Citation : 2010 Latest Caselaw 2483 Del
Judgement Date : 10 May, 2010
06.
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment dated on: 10.05.2010
+ W.P.(C) 3901/2008
NITIN KATARIA ..... Petitioner
Through : Mr. N. Kinra, Adv.
versus
D.D.A. ..... Respondent
Through : Mr. Ajay Verma, Adv.
CORAM:
HON'BLE MR. JUSTICE G.S.SISTANI
1. Whether the Reporters of local papers may be allowed to see
the judgment?
2. To be referred to Reporter or not?
3. Whether the judgment should be reported in the Digest?
G.S.SISTANI, J. (ORAL)
1. Rule. With the consent of counsel for the parties, writ petition is set
down for final hearing and disposal.
2. Brief facts of the case, as set out in the present petition, are that the
petitioner had booked a MIG flat in the year 2006. Petitioner was
allotted a flat bearing no.18, Block M-2, Pocket 4, Sector A-9, Narela,
vide letter dated 5.3.2007. As per the demand-cum-allotment letter,
a copy of which has been placed on record, petitioner was to deposit
a sum of Rs.11,68,737/- by 31.3.2007 and thereafter a sum of
Rs.12,11,964/- with interest upto 1.9.2007. On 3.9.2007, petitioner
received a letter from the SBI that the challans had not been cleared
due to shortfall in the amount. The petitioner is stated to have
cleared the shortfall in the sum of Rs. 5500/- on 25.10.2007. The petitioner was, in the meanwhile, asked by the DDA to obtain a
certificate of clearance from the Bank to show that petitioner had
deposited the full payment of Rs.12,12,000/-. Petitioner obtained
the necessary certificate from the bank on 16.11.2007 and
submitted the same to the DDA.
3. The case of the petitioner is that the amounts were deposited by
him from time to time by means of demand drafts, which were
issued by the State Bank of India in favour of the Delhi Development
Authority on the following dates:
Sl. No. Challan No. Date Amount
1. 11051 31.8.2007 1,80,000/-
2. 98823 31.8.2007 35,000/-
3. 82684 31.8.2007 1,96,000/-
4. 82683 31.8.2007 1,47,000/-
5. 82685 31.8.2007 1,96,000/-
6. 82687 31.8.2007 1,96,000/-
7. 116203 1.9.2007 2,62,000/-
Total 12,12,000/-
4. The grievance of the petitioner is that DDA has failed to condone
the delay and hand over possession of the flat for which the entire
amount stands paid in the year 2007.
5. Mr.Kinra submits that two bank drafts in the sum of Rs.1,96,000/-,
each, dated 31.8.2007 were, in fact, short by Rs.5,500/-. Counsel
further submits that this error occurred inadvertently, which is evident from the fact that the correct amount was filled up in the
challan, a photocopy of which has been placed on record at pages
17 and 18 of the paper book. The error was not noticed by the State
Bank of India when the amount was deposited and the challans
were duly stamped by the bank. Mr.Kinra submits that while all
other bank drafts were credited to the account of the DDA these two
bank drafts were kept in Suspense Account by the bank. DDA
thereafter addressed a communication to the State Bank of India
seeking a clarification whether all bank drafts were received on
31.8.2007 and, if not, the actual date of deposit of additional bank
drafts and the reasons for abnormal delay in credit. The State Bank
of India issued a clarification to the DDA vide letter dated
27.11.2009, relevant portion of which has been reproduced in the
counter affidavit and, which reads as under:
"challan No.82685 and 82687 for Rs.1,96,000/- each were deposited on 31.8.07 but with less amount of Rs.1500/- and Rs.4000/- respectively. On receipt of challans on the same of advice to deposit writing on 3.9.07 but deposited on 25.10.07 with D. Draft of balance amount. Hence total amount of challan under question were sent to DDA on 27.10.07." (sic)
6. Admittedly, the petitioner made up the deficiency and the bank
credited the amount in the account of the DDA on 25.10.2007. Thus,
according to the DDA, there was a delay of 57 days in receipt of
Rs.3,68,000/- as the Bank had not bothered to credit in the account
of the DDA, although the amount was in their possession, though
short by only Rs.5500/-. While counsel for the petitioner contends
that the shortfall was of only Rs.5500/- and for this bona fide mistake the flat allotted by the DDA to the petitioner cannot be
cancelled.
