement dated 6 th November 2006. It held

meetings between June and September 2007 and considered

the applications filed by the both the Petitioner as well as

Respondent No.4. On 6th November, 2007 the Respondent

No.1 wrote to both the Petitioner as well as Respondent No.4

informing them that the central government was contemplating

a joint allocation of the Fatehpur non-coking coal block in

Chhattisgarh in favour of both the Petitioner as well as

Respondent No.4 for meeting their proportionate requirement

of coal. It was stated that based on mineable capacity of the

total geological reserves and requirement of coal as assessed

by the Central Mine Planning and Design Institute Ltd.

W.P.(C) Nos. 7135 of 2008 page 4 of 33 (CMPDIL), the tentative proportionate share of the reserves

was as indicated in the form of a table a copy of which read:

 Blocks     Geological      Tentative   Proposed     Coal              Proportionate
            Reserve(Mt)     Mine        for          Requirement       share       of
                            Capacity    Company      For 30 yrs (Mt)   reserves    of
                            (Mtpa)                                     coal MT
 Fatehpur   120             3/0         M/s SKS      4.6x30=138        73.85
                                        Ispat        For 1000
                                        Power        MW (IPP)
                                        Ltd.
                                        M/s          2.875x30=86.25    46.15
                                        Prakash      for 625 MW
                                        Industries   (CPP)
                                        Ltd.
                                        Total        224.25



10. The first option indicated in the said letter was that mining

could be carried out:

"in consortium of two or more allocattees in any given block by constituting a joint venture/special purpose vehicle company wherein there would be equity stake and management participation from all the consortium partners. The production from the mine could be distributed among the consortium partners in proportion to their assessed requirement at the time of allocation, net of linkages, if any. The equity shares should be held in proportion to the assessed requirement of all the consortium partners."

11. The second option was that one of the allocattee companies

be designated as the leader for the block and the other

allocattees be treated as associates. In such event, the mining

operation would be carried out by the leader and the

production from the mine would be shared between the leader

and the associates in the ratio of their respective requirements

at the time of allocation.

W.P.(C) Nos. 7135 of 2008 page 5 of 33

12. The third option was that for each block, one allocattee was

chosen as the leader and other allocattees as associates. The

CIL would have to arrange the transfer of coal from the leader

to the associates as per the ratio determined at the time of

allocation.

13. It was stated in the letter dated 6th November 2007 that the

Petitioner and Respondent No. 4 should discuss the modalities

mutually acceptable to them and finalise a legally binding and

enforceable agreement opting for any one of the three

alternatives. It was stated that the agreement was required to be

in conformity with the provisions of the Coal Mines

(Nationalisation) Act, 1973 [CMNA] and the guidelines issued

in this regard. The options were directed to be exercised within

thirty days.

14. On 13th November, 2007 PIL wrote to Respondent No.1

drawing the latter‟s attention to the fact that the ratio of share

of coal reserves has not been specified by the Screening

Committee (Respondent No.2) while deciding the allocation of

the Fatehpur coal block. Secondly, PIL had proposed to set up

a thermal power Plant of 625 MW capacity whereas

Respondent No.4 had proposed to set up a power plant of 600

MW and not 1000 MW. It was stated that coal reserves should

be allocated to PIL and the Respondent No.4 in the ratio of the

proposed capacity of their respective power plants. It was W.P.(C) Nos. 7135 of 2008 page 6 of 33 pointed out that any allocation of share on the basis of 1000

MW capacity of Respondent No.4 would amount to excess

allocation of coal beyond the consumption of 600 MW and,

therefore, would also not be in consonance with the policy and

purpose of captive mining for which the coal block was being

allocated. Reference was also made by the PIL to the

correspondence between Chhattisgarh Government and the

Chhattisgarh State Electricity Board (CSEB) with Respondent

No.4 on 1st April, 2007, 10th July, 2007 and 5th September,

2007 which showed that the power plant of Respondent No.4

as proposed was only of 600 MW capacity. The Petitioner

wrote another letter on 15th November, 2007 followed by

various personal visits to Respondent No.1.

15. On 22nd January, 2008 Respondent No.1 asked the

Petitioner and Respondent No.4 to attend a meeting on 30th

January, 2008 in the office of the Joint Secretary, (Coal) "to

discuss the issue relating to formation of Joint Venture

Agreement and for taking final decision relating to allocation

of Coal Block". Thereafter on 29th January, 2008 the Petitioner

and Respondent No.4 entered into a Joint Venture Agreement

(JVA) with a view to complying with the directions of

Respondent No.1. According to the Petitioner, this was done

on the assurance given over to it "that a necessary correction

shall be made and proportionate allocation should also be

made in favour of the parties on the basis of actual proposed W.P.(C) Nos. 7135 of 2008 page 7 of 33 power generation capacity of their plants." Thereafter on 6 th

February 2008, the impugned letter was issued by the

Respondent No.1 in the manner indicated hereinbefore.

16. The Petitioner waited for several months and thereafter on

28th August, 2008 wrote to Respondent No.1 seeking redressal

of its grievance, for necessary correction to be made and a

revised allocation letter to be issued. Thereafter the present

petition was filed. On 3rd October 2008, an interim order was

passed by this Court to the effect that the "case of the

Petitioner pursuant to the communication dated 06.02. 2008

shall not be processed further." The said interim order has

continued since.

Applications to implead Respondents 5 and 6

17. CM No.5035 of 2009 was filed by the Petitioner on 15th

April 2009 soon after the hearing of the case on 25th March,

2009. PIL by this application sought to amend the writ petition.

It was stated in the said application, inter alia, as under:

"3. That it has come to the knowledge of the Petitioner that the Respondent No.4 Company is promoted by the family of Sh. Subodh Kant Sahai, Union Minister of State for Food Processing Industries (Independent Charge).

4. It is submitted that the said fact could only be confirmed when the Respondent No.1 filed its Counter Affidavit in another case being CWP W.P.(C) Nos. 7135 of 2008 page 8 of 33 No.6449 of 2008 wherein Sh. Sudhir K. Sahai, brother of said Sh. Subodh Kant Sahai has been shown to attend a meeting of the Screening Committee on 06.02.2008 as a Director of the Respondent No.4 Company.

5. It is submitted that the representatives of the Respondent No.4, with an object to avail favours to the Respondent No.4, have been holding out before the various Governmental authorities that SKS stands for Subodh Kant Sahai.

6. That under the circumstances it is clear that the Respondent No.1 & 2 are acting in a malafide and partisan manner and in collusion with Respondent No.4 allocated the coal blocks to Respondent No.4 under influence of Sh. Subodh Kant Sahai."

18. The Petitioner sought to insert paras 38a, 38b and 38c in

the writ petition and add grounds P and Q which read as under:

have acted malafide in allocating coal blocks to Respondent No.4, under political influence of Sh. Subodh Kant Sahai, the Union Minister of State for Food Processing Industries (Independent Charge)."

Q. Because the Respondent No.4 and proposed Respondent Nos.5 & 6 have created a corporate veil around Respondent No.4 to mislead and defraud the general public and thereby gain an undue and illegal advantage by influencing the Respondent Nos.1 & 2 by not showing in W.P.(C) Nos. 7135 of 2008 page 9 of 33 public documents that the proposed Respondent No.6 is not a director of the company but at the same time before Respondent Nos.1 and 2 holding out that he is a director of Respondent No.4 and as such gain undue and malafide favours from the said respondents."

19. On the above basis, the Petitioner sought to implead Mr.

Subodh Kant Sahai, as Respondent No.5 and his brother

Mr.Sudhir Kant Sahai, who is a Director of Respondent No.4,

as Respondent No.6.

20. Notice was issued on the above application on 17th April,

2009. Replies have been filed by the proposed Respondent

Nos. 5 and 6 to the aforementioned application.

21. CM No. 13945 of 2009 was filed by PIL for taking on

record an additional affidavit dated 27th October, 2009 to

include a reference to the minutes of the 36th meeting of the

Screening Committee held on 7-8th February, 2008 and 3rd

July, 2008 which considered the allocation of 23 coal blocks

earmarked for the non-power sector. Notice was issued on this

application as well on 7th November 2009.

Case of the Petitioner

22. Mr. Amarendra Sharan, learned Senior counsel for the

Petitioner submits that the central question involved is the W.P.(C) Nos. 7135 of 2008 page 10 of 33 legality of the allocation made by Respondent No. 1 of a larger

percentage of the coal block in favour of Respondent No. 4.

The petitioner assails the decision, made by the impugned

letter dated 6th February 2008, as being discriminatory,

arbitrary and vitiated by malice in law and in fact. It is

submitted that PIL was compelled by the circumstances into

entering into a JVA reflecting the shares of the Petitioner and

Respondent No. 4 as 625 MW and 1000 MW. At the time of

signing the JVA the petitioner‟s representations dated 13th and

16th November 2007 were pending with Respondent No.1.

Therefore the signing of the JVA did not amount to waiver by

PIL of its right to challenge the allocation so made. In this

connection, reliance was placed on the judgments of

Basheshar Nath v. CIT AIR 1959 SC 149; Behram Khurshed

Pesikaka v. State of Bombay (1955) 1 SCR 613 and Olga

Tellis v. Bombay Municipal Corporation (1985) 3 SCC 545.