7. It is the case of the DDA that there was a shortfall of Rs.3,92,000/-
which was received by the DDA only on 25.10.2007.
8. Counsel for the petitioner submits that taking into consideration the
peculiar facts of this case and the bona fide mistake of the
petitioner as also the bank, it was a fit case for the DDA to have
applied its policy dated 1.6.2000 and should have condoned the
delay in receiving the payment, more particularly, when the
petitioner had deposited the entire payment with the Bank except
Rs.5500/-.
9. Counsel for the respondent submits that the policy dated 1.6.2000
would not be applicable to the facts of this case, firstly, on the
ground that the policy pertains to the year 2000 and the petitioner
had applied in the Scheme of 2006 and, secondly, on the ground
that the policy was formulated to condone delay in cases where
problems were faced by the concerned allottees in making the
payment.
10. I have heard counsel for the parties and also perused the pleadings
and documents filed along with the petitioner. The basic facts are
not in dispute that petitioner made an application to the DDA for
allotment of A MIG flat in the year 2006. As per the demand-cum-
allotment letter issued to the petitioner by the DDA, the last date for
making the entire payment with interest in the sum of
Rs.12,11,964/- was upto 1.9.2007. The petitioner deposited various bank drafts with the State Bank of India, as is evident from the
challans, copies of which have been placed on record. As per the
challans, the petitioner had deposited the entire sum of
Rs.12,11,964/-, however, on close scrutiny after receipt of the
payment and after stamping the challan the Bank noticed that two
bank drafts totaling Rs.1,96,000/-, each were short by Rs.1500/- and
Rs.4000/- respectively. Thus the bank did not credit two bank drafts
in the account of the DDA without any plausible reason. The bank
did not credit two bank drafts in the account of the DDA and kept
this amount in a suspense account with the result that DDA received
the amount after 1.9.2007 and only on 25.10.2007 when the matter
was cleared and the short fall was made up by the petitioner.
Counsel for the petitioner has placed reliance on the certificate
issued by the State Bank of India dated 16.11.2007 wherein the
Bank has given the details, in the form of a chart, as to when the
challan was deposited and when, in fact, the amount was credited in
the account of the DDA. The chart is reproduced below:
Challan Challan No. Credited on CHIEF -
Received your a/c MANAGER
on Received on Amount
31-8-07 82684 6.9.07 19,6000/-
31-8-07 82683 6.9.07 1,47,000/-
31-8-07 98823 6.9.07 35,000/-
1-9-07 116203 6.9.07 2,62,000/-
31-8-07 11051 6.9.07 1,80,000/-
31-8-07 82687 27.10.07 1,96,000/-
31-8-07 82685 27.10.07 1,96,000/-
12,12,000/-
11. A careful reading of the certificate issued by the Bank would show
that the amount deposited on 31.8.07 was credited to the account
of the DDA on 6.9.2007, however, with regard to two bank drafts the
amount was credited in October, 2007. No doubt there is a delay of
57 days in crediting the amount in the account of the DDA but the
shortfall on the part of the petitioner is only of Rs.5500/- and not of
Rs.3,62,000/-, as stated by the DDA. Petitioner has given instances
in various cases where DDA has condoned the delay in making the
payment. Having regard to the peculiar facts of this case where the
petitioner deposited the entire amount with the bank within the time
allowed except Rs.5500/- by mistake which was neither noticed by
the petitioner not the bank while accepting the money, in fact, the
bank has stamped the challans in acceptance of receipt of the
money, I am of the view that this is a fit case for condonation of
delay in making the payment. Taking into consideration the policy of
the DDA, which has been formulated keeping in view the hardship
being faced by some of the allottees, which shows that in genuine
and deserving cases the DDA has the discretion to condon the delay
Accordingly, delay is condoned. Order of cancellation is quashed.
Petitioner will pay the interest @ 12% on Rs.5500/- for 57 days.
Plot will be handed over to the petitioner within a period of three
months from the date of receipt of copy of this order and upon
completion of all formalities being completed meanwhile.
G.S. SISTANI, J.
May 10, 2010 'msr'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!