23. Mr. Sharan submitted that the allocation is not based on

relevant materials. Importantly, it is inconsistent with the

recommendation made by State Government on 16th June,

2007 in favour of the Respondent No. 4 for a thermal power

plant of 600 MW capacity. It is submitted that in all the

documents emanating from Respondent No. 4, the request was

for allocation of a coal block for its 600 MW thermal power

plant. At the presentation made by Respondent No. 4 before

the Screening Committee which met on 20th and 23rd June W.P.(C) Nos. 7135 of 2008 page 11 of 33 2007, the capacity projected of the proposed thermal power

plant was of 600 MW only. Both in its letter dated 5th

September, 2007 addressed to Respondent No.1 and in the

MOU entered into with Respondent No. 3 the projected

capacity of the power plant of Respondent No. 4 was only 600

MW.

24. Thirdly, PIL contests the averment in the counter affidavit

of Respondent No.1 that by a letter dated 5th September 2007,

Respondent No. 3 had "superseded" its earlier

recommendation dated 18th June 2007 and indicated the

proposed end use plant capacity of Respondent No. 4 as 1000

MW. The petitioner relies on a response dated 22nd November

2008 received by it from Respondent No. 3 pursuant to an

application made by PIL under the Right to Information Act,

2005 („RTI Act‟) confirming that it had not made a further

recommendation after 18th June 2007. The petitioner PIL states

that in response to a query to it by Respondent No. 1 about the

status of preparedness of the various projects in the State of

Chhattisgarh, Respondent No. 3 had written to Respondent

No.1 on 5th September 2007 indicating inter alia the

information relating to Respondent No. 4 and stating in the

„remarks‟ column that an MOU had been signed by

Respondent No. 4 and Respondent No. 3 on 24th January 2001

for a 600 MW power plant. The proceedings of the meeting of

the Screening Committee, Respondent No. 2 herein, held on W.P.(C) Nos. 7135 of 2008 page 12 of 33 13th September 2007 did not reflect that any representative of

the State of Chhattisgarh was present and in any event a

recommendation of such representative could not supersede

the MOU signed between Respondent Nos. 3 and 4. It is

submitted that by determining the proportionate share of

Respondent No. 4 on the basis that the capacity of its thermal

power plant was 1000 MW, Respondent No. 1 had committed

a manifest error.

25. It is further submitted by Mr. Sharan that the final

allocation order issued on 6th February, 2008 made no mention

of the objections raised by PIL in its letters of 13th and 16th

November 2007. In any event, the said order contained no

reasons why the share of PIL was reduced by nearly 13%.

Reliance was placed on the decisions in Union of India v. G.

Ganayutham (1997) 7 SCC 463 and Common Cause v. Union

of India (1996) 6 SCC 530.

26. Mr. Sharan submitted that the JVA has nothing to do with

the allocation of the coal block but only extraction of coal. It

was in the nature of a quasi-statutory contract. It is submitted

that the allocation finally made to Respondent No. 4, was

contrary to the recommendations of Respondent No. 3. With

Respondent No. 3 confirming that it had not reviewed its

recommendation made by its letter of 18th June 2007 the very

basis of the allocation made in the impugned letter dated 6th W.P.(C) Nos. 7135 of 2008 page 13 of 33 February 2008 was erroneous. It is submitted that on account

of the illegal excess allocation of non-coking coal block by

Respondent No. 1 to Respondent No. 4 the rightful share of the

petitioner in non-coking coal block has been illegally curtailed.

This would result in its power plant not being operated to its

optimal capacity and might result in the failure of its project.

27. Lastly, in support of the plea of malafides both in law as

well as fact, it is pointed out by Mr. Sharan that Mr. Subodh

Kant Sahai (proposed Respondent No. 5), a Union Minister for

State in the Ministry of Food Processing Industries

(Independent Charge) wrote a letter dated 5th February 2008 to

the Prime Minister asking for his personal intervention as

regards the application made by Respondent No. 4 for two coal

blocks. Immediately on the next day, i.e., 6th February 2008,

the Prime Minister‟s Office (PMO) forwarded the said letter to

the Respondent No. 1 "for action as appropriate." It is

submitted that the speed with which on 6th February, 2008

itself the final letter of allocation was issued indicated the

extent to which Respondent No. 4 could bring influence to

have the allocation made in its favour. The Respondent No. 4

admitted that the Minister‟s brother Mr. Sudhir Kant Sahai

(proposed Respondent No. 6) was a Director in the company

and had in that capacity attended the meeting of the Screening

Committee on 7th February 2008. In support of the plea of legal

and factual malafides, reliance was placed on the decisions in W.P.(C) Nos. 7135 of 2008 page 14 of 33 Express Newspapers Ltd. v. Union of India 1986 (1) SCC

133, Bahadursingh Lakhubhai Gohil v. Jagdishbhai M.

Kamala (2004) 2 SCC 65 and S.P. Kapoor v. State of H.P.

(1981) 4 SCC 716.

28. In the additional written submissions of the Petitioner, it is

contended that "SKS was imposed upon the Petitioner by the

Respondent No.1." It is also said that "Respondent No.1

threatened the Petitioner that if it did not sign the JVA it will

cancel the allocation as such the Petitioner had no choice but to

sign the JVA to avail its quota of coal." It is further submitted

as under:

"Sh. Sudhir K Sahai who has been designated as a Director of Respondent No.4 though his name does not appear in the returns filed before the ROC, has been holding out to public at large and Government authorities that SKS stands for Subodh Kant Sahai."

29. The contention of Respondent No. 4 that SKS stands for

"Shree Krishna Structures" is dismissed of as "no good

inasmuch as that being so there was no need to change the

name to SKS in the year 2000. It is apparent that the said

change was effected only with a view to avail political benefits

by holding out that SKS stands for Subodh Kant Sahai."

W.P.(C) Nos. 7135 of 2008                             page 15 of 33
 Case of the Respondents

30. On behalf of Respondent No. 4, Mr. Kailash Vasdev,

learned Senior counsel submitted that as per the Mega Power

Policy of the Ministry of Power, Government of India, any

independent power project of 1000 MW and above would be

considered for exemption from customs duty. It is with this

view that Respondent No. 4 submitted a proposal to

Respondent No. 3 Government of Chhatisgarh on 24th October,

2006 for setting up of a thermal power plant of that capacity,

much before the advertisement inviting bids for the coal

blocks. Reference is made to the proposal dated 24th October,

2006 and the letter dated 11th December, 2006 of the Ministry

of Commerce and Industry, Government of India issuing an

IEM Code to Respondent No.4 for 1000 MW coal based

thermal power plant. On 13th December, 2006 Respondent No.

4 informed the Principal Secretary (Energy) of Respondent No.

3 that it had completed the preparation of the detailed project

report for setting up a power plant with a capacity of 500 x 2

MW (i.e 1000 MW). This was acknowledged on 6th January

2007 by Respondent No. 3.

31. Mr. Vasdev referred to the application of Respondent No. 4

in which it was indicated that an extent of 500 MW capacity

would be completed in the first phase within 24 months and

the remaining 500 MW within 24 months of the

commissioning of the first phase. It is pointed out that Clause W.P.(C) Nos. 7135 of 2008 page 16 of 33 27 of the MOU dated 24th January, 2007 entered into between

Respondents No. 3 and 4 states:

"In the event of any increase in the installed capacity as mentioned above or any expanded capacity to the existing unit(s) under the Project, a fresh MOU shall be signed for such increase in the capacity as per prevailing policies of the Government, at that time."

32. Further, in a power point representation made on 17th

August, 2007 to the Screening Committee, Respondent No. 4

stated that "600 MW IPP shall be expanded to 1100 MW in II

Phase."

33. It is submitted by Mr. Vasdev that the Petitioner had

accepted the offer made by Respondent No. 1 in the allocation

letter dated 6th February, 2008 and consequent thereto on 19th

May, 2008 a Joint Venture Company in the name of Fatehpur

Coal Mining Company Ltd. (FCMCL) was incorporated jointly

by the Petitioner and the Respondent No.4. Two board

meetings of the Directors of FCMCL were held on 28th May

and 31st July, 2008. Reference was made to the several steps

taken by Respondent No.4 including inviting tenders for an

EPC contract, getting land allotted by the Respondent No. 3

and allocation of water on 4th October, 2008. It is pointed out

that Respondent No.4 has accepted such allotment and

invested several crores of rupees for executing the power plant

W.P.(C) Nos. 7135 of 2008 page 17 of 33 project. It is pointed out that PIL has already been declared a

willful defaulter in a list prepared by the Reserve Bank of India

(RBI). PIL was refusing to provide bank guarantee to the Joint

Venture Company.

34. Mr. Vasdev refers to the statement made by the Auditors of

PIL in their report for the period ended 31st March 2007 to the

effect that PIL "has defaulted in repayment of dues to financial

institutions, banks and debenture holders aggregating to Rs.

40,533 lakhs (excluding interest). The annexure to the report

also lists out the amounts due on account of excise duty, entry

tax, income tax and energy cess. It is contended that PIL can

"never raise the required resources in view of their past track

record and financial position of the company. Hence, they are

trying to garner more and more coal blocks and at the same

time resorting to unfair practices to stall the process of

allotment to other industries."

35. Finally, it is pointed out that the JVA was executed on 29th

January, 2008, the final allotment letter was issued on 6 th

February, 2008 and the present writ petition was filed only on

29th September, 2008. The allegation of malafides is denied.

36. Mr. Arvind Nigam, Senior Advocate appeared on behalf of

the proposed Respondent No. 5 vehemently denied the

allegations stating that the very basis of the inference that the W.P.(C) Nos. 7135 of 2008 page 18 of 33 initial SKS stand for Subodh Kant Sahai was false since those

initials stood for Shree Krishna Structures which had initially

been promoted as a private limited company in April, 1995 by

Sri Anil Gupta and Deepak Gupta, both of whom were

devotees of Lord Krishna. Respondent No. 5 categorically

stated that he had nothing to do with the Respondent No. 4

company. As regards the letter dated 5th February, 2008 written

by the proposed Respondent No. 5 and the letter dated 6th

February, 2008 from the PMO to Respondent No.1 it is stated

as under:

"It is most respectfully submitted that replying Respondent being a public figure and representative from Parliament Constituency in the State of Jharkhand is naturally concerned with development of his constituency. SKS Ispat & Power Ltd. proposed to establish Steel Plants in the State of Jharkhand and Chhattisgarh. The replying Respondent on considering of potential development and scope of generation of employment in the State had requested that the application filed by the SKS Ispat & Power for allotment of Coal Blocks for proposed Steel Plant in the State of Jharkhand be duly considered." (emphasis supplied)

37. Mr. Nigam pointed out that in view of the fact that the

recommendation was not for allocation of coal blocks for the

power project of SKS in Chhattisgarh but for its steel plant in

Jharkhand, the allegations made by PIL were wholly

W.P.(C) Nos. 7135 of 2008 page 19 of 33 misconceived. The letter written on 5th February, 2008 was

considered by the 36th Screening Committee which was

considering allocation of coal blocks for non-power sectors.

The decision to jointly allocate the Fatehpur coal block to both

PIL and Respondent No. 4 had already been taken by the

Screening Committee at the meeting held on 13th September,

2007 and this was communicated to both of them on 6th

November, 2007 long before the letter dated 6th February,

2008. It is reiterated that PIL‟s allegation that Respondent No.

4 was promoted by the family of Respondent No.5 was

baseless and malicious and the petition ought to be rejected

with exemplary costs.

38. Appearing for Respondent No.1, Ms. Anjana Gosain,

learned counsel referred to the detailed affidavit filed by it. She

also referred to a subsequent additional affidavit dated 27th

October 2009, in which it was clarified by Respondent No. 1

that the statement that Respondent No. 3 had by its letter dated

5th September 2007 "superseded" its earlier decision dated 18th

June 2007 was an error. It was clarified that Respondent No. 3

had by its letter dated 5th September 2007 furnished a status of

preparedness of the end use projects of applicants and "the

decision to recommend 1000 MW for the end use plant of

Respondent No.4 is based on the recommendations made by

the State Govt. and the capacity indicated in the application of

Respondent No. 4." Ms. Gosain submitted that no illegality W.P.(C) Nos. 7135 of 2008 page 20 of 33 had been committed as the joint allocation was strictly in terms

of the policy. PIL and Respondent No. 4 had formed a joint

venture company preceded by a JVA incorporating the very

percentages of allocation that had been offered to them jointly

by the letter dated 6th November 2007. The impugned letter

dated 6th February 2008 was merely consequential and did not

suffer from any illegality. She denied that any pressure was

brought upon PIL to agree to the JVA as alleged.

39. Respondent No. 3 has filed a counter affidavit reiterating

that its representative was present at the meeting of the

Screening Committee on 13th September 2007. It confirmed

having sent the letter dated 5th September 2007 giving the

status of preparedness of the end use projects as requested by

Respondent No. 1 on 2nd August 2007.

PIL under no compulsion to enter into JVA with SKS

40. The entire thrust of PIL‟s argument has been that it was

arm-twisted into signing a JVA with Respondent No. 4 and

that it was compelled to follow that up with forming a joint

venture company with Respondent No. 4. Yet, till date PIL has

not withdrawn from the joint venture and the joint venture

company FCMCL continues with both PIL and Respondent

No.4 holding the same equity shareholding which mirrors the

share of their coal allocation. This factor is significant in

evaluating PIL‟s submissions about the unfairness of the coal W.P.(C) Nos. 7135 of 2008 page 21 of 33 allocation made by the impugned letter dated 6 th February

2008.

41. The second factor is that the basis on which a joint

allocation was made by Respondent No. 1 to both PIL and

Respondent No. 4 is the guidelines issued by Respondent No. 1

for allocation of captive coal blocks. Para 7 of the guidelines

which are relevant for the present case reads as under:

7. Allotment of Captive blocks to consortium of group of companies

(i) If requirement of coal by an applicant does not match with the reserves in a natural block then clubbing of requirements may be resorted to and in case a number of applicant companies form a consortium for utilization of a block for their captive use, the same may be considered for allocation under a legally tenable arrangement.

(ii) More than one eligible and deserving companies will be allowed to do captive mining of coal by forming a joint venture coal mining company. The constituent applicant companies would hold equity in the joint venture company in proportion to their assessed requirement of coal and the coal produced would be exclusively consumed in their respective end use projects. Distribution of coal would be in proportion to their respective assessed requirements.

(iii) One or more companies (to be called leader companies) from amongst the

W.P.(C) Nos. 7135 of 2008 page 22 of 33 selected, could be allowed to do mining of coal in one or more captive blocks and the other companies (to be called associate companies) would get coal from the captive block in proportion to their assessed requirements. The local Coal India subsidiary could facilitate this arrangement by taking a nominal service charge. Leader companies will deliver coal to associate companies at a transfer prices to be determined by the Central Government."

42. The above guidelines have not been challenged by PIL. On

the other hand, when PIL applied on 12th January 2007 for

allocation of a captive coal block pursuant to the advertisement

issued by Respondent No. 1 on 6th November 2006, it was

aware that the guidelines would apply. Consistent with the

above guidelines both Respondent No. 4 and PIL were

informed by Respondent No. 1 on 6th November 2007 that it

was proposed to make a joint allocation to both of them. The

letter dated 6th November, 2007 clearly indicated the proposed

capacity of the thermal power plant of Respondent No. 4 as

1000 MW and that of PIL as 625 MW. It also clearly indicated

the proportional share of coal reserves as 73.85 MT for

Respondent No. 4 and 46.15 MT for PIL.

43. PIL wrote two letters dated 13th and 16th November 2007

raising the plea that Respondent No. 4 was proposing to set up

a 600 MW Power Plant and that it was on that basis that the W.P.(C) Nos. 7135 of 2008 page 23 of 33 Screening Committee and Respondent No.3 had proceeded. It

asked that the coal allocation be made in the ratio of 625 MW:

600 MW. Having taken that stand, when it was called by

Respondent No. 1 by the letter dated 22nd January 2008 to the

negotiating table PIL gave up its opposition. This is apparent

from the fact that it entered into the JVA on 29th January 2008.

On that basis the joint allocation was made on 6th February

2008.

44. A copy of the Joint Venture Agreement dated 29th January,

2008 entered into between PIL and Respondent No. 4 was

placed on record. In the preamble, it is clearly stated as under:

"The mineable capacity of the total geological reserves as assessed by CMPDIL, the proportionate share of reserves allocated to the parties is indicated under :

  Block                     Fatehpur
  Geological                120 Million Tons
  Reserve
  Tentative                 3 Million Tons per
  Mine                      Annum
  Capacity
  Name of the               Coal requirement for        Proportionate
  Company                   30 Years (Mill Tons)        Share         of
                                                        Reserves of Coal
                                                        (Mill Tons)
  SKS Ispat                 4.6X30=138      Mill        73.85
  and Power                 Tons for 1000 MW
  Limited                   Independent Power
                            Plant
  Prakash                   2.875X30=86.25 Mill         46.15
  Industries                Tons for 625 MW
  Limited                   Captive Power Plant.



In case of any amendment/change in sharing of coal ratio, by Ministry of Coal in future, in such case the JVA shall be amended accordingly."

45. The above table is a virtual reproduction what was W.P.(C) Nos. 7135 of 2008 page 24 of 33 contended in the letter dated 6th November, 2007. For good

measure in Clause 1 (A) it was stated as under:

1 (A) AGREEMENT ON OPTION TO CARRY OUT MINING: The parties have agreed to chose the Option-I as stated in the annexure-I, whereby the mining of allotted block shall be carried out in a joint venture by the parties through a special purpose vehicle company (hereinafter referred to as "Joint Venture Company" and/or "JVC") wherein both the parties shall hold equity stake and management participation. The production from the mine shall be shared in proportion to the assessed requirements at the time of allocation or amended from time to time by the Ministry of Coal, Govt. of India as stated above. The equity shares shall also be held in proportion to the assessed requirement."

46. PIL did not protest at all at that stage. It is impossible to

believe that there was compulsion on PIL to enter into the

above JVA. On the basis of the said JVA a letter was

addressed jointly by PIL and Respondent No. 4 to Respondent

No.1 on 29th January 2008 enclosing a copy of the said

agreement. The said letter, signed by both PIL and SKS, reads

as under:-

"The Under Secretary CA-1 29th January, 2008 Government of India Ministry of Coal Shastri Bhawan New Delhi 110001.

Sub: Allotment of Fatehpur Non-Coking Coal Block in the State of Chhattisgarh-Joint Venture Agreement thereof W.P.(C) Nos. 7135 of 2008 page 25 of 33 Dear Sir, This is with reference to your letter No.38011/2007-CA-I dated 22nd January, 2008 vide which you have called a meeting on 30 th January, 2008 at 11.00 a.m. in the Chamber of Joint Secretary (Coal) to discuss the issue relating to formation of Joint Venture Agreement for the allotted coal block.

In this regard, we would like to inform your goodself that a Joint Venture Agreement has been executed on 29th January, 2008 as per the copy of Joint Venture Agreement in original is enclosed herewith for your kind perusal and further action please.

Thanking you, Yours Truly For Prakash Industries Ltd. for SKS Ispat & Power Ltd.

                   Sd.                           Sd.
              (G.L. Mohta)              (Ravindranath Ratho)
                Director                         Director "


47. On the basis of the above JVA, the coal block allocation

was made by Respondent No.1 jointly to PIL and SKS by the

impugned letter dated 6th February 2008, the contents of which

have already been extracted. Not only did PIL not protest at

that stage but it went ahead and formed the joint venture

company with SKS on 19th May 2008. The questioning of the

allocation was done much later on 28th August 2008.

W.P.(C) Nos. 7135 of 2008 page 26 of 33

48. In the circumstances, this court holds that there is

absolutely no basis for the challenge by PIL to the validity of

the coal block allocation made by Respondent No. 1 by the

impugned letter dated 6th February 2008. There is no merit in

the submission regarding PIL having been compelled to enter

into the JVA. No illegality was committed by Respondent No.

1 in issuing the above letter. It was consistent with policy and

guidelines which were known to both PIL and Respondent No.

4. The series of subsequent events completely demolishes the

case of PIL that it was arm-twisted into entering into a JVA

with Respondent No.4.

Proceedings before the Screening Committee

49. This Court is also not impressed with the submission on

behalf of PIL that the 35th Screening Committee which

considered the applications of the Petitioner and Respondent

No. 4 on 13th September 2007 did not have the full facts before

it. In the counter affidavit filed by the Respondent No.1 in para

10, it is stated as under:

"10. Based on the data furnished by the applicants, and the feedback received from the State Governments and the Ministry of Power and CMPDIL, the Screening Committee assessed the applications having regard to matters such as techno-economic feasibility of end-use plant, past track record in execution of projects, financial and technical capabilities of applicant companies, recommendations of the State Governments and W.P.(C) Nos. 7135 of 2008 page 27 of 33 the Administrative Ministry concerned. Taking cognizance of the advice given by the Ministry of Power that in view of the capacity constraints in transmission network, power producers should limit plant capacity to 500 to 1000 MW, the Committee agreed that this should be taken as the guiding principle. Therefore, 1000 MW was taken as the maximum limit for allocation of coal blocks and the shares of geological reserves in the block, in case the capacity indicate in the application is higher than the maximum limit suggested by Ministry of Power. In view of large number of applications and limited number of blocks on offer, the Committee felt that it would be reasonable to have a satisfaction level in the range of around 40 to 70% to the extent feasible."

50. This Court is unable to find any basis for the criticism of

the manner in which the Screening Committee processed the

applications and took its decisions. There was nothing arbitrary

or irrational about the decision to make a joint allocation to

PIL and SKS in the ratio of their respective power plant

capacities. A careful examination of the chart enclosed with

the letter dated 5th September 2007 from Respondent No. 3 to

Respondent No. 1 shows that in Column No. 3 which is titled

"proposed capacity of end use plant" the figure mentioned

against the name of SKS at Sl. No.173 is 1100 MW. In

Column No. 7 titled "Total requirement (as per feedback

form)" the figure indicated is 1000 MW. The last Column

Remarks no doubt mentions only the MOU dated 24 th January W.P.(C) Nos. 7135 of 2008 page 28 of 33 2007 but what is not mentioned there is that by that date the

Respondent No. 4 had submitted a proposal (on 24th October

2006) to Respondent No. 3 for a 1200 MW power plant and it

had on 11th December 2006 been issued an IEM Code by the

Ministry of Commerce for a 1000 MW coal based thermal

power plant. In addition Respondent No. 3 confirms that its

representative was present at the meeting of the 35 th Screening

Committee on 13th September 2007.

51. Therefore, no fault can be found with the decision of the

Screening Committee to make a joint allocation to PIL and

Respondent No. 4 in the ratio of their respective power plant

capacities. The parties have acted upon the said decision and

taken several steps pursuant thereto. It is now not possible to

accept the case of PIL to issue directions to the Respondents to

go back to an anterior stage and make allocation of the coal

blocks on the basis of recommendation made by the

Respondent No. 3 on 18th June, 2007.

No basis for the case of malafides

52. The above two being the only prayers made in the writ

petition even after its amendment, there is no scope for

examining any other issue. However, since extensive

arguments were advanced by Mr. Sharan learned senior

counsel for the Petitioner that the allocation in favour of

Respondent No. 4 was malafide, this court is required to deal W.P.(C) Nos. 7135 of 2008 page 29 of 33 with that issue as well.

53. The basis for the claim of malafides is that according to

PIL, Respondent No. 4 has been promoted by the family of

proposed Respondent No. 5 who is a Minister of State in the

Union Cabinet and that Respondent No. 5 went out of his way

to get a decision in favour Respondent No. 4 in which his

brother, the proposed Respondent No. 6, was a Director.

54. After examining the records and considering the

submissions of the learned Senior counsel for the Petitioner,

this Court is of the view that PIL has proceeded on a wholly

erroneous premise. It is clear that the initials `SKS‟ in the

name of Respondent No. 4 do not stand for Subodh Kant

Sahai. With Respondent No. 4 itself explaining the history of

its formation, this allegation can only be termed a product of

the fanciful imagination of PIL. Further, not a scrap of paper

has been produced by PIL to prove its claim that Respondent

No. 4 was promoted by the family of Respondent No. 5. This

has turned out to be a preposterous claim made on affidavit by

PIL without any sensible responsibility.

55. The other plank of the plea of malafides is the letter dated

5th February 2008 written by the proposed Respondent No. 5 to

the Prime Minister, the complete text of which reads as under:

"05th February, 2008 W.P.(C) Nos. 7135 of 2008 page 30 of 33 Respected Dr. Sahab

I would like to bring to your kind notice that M/s SKS Ispat and Power Limited have applied for two Coal Blocks for their Steel Plants in the State of Chattisgarh and Jharkhand. A brief note in this regard is enclosed.

I shall be grateful for your personal intervention in this matter.

Yours sincerely, Sd./-

(Subodh Kant Sahai)"

(emphasis supplied)

56. It does not take much to realize that the above letter has

nothing to do with the allocation of coal blocks for a power

project. It specifically mentions allocation of coal blocks for

steel plants to Respondent No. 4. Therefore, nothing also turns

on the subsequent letter dated 6th February 2008 written by the

PMO to the Coal Ministry. The decision to make the allocation

to PIL and Respondent No. 4 jointly was made at the 35th

meeting of the Screening Committee on 13th September 2007

long before the above letter dated 5th February 2008.

57. The presence of proposed Respondent No. 6 at the meeting

of the 36th Screening Committee held on 7th February 2008 is

made much of by PIL. But that meeting was not about making

allocations to the power sector at all. The minutes of the said

meeting show that it was concerned with allocations to the

non-power sectors. It could not have influenced the decision to

allocate coal blocks jointly to PIL and Respondent No. 4, W.P.(C) Nos. 7135 of 2008 page 31 of 33 which decision in any event was already taken at the previous

meeting of the Screening Committee held on 13th September

2007.

58. The above facts show that PIL has set itself on a hopeless

task of trying to join completely unconnected events to bring

about a story of malafides. Not willing to accept that it has

nothing to show for its allegations PIL has desperately

persisted with this misconceived line even in its written

submissions. PIL has needlessly dragged Respondent Nos. 5

and 6 into this litigation knowing fully well that it would be

unable to substantiate its case against them.

59. What is also a matter for concern is that PIL has managed

to have an interim order in its favour for over eighteen months

on the basis of averments which it has been unable to prove.

The inescapable conclusion is that this petition is nothing but

an abuse of the process of law. This case has consumed several

extended hearing days thus resulting in wastage of valuable

time of the court.

Conclusion

60. For the above reasons, this court concludes that the present

petition is an instance of a vexatious litigation that has wasted

the precious time of the court. It should be dismissed with

exemplary costs.

W.P.(C) Nos. 7135 of 2008 page 32 of 33

61. Accordingly, the writ petition and pending applications are

dismissed with costs of Rs. 2.5 lakhs out of which Rs. 50,000/-

will be paid by the Petitioner to Respondent Nos. 1 & 2 jointly

and Rs. 50,000/- each to Respondent Nos. 3, 4 and proposed

Respondent Nos. 5 and 6 respectively within a period of four

weeks from today. The interim order stands vacated.




                                        S. MURALIDHAR, J
MAY 18, 2010
bs




W.P.(C) Nos. 7135 of 2008                             page 33 of 33
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter